Utility Capital Projects
■ In 2021, the City of Hamilton continues with an emphasis on improving the reliability of the existing infrastructure by replacing deficient electric, natural gas, sanitary sewer, storm sewer and water facilities at a total cost of $18,590,000. In addition, there were street and traffic facility improvements totaling $16,200,000. Of the total $34,790,000, grant funding received was $5,700,000.
In 2022, the City of Hamilton is budgeting $6,500,000 to replace deficient electric, natural gas, sanitary sewer, storm sewer and water distribution utilities. The City is also budgeting $8,200,000 for street and traffic facility improvements. In addition, there will be $4,000,000 budgeted for preliminary engineering for the North Hamilton Crossing project. Of the $18,700,000, grant funding totaling $4,200,000 has been received. ❑