Advanced Architectural Construction - Precast Concrete System

Page 1

Advanced Architectural Construction (ARC60104) Project 1: INDUSTRIALISED BUILDING SYSTEM Precast Concrete System

Adlin Sorfina Binti Ramli 0336092 Caryn Wee Shin Yee 0335535 Fathimath Zaha Zuhoor 0336185 Nur Amal Binti Azmi 0336210 Syamimi Binti Mohd Saifuddin 0335690


Table of Content Content List

1.0 Industrialised Building System

01

2.0 Precast Concrete System

02 - 04

3.0 Precedent Study

05 - 07

4.0 Proposed Apartment Design

08 - 22

5.0 IBS Components Features

23 - 25

6.0 Schedule of Modular Components

26 - 36

7.0 Fabrication Process

37 - 40

8.0 Construction Sequence

41 - 46

9.0 IBS Score

47

10.0 Conclusion

48

TES Evaluation

49

Peer Assessment

50

Reference List

51


Industrialised Building System 1.1.0 Introduction Industrialised Building System were introduced to Malaysia in the 60s by Ministry of Housing and Local Government. It is introduce to speed up building construction as well making sure the quality and affordability of the houses.

IBS were used to be an alternative to the conventional system that we are used to. It is a construction method technique which the components are manufactured in a controlled environment whether off or on site. The components are transported, assembled and position into a structure with less additional work given. The materials of the components are produced in a factory where quality control is not compromised on.

Types

Advantages and Disadvantages Advantages : ● ● ●

Steel Frame System Includes steel trusses, beams and a column portal frame

Timber Frame System Involves prefabricated timber truss beams and columns

Formwork System

Generally involves concrete that moulded into different component

● ●

Reduce construction time : Less construction time due to fabrication of the element can take place concurrently Save Cost : Reducing on-site workers,minimizing cost of transferring waste material, provides earlier occupation Optimised use of materials : precision and accuracy of the production can be achieve to produce ibs while reducing material wastage Durability : High-density precast concrete more durable to acid attack, corrosion, impact, reduces surface voids and resists the accumulation of dust High quality and better finishes : Quality control, high aesthetic end product Flexibility : More flexibility in the design of precast element

Disadvantages : ●

Block Work System

Precast Concrete System

A system that uses interlocking concrete masonry units and lightweight concrete blocks

Includes precast concrete columns, beams, slabs, and walls and other component

● ● ● ●

High Initial capital cost : Initial capital cost of IBS is usually higher than conventional method Problem of joints : Sensitive to error and sloppy works Sophisticated plants and skilled operators : Relies on sophisticated plant Site accessibility : IBS requires sufficient site accessibility to transport IBS components form factory to the site Large working area : Requires large working area for tower crane, factory, storage and trailer for the components

01


Precast Concrete System 2.1.0 Introduction Precast Concrete System has been introduced by the government in Malaysia since the 60’ as one of the IBS (Industrialised Building System) method in construction. It is also to enhance the importance of the prefabrication technology rather than conventional method.

Precast concrete system is a form of concrete that was made and formed in reuseable moulds, usually in controlled factory environment before getting transported to the construction site for assembly and installation. Usually used for structural component such as, walls panels, beams, columns, floors, staircases, pipes, tunnels, and more. Precast Concrete System are also economical and more practical to the construction process.

Types

Advantages and Disadvantages

There are three major types of precast concrete system

Advantages : ●

Large Panel System Consists of large walls and floor concrete panels connected in the vertical and horizontal directions

● ● ●

Frame System Precast frames can be constructed using either linear elements or spatial beam-column sub assemblages

Saves contribution times : Save time on construction and the risk of project is also less Quality assurance : Can regulate the quality and monitor the construction Cost-Effective : Reduces time, increase quality, productivity and safety thus the cost will be reduce Durability : High-density precast concrete more durable to acid attack, corrosion, impact, reduces surface voids and resists the accumulation of dust Aesthetic : Wide range of shapes and sizes are available to choose from with smooth finishings and thus the aesthetical value increase Safe construction program : No raw materials on site thus the casualties can be reduced.

Disadvantages : ●

Slab-Column System with Shear Wall

Gravity loads supported by slab-column structure whereas shear walls withstand lateral loads.

● ●

High Initial Investment : Heavy and sophisticated machines are necessary which requires a high initial investment. Transportation Issue : Construction site can be at a distance therefore transportation can be an issue Handling Difficulties : precast members are heavy and large which makes it difficult to handle without damage. Modification : Limitation In case of precast structures, it is difficult to modify the structure. 02


Precast Concrete System 2.1.1 Introduction For precast concrete design structure, temperature variations, concrete deep and shrinkage should be taken inro account as it may vary in the connection of the design leading to substantial damage. In order to have stabilizing units, the design of the connections should be made with the influence of different factors and with consistency to avoid any damage.

Types of Connection Welded Joints

Bolted Joints

Welding joints are made by welding plates or rods which are integrated with details in precast panels.

Bolted joints are made through fixing embedded details in the precast panel and by bolting the plates. Mainly used for areas in which it is difficult to weld. This method requires immense accuracy.

Welded joint with rod which is welded together with the loops reinforcement bar

Welded joint with plate. The steel plate is welded together with other steel plates that are used as embedded details.

Shows the welded joint with anchor plate.

Shows bolted connection of the wall with plate

Bolted connection of the walls

03


Precast Concrete System 2.1.1 Introduction Types of Connection Vertical joints of the wall panels : Wire loop connection

Horizontal joints of the wall panels

These are joints made from rope steel loops in a specialized box which are placed into the formwork before the panel is cast.

This type of connection consists of wall shoes and anchor bolts. This includes the steel box with anchor bars welded to the bic which are placed into the formwork together with the main and supplementary reinforcement

Anchor bolt Continuity reinforcement Wall shoe

Wire loop connection of two outer walls

Anchor bolt

The right location fitting for bolt shoes

The wall is installed on pre leveled shim plates

Wire loop connection of outer and inner walls

The nut and washers are screwed on and tightened

Connection is ready for grouting

Finalized connection after the grounding hardens

Process of erecting walls with wall shoe

04


Precedent Study 3.2.1 Introduction

SERI JATI APARTMENTS , SETIA ALAM Developer : SP Setia IBS System used : Precast System Size per unit : 88m2

● ● c ●

Consists of 948 units and 10 storeys Achieved score of 83% for the vertical and horizontal Repetition criteria , maintained the quality Low forming and construction cost due to the use of precast and in-situ building components

Seri Jati Apartment Unit Typical Layout

05


Precedent Study 3.2.2 Construction System CONSTRUCTION SYSTEM USED IN SERI JATI APARTMENTS , SETIA ALAM :

Seri Jati Apartment uses conventional construction for its foundation and ground floor construction , including transfer beam to transfer the heavy gravity load of structural elements from above along with reinforced concrete components. Other than that , Seri Jati Apartment applies precast construction method with standardized components to facilitate its construction process while having g constant quality control.

A

B

C

Construction Process:

(A)

Construct structure’s foundation

(B) Installation of precast columns

(B) Installation of in-situ floor for Ground Floor and First Floor

(C ) Installation of precast components

D

E

(D) Process were repeated until the 10th Floor

(E) Installation of prefabricated steel roof truss with panels

06


Precedent Study 3.2.3 Building Components and Standardization of Sizes IBS COMPONENTS USED IN SERI JATI APARTMENTS , SETIA ALAM : Standardized Dimensions :

Majority building elements of Seri Jati Apartment uses IBS System of Precast Concrete method to construct. Building Elements including the Roof , Floor Slabs , Walls , Columns and Beams.

Precast Components

A

B

C B

A

C

Dimensions (mm/m2)

Precast Concrete Column

150 W x 150 L

Precast Concrete NonBearing Wall

150 W x 300 H

Precast Concrete Load-Bearing Wall

300 W x 300 H

Precast Concrete Beam

150 x 300

Precast Concrete Slab

200 x 4200

Prefabricated Steel Roof Truss

1610 m2

Precast Staircase

3000 H x 167 Riser x 250 Thread

Precast Bathroom

4.2 m2

Axonometric of Seri Jati Apartment , Setia Alam

07


Proposed Apartment Design 4.0 Introduction

The proposed apartment design implement the precast concrete system with the use of various precast concrete components such as columns beams, slabs and many more. This apartment has a total of 6 units and 3 floors with a 'X' shaped staircase at its center to access the units.. The size per unit of this apartment is approximately 100sqm, equipped with living room, kitchen, 3 bedrooms and 2 bathrooms.

08


Proposed Apartment Design 4.1 Orthographics Drawing Ground Floor Plan - SCALE 1:100

W1

W1

W1

W1

W1

W1

W2

W2 D2

W3

D2

D3

S1

D1

D1 D1

W3

D3

D2

D2

W1

W1 D2

D2

W1 D3

W1

W1

W1

D3

W3

W3

S2

W1

W1

S3

09


Proposed Apartment Design 4.1 Orthographics Drawing First Floor Plan - SCALE 1:100

W1

W1

W1

W1

W1

W1

W2

W2 D2

S1

W3

D3

W1

D2

W1

D2 D1

D1

D2

D2

W1

D2 D3

W1

W3

D3

W1

W1

D3

W3

W3

S2

W1

W1

S3

10


Proposed Apartment Design 4.1 Orthographics Drawing Second Floor Plan - SCALE 1:100

W1

W1

W1

W1

W1

W1

W2

W2 D2

W3

D2

D1

D3

D1

D2

S1

W3

D3

D2 W1

W1 D2

W1

D2 D3

W1

W1

W1

D3

W3

W3

S2

W1

W1

S3

11


Proposed Apartment Design 4.1 Orthographics Drawing Roof Floor Plan - SCALE 1:100

S1

S2

S3

12


Proposed Apartment Design 4.1 Orthographics Drawing North Elevation - SCALE 1:100

13


Proposed Apartment Design 4.1 Orthographics Drawing South Elevation - SCALE 1:100

14


Proposed Apartment Design 4.1 Orthographics Drawing East Elevation - SCALE 1:100

West Elevation - SCALE 1:100

15


Proposed Apartment Design 4.1 Orthographics Drawing Section 1 - SCALE 1:100

16


Proposed Apartment Design 4.1 Orthographics Drawing Section 2 - - SCALE 1:100

17


Proposed Apartment Design 4.1 Orthographics Drawing Section 3 - SCALE 1:100

SCALE 1:100

18


Proposed Apartment Design 4.2 Structural Drawings Foundation Layout Plan - SCALE 1:100

SCALE 1:100

19


Proposed Apartment Design 4.2 Structural Drawings First Floor Beam Layout Plan - SCALE 1:100

SCALE 1:100

20


Proposed Apartment Design 4.2 Structural Drawings Second Floor Beam Layout Plan - SCALE 1:100

SCALE 1:100

21


Proposed Apartment Design 4.3 Isometric View

22


IBS Components 5.0 Proposed Apartment’s IBS Features Repetition of Floor-to-Floor Height

Vertical and Horizontal Repetition on Structural Layout

4000 4000 4000

North Elevation

Ground Floor Plan

Maintaining the same height of floor from the ground floor to the top floor of 4000mm.

Structural components are constructed according to a repeated planned layout with vertical and horizontal grid.

Suitability ● ● ●

Modular coordinated Walls panels can be pre-fabricated and reduce on site labor Ease of construction

Suitability ● Allow prefabrication of wall components ● Ease of construction

23


IBS Components 5.0 Proposed Apartment’s IBS Features Precast Concrete Columns

Precast Concrete Beams

Suitability ● Reduce construction cost by having intentional manufacturing ● Flexible in variety of sizing and configuration

Suitability ● Highly potential in producing consistent connections and construction outcome ● Sturdy and dense character limits Connection Detail

Connection Detail Mechanical splice

Precast Concrete Walls

Shim & grout Grout full

Cast-in-place concrete

Butt-weld

Suitability ● Reinforced with steel will make the long span concrete wall more sturdy ● Have load bearing capabilities and act as a stabiliser Connection Detail

Grout to cover recessed connection

Embedded plate

Roughened surface

Loose feld plate

Bolts

Grout to cover recessed connection

Precast beam

Shim & grout Precast column

Loose feld plate

Precast unit

Embedded plate

24


IBS Components 5.0 Proposed Apartment’s IBS Features Precast Concrete Staircase

Standardized Components

W1

W1

W1

W1

W1

W1

W2

W2 D2

W3

D2

D3

D1

D1

D2

D2

S1

W3

D3

W1

W1 D2

W1

Suitability ● Accurate and flexible during prefabrication process in factory ● More efficient erection process

W1

W1

W3

W3

S2

W1

W1

W1

S3

Uses Modular Coordination

Connection Detail Embed Steel Plate Concrete Staircase

Slab Landing

Bolt

D2 D3

D3

Columns Sizes : Multiples of 0.5M

Beams Sizes : Multiples of 0.5M

Windows Width : Multiples of 1M

Doors ( Door leaf opening width) : Multiples of 0.5M

Suitability ● Prefabrication ensure quality control of components ● More efficient and organised construction process ● Contribute to the Industrialised Building System ‘s scoring

25


Modular Components 6.0 Schedule of Modular Components SLAB COMPONENT SCHEDULE

Component Name

Slab SL1

SL2

Roof Slab

Staircase Landing Slab

Thickness (mm)

150

150

150

150

Width (mm)

10,000 mm

10,000 mm

12000

1000

Length (mm)

10,000 mm

10,000 mm

30000

1200

Quantity

3

3

1

8

Isometric

Plan

26


Modular Components 6.0 Schedule of Modular Components COLUMN COMPONENT SCHEDULE

Component Name

Column C1

C2

Thickness (mm)

200

300

Width (mm)

300

200

Length (mm)

4000

4000

Quantity

12

24

Isometric

Plan

27


Modular Components 6.0 Schedule of Modular Components BEAM COMPONENT SCHEDULE

Component Name

Beam Beam 1

Beam 2

Beam 3

Thickness (mm)

350

350

350

Width (mm)

200

200

1200

Length (mm)

10000

10000

10000

Quantity

6

24

6

Isometric

Plan

28


Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE

Component Name

Wall Panels Wall 1

Wall 2

Wall 3

Wall 4

Wall 5

Thickness (mm)

150

150

150

150

150

Width (mm)

9500

3200

4157

1993

9850

Height (mm)

4000

4000

4000

4000

4000

Quantity

4

4

4

4

4

Isometric

Plan

29


Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE

Component Name

Wall Panels Wall 6

Wall 7

Wall 8

Wall 9

Wall 10

Thickness (mm)

150

150

150

150

150

Width (mm)

1993

4157

3200

9850

6775

Height (mm)

4000

4000

4000

4000

4000

Quantity

4

4

4

6

6

Isometric

Plan

30


Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE

Component Name

Wall Panels Wall 11

Wall 12

Wall 13

Wall 14

Wall 15

Thickness (mm)

150

150

150

150

150

Width (mm)

9550

3200

4157

1993

9850

Height (mm)

4000

4000

4000

4000

4000

Quantity

2

2

2

2

2

Isometric

Plan

31


Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE

Component Name

Wall Panels Wall 16

Wall 17

Wall 18

Wall 19

Wall 20

Thickness (mm)

150

150

150

100

100

Width (mm)

1993

4157

3200

2925

2825

Height (mm)

4000

4000

4000

4000

4000

Quantity

2

2

2

12

6

Isometric

Plan

32


Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE

Component

Wall Panels Balcony Wall 1

Balcony Wall 2

Balcony Wall 3

Balcony Wall4

Balcony Wall 5

Thickness (mm)

150

100

100

100

150

Width (mm)

975

160

3860

1700

975

Height (mm)

1200

1200

1200

1200

1200

Quantity

4

4

4

4

4

Name

Isometric

Plan

33


Modular Components 6.0 Schedule of Modular Components DOOR COMPONENT SCHEDULE

Component Name

Doors Door 1 (D1)

Door 2 (D2)

Door 3 (D3)

Width (mm)

900

800

700

Height (mm)

2100

2100

2100

Specification

Timber Frame/Timber Door

Timber Frame/Timber Door

Timber Frame/Timber Door

Quantity

6 ( 1 per unit)

18 ( 3 per unit)

12 (2 per unit)

Isometric

Plan

34


Modular Components 6.0 Schedule of Modular Components WINDOW COMPONENT SCHEDULE Component

Windows Window 1 (W1)

Window 2 (W2)

Window 3 (W3)

Width (mm)

1400

600

900

Height (mm)

1800

600

1800

Height from floor to window (mm)

900

2000

900

Specification

Aluminium Frame/ Glass

Aluminium Frame / Glass

Aluminium Frame / Glass

Quantity

48 (1 per unit)

12 (2 per unit)

6 (1 per unit)

Isometric

Plan

35


Modular Components 6.0 Schedule of Modular Components STAIRCASE COMPONENT SCHEDULE Component

Straight Staircase with Interlocking Landing

Name

ST 1 & ST 2

Isometric

Plan

Tread (mm)

1400

Riser (mm)

190

Floor to Floor Height

4000

Quantity

12

Specification

Concrete steps (24) / Steel railing

36


Fabrication Process 7.0 Fabrication of Modular Components NORMAL CASTING FABRICATION PROCESS 1.

ASSEMBLY OF MOULD

Workers must ensure the level and flatness of the base before assembling mould for panel casting.

Next, verify the mold size and dimensions are correct according to the design. Lastly, the workers have to check the squareness of the mould forms. ○ The workers have to check the squareness of the mould forms.

2. MOULD CLEANING AND PREPARATION ●

After the assembly of the mould, it must be clean and free from debris and old mortars using remover or scaling bars.

Form oil or mould release agent is evenly applied over the mould surfaces.

The workers will have to check everything is properly secured such as the joints and edges of the mould, bolts, stoppers, tie rods, side props and rubber seal are undamaged.

37


Fabrication Process 7.0 Fabrication of Modular Components 3. FIXING OF REBARS/ CAST IN ITEMS/ PRESTRESSING STRANDS ●

The workers must check if the measurements of the rebar size, spacing and lap length are in line with the drawings.

The rebars, cast-in-items, corrugated sleeve pipes, recesses, lifting hooks and inserts must be accurately positioned and properly connect. With the use of fabrication rig, it can help to make sure the accuracy of rebars fixing and spacing.

Only when needed, tack welding may be carried out to secure these items. To achieve the required concrete cover while casting, the workers should properly place and secure the the sufficient number of spacers with the correct sizes.

4. FINAL INSPECTION BEFORE CASTING ●

The workers must check and verify that all details should exactly comply with the drawings.

To check the mould fitting conditions including blockout details.

To check the base mould level again especially for site precasting since other concurrent site activities may have shifted the mould level.

38


Fabrication Process 7.0 Fabrication of Modular Components 5. CONCRETING

6. CURING

The workers must check that the concrete grade used is according to the design specifications and assess the workability of the concrete mix before placing the concrete mould, they must conduct a slump test.

After the concrete is poured, the curing process begins. During the curing process, the workers is to observe adequate curing time and desired environment.

The drop height of concrete mix should not exceed more than 1m. In more congestion areas, proper vibration and compaction should be carried out.

With a controlled environment, it enables the product to properly cure and reach the desired design strength much quicker.

Then, spreading and levelling of concrete surface level after initial set.

Maintain the required thickness by use of screeder. It is recommended to use power trowel or float to smooth the surface of the finishes.

39


Fabrication Process 7.0 Fabrication of Modular Components 7. DEMOULDING ●

Before demoulding process, cube tests should be conducted to confirm the concrete strengths of elements.

From the test, it will ensure the concrete strengths obtained for reinforced precast elements are minimum 10N/mm2.

Next, it is required to loosen and remove all bots and pins and side mould forms before lifting.

8. FINAL INSPECTION/ TRANSFER TO STORAGE YARD ●

The workers must check the condition of the finished product and verify again the critical dimensions.

Identify all the markings to be placed on the elements showing the location, member type, size, weight and orientation as per shop drawing.

Lastly, check the elements have achieved 75% of their design concrete strength before delivery to site for erection.

40


Construction Sequence 8.0 Construction Process of Proposed Apartment

1. Strip foundation footing.

2. Foundation wall from the footing to the foundation slab.

41


Construction Sequence 8.0 Construction Process of Proposed Apartment

3. Connection of precast concrete columns to the strip foundation.

4. Casting of foundation beam

42


Construction Sequence 8.0 Construction Process of Proposed Apartment

5. Installation of precast floor slabs.

6. Installation of first floor beams.

43


Construction Sequence 8.0 Construction Process of Proposed Apartment

7. Installation of precast walls to its specific location.

8. Installation of prefabricated windows, doors and staircase.

44


Construction Sequence 8.0 Construction Process of Proposed Apartment

9. Repeat the sequence of columns, beams, floor slabs, walls, staircase to the first floor.

10. Repeat the sequence of columns, beams, floor slabs, walls, staircase to the second floor.

45


Construction Sequence 8.0 Construction Process of Proposed Apartment

11. Casting of roof beams.

12.Casting of roof slab and finishes with exterior wall painting and interior tile finishing

46


IBS Score 9.0

N0 1.

2.

ELEMENTS

IBS FACTOR

COVERAGE

IBS SCORE

PART 1 : Structural System Precast Concrete Columns and Beams

621.8 m2

1.0

(621.8/998.4)=0.62

0.62 x 1.0 x 50 = 31

Precast Concrete Roof Slabs

376.6 m2

1.0

(376.6/998.4)= 0.38

0.38 x 1.0 x 50 = 19

Total Part 1

998.4 m2

50

PART 2 : Wall Systems Internal Wall : Precast Concrete Panels

420.0 m

1.0

(420.0/700.6)= 0.6

0.6 x 1.0 x 20= 12

External Wall ; Precast Concrete Panels

280.6 m

1.0

(280.6/700.6)= 0.4

0.4 x 1.0 x 20= 8

Total Part 2 3.

AREA (m2) or LENGTH (m)

700.6

20

PART 3 : Other Simplified Construction Solutions i.Standardised Beam Components follow MS 1064

100%

4

ii.Standardised Column Components follow MS 1064

100%

4

iii.Standardised Walls Components follow MS 1064

50%

2

iv.Standardised Slabs Components follow MS 1064

100%

4

v.Standardised Door Components follow MS 1064

100%

4

vi.Standardised Window Components follow MS 1064

100%

4

vii.. Repetition of floor to floor height

100%

2

viii.Vertical Repetition of Structural Floor Layout

100%

2

ix..Horizontal Repetition of Structural Floor Layout

100%

2

xi. Usage of Prefab Staircases

100%

2

Total Part 3

30

IBS SCORE = Part 1 + Part 2 + Part 3

100

47


Conclusion 10.0

With the use of precast concrete system in the construction of the apartment, an industrialized building system are able to achieved with the score of . Design features such as precast columns, beams , walls ; prefabricated staircase ; standardized components ; and repetition on layout has contributed to the high score. These initiatives allows the construction process to be carry out in a shorter time span , while also benefits the economical prospect with the minimized construction cost and low man power requirement. The quality of the structure is also controlled, minimum wastage is produced. Through this project we have learned the knowledge of Industrialised Building System, especially Precast Concrete System that will benefit us in a long period of time during our pursue on Architecture or even on the workfield.

48


TES Evaluation

49


Peer Assessment

50


Reference List

1.

https://civiltoday.com/civil-engineering-materials/concrete/232-advantages-and-disadvantages-of-precas t-concrete

2.

http://rehdainstitute.com/wp-content/uploads/2017/05/4.-Kow-Choong-Ming.pdf

3.

https://theconstructor.org/building/methods-precast-concrete-constructions/26523/

4.

https://theconstructor.org/building/methods-precast-concrete-constructions/26523/

5.

https://www.bca.gov.sg/Publications/BuildabilitySeries/others/bsl_cp4.pdf

6.

https://www.jpconcrete.co.uk/precast-concrete-stairs/

7.

https://www.bca.gov.sg/Professionals/IQUAS/others/precastfabrication.pdf

8.

https://www.matec-conferences.org/articles/matecconf/pdf/2014/01/matecconf_bust2013_01002.pdf

9.

https://www.ukessays.com/essays/construction/the-classification-according-to-structural-system-constr uction-essay.php

10.

http://precast.org/wp-content/uploads/2014/08/Precast-Concrete-Architectural-Connections-Guide.pdf

51


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.