Advanced Architectural Construction (ARC60104) Project 1: INDUSTRIALISED BUILDING SYSTEM Precast Concrete System
Adlin Sorfina Binti Ramli 0336092 Caryn Wee Shin Yee 0335535 Fathimath Zaha Zuhoor 0336185 Nur Amal Binti Azmi 0336210 Syamimi Binti Mohd Saifuddin 0335690
Table of Content Content List
1.0 Industrialised Building System
01
2.0 Precast Concrete System
02 - 04
3.0 Precedent Study
05 - 07
4.0 Proposed Apartment Design
08 - 22
5.0 IBS Components Features
23 - 25
6.0 Schedule of Modular Components
26 - 36
7.0 Fabrication Process
37 - 40
8.0 Construction Sequence
41 - 46
9.0 IBS Score
47
10.0 Conclusion
48
TES Evaluation
49
Peer Assessment
50
Reference List
51
Industrialised Building System 1.1.0 Introduction Industrialised Building System were introduced to Malaysia in the 60s by Ministry of Housing and Local Government. It is introduce to speed up building construction as well making sure the quality and affordability of the houses.
IBS were used to be an alternative to the conventional system that we are used to. It is a construction method technique which the components are manufactured in a controlled environment whether off or on site. The components are transported, assembled and position into a structure with less additional work given. The materials of the components are produced in a factory where quality control is not compromised on.
Types
Advantages and Disadvantages Advantages : ● ● ●
Steel Frame System Includes steel trusses, beams and a column portal frame
Timber Frame System Involves prefabricated timber truss beams and columns
Formwork System
●
Generally involves concrete that moulded into different component
● ●
Reduce construction time : Less construction time due to fabrication of the element can take place concurrently Save Cost : Reducing on-site workers,minimizing cost of transferring waste material, provides earlier occupation Optimised use of materials : precision and accuracy of the production can be achieve to produce ibs while reducing material wastage Durability : High-density precast concrete more durable to acid attack, corrosion, impact, reduces surface voids and resists the accumulation of dust High quality and better finishes : Quality control, high aesthetic end product Flexibility : More flexibility in the design of precast element
Disadvantages : ●
Block Work System
Precast Concrete System
A system that uses interlocking concrete masonry units and lightweight concrete blocks
Includes precast concrete columns, beams, slabs, and walls and other component
● ● ● ●
High Initial capital cost : Initial capital cost of IBS is usually higher than conventional method Problem of joints : Sensitive to error and sloppy works Sophisticated plants and skilled operators : Relies on sophisticated plant Site accessibility : IBS requires sufficient site accessibility to transport IBS components form factory to the site Large working area : Requires large working area for tower crane, factory, storage and trailer for the components
01
Precast Concrete System 2.1.0 Introduction Precast Concrete System has been introduced by the government in Malaysia since the 60’ as one of the IBS (Industrialised Building System) method in construction. It is also to enhance the importance of the prefabrication technology rather than conventional method.
Precast concrete system is a form of concrete that was made and formed in reuseable moulds, usually in controlled factory environment before getting transported to the construction site for assembly and installation. Usually used for structural component such as, walls panels, beams, columns, floors, staircases, pipes, tunnels, and more. Precast Concrete System are also economical and more practical to the construction process.
Types
Advantages and Disadvantages
There are three major types of precast concrete system
Advantages : ●
Large Panel System Consists of large walls and floor concrete panels connected in the vertical and horizontal directions
● ● ●
●
Frame System Precast frames can be constructed using either linear elements or spatial beam-column sub assemblages
●
Saves contribution times : Save time on construction and the risk of project is also less Quality assurance : Can regulate the quality and monitor the construction Cost-Effective : Reduces time, increase quality, productivity and safety thus the cost will be reduce Durability : High-density precast concrete more durable to acid attack, corrosion, impact, reduces surface voids and resists the accumulation of dust Aesthetic : Wide range of shapes and sizes are available to choose from with smooth finishings and thus the aesthetical value increase Safe construction program : No raw materials on site thus the casualties can be reduced.
Disadvantages : ●
Slab-Column System with Shear Wall
●
Gravity loads supported by slab-column structure whereas shear walls withstand lateral loads.
● ●
High Initial Investment : Heavy and sophisticated machines are necessary which requires a high initial investment. Transportation Issue : Construction site can be at a distance therefore transportation can be an issue Handling Difficulties : precast members are heavy and large which makes it difficult to handle without damage. Modification : Limitation In case of precast structures, it is difficult to modify the structure. 02
Precast Concrete System 2.1.1 Introduction For precast concrete design structure, temperature variations, concrete deep and shrinkage should be taken inro account as it may vary in the connection of the design leading to substantial damage. In order to have stabilizing units, the design of the connections should be made with the influence of different factors and with consistency to avoid any damage.
Types of Connection Welded Joints
Bolted Joints
Welding joints are made by welding plates or rods which are integrated with details in precast panels.
Bolted joints are made through fixing embedded details in the precast panel and by bolting the plates. Mainly used for areas in which it is difficult to weld. This method requires immense accuracy.
Welded joint with rod which is welded together with the loops reinforcement bar
Welded joint with plate. The steel plate is welded together with other steel plates that are used as embedded details.
Shows the welded joint with anchor plate.
Shows bolted connection of the wall with plate
Bolted connection of the walls
03
Precast Concrete System 2.1.1 Introduction Types of Connection Vertical joints of the wall panels : Wire loop connection
Horizontal joints of the wall panels
These are joints made from rope steel loops in a specialized box which are placed into the formwork before the panel is cast.
This type of connection consists of wall shoes and anchor bolts. This includes the steel box with anchor bars welded to the bic which are placed into the formwork together with the main and supplementary reinforcement
Anchor bolt Continuity reinforcement Wall shoe
Wire loop connection of two outer walls
Anchor bolt
The right location fitting for bolt shoes
The wall is installed on pre leveled shim plates
Wire loop connection of outer and inner walls
The nut and washers are screwed on and tightened
Connection is ready for grouting
Finalized connection after the grounding hardens
Process of erecting walls with wall shoe
04
Precedent Study 3.2.1 Introduction
SERI JATI APARTMENTS , SETIA ALAM Developer : SP Setia IBS System used : Precast System Size per unit : 88m2
● ● c ●
Consists of 948 units and 10 storeys Achieved score of 83% for the vertical and horizontal Repetition criteria , maintained the quality Low forming and construction cost due to the use of precast and in-situ building components
Seri Jati Apartment Unit Typical Layout
05
Precedent Study 3.2.2 Construction System CONSTRUCTION SYSTEM USED IN SERI JATI APARTMENTS , SETIA ALAM :
Seri Jati Apartment uses conventional construction for its foundation and ground floor construction , including transfer beam to transfer the heavy gravity load of structural elements from above along with reinforced concrete components. Other than that , Seri Jati Apartment applies precast construction method with standardized components to facilitate its construction process while having g constant quality control.
A
B
C
Construction Process:
(A)
Construct structure’s foundation
(B) Installation of precast columns
(B) Installation of in-situ floor for Ground Floor and First Floor
(C ) Installation of precast components
D
E
(D) Process were repeated until the 10th Floor
(E) Installation of prefabricated steel roof truss with panels
06
Precedent Study 3.2.3 Building Components and Standardization of Sizes IBS COMPONENTS USED IN SERI JATI APARTMENTS , SETIA ALAM : Standardized Dimensions :
Majority building elements of Seri Jati Apartment uses IBS System of Precast Concrete method to construct. Building Elements including the Roof , Floor Slabs , Walls , Columns and Beams.
Precast Components
A
B
C B
A
C
Dimensions (mm/m2)
Precast Concrete Column
150 W x 150 L
Precast Concrete NonBearing Wall
150 W x 300 H
Precast Concrete Load-Bearing Wall
300 W x 300 H
Precast Concrete Beam
150 x 300
Precast Concrete Slab
200 x 4200
Prefabricated Steel Roof Truss
1610 m2
Precast Staircase
3000 H x 167 Riser x 250 Thread
Precast Bathroom
4.2 m2
Axonometric of Seri Jati Apartment , Setia Alam
07
Proposed Apartment Design 4.0 Introduction
The proposed apartment design implement the precast concrete system with the use of various precast concrete components such as columns beams, slabs and many more. This apartment has a total of 6 units and 3 floors with a 'X' shaped staircase at its center to access the units.. The size per unit of this apartment is approximately 100sqm, equipped with living room, kitchen, 3 bedrooms and 2 bathrooms.
08
Proposed Apartment Design 4.1 Orthographics Drawing Ground Floor Plan - SCALE 1:100
W1
W1
W1
W1
W1
W1
W2
W2 D2
W3
D2
D3
S1
D1
D1 D1
W3
D3
D2
D2
W1
W1 D2
D2
W1 D3
W1
W1
W1
D3
W3
W3
S2
W1
W1
S3
09
Proposed Apartment Design 4.1 Orthographics Drawing First Floor Plan - SCALE 1:100
W1
W1
W1
W1
W1
W1
W2
W2 D2
S1
W3
D3
W1
D2
W1
D2 D1
D1
D2
D2
W1
D2 D3
W1
W3
D3
W1
W1
D3
W3
W3
S2
W1
W1
S3
10
Proposed Apartment Design 4.1 Orthographics Drawing Second Floor Plan - SCALE 1:100
W1
W1
W1
W1
W1
W1
W2
W2 D2
W3
D2
D1
D3
D1
D2
S1
W3
D3
D2 W1
W1 D2
W1
D2 D3
W1
W1
W1
D3
W3
W3
S2
W1
W1
S3
11
Proposed Apartment Design 4.1 Orthographics Drawing Roof Floor Plan - SCALE 1:100
S1
S2
S3
12
Proposed Apartment Design 4.1 Orthographics Drawing North Elevation - SCALE 1:100
13
Proposed Apartment Design 4.1 Orthographics Drawing South Elevation - SCALE 1:100
14
Proposed Apartment Design 4.1 Orthographics Drawing East Elevation - SCALE 1:100
West Elevation - SCALE 1:100
15
Proposed Apartment Design 4.1 Orthographics Drawing Section 1 - SCALE 1:100
16
Proposed Apartment Design 4.1 Orthographics Drawing Section 2 - - SCALE 1:100
17
Proposed Apartment Design 4.1 Orthographics Drawing Section 3 - SCALE 1:100
SCALE 1:100
18
Proposed Apartment Design 4.2 Structural Drawings Foundation Layout Plan - SCALE 1:100
SCALE 1:100
19
Proposed Apartment Design 4.2 Structural Drawings First Floor Beam Layout Plan - SCALE 1:100
SCALE 1:100
20
Proposed Apartment Design 4.2 Structural Drawings Second Floor Beam Layout Plan - SCALE 1:100
SCALE 1:100
21
Proposed Apartment Design 4.3 Isometric View
22
IBS Components 5.0 Proposed Apartment’s IBS Features Repetition of Floor-to-Floor Height
Vertical and Horizontal Repetition on Structural Layout
4000 4000 4000
North Elevation
Ground Floor Plan
Maintaining the same height of floor from the ground floor to the top floor of 4000mm.
Structural components are constructed according to a repeated planned layout with vertical and horizontal grid.
Suitability ● ● ●
Modular coordinated Walls panels can be pre-fabricated and reduce on site labor Ease of construction
Suitability ● Allow prefabrication of wall components ● Ease of construction
23
IBS Components 5.0 Proposed Apartment’s IBS Features Precast Concrete Columns
Precast Concrete Beams
Suitability ● Reduce construction cost by having intentional manufacturing ● Flexible in variety of sizing and configuration
Suitability ● Highly potential in producing consistent connections and construction outcome ● Sturdy and dense character limits Connection Detail
Connection Detail Mechanical splice
Precast Concrete Walls
Shim & grout Grout full
Cast-in-place concrete
Butt-weld
Suitability ● Reinforced with steel will make the long span concrete wall more sturdy ● Have load bearing capabilities and act as a stabiliser Connection Detail
Grout to cover recessed connection
Embedded plate
Roughened surface
Loose feld plate
Bolts
Grout to cover recessed connection
Precast beam
Shim & grout Precast column
Loose feld plate
Precast unit
Embedded plate
24
IBS Components 5.0 Proposed Apartment’s IBS Features Precast Concrete Staircase
Standardized Components
W1
W1
W1
W1
W1
W1
W2
W2 D2
W3
D2
D3
D1
D1
D2
D2
S1
W3
D3
W1
W1 D2
W1
Suitability ● Accurate and flexible during prefabrication process in factory ● More efficient erection process
W1
W1
W3
W3
S2
W1
W1
W1
S3
Uses Modular Coordination
Connection Detail Embed Steel Plate Concrete Staircase
Slab Landing
Bolt
D2 D3
D3
Columns Sizes : Multiples of 0.5M
Beams Sizes : Multiples of 0.5M
Windows Width : Multiples of 1M
Doors ( Door leaf opening width) : Multiples of 0.5M
Suitability ● Prefabrication ensure quality control of components ● More efficient and organised construction process ● Contribute to the Industrialised Building System ‘s scoring
25
Modular Components 6.0 Schedule of Modular Components SLAB COMPONENT SCHEDULE
Component Name
Slab SL1
SL2
Roof Slab
Staircase Landing Slab
Thickness (mm)
150
150
150
150
Width (mm)
10,000 mm
10,000 mm
12000
1000
Length (mm)
10,000 mm
10,000 mm
30000
1200
Quantity
3
3
1
8
Isometric
Plan
26
Modular Components 6.0 Schedule of Modular Components COLUMN COMPONENT SCHEDULE
Component Name
Column C1
C2
Thickness (mm)
200
300
Width (mm)
300
200
Length (mm)
4000
4000
Quantity
12
24
Isometric
Plan
27
Modular Components 6.0 Schedule of Modular Components BEAM COMPONENT SCHEDULE
Component Name
Beam Beam 1
Beam 2
Beam 3
Thickness (mm)
350
350
350
Width (mm)
200
200
1200
Length (mm)
10000
10000
10000
Quantity
6
24
6
Isometric
Plan
28
Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE
Component Name
Wall Panels Wall 1
Wall 2
Wall 3
Wall 4
Wall 5
Thickness (mm)
150
150
150
150
150
Width (mm)
9500
3200
4157
1993
9850
Height (mm)
4000
4000
4000
4000
4000
Quantity
4
4
4
4
4
Isometric
Plan
29
Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE
Component Name
Wall Panels Wall 6
Wall 7
Wall 8
Wall 9
Wall 10
Thickness (mm)
150
150
150
150
150
Width (mm)
1993
4157
3200
9850
6775
Height (mm)
4000
4000
4000
4000
4000
Quantity
4
4
4
6
6
Isometric
Plan
30
Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE
Component Name
Wall Panels Wall 11
Wall 12
Wall 13
Wall 14
Wall 15
Thickness (mm)
150
150
150
150
150
Width (mm)
9550
3200
4157
1993
9850
Height (mm)
4000
4000
4000
4000
4000
Quantity
2
2
2
2
2
Isometric
Plan
31
Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE
Component Name
Wall Panels Wall 16
Wall 17
Wall 18
Wall 19
Wall 20
Thickness (mm)
150
150
150
100
100
Width (mm)
1993
4157
3200
2925
2825
Height (mm)
4000
4000
4000
4000
4000
Quantity
2
2
2
12
6
Isometric
Plan
32
Modular Components 6.0 Schedule of Modular Components WALL PANEL COMPONENT SCHEDULE
Component
Wall Panels Balcony Wall 1
Balcony Wall 2
Balcony Wall 3
Balcony Wall4
Balcony Wall 5
Thickness (mm)
150
100
100
100
150
Width (mm)
975
160
3860
1700
975
Height (mm)
1200
1200
1200
1200
1200
Quantity
4
4
4
4
4
Name
Isometric
Plan
33
Modular Components 6.0 Schedule of Modular Components DOOR COMPONENT SCHEDULE
Component Name
Doors Door 1 (D1)
Door 2 (D2)
Door 3 (D3)
Width (mm)
900
800
700
Height (mm)
2100
2100
2100
Specification
Timber Frame/Timber Door
Timber Frame/Timber Door
Timber Frame/Timber Door
Quantity
6 ( 1 per unit)
18 ( 3 per unit)
12 (2 per unit)
Isometric
Plan
34
Modular Components 6.0 Schedule of Modular Components WINDOW COMPONENT SCHEDULE Component
Windows Window 1 (W1)
Window 2 (W2)
Window 3 (W3)
Width (mm)
1400
600
900
Height (mm)
1800
600
1800
Height from floor to window (mm)
900
2000
900
Specification
Aluminium Frame/ Glass
Aluminium Frame / Glass
Aluminium Frame / Glass
Quantity
48 (1 per unit)
12 (2 per unit)
6 (1 per unit)
Isometric
Plan
35
Modular Components 6.0 Schedule of Modular Components STAIRCASE COMPONENT SCHEDULE Component
Straight Staircase with Interlocking Landing
Name
ST 1 & ST 2
Isometric
Plan
Tread (mm)
1400
Riser (mm)
190
Floor to Floor Height
4000
Quantity
12
Specification
Concrete steps (24) / Steel railing
36
Fabrication Process 7.0 Fabrication of Modular Components NORMAL CASTING FABRICATION PROCESS 1.
ASSEMBLY OF MOULD
●
Workers must ensure the level and flatness of the base before assembling mould for panel casting.
●
Next, verify the mold size and dimensions are correct according to the design. Lastly, the workers have to check the squareness of the mould forms. ○ The workers have to check the squareness of the mould forms.
●
2. MOULD CLEANING AND PREPARATION ●
After the assembly of the mould, it must be clean and free from debris and old mortars using remover or scaling bars.
●
Form oil or mould release agent is evenly applied over the mould surfaces.
●
The workers will have to check everything is properly secured such as the joints and edges of the mould, bolts, stoppers, tie rods, side props and rubber seal are undamaged.
37
Fabrication Process 7.0 Fabrication of Modular Components 3. FIXING OF REBARS/ CAST IN ITEMS/ PRESTRESSING STRANDS ●
The workers must check if the measurements of the rebar size, spacing and lap length are in line with the drawings.
●
The rebars, cast-in-items, corrugated sleeve pipes, recesses, lifting hooks and inserts must be accurately positioned and properly connect. With the use of fabrication rig, it can help to make sure the accuracy of rebars fixing and spacing.
●
Only when needed, tack welding may be carried out to secure these items. To achieve the required concrete cover while casting, the workers should properly place and secure the the sufficient number of spacers with the correct sizes.
4. FINAL INSPECTION BEFORE CASTING ●
The workers must check and verify that all details should exactly comply with the drawings.
●
To check the mould fitting conditions including blockout details.
●
To check the base mould level again especially for site precasting since other concurrent site activities may have shifted the mould level.
38
Fabrication Process 7.0 Fabrication of Modular Components 5. CONCRETING
6. CURING
●
The workers must check that the concrete grade used is according to the design specifications and assess the workability of the concrete mix before placing the concrete mould, they must conduct a slump test.
●
After the concrete is poured, the curing process begins. During the curing process, the workers is to observe adequate curing time and desired environment.
●
The drop height of concrete mix should not exceed more than 1m. In more congestion areas, proper vibration and compaction should be carried out.
●
With a controlled environment, it enables the product to properly cure and reach the desired design strength much quicker.
●
Then, spreading and levelling of concrete surface level after initial set.
●
Maintain the required thickness by use of screeder. It is recommended to use power trowel or float to smooth the surface of the finishes.
39
Fabrication Process 7.0 Fabrication of Modular Components 7. DEMOULDING ●
Before demoulding process, cube tests should be conducted to confirm the concrete strengths of elements.
●
From the test, it will ensure the concrete strengths obtained for reinforced precast elements are minimum 10N/mm2.
●
Next, it is required to loosen and remove all bots and pins and side mould forms before lifting.
8. FINAL INSPECTION/ TRANSFER TO STORAGE YARD ●
The workers must check the condition of the finished product and verify again the critical dimensions.
●
Identify all the markings to be placed on the elements showing the location, member type, size, weight and orientation as per shop drawing.
●
Lastly, check the elements have achieved 75% of their design concrete strength before delivery to site for erection.
40
Construction Sequence 8.0 Construction Process of Proposed Apartment
1. Strip foundation footing.
2. Foundation wall from the footing to the foundation slab.
41
Construction Sequence 8.0 Construction Process of Proposed Apartment
3. Connection of precast concrete columns to the strip foundation.
4. Casting of foundation beam
42
Construction Sequence 8.0 Construction Process of Proposed Apartment
5. Installation of precast floor slabs.
6. Installation of first floor beams.
43
Construction Sequence 8.0 Construction Process of Proposed Apartment
7. Installation of precast walls to its specific location.
8. Installation of prefabricated windows, doors and staircase.
44
Construction Sequence 8.0 Construction Process of Proposed Apartment
9. Repeat the sequence of columns, beams, floor slabs, walls, staircase to the first floor.
10. Repeat the sequence of columns, beams, floor slabs, walls, staircase to the second floor.
45
Construction Sequence 8.0 Construction Process of Proposed Apartment
11. Casting of roof beams.
12.Casting of roof slab and finishes with exterior wall painting and interior tile finishing
46
IBS Score 9.0
N0 1.
2.
ELEMENTS
IBS FACTOR
COVERAGE
IBS SCORE
PART 1 : Structural System Precast Concrete Columns and Beams
621.8 m2
1.0
(621.8/998.4)=0.62
0.62 x 1.0 x 50 = 31
Precast Concrete Roof Slabs
376.6 m2
1.0
(376.6/998.4)= 0.38
0.38 x 1.0 x 50 = 19
Total Part 1
998.4 m2
50
PART 2 : Wall Systems Internal Wall : Precast Concrete Panels
420.0 m
1.0
(420.0/700.6)= 0.6
0.6 x 1.0 x 20= 12
External Wall ; Precast Concrete Panels
280.6 m
1.0
(280.6/700.6)= 0.4
0.4 x 1.0 x 20= 8
Total Part 2 3.
AREA (m2) or LENGTH (m)
700.6
20
PART 3 : Other Simplified Construction Solutions i.Standardised Beam Components follow MS 1064
100%
4
ii.Standardised Column Components follow MS 1064
100%
4
iii.Standardised Walls Components follow MS 1064
50%
2
iv.Standardised Slabs Components follow MS 1064
100%
4
v.Standardised Door Components follow MS 1064
100%
4
vi.Standardised Window Components follow MS 1064
100%
4
vii.. Repetition of floor to floor height
100%
2
viii.Vertical Repetition of Structural Floor Layout
100%
2
ix..Horizontal Repetition of Structural Floor Layout
100%
2
xi. Usage of Prefab Staircases
100%
2
Total Part 3
30
IBS SCORE = Part 1 + Part 2 + Part 3
100
47
Conclusion 10.0
With the use of precast concrete system in the construction of the apartment, an industrialized building system are able to achieved with the score of . Design features such as precast columns, beams , walls ; prefabricated staircase ; standardized components ; and repetition on layout has contributed to the high score. These initiatives allows the construction process to be carry out in a shorter time span , while also benefits the economical prospect with the minimized construction cost and low man power requirement. The quality of the structure is also controlled, minimum wastage is produced. Through this project we have learned the knowledge of Industrialised Building System, especially Precast Concrete System that will benefit us in a long period of time during our pursue on Architecture or even on the workfield.
48
TES Evaluation
49
Peer Assessment
50
Reference List
1.
https://civiltoday.com/civil-engineering-materials/concrete/232-advantages-and-disadvantages-of-precas t-concrete
2.
http://rehdainstitute.com/wp-content/uploads/2017/05/4.-Kow-Choong-Ming.pdf
3.
https://theconstructor.org/building/methods-precast-concrete-constructions/26523/
4.
https://theconstructor.org/building/methods-precast-concrete-constructions/26523/
5.
https://www.bca.gov.sg/Publications/BuildabilitySeries/others/bsl_cp4.pdf
6.
https://www.jpconcrete.co.uk/precast-concrete-stairs/
7.
https://www.bca.gov.sg/Professionals/IQUAS/others/precastfabrication.pdf
8.
https://www.matec-conferences.org/articles/matecconf/pdf/2014/01/matecconf_bust2013_01002.pdf
9.
https://www.ukessays.com/essays/construction/the-classification-according-to-structural-system-constr uction-essay.php
10.
http://precast.org/wp-content/uploads/2014/08/Precast-Concrete-Architectural-Connections-Guide.pdf
51