INTRODUCTION

From the main screen of MSP: •Task mode: Shows if it is auto schedule or manually scheduled. •Task name:The name of task or description of the work to be done is to be entered her. •Duration: Time required for activity to be completed. •Start: Start date of the activity. •Finish: Shows the finish date of activity •Predecessor: If activity is dependent on some other activity, i.e: If some activity is required to be done before commencing the current activity than the activity to be done is called predecessor. e.g: CONCRETING is predecessor OF CURING . •Resource name: resource needed for activity is entered in resource name. •Add column: To add other than default column.