336 units 190,600 sq. ft. of commercial space

328 Parking spaces 24,200 Square ft Lobby BUILDING PROGRAM


PARKING GARAGE


MATERIALS


EXTERIOR PERSPECTIVE

EXTERIOR ELEVATION


RENDERING IN SAN DIEGO SKYLINE


FIRST FLOOR SPACE DIAGRAM

RESIDENTIAL FLOOR SPACE DIAGRAM


SUSTAINABILITY


Total Project Cost: $165,822,472 Cost of work: $149,811,222 General Requirements: $16,011,250

Project Duration: 36 Months

CONSTRUCTION COST ESTIMATE & SCHEDULE


CONSTRUCTION SITE LOGISTICS