REPORTPRACTICUM Submitted To: Department Of Architecture Kathmandu Engineering College Kalimati, Kathmandu YOJANA ACHARYA 75048“One of the great beauties of architecture is that each time, it is like life starting all over again.” – Renzo Piano
1
ABSTRACT
-Zaha Hadid
“Architecture is like writing. You have to edit it over and over so it looks effortless.”
Acording to the syllabus of IV/I prescribed by Tribhuwan University, students of architecture are required to work in an arcitectural firm for atleast 90 days (14 weeks). This period is termed as Practicum.
Its is a specialized field of study, that is designed to provide supervised practical application of a previously studied theory. One should learn under the supervision of practicing architects as an apprentice architect regarding the office management, project handling, bye laws, client dealings, site works etc.
ABSTRACT
A practicum report is an explanation of what one has done during practicum and their outcome. As per the requirement of the course, I Yojana Acharya engaged myself as an trainee architect under an architectural firm ArchSolar Designs.
During this period, I was involved in various projects as well as site visits. This report contains all the works assigned and completed by me during the practicum.
Creative ideas and design works are only fulfilled when it goes for construction and is completed on the given site. so the course is designed in a view to develop the overall ability of a student and experience the realistic side of the profession.
2
3
“Architecture is like writing. You have to edit it over and over so it looks effortless.”
-Zaha Hadid
ACKNOWLEDGEMENT
I am greatly indebted to Ar. Subash Phuyal, under whose supervision I was able to complete my training.
For this, the whole credit goes to Ar. Shreejay Tuladhar and Ar.Arunima dev, principal architects who have let me to work in this office. My special thanks goes to Ar. Lunibha Manandhar and Ar. Aakritie Karki who throughout my practicum period gave me invaluable suggestions and helped me learn a lot. They have been a really wonderful guide who have always tried their best in every possible way to help me to be more competent and practical.
I heartily express my sincere gratitude to the Department of Architecture of KEC for the inception of practicum which has exposed many going-to-be architects like me to the professional field and thus, boosted our confidence. and be aware about our responsibilty as an architect in days ahead.
I am sure the experience, knowledge, vision and vitality that I gained in this office will always remain with me and will serve as a milestone in the development of my career as an architect.
ACKNOWLEDGEMENTThereportsummarizesthepracticalknowledgeIgained,experiencedandtheprojectsIgotinvolvedduringmyinternshipperiodatArchSolarDesign,Kathmanduforover90dayswiththecontinuousguidanceandsupport of the individuals and the firm. Its privilege for me that I got an opportunity to work in ArchSolar Design as a trainee architect.
4
Designingpriate.
Architecture being a distinct academic discipline, extends beyond the bound of theoretical knowledge. One involved in any field can only attain a better understanding of the field, once they have completely gone through it practically. It is easier for one to attain a better grasp of the knowledge through prac tice than through the use of books. Similarly, in architecture, though thetheoretical knowledge goes into the in depth analysis, it cannot be completely fulfilled until and unless the theoretical knowledge is practiced in the practical field. Hence, practicum is a platform where we get an opportunity to be involved in the practical world of architecture, where the designs and drawings that we prepare on paper comes to be concretized on the ground of reality.
This practicum course in B.Arch. IV/I curriculum is intended to endow the students of architecture with a base for using their theoretical knowledge that they gained during their class hours which helps them to work more efficiently with self confidence in the future, with their own ability when they put their step in the actual pro fessional architectural world. During the design projects in class, we just put our imaginative ideas into the design consideration regardless of any constructional restrains, economy and many other things. But in practicality, they might be infeasible. In the class projects, we, ourselves being the virtual clients, design according to our wish. But when we design in the real life,the design is for the client, meaning his decision proves to be the most, which we have to trail up. So, most of the times, we have to compromis in our ideas. This practicum teaches us how to interact with the clients and how to convince them if their stipulate isn’t feasible and appro -
on paper is an easy task, but during the process of concretizing them, many problems maybe raised which we aren’t conscious of until it is confronted in the real practice. Hence, practicum proves to be beneficial in the exposure of those factual problems and helps us to experience the design by ourselves. In architectural field, along with the architects, many other allied professionals are involved in the creation of any built spaces. Practicum teaches us the team spirit to work in coordination with those personals. Moreover, the ethical norms like the essence of endeavor, commitment and enthusiasm in our work, are all learnt during the internship period.
Introduction
5 INTRODUCTION
Objective of practicum
To understand the range of field up to which and architectural firm should deal with the project.
07060504030201
To adapt to the corporate world and learning the rules and regulations of the business.
6 OBJECTIVE
To further develop research skill, personal skill and communication skill.
To gain an opportunity to be familiar with the professional field while utilizing the academic knowledge gained in previous semesters and consolidate their knowledge.
The objective of this practicum is to acquaint us with the various architectural and other issues. The institute provide us ac quaintance with the theoretical aspect of architecture. But this does not build the architect to cope with the practical circumstances. It is necessary for every architect to gain knowledge of professional life, which is gained through practicum. The practicum session has been planned with the following objectives:
To work under the supervisiom of senior architects and learn from their experience and design idealogies.
To compare and contrast between academic teachings and professional life.
To know the general concept of working method of an architectural firm.
ECIFFO ELIFORP
In this context, the essence of every project, be functionality, aesthetics, society, heritage or economy, identified and served accordingy.The projects at ARCHSOLAR range from scale luxury hotels to small interior spaces, each with it’s own personality. The variation in design requirements renders each project with its own unique spirit.There is no hierarchal inequality in the offce although I was a trainee in the office. This made the communication and team work better. I felt like I had equal participation in every project as my senior architects.
7 OFFICE PROFILE
Architectural / Sustainability/ Green Building Consultant/ Renovation/ Interior Design JORPATI, KATHMANDU
ARCHSOLAR?WHY
I have been updated with ARCHSOLAR since a year. Their type of project and quality of work had been captivating me since then. Also my keen interest has always been towards hospi tality because of their rich and luxury architecture whether exterior or interior. Similarly, the qualification of principal architects are praiseworthy.
design is established by Ar. Shreejay Tuladhar and Ar. Arunima Dev with the years of independent practice. Ar. Shreejay Tuladhar is a Havard Graduate who has worked in Page WSoutherland, USA that comes under top 22 architecture firm of the world. Ar. Arunima Dev has been In-house architect of Hyatt Regency, Nepal for 4 years. Their accomplished experience in architecture field has given emphasis to research and design.
At archsolar, every project is treated as a creative variance of functionality and beauty, where multiple possiblities are taken into consideration to create a per fect harmony between two. Every project is treated not only as another mass, but as an opportunity to explore the effective transformation and aesthetic aspects of the environment and as a potential benefactor of the society. Although clients tend to approach designers for primarily spatial purposes, th project at ARCHSOLAR strive to provide an enrchment in the user’s experience of not only the space but also al the aspects related to it.
ARCHSOLAR DESIGN
When I was called for the trainee interview, I was asked alot of architecture related and detailed question. They explained me about their projects and working environment which I thought would be suitable for me to work. I joined the office on 6th of Baisakh. I completed 97 days working days as a trainee architect. Ever since then, my experience in practical field of architecture has been knowledgeable and fruitful.
Archsolar
8 ArchSolar Designs tants*And-Er.Civil-Ar.-Ar.Architects-Ar.-Ar.FounderEstd:Jorpati,Location:Kathmandu2020membersShreejayTuladharArunimaDevLunibhaManandharAakritiKarkiEngineerSwornimaDevvarioussubconsulinIndiaandNepal07060504030201 REQUIREMENTSCONCEPTUALPLANNING & CONCEPTUAL 3D OFFICE SOURCESCLIENTPROPOSALMEETING&INITIAL CLIENT MEETING CHANGES, OPTION & FINALIZATION SITE ANALYSIS 14131211100908 STRUCTURAL ANALYSIS BOQ AND SPECIFICATION WORKING DETAILEDIMPLEMENTATIONDRAWINGPLANAND DETAILED 3D SITE SUPERVISION AND SITE VISIT MUNICIPAL SETWOLFKROWECIFFO OFFICE PROFILE
9 TABlE OF CONTENT CONTENTS11HYATTINCUBATIONYATRIRADISSONREGENCYNIWASTVSSHOWROOMBACKPACKERHOSTELCENTER4743335561
10 TABLE OF CONTENT 65 JORPATI APARTMENT 103 BASBARI RESIDENCE 75 BIHAR FARMHOUSE 83 BALWATAR RESIDENCE 89 GAIRIDHARA RESIDENCE 93 NAXAL RESIDENCE 93 NAKHIPOT RESIDENCE
1. HYATT REGENCY HOTELS 2. RADISSON 3. YATRI NIWAS
-planPlanning of offices - 3D development
Client: Hyatt Regency
- Design
Project Requirement of existing offices gym block banquet
Project type: Hotel
My Involvement: drafted of gym block of banquet
- Rennovation
Project status: Conceptual
du near Boudhanath Stupa. It is situated in a city with a plethora of ancient sites and fascinating architecture. It is set on 37 acres of landscape grounds. The building style is a traditional style of newari architecture. It came to operation on 31 August, 2000.
- New
-officesDesign of
is the biggest luxury 5 star hotel in the country. It is located in Taragaon,Kathman
and 3D development -Site Modeling for presentation INVOLVED PROJECTS FIG: SITE PLAN
- New HbakeryyattRegency
- New
HYATT REGENCY
Location: Taragon, Kathmandu
- Site measurement of existing office and
11 HYATT REGENCY
The need of squezing office spaces was felt as new studio meeting room would lead to profit for the
The objective for renovation is to create an open planned offices and to provide space for studio meeting room.
FIG: PROVIDED EXISTING PLAN
1. Offices
Concept for planning
EXECUTIVE OFFICE
Forhotel.this new planning was done such that there is minimum partition and all the partition used were glass to avoid narrow corridor.
LEGENDS
The first option was presented to the client where around 50% of the space was separat ed for studio meeting room and rest of the spaces were divided as office space. The planning is done according to their major function. The corporate is separated from executive section. STUDIO
FIG: OPTION 1 PLAN
12 HYATT REGENCY
CIRCULATIONW/CHCAVELECTRICALCORPORATEMEETINGMEETINGSECTIONANDFAFROOM
Software used
NOTE: REFER TO ANNEX
The existing office layout was planned when hotel was first built and hasnot been updated since then. Hyatt offices is divided into two parts corpo rate and executive. All the office member are provided with separate rooms parted with gypsum partition which makes the space conjusted and dark since there is no window and only vetilation is provided by central hvac system.
13 HYATT REGENCY
After the first option was presented to the client, he wanted some changes. He demanded separate meeting rooms for corporate and executive sec tion. Also, separate pantry w/c was provided for Owner and VP in option 2.
LEGENDS
NOTE: REFER TO ANNEX
EXECUTIVE OFFICE STUDIO CIRCULATIONW/CHCAVELECTRICALCORPORATEMEETINGMEETINGSECANDFAFROOM
Then, the client felt like the entrace space which was used as waiting lobby was kept wasted. So, he demanded a separate meeting room there and the previous meeting room was changed to account section. Hence, more staff were able to adjust.
For the final plan, the client demanded a phone booth in the entrance section with some cabin seating space.
FIG: OPTION 2 PLAN
The UPS room was made small and accountant section was added facing towards corridor.
FIG: FINAL OPTION
FIG: OPTION 3 PLAN
14 HYATT REGENCY officevpofficeowner officedof officefinAnce recepTion wMALe/c wfeMALe/c rooeLecTricALM eXecUTive officeS cooperATe officeS MeeTinG rooM MeeTinG rooM officeGM pAnTrY w/cenTrY enTrY Final office plan
FABRIC PRIVACYPROVIDEDPANELFOR
OPTION 4 OPTION 5
OPTION 2
OPTION 1
PARTITION USED AS WITH STORAGE UNIT
SEATING WITH DOUBLE STORAGE
OPTION 3
15 HYATT REGENCY Conceptual Furniture Design
CLOTH TO BE USED AS PIN BOARD STORAGE UNIT WITH WHEEL FOR EASY MOVE MENT WITH CUSHION ON TOP THAT CAN BE USED AS SEATING
SEATING WITH SINGLE STORAGE
STORAGE FORVELVETFILE
EXISTING OFFICE FURNITURE USED AS REFRENCE FOR DIMENSION AND DESIGN
The device takes air from the outdoors, cleans and conditions it, and heats or cools it as needed. Once properly conditioned, the air is forced through ductwork inside the rooms of the building.
VICECHANGES
Air handling unit (AHU) is used to condition and distribute fresh air throughout the building. An AHU is part of the larg er HVAC system (heating, ventilating, and air conditioning).
Units (FAHU) which regulate and circulate fresh air as part of a heating, ventilating, and air-conditioning (HVAC) system.
SITE MEASURED USING LASOR DE
FAHU gives an output of a constant volume of fresh & cleaned air.
DONE DURING CLIENT MEETING
During site visit to hyatt I got chance to see dif ferent hvac system machines and its function. I also got chance to see earth air tunnel system, FAHU (Fresh Air Handeling Unit) and AHU (Air Handeling FreshUnit).AirHandling
16 HYATT REGENCY Site Visit
EXPOSED DUCTS RUNNING THROUGH OFFICE CORRIDOR
2.layoutHorizontal wooden baffle ceiling 75*100mm running through corridor with light running through
Ceiling Plan 1.
3.themFloating
Reflected 600*600 BAFFLE CEILING
Hyatt Offices have very low and varring height due to ducts of hotel running through the office ceilling. I was assigned to design reflected ceiling plan under the guidance of Principal Architect Ar. Arunima Dev maam. The false ceiling was kept as simple as possible with three major design element:
3. FLOATING
PANEL 2. 75*100 WOODEN
17 HYATT REGENCY
1. 600*600 prefab panel for open planned office
FIG: FINAL REFLECTED CEILING PLAN
Ceilling in head officers offices and meet ing room
I was also assigned to include sprinkler and fire detector in the plan. For this I researched and found the radius of them as:
DETAIL REFLECTED CEILING PLAN
2. Smoke detector= 7.5m
18 HYATT REGENCY
1. Sprinkler= 2.4m
NOTE: REFER TO ANNEX
Research Done
SPRINKLERSMOKEDETECTOR
FIG: SECTION AT A-A
DETAIL DRAWING IN ANNEX
FIG: OWNER OFFICE
FIG: VP OFFICE WITH HIDDEN CABINET ROOM
19 HYATT REGENCY Office 3D
- 3D visualization of overall office area was done using sketchup and enscape which helped me to improve my 3d skills.
FIG: EXISTING OFFICES
FIG: TOP VIEW OF OVER ALL 3D MODEL OF OFFICE
GYPSUMdesign).PARTITION
- Glass partition was used instead of gypsum partition like in exist ing offices.
- Ceilling designed such that it guides visitor to different part of office(wooden baffle
FIG: EXECUTIVE MEETING ROOM
FIG: FINANCE OFFICE
FIG: OPEN SEATING SPACE IN CORPORATE PART OF OFFICE
FIG: CORPORATE MEETING ROOM
20 HYATT REGENCY
When I joined office phase1 of gym planning was going on, the building foot print and site selection was already done.
of hotels should be upto date with current demand of the users for better hospitality experience. Existing gym of hyatt is small and client wanted to upgrade it with minimum investment.
The planning of gym was done in different phases as per change in client requirements.
FIG: OPTION 1 FIG: OPTION 2 GYM BLOCK 3D BY AR. SHREEJAY TULADHAR
21 HYATT REGENCY 2. GYM
Phase 1
I was involved in designing plan in the finalized building foot print.
Gym
CONCEPTUAL DEVELOPMENT
EXISTING GYM
22 HYATT REGENCY
The planning of gym was done by aligning it’s shape with the contour line of existing site. It had to be placed in such a way that it would create a visual connection with the existing gym and is easy accessible form existing staircase.
During phase 2 I was involved in over all design development of the gym block. With guidance of Ar.Lunibha Manandhar I was able to complete the conceptual development of gym block.
Conceptual Planning
Development of Building foot
In second option dogleg staircase was provided which created separationtheof entry way for male and female unlike in option 1.
Phase 2
In first option straight flight staircase was provided so as to go to gym from ground floor which had sau na, steam and jacuzi.
After presentation there was changes in client -Relocationrequirementsof gym block
OPTIONOPTION12
EXISTING STAIRCASE
Updated Requirement
-Addition of sauna, steam and kids recreation space.
Rectangular block with zen garden as per the shape of contour
Block with curve fornt facade
EXISTING ZEN GARDEN
GARDEN?ZEN
Zen Gardens may contain elements of water, trees, stone, sand, plants, moss, gravel, grass, and bushes – although a Zen Garden can be as simple as one stone in a square of sand.
23 HYATT REGENCY
Zen Gardens are miniature landscapes composed of natural elements and arranged in such a way that reflects the essence of the natural world.
Phase 3
After consultation with principal architect gym footprint was further changed and two option were designed.
24 HYATT REGENCY
3. Difference between wet zone and dry zone; dry zone includes steam, sauna, jacuzzi while wet zone includes washroom, shower, urinal and basin.
FIG: OPTION 1 GROUND FLOOR
FIG:
FIG: OPTION 2 FIRST FLOOR
Designing
drop to be provided; for people to dispose towel after use.
CONCEPTUAL PLANNING
4. Store should be in close proximity to the recep 5.tion.Towel
FIG: OPTION 1 FIRST FLOOR OPTION 2 GROUND FLOOR
for hotel gym there were few point to be considered :
of vestiblue and double door sys tem. If two doors are provided it ensures privacy for the people inside.
1.Entrance for male and female must be clear and apart from each other so that no one gets con2.fused.Importance
Acess from hotel building(indoor)
Acess from existing staircase landing (outdoor)
NOTE: REFER TO ANNEX
25 HYATT REGENCY OFRACK DUMBELL13 44444 TRADE MILL TRADE MILL TRADE MILL TRADE MILL TRADE MILL PEAK RECUTING BIKE2 33 CROSS TRAINER CROSS TRAINER 5 CYCLE CROSSCABLE7 MACHINESMITH8 CHEST PRESS109 11 LEG CURL EXTENSION LEG PRESS LAT PULLDOWN612 MULTI BENCH12 MULTI BENCH PLAN DEVELOPMENT FIG: OPTION 1 GROUND FLOOR FIG: OPTION 1 FIRST FLOOR
26 HYATT REGENCY
When the design was presented client liked both the options, but after long discussion option 2 was finalized.
West facing?
The finalized plan is west facing, front facade of the building is fully glazed on addition to being west facing. This was one of the biggest problem faced during the designing of gym block.
PLAN DEVELOPMENT
27 HYATT REGENCY
To encounter this problem large overhang roof was proposed which compli mented the built structure.
Calculation of the overhang length was done by Ar. Shreejay Tuladhar by doing glare analysis.
FIG: OPTION 2 GROUND FLOOR
Option 2 since was simple to construct it would cost much less than the option 1 i.e, it is easier to find straight glass for facade treatment at low cost than for the curved facade i.e, customized curved glass.
NOTE: REFER TO ANNEX
Approved Design
28 HYATT REGENCY
CONCEPTUAL PLANNING COURTTENNISKITCHENFUNCTIONPRE DOCKLOADING STORAGE303.45m2 47.87m2GROUND567m2FLOOR PLANSERVICESTATION37.39m2 BANQUET525.47m21 525.47m2BANQUET237.83m2FEMALETOILETMALETOILETVANITY37.18m2HCTOILET 28462.71 10661.62 46500.00 51927.82 40000.00 13500.00 20000.00 26273.82 20000.00 26273.82 3000.00 4500.00 10037.03 4647.7412161.62 6013.89 7997.54 1500.00 2000.00 4500.00 1500.00 1500.00 1200.00 1300.00 3000.00 10661.62 8263.46 12612.93 2397.43 4500.00 13500.00 6500.00 10000 3500 3500.00 3000 FIG: GROUND FLOOR PLAN LAwn
When I joined office phase2 of banquet plan ning was going on, the building foot print and site selection was already done. I was involved in designing plan which encountered the changes concluded form phase1.
Prefunction area is where people first gather and food is served. Here there is lawn at the en trace of banquet which can be used as outdoor prefunction area.
1. PRE FUNCTION AREA 2. CIRCULATION 3. TOILET 4. SATELLITE KITCHEN 5. BANQUET HALL 6. ROAD NOTE: REFER TO ANNEX
29 HYATT REGENCY 3. BANQUET Concept for the banquet design was to create a hall with long span structure made of prefabricated material with modern look.
1. void 2. circULATion 3. ToiLeT 4. Green rooM 5. SpAce for HvAc MAcHineS
30 HYATT REGENCY BANQUET1 BANQUET2 COURTTENNIS555.47m2FUNCTIONPRE 555.47m2FIRST567m2FLOOR PLAN VOID 1500.00 1000.00 FEMALEGREENMALEROOMGREEN60m2ROOM50m210000.00 10000.00 4508.74 6000.00 3500.00 3500.00 Kitchen?Satellite
Satellite kitchen is a food service establishment where food is stored, prepared, portioned or packaged for service else where. It is different from the central kitchen as it is created to specifically cater to 1 outlet when the central kitchen cannot do so due to geographical disadvantages. While a central kitchen is created to cater to all the outlets of the restaurant within the serviceable region.
Front facade was designed to be of glass so there is space left between facade and staircase so as not to distrub the clean modern look.
BANQUET 3D
FIG: FRONT FACADE
REGENCY
HYATT
FIG: VIEW FROM ROAD
FIG: BIRD EYE VIEW OF OVER ALL SITE
31
SITE MODELING
FIG: VIEW FROM SWIMMING POOL
DIFFERENT TYPES OF HVAC AND FAHU SYSTEM
32 HYATT REGENCY
IDEA ABOUT LUXURY HOTELS
060504030201
Hyatt was the first project I did when I joined the firm. I learnt a alot of things while working on the project. Many site visits were done where I learnt about different architectural things of a hotel. It’s space planning, function, materials, etc.
MORE UNDERSTANDING TOWARDS CLIENT’S OPINION
SPACE PLANING OF OFFICE, BANQUET AND GYM
LEARNINGS
I also learnt about spaces planning of a gym, banquet and office.
LEARNED ABOUT ZEN GARDEN
During site visit, I visit the service room and learnt about its working process and necessaity in a pub lic Interiorbuilding.3Ds
IMPROVEMENT IN USE OF SOFTWARE
also helped me to explore more of my software skills.
Project status: Construction
- Terrace Bar, Garden renovation to create modern minimalistic asthetic - Outdoor Seating Design - Addition Of Washroom Project
Radisson
is the biggest luxury 5 star hotel in the country. It is located in Lazimpat, Kathmandu. Radisson Hotel Kathmandu provides upscale accommodations and places guests near corporate offices, embassies, and popular attractions like the lively and buzzing entertainment district-Thamel, Narayanhiti Palace Museum, and historical Kathmandu Durbar Square. It came to operation in the year 1998.Radisson Hotels is an international hotel-chain headquartered in the United States.
RADISSON
Project type: Hotel
My Involvement: - Design of Seating Hall - Pergola Detailing - Bar Detailing - Washroom Detailing and updated 3d -Site Supervision and Cordination
TERRACE Requirement:
1. TOILET 2. TERRACE GARDEN INVOLVED PROJECTS
RADISSON33
Client: Location:RadissonLazimpat, Kathmandu
RADISSON
SECTION
RD-BAR B RD-BAR B RD-BARA AA 4525 450 4975 4295 100 450 50 700 50 700 50 700 50 700 50 700 50 700 50 700 50 700 50 700 50100 75 505 P2 CEILING PLAN 7350 CEILING PLAN NOTE: REFER TO ANNEX
Roofing material CGI sheet with tile sel. finish. 19 mm Cement Board Ceiling 50X100 mm Rafters 45050700507005070050700507005070050700507005070050 100 7350 40 220 40 300 34
1. Pergola Detailing
Software used AT B-B
Outddor Seating with toughen glass used as covering was the approved design. The tough ened glass would cost much high and time to be imported would be more because of recent changes in government policy.
So, CGI sheets was used instead of the toughened glass. Ceraboard was used to cover the purlin and CGI sheet for clean look.
When I joined the firm this project was on construction phase and I was given task to solve the site problem and give proper solutions to site Mostchanges.ofthe changes was because of government stopping import of material which caused price hike of materials and the estimated cost happened to be more than periviously published BOQ. So, alternate options were done with out compromising the final output of the project.
Site Changes
RADISSON35
36
4’x8’CeraboardDrainageMetalChanelRADISSON
Skeleton Details Of Pergola
Cera board??
Post and strut connection
form (EPE) roll
ExpandedPurlinPolyethylene
Cera board is used because it can resist the heat produced by CGI sheet and is a rigid, self supporting and insulating product and it also has good resistance to physical damage.
I learned about the use of back splash on the counter top of basin. A backsplash is a section of material added onto the wall behind a sink or a counter, usually in a kitchen. Tiles are one of the most common types of backsplash materials. The main purpose backsplashes is to provide an easy-to-clean surface so that messes or splashes.
RADISSON37
An angle bracket or angle brace or angle cleat is an L-shaped fastener used to join two parts generally at a 90 degree angle. The metallic angle brackets feature holes in them for screws. Its typical use is to join a wooden shelf to a wall or to join two furniture parts together.
ELEVATION OF MALE TOILET
2.
Washroom Construction Detailing
Radisson washroom was addition to the existing site condition. There was voild before which was covered and hence bought to existing entrance floor level. Previously provided plan was not com patible because of many reason mainly due to space specified for drainage pipe to pass. So, there was change in plan and I was assigned to do detailing of new plan .
RADISSON38 Render Elevation Of Male Toilet
IN
RADISSON39 2. Washroom Construction Detailing HOT WATER PIPE FOR COLD WATER PIPE OR SINK COLD WATER PIPE FOR FLUSH WASTE PIPE SOIL DifferentPIPE phases of constructionCOLDWATER PIPE FOR HANDHELD
SOIL PIPE
Option 3
For third option I designed 4 niche on the longer side of wall and single niche on shoter side with downlight. Niches wouldnt create the visual obstruction and the construction cost wouldnot be affected.
For second option I replaced the painting from option 1 and used wall paper instead as client wanted cheaper option.
Coffer was given through out the seating area hall to avoid visual obstruction.
Previously approved design had to be changed because client now wanted to use the bar seating area to be also rented out as event hall.
Option 2
Problem Identification
RADISSON40
In this design coffer was given as per seating arrangements, since seating arrangement was changed the coffer now created visual divisions.
Option 1
3.Seating Area Design
RADISSON41 DIFFERENT PHASES OF CONSTRUCTION 200 Wall niches to be sel.finish 165 50 3352 200 200mm false ceiling level. 125 mm brick wall to be added 125 mm brick wall 200 mmx275 mm cornice 200 275 75 165 mmx75 mm board to be sel.finish led lights 1560 125 mm brick wall to be added 125 mm brick wall Skirting to be sel. stone finish. 3152 125 875 75 1560 75 442 165 mmx 75 mm board to be sel.finish F.L.
RADISSON420504030201 SiteImportanceCoordinationofdetail drawing Material Constructioncode procedure Different materials used LEARNINGS CONSTRUCTION OF PERGOLA
Project type: Hotel Project status: Construction Phase
YATRI NIWAS
- Detail of bar
Yatri
- Rennovation of old wing - New wing addition - Banquet design
Project Requirement:
My Involvement:
43 YATRI NIWAS
- Drafted elevation from given plan
SITE PLAN INVOLVED PROJECTS
Client: Yatri Niwas Location: Janakpur
Niwas is the brand franchise of The Soltee, Kthmandu. Design of a new four-star hotel. It includes renovation of existing block of 30 rooms along with addition of a new wing with 30 rooms. It is located in Janakpur, Nepal. It is designed in traditional mithila architecture to blend with the site. Dome structure on the roof is designed with traditional arches on the wall. The color choosen for the building is also similar to the mithila style architecture. Yet, it is simple and less ornamentation is used on the facade designing.
are chamfered at 45 degree usually There6mm. are different effect of different types of lighting.
NOTE: REFER TO ANNEX
44 YATRI NIWAS
Bar counter workspace should be hidden from front Marblecounter.edges
45 YATRI NIWASNOTE: REFER TO ANNEX
46 YATRI NIWAS LEARNINGS 030201 LEARNT ABOUT Bar Details LEARNT ABOUT MATERIAL CODE FIG: FRONT ELEVATION OF NEW WING FIG: BACK ELEVATION OF NEW WING DIFFERENT TYPES OF LIGHTING 04 MATERIALS USED IN ELEVATION TREATMENT I was assigned to draft elevation from given plan by the firm for municipal set.
1. INCUBATION CENTER 2. TVS SHOWROOM 3. BACK PAKER HOSTEL COMMERCIAL
-Uselanguageofcustom made and multiuse furniture
centre is a workspace created to offer startups and new ventures access to the resourc es they need, all under one roof. In addition to a desk or office, incubators often provide resident companies with access to expert advisors, men tors, administrative support, office equipment, training, and/or potential investors. These are centres where transitory and facilitative assistance is given to small enterprises or start-ups.
Incubation
Project type: Commercial Project status: Construction My Involvement:
-To create three classroom for teaching Japanese
-Site measurement and measured drawing
-Create a co-working space
-BOQ-Client-PlanningMeeting
Project Requirement:
Location: Anamnagar, Kathmandu
47 INCUBATION CENTRE
FIG: AFTER CONSTRUCTION
FIG: EXISTING SPACE
-Case study at KMC Idea Studio
incubation centre
Client: Dr. Tshering Lama
Studio provides encouragement, resources, space, exposure, learning, networking, and investment opportunities for socially conscious business ideas. It acts as a platform to turn promising ideas into business igniting social change and unlocking young potentials. A team of experienced profes sionals helps startups bootstrap during its early stages and often provides mentoring, guidance, co-working space and also at times some funding.
THAT ACT AS RECEPTION AND CAN BE USED AS WORKING DESK
ENTRYDESK
HEXAGONAL SEATING AREA AT LOUNGE
FURNITURE DESIGNED WITH INTRESTING STORAGE UNITS AND PLANTER AREA
Incubation centre is the project that was given to me from conceptual phase. As this project was new for me principal architects of the firm encouraged me to study about if before starting planning. Since I new Idea Studio existed in KMC I went there for case study to boarden the knowledge about the project.
CABINET IN LOGO DESIGN
FIG: LOGO OF KMC
-Interestingfurniturelounge area
48 INCUBATION CENTRE
-Multi use
-Multi purpose meeting hall and coworking spaces
-Open planning
1. Case Study at Kathmandu
Model College Idea studio
FIG: ENTRY AREA OF IDEA STUDIO KMC
Concept for planning
Software used
DIFFERENT MATERIALS
FIG: BAR LIKE SEATING SPACE
FIG: STORAGE UNDER SEATING
FIG: SEATING SPACE ON ONE SIDE OF PARTION WALL
FIG: DOWN LIGHT CREATING INTERESTING SHADOW
INCUBATION49 CENTRE
FOR WRITING NOTES FIG:
ON SEATING
FIG: USE OF ON WALL CHARGING PORT
FIG: COWORKING SPACE
FIG: CABINET
50 INCUBATION CENTRE
FIG: DEATTACHABLE TABLE
After visit to Idea studio my vision about the project became clear. From material to be used to different multi use spaces and furniture I learned many things that I have encoporated while planing the new incubation center.
D
The final plan was chosen after various changes
THIRD FLOOR PLAN
-Oppostitesustainable.toIcafethere
-Open lobby is provided after entry in fourth floor, this space will act as break-out-zone when students leave class.
LEGENDSCOWORKINGSITTINGCLASROOMBARPODAREAPRIVATECABINMEETINGROOM
-Private cabin are provided for finance team of the incubation
-Twocentre.pods spaces are created as a private cabin for private meeting. -It can also be used as smoking zone.
INCUBATIONNOTE:CENTREREFERTO ANNEX
-Two classrooms and one meeting room are provided as per the requirement. ICAFEWAITING
Fourth Floor
FOURTH FLOOR PLAN
Third Floor
- Near the entrace, there is Icafe which also serves the purpose of reception. This space contains bakery items, microwave, freeze for storage, coffee ma chine, etc which van be used by visitors and people using coworking space hence can be rented to make the centre self
A B C C C D D G ECABD F GF
is two step seating space like amphithreater where visitor can wait or people can work seating there also this space can be used as meeting area too. The two step seating shall include storage self within them.
51
52 INCUBATION CENTRE 1236 mm X 100 mm X 125 mm Furniture Design 1. Light box 2. Workstation 1050 mm X 600 mm X 750 mm 3. Classroom Table Type A: 1200 mm X 450 mm X 750 mm Type B : 600 mm X 450 mm X 750 mm
FIG: TWO STEP STEATING SPACE WITH CABINET
FIG:CABINS MADE OF GYPSUM PARTITION FIG: CLASSROOM
FIG: VIEW FROM ENTRANCE (ICAFE ON RIGHT)
FIG: CLASS ROOM
INCUBATION53 CENTRE 3D VIEWS
FIG: COWORKING AREA
FOURTH
FLOOR -ONGOING CONSTRUCTION
FIG: FOURTH FLOOR VIEW FROM EN
3D BY AR. SHREEJAY TULADHAR
4'-2" X 2" X 4" Hanging vase above the work stations Nos. 4.00
Ottoman chair Nos. 2.00
5 Bakery Overhead Cabinet Sqft 10.00
6 Amphitheatre Seating Sqft 80.75
Total= NPR
NOTE: REFER TO ANNEX
5 Wall Putty on the Walls
Sqft 3,256.54
7 Painting Work(Premium emulsion) Sqft 6,333.54
54 INCUBATION CENTRE
Sqft 3,156.00
2 Table
3 Chair
Café area bar chair Nos. Sofa for Pod Nos. 4.00
LEARNINGS
-Knowledge about rate of different materials. -Importance of BOQ for startup of a project
Sqft 678.27
Total Cost - NPR
ESTIMATION OF QUANTITIES
B Carpentary and Furniture Works
Knowledge about multi use furniture
Knowledge about estimation procedure
Learned about concept of incubation centre
Classroom Chair Nos. 94.00
Use of color pop technique
-Estimation of different quatities of materials through plan and internal elevation. -Learnt about BOQ format.
04020103
1 Terrazo flooring
Sqft 432.52
7 Locker Sqft 36.00
8 Ply Boaxing and Cladding with Sunmica(Seating Pod) Sqft 96.03
Map of Nepal Table Nos. 1.00
A. Civil Work
Workstation Table Sqft 208.00
C AC Work as Per Thumb Rule Ton - - NPR
9 Plywood box for Tube light Nos. 50.00
Workstation Chair Nos. 21.00 bar/ high seating chair Nos. 11.00
4 POP on the Ceiling Sqft 4,077.00
1 Sliding Folding Partition
D Electrical System(10% of Civil Cost(3600*3000)) Sqft 3,600.00 NPR
2 Dry wall Partition with Double Layer Cement and Gypsum Board
Yet to be decided
4 Bakery Display Counter Sqft 40.33
3 12mm Toughen Glass Partition Sqft 441.72
Pod table Sqft 10.00
Raised bar area Table Sqft 22.88
Classroom Table Sqft 292.00
S.N Description Unit Quantity Rate Amount Remarks
Project status: Conceptual
TVS
Location: Lazimpat, Kathmandu
Project Requirement:
TVS55SHOWROOM
My Involvement:
-3D of -SignageshowroomDesign
TVS SHOWROOM
Client: Mr. Sirohiya
Project type: Commercial
-Study of TVS facade and signage
ZSpAceoninG
-Rennovation Of Existing building ground floor into a showroom
Brand is a well-established in brand Two-Wheeler industry in Nepal. Both motorcycles and scooter of these brand are widely popular among public of Nepal with TVS RTR being the flag ship model. The brand has gained popularity in terms of good power and pick up motorcycle with sporty looks appealing to youths and middle aged alike. The company occupies 5th largest market share in Nepal.
-White ACP with Stalin to be place in the center and Blue & Red band on either side
-Width of the main road which influence the view ing
10. Plinth, steps and ramp cladded with Granite
1. Dealer name :
8. Entrance portal: Printed Vinyl on WhiteACP
6. Horizontal“I” section painted in DarkGrey
1. Learnt Guideline:
9. Toughened glass: 12mm thick
“I” section painted in Dark Grey
-Cleardistancevisibility of signage from a distance
White acrylic backlit letter inserted from 3.2.backsideBlueACPRedacrylic strip, backlit LED lights
2. Materials Used on the frontage of showroom.
3. Installation of toughened glass(12 mm) as fra meless glass.
56 TVS SHOWROOM
Study from TVS showroomguide lines
4. White ACP clip-on board housing TVS & Horse
7. Entrance canopy in WhiteACP
5.logoVertical
TO LEDGE
Facade Design
After studing the guidelines I did the 3d according to it. Glass facade is used as elevation treatment. For the glass facade I studied about different types of glass facade and did the 3D and wall section with guidance of principal architects.
FRAMLESS GLASS MOUNTED
57 TVS SHOWROOM
NOTE: REFER TO ANNEX
58 TVS SHOWROOM 150 450 230 3140 230 1200 600 3600 1200 5400 1000 230 130 300 90 652 90 FIG: WALL SECTION FIG: SPIDER CLAMP
FIG: FITTING OF SPIDER CLAMP
59 TVS SHOWROOM
3D VIEWS
Learnt about how glass facades are built
60 TVS SHOWROOM
FIG: OPTION 1 SIGNAGE RESTING ON GROUND
LEARNINGS
Signage is the design or use of signs and symbols to communicate a message.
FIG: OPTION 2 SIGNAGE MOUNTED ON FAA CIA AND GLASS (FLAG SIGNAGE)
04030201
FIG: OPTION 3 SIGNAGE MOUNTED ON WALL
Knowledge about showroom spaces, its zoning
SIGNAGE?
Study about showroom guidelines in Nepal
Learned about signage
61 Fig: Site Visit
-Site measurement and measured drawing
Project Requirement:
-Change in upper floor hotel to back packer hostels
-Mirror Design
BACKPACKER HOSTEL
Hostels and Guesthouses are the first choice as an accommodation for real travel ers. Unlike tourists, real travelers (“backpacker”) depend on cheap, affordable accommodation when traveling the world on a small budget, having no income for several months or even years. Especially young people aged 20-30 traveling alone or in groups often share accommodation with others in dormitory rooms.
My Involvement:
-Case-study of existing hostel
Client: Mr. Tashi
Backpacker
11 BACKPACKER HOSTEL
Location: Boudaha, Kathmandu
Project type: Commercial Project status: Construction
Software used visit
PRIVATE CABINETS PROVIDED TO USERS CURTAINS PROVID ED FOR PRIVACY
COMMON STORAGEUNITS
These rooms had already been constructed on one floor and now client wanted the same for upper floors.
62 BACKPACKER HOSTEL Site
12
I was assigned to measure site for calculation of carpet area and design instagramable mirror for existing hostel.
ATTACHED
WASHROOM FOR EACH ROOM
First option was designed such that the mirror had irregular shape and led strip light along its perim eter behid mirror giving it some depth and nice look.
BACKPACKER HOSTEL 63
Second optiom was designed being inspired from trending mirror designs which looks like semi-cir cle or half moon shape. This mirror would enhance the asthetic look of the hostel.
Third option was designed such that it had small bulbs with hidden wire along the perimeter of the mirror. The border around the mirror would hide the wiring of bulb.
Fourth option was also done inspired from trending mirror that looks like leaf and is hung to the wall.
This is the one line meaured drawing done after site measurement for the calculation of carpet area. This was first site measurement and measured drawing I did after joining the firm. During this process I learned the different ways of site measurement.
64 BACKPACKER HOSTEL
1. JORPATI APARTMENT 2. BIHAR FARMHOUSE 3. BALWATAR RESIDENCE 4. GAIRIDHARA RESIDENCE 5. NAXAL RESIDENCE 6. NAKHIPOT RESIDENCE 7. BASBARI RESIDENCE RESIDENCE
-
-
Project status: Conceptual EXISTING SPACE
- Rennovation of ground floor to create a suite room Bathroom with steam and sauna Sliding door connecting different
Project Requirement:
JORPATI APARTMENT
65 FIG:
-
spacesJorpati
apartment is at the ground floor of existing three storey residence located at Jorpati, Kathmandu. Client wanted to renovate existing space into suite room. Clients idea of the new space guided the reqirement for new planning. I was involved in this project from conceptual phase.
-
-
--planningdevelopment
Location: Jorpati, Kathmandu
11 JORPATI APARTMENT
My Involvement: Site measurement and drafting of interior 3d Quantity estimate Preparing client presentation
Project type: Residence
sheetClient: Dr. Tshering Lama
ENTRYCLOSET PRIVATEBATHROOMW/C PANTRY
CIRCULATION
66
12 JORPATI APARTMENT Design Development Software used
Suite refers to a set of rooms with luxurious facilities. A general suite includes a separate bedroom, private bathroom and a living area. Much grander suites can consist of a kitchen, balcony, and even offices. A suite gives the ambiance of an apartment.
BED ROOM
FIG: EXISTING PLAN WITH CIRCULATION
Room?Suite NOTE: REFER TO ANNEX
LIVING ROOM
FIG: CIRCUALATION DIAGRAM
such that there was mini mum changes in existing wall so as to reduce cost of -Circulationconstruction.waslimited upto the existing toilet.
-Sliding door was given from porch to provide easy acess of living room for guest.
-Luxury toilet that includes sauna, steam, jacuzi and shower was provided for guest suite.
FIG: OPTION1
JORPATI67
Design Development
- For first option existing wall was not altered at all, planning was done ac cording to existing condition.
-PlanningAPARTMENTwasdone
-Along with existing door another sliding door was given for providing connection between living room and guest bedroom which served the purpose of guest suite.
-Seperate luxury toilet was designed which included all the requirement of client sauna, steam, jacuzzi and shower.
68 JORPATI APARTMENT
-Access to washroom was changed and only provided through closet.
FIG: OPTION2
- In third option entry was only provided through living room comletly blocking access from existing main entry.
-Small walking closet was also added.
FIG: OPTION3
-Access to washroom was provided from main entry and closet.
- For second option pantry was placed along the entry in an enclosed room other remaining same as option1.
-Final plan was the updated option 4 after client meeting.
JORPATI69 APARTMENT
- For option 4 access to luxury toilet was given such that both the owner and guest can use it.
-Sliding door connecting living room and bedroom was placed off-center to entry for living room for privacy of guest bedroom.
-Further private washroom was also provided to guest room.
-Space For closet was increased, console was added.
FIG: FINAL PLAN
FIG: OPTION4
FIG: RENDER OF FINAL PLAN
70 JORPATI APARTMENT
JORPATI71 APARTMENT
FIG: PANTRY INBUILT MICROWAVE
FABRIC PANEL
FINISHSTAINLESSBRONZE
FIG: BED ROOM WITH STUDY TABLE
MATERIAL
The design of the living had to be designed in a sophiscated manner yet in a homely way. For that, the choice of color and material has made a great impact. Light wood has been choosen for furniture and warm color for wall while the flooring is wooden parquet not allowing to pass cold even in the ground floor.
Japnese door is used while connecting living room with bedroom as per the client choice.
I FIG:
FIG: LIVING ROOM
WOOD SAMPLE
FIG: JAPNESE SLIDING DOOR
INTERIOR 3D
DARK
MATT STATUARIOWHITEMARBLE
FIG: SHOWER NICHE EMPERADORGREY MARBLE
72 JORPATI APARTMENT
INTERIOR 3D
FIG: CLOSET WITH CONSOLE
FIG: TOILET INCLUDING SHOWER, BATHTUB OF GUEST ROOM
Shower niches are suitable for utilizing space in a small area.
FIG: TOILET INCLUDING SHOWER, SAUNA OF COMMON AREA
Quantity estimate NOTE: REFER TO ANNEX
JORPATI73 APARTMENT Length Breadth Height m m m 2.11.61.51.41.31.21.112 16.212 1 -2.1 1 -0.9 Total- 13.212 0.15 2.2 14.718 1 -1.5 1 -0.75 Total- 12.468 0.15 2.3 4.36 0.15 2.4 8.62 0.15 2.5 7.08 0.15 3.13 14.665 0.115 2.79 3.2 0.9 0.15 2.79 3.3 4.665 0.23 2.79 3.4 1.7 0.23 2.79 3.5 -0.9 0.115 2.1 -0.75 0.115 2.1 Total4.14 16.1 2.79 -2.1 2.1 -0.9 2.1 -1.8 1.5 Total4.2 14.7 2.79 1.5 -2.1 0.75 -2.1 1.8 -1.5 Door DeductionDoorDoorDeductionPrivateW/CPantryDeductionLiving3RoomW/C34 Brickwall Door 2,3,4 & 5 Door 1 Door Window2 1 Painting in Bed room Window 2 Wall Finish Door 4 S.N Description Of Items No Parquetting in Living Room Flooring Parquetting in Bedroom Parquetting in Closet Internal wall 115 Internal wall 230 Internal wall 150 Tile in WoodenW/CTileTilePrivatePantryW/cinBathroominShowerFlooring in Sauna Tile in Shower Tile in Toilet Tile in Bathroom Skirting Door 1 Door External2 wall 230 Door PaintingDeductionBedDeduction1Roomin Living room Area Quantity Rate Unit sqm 8.7678612.9935314.7052651.87021.981813.05816.2126.9087.3954.9221.1622.4941.6031.3869.9880.6541.2931.0620.376651.09089-0.21735-0.1811344.919-4.41-1.89-2.735.91941.013-3.15-1.575-2.7WallBrickwallFinishFlooringSkirting
Remarks
74 JORPATI APARTMENT 060504030201
KNOWLEDGE
USE
ROOM ENHANCED
BOQ LEARNINGS
LEARNED ABOUT RENOVATION ON EXISTING BUILDING OF NICHES IN TOILET ABOUT
KNOWLEDGE ABOUT SUITE 3D DEVELOPMENT SKILLS UNDERSTANDING TOWARDS MATERIAL USE
MORE
My Involvement:
11 BIHAR FARMHOUSE
Project status: Construction
Bihar
Farmhouse is a renovation project. There was existing building which construction was going on without proper planning. I was assigned to design new plan retaining the external walls under the guidance of principal architect Ar. Arunima Dev maam.
Location: Bihar, India
-Incoperation of Newari and Bihar architecture style
-Renovation of existing building into a farmhouse for client
Bihar Farmhouse
Project type: Residence renovation
75 EXISTING SITE
Project Requirement:
-Preparation-Planning of render for client meeting
Client: Mr. Aditya Jha
-Measured drawing
GROUND FLOOR PLAN
BEDROOM 1 BOOKFILECABINETCABINETBOOKLIBRARY BOOK CONSOLELIBRARY W/C KITCHEN STORE DRESSER DRESSER WADROBE WADROBEBEDROOM 2 KITCHEN DINING STAIRCASE
Plan Development
DININGW/COFFICEBEDROOMKITCHENCIRCULATION
Kitchen having island counter is planned along with dining enough for upto 8 people along with basin near dining area for easy access.
W/C
W/C
OFFICE
EXISTING WASHROOM
Phase 1
ENTRY PORCH
LEGENDS
Planning is done such that there is minimum changes in exterior walls for cost cutting. Since the location is Bihar we know that it has very hot climate. So for bedroom seatings are provided near window and beds are placed further away from window so that there is no direct heat while having sufficient natural light. Individual wardrobe is provided for each bedroom along with attached washroom and dresser .
Office is provided in ground floor which includes disuccion table for 6 and also sofa is provided. File cabinet is planned such that it is hidden from entry. Book library/cabinets are provided as client has book collection and wants it on display.
12 Software used 76 BIHAR FARMHOUSE
DRESSER
LEGEND
WADROBE WADROBEBEDROOM 2 KITCHEN
CLOSET W/C KITCHEN STORE DRESSER
-Kitchenwish. size was increased compromising the size of store.
W/C OFFICE BEDROOM 1 FILE CABINET BOOK LIBRARYCONSOLE W/C
GROUND FLOOR PLAN
Phase 2 BIHAR FARMHOUSE NOTE: REFER TO ANNEX
77
ENTRY PORCH
-Seperate seating area was added behind sofa and cabinate for privacy also bed was added as per client
BOOK LIBRARYLIBRARYBOOK SHOWERSHOWER SHOWER FRIDGE
After client meeting few changes were done in the presented plan.
DINING
CIRCULATIONDININGW/COFFICEBEDROOMKITCHEN EXISTING WASHROOM
STAIRCASE
BIHAR FARMHOUSE Final
After second client meeting minor changes were done:
78
-Also the position of staircase was changed because client wanted store room behind the staircase.
-Washroom were placed side by side unlike in previous plan for easy sanitary works and ventilation.
GROUND FLOOR PLAN
-This was the final updated plan until I worked on the firm. Plan
Phase 1
Few minor changes were done after first client -meeting:Clientwanted smaller living room so that the guard room also has wardrobe which could be ocassonaly used by his family members too. -Position of toilets were also re-arranged.
W/C
FIRST FLOOR PLAN
W/CW/CW/C
BALCONY
LIVING
LIVINGCONSOLEBOOK BEDROOMW/CWADROBE3
LIVINGBEDROOMW/C 4
BALCONY CLOSET CLOSETTVWALL
W/CCLOSETBEDROOMLIVINGCIRCULATION
Phase 2
STAIRCASE
BIHAR FARMHOUSE Plan Development
WADROBE WADROBE WADROBE
LIVING BOOK CONSOLE BEDROOM 3 STAIRCASE
FIRST FLOOR PLAN
79 CONSOLE
MASTER BEDROOM BEDROOM 4 CLOSET CLOSET CLOSET TVWALL TVWALL
LEGEND
WADROBE WADROBE MASTER BEDROOM
In first floor 3 bedrooms were designed. Master bedroom was deigned for the client which guard room next to it. Guard room has access to the master bed room while main entry to the room is from the corridor.
- Bed position of master bedroom was changed and double vanity basin was added to the toilet. -Pantry was added in the living room and ward robe size was increased as per clients interest. -Guard room was placed near staircase . -This was the final updated plan until I worked on the Phasefirm.3
Final Plan
FIRST FLOOR PLAN
80 BIHAR FARMHOUSE
BY: ARCHSOLAR DESIGNS
81 BIHAR FARMHOUSEDESIGNED
Knowledge about planning farmhouse
learnt about sanitary layout
82 04030201
LEARNINGS
BIHAR FARMHOUSE
Importance of shades and its incoporation in design
Relation of spaces according the individual needs
11 BALWATAR RESIDENCE
Balwatar
Project Requirement:
Project status: Municipal
-Sanitary And Electrical Drawings
-Site Draft, elevation and section for municipal set
- Duplex apartment in ground and first floor as per client demand
residence project was at municipal phase when I joined the firm. As all the planning was done I was involved in drafting the elevation from provided plan, electrical drawing and to do sanitary drawing. The basic plannning concept is based on duplex style with a central courtyard. For the facade, mediterrean style of architecture is chosen. It has features like arch windows, brick and stucco painted white, textured white walls combine with natural woods for a warm, inviting atmosphere. Also natural lights and views is maximized.
Project type: Residence
My Involvement:
83 FIG: CONCEPTUAL DEVELOPMENT DESIGNED BY: ARCHSOLAR DESIGNS
Location: Balwatar, Kathmandu
-Mediterranean Style Elevation treat -Coutyardment Planning
Client: Mr. Sanjay Sirohiya
Balwatar Residence
-Spaciouswallsoutdoor living areas
12
-Stucco
What is a duplex?
Each unit has a separate entrance and there is no interior connection between the two units. If there is outdoor space on the lot, the residents of the two units must share it, or it will be partitioned.
A duplex is a multi-family home that has two units in the same building. These two units always share a common wall, but the floor plan can vary. Units can be arranged either side by side or stacked on top of one anoth er, each occupying an entire floor or two of the building.
-Wrought-iron details
Mediterranean style
-Arched windows and doors
Mediterranean style varies depending on the specific architectural influences, but many of these homes showcase similar exterior elements. Typical characteristics include:
-Clay roof tiles
Software used
84 BALWATAR RESIDENCE
Several of these distinctive exterior Mediterranean features, including the stucco and roof materials, are intended to help keep these homes cool in hot, sunny climates.
WEST ELEVATION
NO DATEAMENDMENT JOB NO : JOB DRAWNDESIGNERDATETITLESCALEBY : CLIENT SANJAY SIROHIYA SHEET DRAWINGNO TITLE : JORPATI, CONTACTKATHMANDUNO9843587935, archsolardesigns@gmail.com9841552155ArchSolarDesignsLOCATIONBALUWATAR,KATHMANDUPLOTAREA:SQ.FT.PLINTHAREASQ.FT.BUILDINGTYPE:RESIDENCEPLOTNO. NOTE: REFER TO ANNEX
All designs are the property of ArchSolar Designs and cannot be used without their written permission. All prints specification and copyrights are the property of ArchSolar Design and shall be returned at the completion of the work. Measurement must be checked at the site contractor.
11 BALWATAR RESIDENCE 85 Drafted Elevation EAST ELEVATIONNORTHSOUTHELEVATIONELEVATION
12 86 BALWATAR RESIDENCE
11 BALWATAR RESIDENCE 87
Steel tubes for structural purpose:
Available: 1/2” to 8”
LEARNINGS
ISNB Hulas65MSteel Pipe
learnt about sanitary layout
Drafting skill development
ISNB 50M
Knowledge about duplex style
Knowledge about Mediterranean style
knowledge of municipal set
12 88 BALWATAR RESIDENCE 060504030201
knowledge about electrical layout
residence project was an on-going project when I joined the firm. Since I was involved in furniture design on previous project I was assigned to do furniture detail of few remaining furniture of this project so as to enhance my knowledge about the importance of detail, how its constructed and what material is to be used. I completed these details under the guidance of Ar.Lunibha Manandhar.
FIG: AFTER CONSTRUCTION DESIGNED BY: ARCHSOLAR DESIGNS
My Involvement: Furniture Detail
Project Requirement: -Interior Location:Client:-RenovationDesignMr.SatyalGairidhara,
GAIRIDHARA RESIDENCE
89 GAIRIDHARA RESIDENCE
Kathmandu
Project type: Residence
Project status: Construction
Gairidhara
90 GAIRIDHARA RESIDENCE NOTE: REFER TO ANNEX
91 GAIRIDHARA RESIDENCE
LEARNINGS
LEARNT ABOUT FURNITURE CONSTRUCTION
LEARNT ABOUT MATERIAL CODE
DESIGNED BY: ARCHSOLAR DESIGNS GAIRIDHARA RESIDENCE
INFORMATION ABOUT TYPES OF WOOD USED IN FURNITURE
030201
92
Client: Mrs. Rani Banji
Project type: Residence
Project status: Construction
My Involvement:
Project Requirement:
93 NAXAL RESIDENCE
DESIGNED BY: ARCHSOLAR DESIGNS FIG: ON-GOING CONSTRUCTION
alwatar residence project was at construction phase when I joined the firm. I was assigned to cordinate with site engineer and counter site problem along with doing door window sched ule, detail and electrical layout drawings. The basic concept of the residence utilizing maximum space since the plot area is very less. For proper lightning and view, ribbon windows. Voild is left for ribbon window and ventilation on toilet.. The facade design is modern and minimalist.
Location: Naxal, Kathmandu
Requirement was to create a modern building and use maximize space. Various elevation options were presented to the client. After the approval from
Naxal Residence
Nclient.axal
-Site -Options-Door-OpeningCo-ordinationscheduledetailforelevation treatment
1
Ventilation
- -
33 -1 1 Window
FIRST FLOOR PLAN
- -
WINDOW SCHEDULE 1ST 2ND 3RD - - 11 Ventilation V1.0 - - - - 1 Ventilation V2.0 1 2 2 2 2 V4.0 V3.0 2 D2.6 D3.0 D4.0 1 1 1 1 4 1 2 Window DW2.6 Door SD5.0 2 2 1 1 3 4.6 2 2.6 1 2.7 1 Window CW8.0 1 1 3 3.0 111- - 3 6.0 2 -1 4 --Window DW2.11 --1 1
94 Software used NAXAL RESIDENCE
Window
1 Corner
2111
1 Sliding
3 3 Door
Door
TOP TOTAL - -
329 Door
1
Descriptions
16.15. 25 Window
Window
- -
-Door
Door
Ventilation V38.8
Window
There was addition of opening on east side for ventilation, so I was assigned to upgate the existing plans along with new opening schedule.
S.No1.2.3.5.6.7.8.9.12.13.11.10.4.14.
121321 -
17. 65
- -
NO. OF OPENINGS G.F
Ventilation
The wall enclosing study didnot feel right so, I re moved the wall and door to create free space for circulation. Also I rearranged the study table such that when being used chair we could still face north side and when closet is being used chair can be kept underneath the study
There was need to change in plan of box room because of insuffi cient space for circulation as during wall layout the space seemed to be smaller than in plan.
Storagetable.
95 NAXAL RESIDENCE
Closet Design (site change)
unit was also provide above and next to study table for enough storage while having clear circulation space of 3’-6”.
SOIL PIPE
Site Visit 96 NAXAL RESIDENCE
REINFORCEMENT ON SLAB
DOWN SLAB FOR W/C
POINTS LEFT FOR ELECTRICAL WIRES ON THE SLAB
MANHOLE WITH IN THE BUILDING DUE LESS SITE AREA PLY USED ON FRAMEWORK FOR PROPER FINISHED CONCRETE SLAB
OPTION 1 OPTION 2
So, other possible elevation treatment were designed which looked similar to one first designed. Also different methods of used of material was explored while trying to achile the previous design.
97RESIDENCE
NAXAL
Elevation Treatment (site change)
As per elevation treatment approved by client there was need to give cantilever space of 4’ on front facade only on second and fourth floor but the contractor made mistake and same cantilever was repeated on every floor.
USE OF DOWN SLAB
IMPORTANCE OF USE OF ARCHITRAVES IN DOOR
CONSTRUCTION DETAILING OF DOORS
LAYOUT OF WINDOW IN SITE 2'-4" 1'-2" 3'-3" 3'-9" 2'-4" 1'-2" 9'-4" +3'6"SILL LVL +0'0"PLINTH LVL
LEARNINGS
98 NAXAL RESIDENCE
1'-4" 3'-2" 4" 3'-6" 4" 2'-0" 1'-2" 3'-3" 3'-9"
04030201
1'-2" 9'-4" 1'-2" 3'-3" 46'-7"
3'-3" 3'-9" 2'-4" 1'-2" 3'-3" 1'-4" 10'-8" 1'-2" 9'-4" 1'-2"
+24'6"SILL +10'6"FIRST+7'0"LINTELLVLLVLFLOOR LVL +14'0"SILL+17'6"LINTELLVL LVL +21'0" SECOND FLOOR LVL +28'LINTEL LVL +31'6" THIRD FLOOR LVL +35'0"SILL +42'0"FOURTH+38'6"LINTELLVLLVLFLOOR LVL +45'3"PARAPET LVL
-1'4"GROUNDLVL
Project status: Municipal Phase
DESIGNED BY: ARCHSOLAR DESIGNS CommercialResidential
Project Requirement
Nakhipot
NAKHIPOT99 RESIDENCE
residence project was at municipal phase when I joined the firm. I was assigned to do opening schedule, overlap plan, sabiatry drawing and electrical drawing at first. Then due to change ni municipality rules I was assigned to update the drawings as per new rules. The basic concept of the residence is mixed used type of building. Two lower floors are used for commercial purpose where as upper floors are used as residential purpose.
Nakhipot Residence
-Mixed used type of building i.e. residential cum -commercialElevationtreatment
only on front facade
My Involvement: - Municipal - Electrical drawings - Sanitary drawings
-3D development according to provided drawings
Client: Mr. Pramode
Project type: Residence
Location: Nakhipot, Lalitpur
100 NAKHIPOT RESIDENCE
i.DrawingsLightswitches and power socket were provided using simple Thumb rule. ii. The position of power socket and light fixture were taken in account.
Electrical Layout
NAKHIPOT101 RESIDENCE
ix. Concrete of grade M25 is mostly used. Readily Mixed Concrete (RMC) is used for high rise
LEARNINGS
v. The stirrup near the pillar is placed more closely in the beam(4” c/c) because it needs to tolerate more shear force at the connection of beam and column. While at the central of the beam due to less shear force, stirrups are provided are more distance (6” c/c)
Mild steel- low carbon steel Tor Steel-Fe415
iii. Extra bars are added on the upper side of the rebar mesh to prevent the hogging moment and also flexing of the salb.
vii. The sizes of stirrups are 4mm, 6mm, 8mm, 10mm but most commonly 8mm is used.
iv. The rebars are larger in diameter on the lower floors of the building because more load are beared by the lower floors.
SANITARY ELECTRICALDRAWINGSDRAWINGSREQUIREMENTOFMUNICIPAL SET OF LALITPUR
The structural municipal set of this building was taken as reference and studied. The following things were learned:
vi.The rebar are mainly of 3 types: TMT- Fe500
102 NAKHIPOT RESIDENCE
buildings.NOTE:REFER TO ANNEX
viii. The cranking is done in stairs at L/4 length where, L is the length of stairs.
04030201
i. Knowledge about lower tie and upper tie beam.
ii. The slab tends to sag most at the central area where supports are not present, hence to prevent the slab from sagging and to support the load, bars are cranked on the lower part of the slab.
MIXED USE BUILDING TYPE
- Landscape
My Involvement: -Site -Landscape-Ceilling-Detailingco-ordinationofgymblockDetailDetailing
Basbari Residence
- Interior
VAASTU PURUSH MANDALA
Client: Mr. Sirohiya Residence Location: Basbari, Kathmandu
BASBARI103 RESIDENCE
residence is developed from basic concept of planning of this residence is Vaastu Purush Mandala. It is a sinuous volume with no sharp edges. The building is constructed in a luxury neo-clasical style. It has features of neo-classical design like grand scale, extensive use of doric col umn, vaulted and groin ceiling in different rooms, dome in the design. The building has been designed by Ar. Bibuti Man Sigh. It took around five years for the building block to be built. Now, the interior and exterior finishing design is being done by Archsolar Design since 6 months. . The detailing is done very precisely both of interior and exterior .
BUILDING FOOTPRINT 3D BY AR. SHREEJAY TULADHAR ADG E' 5'3' H ADG E'H 5'3' FIG: CONCEPTUAL DEVELOPMENT
- Exterior
Project Requirement: Addition of gym block Design Design Design
Project type: Residence Project status: Construction
-
Basbari
Pedestrian Entry Lotus -DetailingPondof Pond -Elevation pedestrianofblock
-Design of closet ceiling and its detailing -Detailing of other -Corniceceillingroomdetails
-DesignedBedOptions for flower -Layoutbedon site -Detailing of flower bed
-Designed back of garage -Draftedwall elevation andsectionFlower
Garage/ Gym Block
BANSBARI RESIDENCE
Main Block
Pond and Deck Details
I designed first option such that -The curves of deck and pond ended on same line.
This was the previously approved design for pond and deck. Changes had to be done as -Client prefere’s symmetry and hence wanted deck and pond to end at same line. -The shape of pond was not fully circular because of pizza stand area so that also had to be updated.
POND UP UP DECK
While the option 1 already encountered all the problem, option 2 was de signed because addition of another curve at end also it being steps would be complicated. Also it only differed in 300mm for having same ending line.
-The problem of sharp edges was encountered by addition of curved ending. -The pond outline was also extended for it to have undisturbed semicircular outline.
PIZZA BARBEQUEOVEN/ UP UP
PIZZA BARBEQUEOVEN/ POND 304UP UP DECK
DECK
PIZZA BARBEQUEOVEN/
OPTION 1 OPTION 2
BASBARI105 RESIDENCE
After client meeting option 1 was selected, its detailling was done and I was assigned for its on so, I prepared layout diagram needed.
site
Client wanted both lotus pond and fountain on specified area which was not possible because lotus plant needed stagnant water and as for fountain the water need to be running. So, for this problem another partation was added for lotus water to be not affected by the fountain water.
FINAL UPDATED POND PLAN NOTE: REFER TO ANNEX
106 BANSBARI RESIDENCE 50150 50 SILL LVL "A" = 1575MM SILL LVL "B" = 1850MM SILL LVL "C" = 2125MM LINTEL LVL = 2600MM 2726 150 R2730 734PONDLOTUSBATHROOM1311 925 2075 2149 BC A LN-DPS3 LN-DPS3 100MM THK RCC M20 COMPACTED EARTH ONE LAYER FLAT BRICK SOLING WATER PROOF LAYER 20 MM THICK SCREEDING 12 MM THK STONE/TILE FINISH 600 SILL LVL "A" +1350MM 2550 LINTEL LVL +2550 MM SILL LVL "A" +1150MM 200 500 1150 700 1850 700 150 759 125 774 125 GROUND LEVEL HT +000M LN-DP S3 SECTION SCALE = 1: 25 Wall WallstaircaseAnnexnicheblockopeningPetalfountain600mmhighpond ledge Freshwater pond Lotus pond 200MM BRICK BATS FILLING Pond division 1250 75 525 700 437 1250 700 437
layout
BASBARI107 RESIDENCE Different phases of construction Brick layout for flowerbedConstructed curve flower bed First flower bed was straight but client had change in his mind and wanted it to be curve. -So I designed a flower bed with the width of -Layout600mm.was done and client thought its width was more. Again flower bed width was reduced to 350mm and was finally approved after again doing layout on the site. 110 350 25 725 125 2150 125 725 TYPICAL FLOWER BED PLAN 600 250 819 350 125 2150 125 874 TYPICAL FLOWER BED PLAN C Brick wall ledge Floor MetallightmeshNiches Boundary wall Planter Ledge Plaster to be sel. finish on existing wall 115 mm Brick wall with 12mm plaster finish35010007506002700 6002100600 75 mm lintel band G.L. Foundation brick wall 2100 MM HT -600 MM HT 750 MM HT 1750 MM HT 75 mm sill band 2700 MM HT 125 75 mm THK COMPACTEDPCC[1:3:6]EARTHONELAYERFLATBRICK SOLING GL 5075 225350125 Flower bed Details FINAL PLAN
108 BANSBARI RESIDENCE Cornice design facia, casted using formwork. Gym/Garage Block Details BALCONY GYM300 mm down main building first floor lvl GROUND FLOOR(LIV.) +101.95 PLINTH LEVEL +101.5 FIRST FLOOR +104.95 SECOND FLOOR +111.45+108.25 THIRD FLOOR BRIDGE 300 mm down main building plinth floor lvl ROAD LEVEL 7501200 450 3450 3300 300 1000 150 300 150 230 125 3297 2400 1325 PLINTHGL +150 3448 MM HT 5887 MM HT 7223 MM HT 75 MM gutter 230 mm brick wall 125 mm concrete roof 125 mm brick wall water proofing layer 50mm thk. cement screeding 3219 1200 160 125 375 150 100 50 50 10075 50 50 100 100 450
272 345 1738 707 1738 345 351 5496 700 50 100 25 695 1131 175 570 3448 345 1738 707 1738 345 4873 R870R870 1738 1306 869 175BASBARI109 RESIDENCE
I was assigned to design garage backwall, science the client always choosed curve I designed archs for it which would be costructed over wall using plaster and there will be darker shade of paint used within it.
FACIA BEAM
NORTH ELEVATION
110 BANSBARI RESIDENCE
VOID DN DAD'S ROOM DRESSING ROOM DN UP SUITE ROOM RMPUJA TERRACE FIRST FLOOR PLAN LIVING ROOM FAMILY GUEST BEDROOMBASBARI111 RESIDENCE Curtain Architecturalpelmetdownlight 150F.L.MM HT 3200 MM HT 150mm high skirting SF-B RM S1 SECTION X-X SCALE = 1:25 19mm thk. gypsum board ceiling to be sel. finish 01 R-04 LED strip light 200 200 02 R-04 19mm thk. gypsum board ceiling to be sel. finish LED strip Architecturallight downlight2550 MM HT 3200 2790 32003162 2690 3200 12mm thk. plaster cross pattern 450 1015 920 2040 1501100X100 mm cornice 100X100mm cornice 26902790 350 100 25037 576 152 100 410 300 200 563 37 700 37 563 100100 300 300 1525 1650 26002600 Ceiling cassette BRM-SF Y SF-B RM P1 REFLECTED CEILING PLAN SCALE = 1: 25 SF - BRM X SF -BRM X BRM-SF Y 100 200 37 600 1700 700 1700 100 300 300 37 700 600 663 663 200 37 663 100 300 200 100 12.5mm thk. cement sand plaster (1:4),2mm thk. 2 coats of wall putty with 2 coats of emulsion paint gypsum board ceiling with exterior surface duly taped at all joints, frames with suspension hangers less than 400m spacing CEILING AT +2700mm LVL CEILING AT +2800mm LVL CEILING AT +3200mm LVL Curve ceiling end cornice 200 450 250 37 662 350 300 300 100 663 37 700 350 2100 200 1037710 152 100 100 200500 1525900cassetteCeilingx900 coffer 900 900 coffer 400 900 350 900 350 900 450 212900312 312 312 50 25 750 2550 100 100 CEILING DETAIL DRAWING
37
For curtain pelmet, 200mm is left. The material used in the false ceiling as well as cornice is Plaster of Paris. Various lights like architectural down light and strip light is also used for the lighting as well as aesthetic purpose. They are hidden in the false ceiling.
LED strip thk. cement sand
DETAIL AT = 1:20
CORNICE DETAIL SCALE: 1:2
DETAIL =
Architecturallight downlight 12mm
DESIGNED BY: ARCHSOLAR DESIGNS
CORNICE DETAIL 12 25 25 12 37 SCALE= 1:2 20 15 75 15 10 60 15 100
Gap to be leveled upto beam bottom level
19mm thk. gypsum board ceiling to be sel. finish 12mm thk. cross pattern 10 60 15 100
AT 01 SCALE
plaster100x125mm cornice 60 200 210 140 100 250 37 260 350 100 287 610 350 37 37 338 125 110500 140 100 250 2512 540 37 727 20 15 75 15 125 15
37
CORNICE DETAIL SCALE: 1:2 CORNICE DETAIL 12 25 37 25 12 SCALE= 1:2
The designing and detailing of ceiling is a long and tedeous process. The oval shape ceiling vault was demanded by the client. So, equal offset from the wall and beam was taken i.e 300mm. Again offset of 700mm was taken from the inner oval making it look like a vault like structure. For the passage, coffer ceiling is chosen where as ceiling above the sofa follows the shape of the ceiling.
112 BANSBARI RESIDENCE 19mm thk. gypsum board ceiling to be sel. finish 01 R-04 LED strip light Curtain Architecturalpelmetdownlight 200 350 12mm thk. cement sand plaster
plasterCurtain pelmet
03 SCALE
125 15
1:20 550 12mm thk. cross pattern plaster 100 250 37 100 286 144 191 140 100 825 2512 862 25 12 37 338 125 463 727500 R-05 03
BASBARI113 RESIDENCE In similar ways other ceiling details were also done which is included in annex. VOID DN DAD'S ROOM DN SUITE ROOM RMPUJA TERRACE FIRST FLOOR PLAN DRESSING ROOM LIVING ROOM FAMILY GUEST BEDROOM MASTER SUITE LIVING SPACE SF -BRM X' SF - B RM X' BRM-SF Y' RMB-SF Y' SF-B RM P2-A REFLECTED CEILING SEATING PLAN SCALE = 1: 30 CEILING AT +2800 mm LVL gypsum board ceiling with exterior surface duly taped at all joints, frames with suspension hangers less than 400m spacing CEILING AT +3200mm LVL CEILING AT +2700 mm LVL Curve ceiling starting point 150 150 1650300 1501501501650 150 Groin CEILINGvaultAT +2600mm LVL Groin vault Arch bottom-2700mm LVL Arch top-3200mm LVL 350 150 1200 350 1950 600 1950 1200 6050 200 Groin vault Arch bottom-2700mm LVL Arch top-3200mm LVL 838 150 2068 150 1339 200 1540 2368 838 4746 Curtain Pelmet 2299 F.L. 3200 MM HT 02 R-04 19mm thk. gypsum board ceiling to be sel. finish LED strip Architecturallight downlight SF-B RM S1 SECTION X'-X' SCALE = 1:25 150mm high skirting 01 R-03 350 150 1650 150150 300 150150 1650 150 1200 350 1950 600 1950 1200 1650 481 19 2700 3200 500 2700 2700 MM HT 2600 MM HT 500 2700 500 2700 2299
114 BANSBARI RESIDENCE DESIGNED BY: ARCHSOLAR DESIGNS
Fig: Cornice negative
BASBARI115 RESIDENCE SITE VISIT
Fig: Cornice sample
Atcornicefirstthe
Cornice design process
CorniceCornice
Fig: Cornice nega
Space for
cornice is designed and it’s negative as well postive is printed in the scale 1:1. Then it is drafted on the site and hand brace is made according to cornice negative. Different samples are showed to the client. The chosen sample are made into long pieces using Plaster Of Paris. They are laid hanging to be dried on the sun. Finally, they are cut into required length and used on the required surface area.
Fig: Cornice sample
Fig: Drying of cornice
Fig: Cornice sample
Fig: Hand brace for running
walls.Fig:Step 1 Fig: Step 2 Fig: Step 3 Fig: Step 4
116 BANSBARI RESIDENCE SITE VISIT
Fitting of window frame in curve wall
Fig: Construction of building
At first, the frame size required is measured on wall then it is traced and cut on thin sheet of wood. Then, it is further traced on wooden frame and cut accordingly. Finally, they are ready to be fitted on the wall. The frames are made very small and large ribbon windows are avoided in curve
Fig: POP on wall
Fig: Wooden detailing for dome
FIG: FRAMING OF FALSE CEILING
BASBARI117 RESIDENCE SITE VISIT
Ceiling hanger is used whose one end is on ceiling and another end is on perimeter chanel. They are not kept more than 600mm spacing. There after, the perimeter chanel is connected to each other by C section. The metal wire mesh is bolted on C section. Finally POP is applied and let to dry. The holes for electrical wires are also covered by POP.
FIG: BOLTING OF METAL WIRE MESH
False Ceiling framing and laying POP
C-SECTERPERIMEINGCEIL
FIG: APPLYING POP ON ELECTRICAL WIRE HOLES
FIG: CEMENT BLOCK
FIG: ANNEX BUILDING REINFORCEMENT
SITE VISIT
CIRCULAR COLUMNFORMWORK OF CIRCULAR
FIG: FINAL RESULT OF POP ON VAULTED CEILING
SPACE REINFORCEMENTFORREINFORCEMENTINBETWEENCEMENT
118 BANSBARI RESIDENCE
FIG: CEMENT BLOCK
BY: ARCHSOLAR DESIGNS
BASBARI119 RESIDENCEDESIGNED
STRUCTURE OF CURVE BUILDINGS
METHODVASTU
Since the building is designed in neoclassical style, I gained more knowledge about its style, characteristics, construction process, etc.
c.Use of POP on wall instead of wall putty to make the building more iii.stronger.Different styles of vault on ceiling
OF CONSTRUCTION of POP ON CEILING
Since I was involved in ceiling detailing, I learnt about different ceil ing styles like coffer ceiling, groin vault, oval vault, etc.
120 BANSBARI RESIDENCE LEARNINGS 07060504030201
SITE DIFFERENTSUPERVISIONSTYLES
INSTALLATION OF WINDOW FRAME ON CURVE WALLS
OF VAULT ON CEILING
A curve building is generally not built. Even if it is built, it is very im portant for it’s structure to be durable especially in case of Nepal as it lies in earthquake zone. Inorder to make the curve building stronger, following things were considered:
iv. Method of construction of POP on false ceiling
Through site visit, I had gained knowledge about the construction of POP and false ceiling.
v. Vastu
It played a vital role in planning. According to it, furniture layout was vi.done.Installation of windows on curve wall
vii. Site supervision
Every Tuesday, detail drawings were presented to the client, site engineer and layman.
a. Use of cement blocks with vertical space left for reinforcement in regular b.Maximuminterval.use of secondary beam to make the structure strong.
Through site visit, I had gained knowledge about the construction of curve window frames and it’s installation
ii. Structure of curve building
KNOWLEDGE ABOUT NEO-CLASSICAL STYLE
i. Knowledge about Neo-classical style
-Zaha Hadid
121
Conclusion
“Architecture is like writing. You have to edit it over and over so it looks effortless.”
In this period of over 90 days, I’ve been involved projects having design, conceptualization, architectural visualizations, walkthrough, working drawings, preparation of municipal set, etc. with a large array of variety of works involving, residences, commercial complexes, hotels, etc. that have been a companion in this journey of internship I have learned that designing in college used to be about employing out of the world designs while in professional life, it is much different to stick to simple but effective and functional design. All these could have never been possible without the regular supervision and consultation of the supervisors, teachers, seniors and collegues.
122
Architect, it has made me realise how much I’ve grown as a person and the level of confidence I have endured as a student to a Trainee Architect. This period of time has brought a great change in my mindset as a student and learned what it feels like to work professionally.
ConclusionLookingbackatallthesemonthsworkingasaTrainee
“Architecture is the learned game, correct and magnificent, of forms assembled in the light.” – Le
ForABOUTCorbusierCOVERPAGE:coverpagedesign
Ive choosen the render image of project I was involved during my internship. I have tried to create balance by leaving some white space and using colorpop technique.