شركة الجيل الثالث للمقاولات المحدودة

Page 1

Company Profile Al-Jeel Al-Thalith Contracting Company Ltd.

SERVICES AVAILABLE

NO JOB OR NO TASK IS MORE IMPORTANT THAN WORKER HEALTH AND SAFETY.

ELECTRICAL Transmission lines, Distribution Lines, Services Connections, Underground Substations, Cathodic Protection Systems.

Our vision is to be the pre-eminent

threat, every effort will be made to

institution in the Kingdom of Saudi

plan a safe way to do the task.

Arabia and achieve market recog-

Every procedure must be a safe

MECHANICAL

nition both in quality and delivery of

procedure. Shortcuts in safe pro-

Equipment, Structures, Pipelines, Fencing.

service as well as the range of

cedures by either foremen or

services offering.

workers will not be tolerated.

COMMUNICATIONS

We believe that no job or no task

Fiber Optics Cables, Copper Cables, Communication Equipments

is more important than worker

CIVIL

sents a potential safety or health

health and safety. If a job repre-

Building, Land Development, Road, Water & Sewage System, Renovations. TRANSPORTATION Aggregates, Fuel, Sweet & Raw Water, General Cargo.

P.O Box 30158, Al-Khobar 31952, Kingdom of Saudi Arabia. Tel +966-3-8994747 Fax +966-3-8994949 +966-3-8653802

sagri@emeksa.com


Contents Al-Jeel Al-Thalith Introduction……………………………………………………….……………03 Services…………………………………………………………………………………………………………..04 Corporate Information…………………………………………………………………………………07 Health & Safety Policy………………………………………………………………………………….11 Quality Assurance & Quality Control…………………………………………………………15 Facilities…………………………………………………………………………………………………………..17 Manpower Details…………………………………………………………………………………………19 Equipment Details…………………………………………………………………………………………23 Completed Projects……………………………………………………………………………………...27 Ongoing Projects…………………………………………………………………………………………..39 Glimpses of Projects…………………………………………………………………………………….43 Legal Documents……………………………………………………………………………….…………64 DOCUMENT TITLE Company Profile COMPILED BY Adnan Akhtar CONTACT T. +966-3-8994747 F. +966-3-8994949 sagri@emeksa.com


Company Profile

Introduction Al-Jeel Al-Thalith Contracting Co. Ltd. formerly known as Mohammad Mana Al-Sagri & Partners Trading & Contracting Company is a 100% Saudi collective company established in the year 1996 and is located in Al-Khobar, Saudi Arabia. Al-Jeel Al-Thalith is well represented in the Kingdom and has participated in some of the SEC and Saudi ARAMCO construction and services projects as well as other agencies. We are proud to say that “successful projects completion� has always received our highest priority. Our relative success as a construction and services contractor has been due to our ability to maintain a stable and skilled workforce, including management and our ability to introduce the latest technology related to our work. All of our projects coordinate closely in order to achieve a coordinated effort and therefore, can offer full-service within the stipulated time anywhere in the Kingdom.

Page No.3


Services We are providing comprehensive services in the fields of construction, operation & maintenance of Civil, Electrical, Mechanical, Communication and Transportation Sectors since 1996. This includes but is not limited to the following:

Electrical Department ·

Transmission Lines design & erection

·

Distribution Lines

·

Services Connections

·

Cathodic Protection Systems

·

Grounding system design, supply, installation, testing & commissioning

·

Package & unit substations installation, testing and commissioning

·

13.8 kV Switchgears (EPC)

·

Transformers installation, testing and commissioning.

·

MV/LV cable laying, testing and Termination

·

Installation, testing and commissioning of backup generators.

·

Installation, testing and commissioning of UPS systems.

·

Design, supply and installation of cable Trays and raceaways.

·

Conceptual design, installation and Testing of HV, MV and LV protection relays.

·

Old switchgear modification & retrofitting

·

DC power supply system

·

DC battery banks design, installation, testing and commissioning.

Page No.4


Company Profile

Services Instrumentation & Control Department ·

Fiber Optics and Structure Cabling

·

Control Cabling

·

Communication Equipments -

·

Instrumentation, conceptual design, installation testing and commissioning

·

Installation, testing & commissioning of: -

Page No.5

Low Density and Medium density Multiplexers SDH PABX System Wireless Connection.

RTUs / SCADA System CCTV & Access Control Systems Control & instrumentation cabinets, assembling & wiring.

·

Old instrumentation and controls upgrading and retrofitting.

·

Distribution Lines

·

Services Connections

·

Cathodic Protection Systems

·

BMS (Building Management System)

·

Fire Detection System.

·

Industrial Gas Monitoring System installation, testing and commissioning.


Services Mechanical Department ·

HVAC Division

·

Industrial Fabrication

·

Pipelines (BS, GS, SS, PVC, HDPE, GRP, VCP, DI)

·

Fencing

·

Pumping Stations

·

Sewerage lifting stations

·

Fire Protection System

Civil & Construction Department ·

Building

·

Land Development (Earth Moving)

·

Road, Water & Sewage System

·

Renovations

·

Underground non-invasive surveying for buried utilities.

· ·

Trenching PEB design and erection

·

Switchgear rooms.

·

Foundation pads.

Transportation ·

Aggregates

·

Fuel

·

Sweet & raw water.

·

Molten Sulpher

Page No.6


Company Profile

Corporate Information Saleh Mana Al-Sagri Managing Director

Management Fayez Mana Al-Sagri Asst. Managing Director & Finance Manager

Auditors

Vendor Registration Numbers

Tariq M. Al-Shabbani Certified Accountants License No.388

Saudi Aramco:

10006416

Saudi Electricity Company:

1000644

Royal Commission (MARAFIQ):

1676

Saline Water Conversion Corp:

Registered

National Commercial Bank Thoqbah Branch, Al-Khobar

Banks

Riyadh Bank, King Abdul Aziz Street, Al-Khobar. Saudi Al-Fransi Bank, Thoqbah Branch, Al-Khobar

Head Office

Page No.7

Prince Mumdouh Street, Cross No.22, Al-Khobar 31952, Saudi Arabia. Tel: +966-3-8994747, 8653884, 8653802 Fax: +966-3-8994949 E-mail: sagri@emeksa.com




Health & Safety Policy

Page No.10


Company Profile

Health & Safety Policy Al-Jeel Al-Thalith Contracting Company Limited believes that NO JOB OR NO TASK IS MORE IMPORTANT THAN WORKER HEALTH AND SAFETY. If a job represents a potential safety or health threat, every effort will be made to plan a safe way to do the task. Every procedure must be a safe procedure. Shortcuts in safe procedures by either foremen or workers will not be tolerated. If a worker observes any unprotected job, which may pose a potential threat to their health or safety, he or she must inform management and management must take adequate precautions. The Company’s Management is responsible for ensuring that there is effective governance of health and safety matters through the provision of approved and appropriate organizational arrangements and policies that are effectively implemented in practice. This is exercised directly by the management itself in certain ways e.g., through the annual report, but also through the Employees Committee (EC) which has a specific remit in this respect. An employee member of the Board also attends the regular meetings of the Project Managers (PMS) when quarterly health and

Our futures are only built through our people. We

aim

to

protect

them. No Job or no task is more

important

workers’

health

than and

safety.

safety reports are considered, so as to informally observe that appropriate matters are being reported on, discussed and considered and, where appropriate, acted on. The PMS are collectively responsible for considering recommendations, from

professional

advisers

and

others,

for

how

the

governance

and

management arrangements are effectively implemented and made operational and for giving/gaining approval to changes from time to time. Arrangements for overall health and safety management, policy development and auditing largely fall within the remit of the Executive Director – Human Resources.

Page No.11


Health & Safety Policy All heads of organizational operating units are personally responsible for implementation of approved health and safety policies and procedures within their areas of responsibility and for safe working practices. They have the support and professional advice of health and safety and professionals, and access to specialist internal and external advice where this is needed. Depending on particular. Health and safety coordinators also operate to support implementation within the company.

Page No.12



Quality Assurance & Quality Control

Page No.14


Company Profile

Quality Assurance & Quality Control Quality Assurance Al-Jeel Al-Thalith Contracting Company Ltd. recognizes the requirement for Quality Assurance within all business areas in which it operates and has therefore committed itself to the establishment of an effective Quality Management System which can be implemented as required on any project, study or proposal it undertakes. The aim of the system is to ensure that client’s objectives are met with minimum wastage, rework or concessions and thus achieving a reliable cost system of management. Al-Jeel Al-Thalith Contracting Company Ltd. considers satisfying client requirements and achieving the prime project objectives as an essential quality issue. J.T. operates a total quality management system, fully supported by the management and staff. A commitment to quality is required from all employees and the “think quality” philosophy is encouraged in all aspects of J.T. operations. To ensure the achievement of these objectives, J.T. has appointed a Quality Assurance Manager, who is responsible for the introduction, documentation, implementation and maintenance of the Quality System. The Quality Assurance Manager has a direct reporting link to the Managing Director on all Quality Matters in order to ensure independence. J.T. Quality Assurance procedures and Quality Manual have been developed to meet the requirements of the International Standard Organization ISO 9002. Our policy statements have been developed in line with these standards. Quality Control The Quality Control department is an integral part of the contractors overall organization, and the contractor’s organizational chart should clearly define its place with in. The Quality Control Officer reports directly to the project manager and coordinate the Quality Control function with the Project Superintendent on site. The Quality Control Officer will coordinate technicians and site engineers as required to assist in managing and administering the contractor’s quality control program set forth in this document.

Page No.15


Facilities Warehousing Facilities There are two warehouses located in Dammam and Rafha consisting of open storage and covered storage area for storing materials and equipments, which are required for work. These warehouses are controlled by storekeeper for material tracking and scheduling. Camps and Accommodation Facilities The company operates and maintains its own labor camps and accommodation facilities in the following locations:

Camp

Location

Capacity

Al-Khobar Camp

Al-Khobar

20

Hafr ul Batin Camp

Al-Olaiya

20

Rafha Camp

Rafha

66

Page No.16



Manpower Details

Page No.18


Company Profile

Manpower Details Description Management

Nationality

Number

Saudi

3

Civil Engineer

Filipino, Egyptian.

7

Electrical Engineer

Egyptian, Pakistani.

5

Electronics Engineer

Pakistani

1

Surveyor

Egyptian

2

Foreman

Egyptian, Filipino, Pakistani.

3

Fiber Optic Splicer/Power Cable

Filipino, Indian.

3

Electrician

Egyptian, Indian, Filipino

8

Telecommunications Technician

Filipino.

4

HE Operator

Filipino, Sri Lankan, Indian.

7

Lineman

Filipino, Pakistani

15

Steel Fixer & Welder

Indian, Pakistani

2

Field & Technical Staff

Transportation & Mechanic Staff.

Page No.19

Chief Mechanic

Pakistani.

1

Mechanics

Filipino, Indian, Pakistani

5

Drivers

Indian, Sri Lankan.

7

Auto Electrician

Indian.

1


Manpower Details Description

Nationality

Number

A.C Technician

Filipino, Indian

2

Tyre man

Sri Lankan.

1

Accountant

Egyptian, Indian, Pakistani.

4

Office Assistants.

Pakistani.

2

Govt. Relation

Saudi.

1

Finance & Admin Staff.

Civil Works & Others. Carpenter

Filipino, Indian.

04

Shuttering Carpenter

Pakistani

Mason

Filipino, Indian, Pakistani

Tile Fixer

Pakistani.

Plumber

Indian, Pakistani.

02

Labour

Nepali, Indian, Filipino, Pakistani

25

8 14 8

Page No.20



Equipments Details

Page No.22


Company Profile

Equipments Details Description

Page No.23

MFG/Model

Quantity

Trailer

50/30 Ton Low Bed

5

Trailer

20 Ton Flat Bed

Trailer

Wire Rack

3

Trailer

Water & Fuel Tanker

2

Cabin Tractor

2 x 4Merc/IVECO

Dump Truck

4 x 4 IVECO / 4 x 6 Merc.

3

Winch Truck

2 x 4 CAT/Merc. 5 Ton

2

Water Truck

2 x 4 GMC

1

Bucket Truck

GMC/Merc.

Backhoe

Volvo/CAT 420/Case 428

4

Front Loader

John Deer/CAT 920/CAT 966

3

Rock Breaker

CAT Poclain

2

Rock Drill

Robbin

1

Bulldozer

CAT D6/D8

2

Grader

CAT G14

1

Forklift

CAT Clark

2

Loader

CAT

2

Mobile Crane

Grove 25 Ton

1

10

24

12


Equipments Details Description

MFG/Model

Quantity

Rough-Terrain Crane

Grove 40 Ton

1

Vibro Hammer

40 Ton

1

Pickup

Ford F-150/F-350/Nissan

12

Jeep

Toyota Land Cruiser

10

Passenger Car

Suburban/KIA Car

2

Others

KIA Mini Truck

1

Hydraulic Cable Puller

Tema Italy/Timberland USA

4

Air Compressor

Ingersoll Rand/Sulair

2

Hydraulic Pump

Tema Italy

2

Generator

400 Watts Robbin

8

Electrical & Mechanical Tools

Assorted

Lot

Civil Works Tools

Assorted

Lot

Safety Equipments

Assorted

Lot

Lineman Safety Tools

Assorted

Lot

Scaffoldings

Assorted Lot

Lot

Fiber Optics Splicing Equipment Ericson

2

OTDR

Exfo

1

Light Source

Exfo

1

Power Meter

Exfo

1

Page No.24


Company Profile

Equipments Details Description

Quantity

Welding machine

13

Jack trolley

5

(2 Ton)

Boom jack trolley (2.5 Ton)

3

Lifting A frame

4

Lifting Chain block (5 Ton)

2

Lifting Chain Block (3 Ton)

5

Lifting Chain Block (2 Ton)

6

Lifting Chain Block ( 1 Ton)

4

Makita cutter 16”

4

Grinder 9”

12

Grinder 4”

10

Drill machine

7

Drill hammer machine

5

Jack Hammer

4

Generator welding machine

1

Diesel Generator

1

Air compressor

4

Flash Light

12

Hand Lamp

10

Magnate Drill

1

Oxygen Gas Cylinder sets

8

Lathe Machine

1

Electric cable drum

12

Electric lifting crane (2 Ton)

2

Tool trolley

6

Spanner all size

Lot




Completed Projects

Page No.28


Company Profile

Completed Projects Contract No. & Client 33005/06 Main Contract SEC-EOA

Type of Contract Electrical

Value in SR

Duration

356,842.39

26th Nov 2005 to 24th May 2006

Status Completed

Washing of 380KV Overhead Transmission Lines by climbing in the Eastern Operating Area. Ghunan-Ghazlan A&B Transmission Lines, Qurayah-Shedgum A&B, Ghazlan-Fadilih A&B and Ghazlan-Fadilih C&D

Contract No. & Client 32003/44

Type of Contract Civil & Electrical

Value in SR

Duration

386,986.00

17th Sep 2005 to 10th Mar 2006

Status Completed

Construction and installation of street lighting system at Berri Power Plant as per scope of work.

Contract No. & Client Private Main Contract

Type of Contract

Value in SR

Duration

Transportation

300,000.00 Unit rate

04th Mar 1999 to 07th Mar 2003

Status Completed

E.A. JUFALI, Dammam Transportation of household supplies from Mina Store, Dammam to various location in Saudi Arabia.

Contract No. & Client 546/2 Amanatul Dammam Main Contract

Type of Contract

Civil Works

Value in SR

Duration

29th May 2004 to 1,376,084.20 28th May 2005

Status

Completed

Construction of hallow block perimeter fence around cemeteries for Qurayat, Al-Olayah, Al-Shait and Al-Redaifha Villages.

Page No.29


Completed Projects Contract No. & Client SCECO-South Sub-Contract (Private) NEC Saudi Arabia.

Type of Contract Communication

Value in SR

Duration

15,120.00

25th Sep 2004 to 25th Dec 2004

Status Completed

Under NEC Saudi Arabia Ltd. Splicing & Testing of Single Mode (SM) Fiber Optics Pigtail connection for Juaymah DOC 48 cores and Rastanura 230 KV S/S # 8024 cores.

Contract No. & Client 546/2 Amanatul Dammam Main Contract Qurayat-Al-Olaiya

Type of Contract

Civil & Electrical

Value in SR

Duration

1,992,720.00

01st Jan 2002 to 31st Dec 2002

Status

Completed

Supply and Installation of street lights including cable trenching, laying, erection of poles, testing and commissioning, asphalting of roadways, concreting of sidewalks and gutters.

Contract No. & Client SAUDI ARAMCO Contract # 6600007908 Sub-contract (Manpower & Equipment Supply To Nasser Manea Wabran)

Type of Contract

Value in SR

Civil and 1,800,000.00 Communication

Duration

26th Aug 2003 to 09th Dec 2003

Status

Completed

Installation, testing and commissioning including excavation of cable trench, fiber optics cable laying, installation of optical pedestal, terra tape, backfilling, 4-4� diameter PVC duck bank concreting, splicing and cable terminations at pump station # 2. Underground copper cable installation for telecommunication and pedestal at pump station # 3 in Khurais.

Page No.30


Company Profile

Completed Projects Contract No. & Client Nil Private Main Contract

Type of Contract

Value in SR

Duration

Transportation

29,250.00 Unit rate

12th Jan 2000 to 11th Jan 2001

Status Completed

GULF STEEL COATING INDUSTRIES, DAMMAM. Transportation of steel from Jubail factory to various locations in Saudi Arabia & GCC.

Contract No. & Client 47275/00 SAUDI ARAMCO Sub-Contract

Type of Contract Civil & Electrical

Value in SR

Duration

243,000.00

02nd Jan 2000 to 01st Jun 2001

Status Completed

Cathodic protection & 13.8 KV overhead power lines for Shaybah Wells.

Contract No. & Client SH-N/004/19 SEC-SOUTH Sub-Contract

Type of Contract

Value in SR

Civil, Electrical & 1,404,500.00 Mechanical

Duration 10th Jun 2000 to 31st Mar 2001

Status Completed

Stringing, clipping & jumper of 102 Km, 33 KV 3Ph overhead HT line and 168 Km LT line and erection, testing and commissioning of 309 Nos. 100,200 and 500 KVA H-pole transformer in feeder noose. 1 & 2 in Al-Habil Area.

Contract No. & Client 84198/00 SEC-ERB Main Contract

Type of Contract Electrical

Value in SR

Duration

Status

6,987,126.00

07th Jul 2001 to 06th Jul 2004

Completed

Expansion, reinforcement, maintenance of electrical network & provide power supply to the customers in Sakaka, Domat-Al-Jandal, Tabarjal, Qurayyat, Turaif, Awaiquila.

Page No.31


Completed Projects Contract No. & Client 152/4 Amanatul Dammam Main Contract Qurayat, Al-Olaiya

Type of Contract

Civil

Value in SR

Duration

29th May 2004 1,376,084.20 to 28th May 2005

Status

Completed

Construction of Hallow block fencing around the cemeteries of Qurayat, Al-Olaiya...

Contract No. & Client 835064/84 SEC-ERB Main Contract

Type of Contract Electrical

Value in SR

Duration

Status

97,656.00

13th Jan 2001 to 17th Mar 2001

Completed

Replacement of 36 Nos. outdoor focus lights at Qateef office complex. Works includes all Civil Works, installation of lighting fixtures and testing and commissioning

Contract No. & Client MODA SEC-ERB Sub-Contract

Type of Contract Fiber Optics

Value in SR

Duration

Status

68,200.00

30th Aug 2000 to 25th Apr 2001

Completed

Duration

Status

Fiber Optics cable splicing, testing and commissioning.

Contract No. & Client SHT/04/A/20 SEC-SOUTH Sub-Contract

Type of Contract Electrical

Value in SR

774,600.00

01st Nov 2001 to 01st May 2001

Completed

Supply and installation of all electrical network 22 KV with SEC South Branch for Asir Villages.

Page No.32


Company Profile

Completed Projects Contract No. & Client 82569/00 SEC-EAST Main Contract.

Type of Contract

Communication

Value in SR

850,000.00

Duration 01st Feb 1999 to 31st Oct 1999

Status

Completed

Fiber Optics splicing, testing and commissioning of 115 KV transmission line from Nariyah BSP to Nariyah S/S # 2. Nariyah BSP to Qaryat Al-Ulyah, Safaniyah to Khafji S/S # 3.

Contract No. & Client 85041/65 SEC-EAST Main Contract

Type of Contract Civil

Value in SR

46,699.00

Duration 22nd Nov 1999 to 15th Feb 1999

Status

Completed

Repair and repainting of the control room of Salwa power plant flooring and repair and waterproofing of the control room roofing. Activities include polishing, smoothing of floor concrete surface with sealant/putty, scraping and filling roof cracks with sealant and polyurethane foam.

Contract No. & Client Nil Private Main Contract.

Type of Contract Civil

Value in SR

2,660,000.00

Duration 14th Jun 1999 to 14th Dec 2001

Status

Completed

Complete construction and finishing works including structural, finishing, painting, plumbing, electrical, carpentry, steel fabrication, interior decoration etc. on a turnkey basis for four villas located in Al-Khobar.

Contract No. & Client Nil Private Main Contract.

Type of Contract Equipment Supply.

Value in SR

2,002,950.00

Duration 10th Aug 1998 to 28th Feb 1998

Status

Completed

SALIM W. AL-YAMI CO. & PART. Supply of heavy equipment and trucks with operators / drivers within the Eastern Region of Saudi Arabia on rental basis.

Page No.33


Completed Projects Contract No. & Client 85064/51 SEC-EAST Main Contract

Type of Contract

Civil

Value in SR

Duration

Status

61,900.00

10th Aug 1999 to 08th Sep 1999

Completed

Modification of two toilet rooms in building No.16, SEC, Dammam. Activities include demolition, replacement of the existing walls and flooring with new ceramics tiles and glazed marbles, installation of corian solid, western closets water heaters, marble partitions, plumbing works, painting and restoration

Contract No. & Client 83140/00 SEC-EAST Main Contract.

Type of Contract Civil & Electrical

Value in SR

Duration

Status

832,543.00

15th Dec 1998 to 14th Dec 2000

Completed

Installation, testing, commissioning of 97 Nos. grounds, replacement of shield wire jumpers and replacement of 121 Nos. defective aerial warning lights on Khursaniyah-Nariyah -Qaisumah 230 KV transmission lines.

Contract No. & Client Nil Private Main Contract.

Type of Contract Transportation

Value in SR

Duration

Status

300,000.00

14th Feb 1998 to 13th Apr 1998

Completed

NASSIR MANEA WABRAN CO. & PART. Providing construction equipment, material and fuel transportation, flat and low bed tankers and trailers.

Contract No. & Client 72375/00 SAUDI ARAMCO Sub-Contract

Type of Contract

Value in SR

Civil Equipment & 1,120,260.00 Mechanical

Duration

Status

10th Aug 1998 to 28th Feb 1999

Completed

Complete assembly, erection and conductor installation for the 50 structures of 34.5 KV DC transmission line. Supply and installation of portal cable risers, installation of substation equipment and the related tie-in overhead and underground substation modification works.

Page No.34


Company Profile

Completed Projects Contract No. & Client 82569/01 SEC-EAST Sub-Contract

Type of Contract

Communication

Value in SR

100,000.00

Duration 15th Jul 1998 to 14th Oct 1998

Status

Completed

Splicing, testing, commissioning of OPGW on Berri Ghazalan 230 KV transmission line, approx. 4.1 km.

Contract No. & Client 400477/033 SAUDI ARAMCO Sub-Contract

Type of Contract Civil, Electrical and Mechanical

Value in SR

436,427.00

Duration 13th Sep 1997 to 25th Feb 1997

Status

Completed

Upgrade SASREF Metering Control Building in Jubail Industrial City. Activities include expansion and renovation, extension, construction, relocating, supplying, installation, disconnection, re-routing, caging, verifying, sealing etc.

Contract No. & Client 72375/00 SAUDI ARAMCO Sub-Contract

Type of Contract

Value in SR

Civil Equipment & Manpower Sup- 1,100,000.00 ply

Duration 03rd Oct 1998 to 28th Feb 1999

Status

Completed

Complete foundation works for 34.5 KV DC direct impeded steel poles transmission lines from Rabigh refinery to Rabigh community, approximately 24 km, including equipment and manpower supply.

Contract No. & Client Nil SAUDI ARAMCO Main Contract

Type of Contract

Transportation

Value in SR

460,000.00

Duration 01st Jan 1998 to 31st Dec 1998

Status

Completed

Transportation services to Salim Al-Yami Co. for Rabigh jobsite under SAUDI ARAMCO Contract # 723375/00 (Power supply to Rabigh Community).

Page No.35


Completed Projects Contract No. & Client Nil Private Main Contract

Type of Contract Civil & Manpower Supply

Value in SR

Duration

Status

55,000.00

22nd Dec 1996 to 21st Jan 1997

Completed

Value in SR

Duration

Status

350,000.00

01st Dec 1996 to 30th Jan 1997

Completed

Mr. Ahmed Nassir Al-Wabran Renovation services for a private villa in Al-Khobar.

Contract No. & Client Nil Private Main Contract.

Type of Contract Supply of Const. Equipments

M/S Al-Salem Est. Supply of construction equipments at Dhahran Airport on rental basis.

Contract No. & Client 82792/00 SEC-EAST Sub-Contract

Type of Contract Civil & Electrical

Value in SR

Duration

Status

1,377,419.44

01st Jan 1997 to 17th Jun 1998

Completed

Installation, testing, commissioning of approximately 800 Nos. steel tower grounding on Khursaniyah-Nariyah-Quisumah 230V transmission lines.

Contract No. & Client 30542158/00 SEC-ERB

Type of Contract Meter Reading

Value in SR

Duration

Status

2,801,400.00

27th Dec 2005 to 26th Dec 2008

Completed

Meter reading and distribution of energy consumption invoice EOA.

Contract No. & Client 109/B—Main Contract Ministry of Municipality Affairs

Type of Contract Civil

Value in SR

Duration

01st Apr 2005 to 2,999,350.00 30th May 2008

Status Completed

Construction of Qaryatul Olaiya Municipality Building.

Contract No. & Client Sub Contract SAUDI ARAMCO

Type of Contract Aviation

Value in SR 1 Million

Duration

Status

01st Oct 2009 to Completed 01st Jan 2010

Supply, installation, Testing & Commissioning of Helipad Lighting System at Aramco Site in Manifa.

Page No.36


Company Profile

Completed Projects Contract No. & Client 956 Ministry of Finance

Type of Contract

Value in SR

Duration

Status

Electrical

4,862,174

16th Feb 2008 to 15 Dec 2009

Completed.

Completion of 13.8 KV overhead distribution line for provision of electricity to three fuel stations, housing facility of Ministry and airstrip situated at Batha border.

Contract No. & Client 10541048/00 SEC-EOA Main Contract

Type of Contract

Value in SR

Duration

Status

Civil & Electrical

18,713.883.00 approx

15th April 2005 to 30th May 2008

Completed

Install, remove, replace and modify overhead distribution facilities for operating voltage up to and including 35 KV, Central Operating Area (including Riyadh City, Riyadh Rural Area, Qassim, Dawadmi, Kharj and Hail)

Contract No. & Client

Type of Contract

Value in SR

Duration

Status

Nil King Faisal University

Time & Attendance System

1,368,659

One year.

Completed

Installation of Time & Attendance System in different campuses of King Faisal University located in Dammam, Khafji, Nariya, Qatif, Hafr Al Batin and Jubail.

Contract No. & Client DT-KFSH-E09 King Fahad Specialist Hospital, Dammam. (Sub Contract)

Type of Contract

Value in SR

Duration

Status

Electrical

4 million

One year.

Completed

Up-gradation of HVAC Equipment at King Fahd Specialist Hospital, Dammam.

Page No.37


Completed Projects Contract No. & Client

Type of Contract

Value in SR

Duration

Status

13/96 King Faisal University

Electrical

SR 998,142

11 months

Completed

Replacement of Sub Stations from Building No.27 of the University.

Contract No. & Client

Type of Contract

Value in SR

Duration

Status

King Faisal University Teaching Hospital

Electrical

480,000

02 months

Completed

Supply & Installation of New Switchgear and dismantling of existing switchgear.

Contract No. & Client

Type of Contract

Value in SR

Duration

Status

King Fahd Specialist Hospital, Dammam

Electrical

248,000

01 month

Completed

Installation of Electrical Panels, Cables, Cables Trays and associated work.

Contract No. & Client Sub Contract Al-Bilad Compound

Type of Contract

Value in SR

Duration

Status

Electrical

SR 33,000

02 weeks

Completed

Removal of existing transformers and installation, testing & commissioning of new transformers.

Contract No. & Client

Type of Contract

Value in SR

Duration

Status

Sub Contract U.S Embassy, Riyadh

Electrical

21,184

02 weeks

Completed

Supply of surge protectors to American Embassy.

Page No.38



Ongoing Projects

Page No.40


Company Profile

Ongoing Projects Contract No. & Client

Type of Contract

Value in SR

Duration

Status

30841036/00 SEC

Electrical

Unit Rate

3 years

Ongoing

Contract for maintenance of Overhead and Underground Distribution Networks up to 36 KV.

Contract No. & Client 732/51 Ministry of Education.

Type of Contract

Value in SR

Duration

Status

Construction

4595136.70

22 months

Ongoing

Construction of Abada Bin Al Samit Primary School in Hafr-ul-Batin.

Contract No. & Client 733/51 Ministry of Education

Type of Contract

Value in SR

Duration

Status

Construction

4559088.00

22 months

Ongoing

Construction of Al-Moghira Bin Shoba Secondary School in Hafr-ul-Batin.

Contract No. & Client Kuwait International Aircraft Leasing Company.

Type of Contract

Value in SR

Duration

Status

Transportation

Unit Rate

-

Ongoing

Kuwait International Aircraft Leasing Company. Supply and transportation of Jet A1 fuel from Dhahran to Khafji.

Page No.41


Ongoing Projects Contract No. & Client

Type of Contract

Value in SR

Duration

Status

Sub Contract Al Noor Specialist Hospital, Makkah.

Electrical & Control

11000000

01 year

Ongoing

Electrical & BMS controls system Works.

Page No.42



Glimpses of Projects

Page No.44


Company Profile

Glimpses of Projects

Well prepared OPGW Joint Box with accessories.

Page No.45


Glimpses of Projects

OPGW Joint Box Preparation

Page No.46


Company Profile

Glimpses of Projects

Stringing Equipment

Page No.47


Glimpses of Projects

Cable Puller

Page No.48


Company Profile

Glimpses of Projects

Digger Equipment

Page No.49


Glimpses of Projects

Digger Equipment

Page No.50


Company Profile

Glimpses of Projects

Rebar for Pole Foundation

Page No.51


Glimpses of Projects

Casing Vibrator

Page No.52


Company Profile

Glimpses of Projects

Construction of Municipality Building in Qaryat-ul-Olaiya.

Page No.53


Glimpses of Projects

Construction of Municipality Building in Qaryat-ul-Olaiya.

Page No.54


Company Profile

Glimpses of Projects

Construction of Municipality Building in Qaryat-ul-Olaiya.

Page No.55


Glimpses of Projects

Installation of Street lighting including cable trenching, laying, erection of poles, testing and commissioning in Qaryat-ul-Olaiya.

Page No.56


Company Profile

Glimpses of Projects

Supply, installation, Testing & Commissioning of Helipad Lighting & Control System at Aramco Site in Manifa.

Page No.57


Glimpses of Projects

Supply, installation, Testing & Commissioning of Helipad Lighting System at Aramco Site in Manifa.

Page No.58


Company Profile

Glimpses of Projects

Up gradation of HVAC Equipment at King Fahd Specialist Hospital, Dammam. (Construction of Switchgear Room)

Page No.59


Glimpses of Projects

Up gradation of HVAC Equipment at King Fahd Specialist Hospital, Dammam. (Construction of Switchgear Room)

Page No.60


Company Profile

Glimpses of Projects

Up gradation of HVAC Equipment at King Fahd Specialist Hospital, Dammam. (Construction of Switchgear Room)

Page No.61


Glimpses of Projects

Up gradation of HVAC Equipment at King Fahd Specialist Hospital, Dammam. (Construction of Switchgear Room)

Page No.62



Legal Documents

Page No.64








HEAD OFFICE Prince Mumduh Street, Cross No.22, Madinatul Ummal, Al-Khobar 31952, Kingdom of Saudi Arabia. T. +966-3-8994747 / F. +966-3-8994949 sagri@emeksa.com

8653884


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.