WC Food Store Cold Room Kitchen WC hatch Staff counter Store Plant shelves platform lift cpbrd customer entrance bi-fold doors dwarf wall Outdoor Terrace Balcony WC WC Store Kitchenette shelves Office Store dwarf wall roof light roof light roof light roof light roof light roof light platform lift bi-fold doors shelves dwarf wall WC Food Store Cold Room Kitchen WC hatch shelves Staff counter Store Plant shelves platform lift cpbrd customer entrance bi-fold doors dwarf wall Outdoor Terrace Balcony WC WC Store Kitchenette Office Store dwarf wall roof light roof light roof light roof light roof light roof light platform lift bi-fold doors dwarf wall 01 02 06 04 03 05 07 08 Located on an isolated rural site within the curtilage of a farm shop, the owner desired a restaurant/café with ancillary facilities and strong visual presence within the landscape and street scene. I liaised directly with the client to establish the schedule of accommodation, the scheme concept, layout and preliminary proposal.
design references the mass and shape of typical agricultural buildings within the wider context and features a contemporary mix of traditional vernacular and industrial external materials - natural timber cladding and weatherboarding, standing seam zinc roof and facing brick plinth. Throughout the entire process, I produced all drawings and documents. 01-ground floor plan 02-first floor plan 03-side elevation 04-front elevation 05-rear elevation 06-side elevation 07-entrance corner view 08-street view New Build E[b] Commercial Staplehurst Stage 2 Dec.18-Jan.19
The
Private Extension C3 Dwellinghouse
Tunbridge Wells Stages 2+3+4 Sep.18-Mar.19
The project comprises the reconfiguration and extension of the rear ground floor of the dwelling to create an open plan kitchen-dining area, utility room and external pergola. The Victorian property is located in a Conservation residential area.
I developed the design through stages 2 and 3 under guidance and supervision from a senior designer. I prepared, submitted and monitored the Planning Application and the proposal successfully acquired planning permission.
I liaised directly with the client, consultants and Building Control Officer throughout the stage 4 process.
I managed the Building Control application, ensured successful approval and produced all drawings and documents.
01-stage 4 floor plan
02-stage 4 section AA
03-stage 3 site plan
04-stage 3 rear elevation
05-stage 3 side elevation
06-stage 3 side elevation
07-stage 3 elevational section
existing SVP Lounge WC Rear Garden Patio TBC by client full height units kitchen island Dining Kitchen shelving TBC existing boiler 1178 900 rooflight timber glazed door crittall style door B B ED.01 ED.02 W.01 RL.02 RL.03 RL.04 lintel above by strct. eng. over by strct. eng. proposed retaining wall proposed retaining wall 900 900 900 984 1965 292 7078 300 2217 120 4440 647 to suit 418 2583 1153 900 [2100] 530 303 1980 300 2602 [2100] 898 3602 TBC on site ducted through kitchen island, hob installation and floor - final position and detail TBC Existing structure to be removed shown dashed grey. Contractor investigate loadbearing and report findings to Engineer. All surface water drainage connect into existing systems and to be agreed site with the building control officer prior to commencement of relevant stage. New proposed drainage to connect into existing main run. 1097 beam over engineer be encased to achieve min 30 mins fire resistance outline foundations shown dashed 1178 900 rooflight 1178 900 rooflight Catnic stronghold or equivalent approved with vertical DPC junction with existing wall. Catnic stronghold or equivalent approved with vertical DPC junction with existing wall. mechanical extract ductwork through ceiling A A 838mm timber glazed door 100 898 967 existing table heat detector smoke detector direction rafters over strct. eng. datum 0.000. underside wall plate +2.220. DPC DPC 423 451 451 1178 900 rooflight RL.02 W.01 lintel above by strct. eng. by strct. eng. safety glass to Provide Code lead flashing cavity tray and weep holes where roof abuts existing wall min 200 ventilated void bespoke cantilevered fixed bench, steel frame timber finish match cladding as per strct. eng. spec External Wall 103mm thick outer skin facing brickwork to match existing, 100mm nominal cavity filled with 100mm thick Isover CWS 32 silicone impregnated glass mineral wool insulation [or equivalent approved] Inner skin of 100mm Thermalite Shield blocks in accordance with structural engineer's spec; Cavity ties to be approved stainless steel vertical twist type built 750mm horizontal and 450mm vertical maximum staggered centres. Internal face of block plastered ready to receive finish. Overall U-value=0.23 W/m²K. proprietary telescopic vent proprietary telescopic low-e double glazed window type and model TBC by client all levels measured and checked on site before commencement works patio TBC by client natural slates mechanically fixed centres strct. eng. spec. Breather membrane draped over battens. Full 150mm Kingspan Kooltherm K107 insulation [or equivalent approved] between rafters and 32.5 mm Kingspan Kooltherm K118 insulated plasterboard [or equivalent approved] below rafters ready to receive finish. Overall U-value=0.15 W/m²K. natural vertical timber cladding rafters by strct. eng. brickwork finish match existing Bootroom 25° in-situ concrete strip foundation footings structural engineers details and specification, foundations shown indicatively final depth be agreed site with BCO in-situ concrete strip foundation footings structural engineers details and specification, foundations shown indicatively final depth be agreed on site with BCO Code lead flashing DETAIL A Floor Concrete suspended floor system by specialist consisting of 150mm deep prestressed concrete beams supporting 440 215 100mm thick approved concrete blocks (3.5N/mm minimum) upon prepared level bearings. Minimum end bearing beams 100mm. DPC be installed below all beams and built blocks. Thoroughly grout between beams and blocks with cement/sand mortar. Minimum void between underside of floor and sub-soil level be 200mm. Lay 1200g polythene d.p.m. (bonded continuously with wall d.p.c.) over beams and blocks and lay 75mm Kingspan Kooltherm K103 insulation. Flooring perimeters be insulated with Kingspan TF70 vertical board 25mm thick. Lay over insulation separating layer building paper to BS 1521 :1972 min 500g, joints lapped minimum 150mm. Finish with 75mm fibre reinforced sand and cement screed ready receive finish. Overall U-value=0.19 W/m²K. safety glass to spec 2100 FFL to match with existing ensure DPM linked existing. 01 02 03 04 05 06 07
The
01-ground
A A B B C C S/D 5 6 10 11 Master Bedroom En-suite En-suite Bedroom Landing Wardrobe Wardrobe 100 4760 100 2828 100 2084 100 1757 100 2918 as existing 1176 TBC 100 3330 100 921 TBC 2342 TBC 900 [x1950] 2385 TBC 1121 TBC 100 3385 100 921 TBC 2342 TBC 900 [x1950] 2385 TBC 1726 946 673 1476 100 762 leaf 762 leaf 762 leaf 762 leaf 673 1671 947 100 648 WF. 01 RL. 01 RL. 02 RL. 03 RL. 04 150 980 780mm roof light 980 780mm roof light 780 780mm roof light 780 780mm roof light mechanical extract ductwork to run vertically through ceiling mechanical extract ductwork to run vertically through ceiling safety glass to spec safety glass to spec SVP SVP pocket door pocket door pocket door 46 degree pitch 46 degree pitch 46 degree pitch 46 degree pitch 23 degree pitch 46 degree pitch clay tiles to match existing clay tiles to match existing 46 degree pitch 46 degree pitch ashlar walls to spec ashlar walls to spec timber frame external walls to spec timber frame external walls to spec rwp new rwp new rwp new rwp new rwp DF. 01 DF. 02 DF. 03 DF. 04 DF. 05 DF. 06 DF. 07 DF. 08 1351 1092 425 1275 mechanical extract ductwork run vertically through ceiling UP egress window wood burning stove flue outlet located min 2300mm horizontally from roof weathered surface, min. as high as ridge and min. 1000mm from flue intersection with roof weathered surface post by structural engineer post by structural engineer post by structural engineer WF. 02 egress window new post by strct. eng. new post by strct. eng. new post by strct. eng. Beam by strct. eng. Beam by strct. eng. direction of rafters over direction of rafters over Staircase with total rise of 2385mm divided equally into 11no risers, goings to be approx 240.8mm, max pitch 42°. min. head-height to stair 2m. A A B B C C H/D S/D C/M S/D rwp Wardrobe Wardrobe Coats Boots Bedroom 3 Kitchen Entrance Lobby Boiler Services Utility Bathroom Living Bi-fold doors Bi-fold doors 1 3 4 10 11 new rwp new rwp new rwp new rwp SVP IC1 IC2 IC3 IC6 IC5 Bedroom 4 Dining 4111 200 TBC 5880 200 TBC 5627 TBC 200 TBC 3113 TBC 2714 [x2100] TBC 200 TBC 6027 TBC 200 TBC 4131 200 TBC 2740 [x2100] 1391 4331 6897 TBC 100 1514 TBC 200 TBC 200 TBC 2740 [x2100] 200 TBC 2521 [x1100] 1366 882 [x2100] 783 TBC 1703 100 2084 100 500 100 920 [x1250] 895 925 [x1250] 934 [x1250] 200 TBC 1402 100 3655 TBC 200 TBC 2874 TBC 1358 [x1100] 1325 6878 TBC 100 1514 TBC 200 TBC 200 TBC 3232 [x2100] TBC 200 TBC 3233 [x2100] TBC 663 500 [x900] 663 TBC as existing 5557 TBC as existing 200 TBC 2343 100 3185 200 TBC 3035 1340 [x2100] 1652 as existing 1976 100 2773 200 TBC 1888 1031 920 [x1350] 100 1522 100 1755 100 500 100 1484 1197 100 2678 838 leaf 838 leaf 2442 463 838 leaf 926 leaf 1370 leaf 762 leaf 2898 980 2041 1931 1651 1801 1931 Beam by strct. eng. Beam by strct. eng. Beam by strct. eng. Beam by strct. eng. Beam by strct. eng. new post by strct. eng. Post by strct. eng. ED. 01 ED. 02 ED. 03 ED. 04 WG. 01 WG. 02 WG. 03 WG. 04 WG. 05 WG. 06 WG. 07 WG. 08 WG. 09 WG. 10 WG. 11 WG. 12 safety glass to spec safety glass to spec safety glass to spec safety glass to spec safety glass to spec safety glass to spec beam and block floor construction spec step up step up step up step up 826 leaf DG. 01 DG. 02 DG. 03 DG. 04 DG. 05 DG. 06 DG. 07 DG. 08 DG. 09 DG. 10 Suitability of existing structural elements retained to be checked on site by structural engineer to BCO approval. new post by strct. eng. new post by strct. eng. new post by strct. eng. new post by strct. eng. new post by strct. eng. new post by strct. eng. new post by strct. eng. new post by strct. eng. existing post to be retained existing post to be retained existing post to be retained existing post be retained existing post to be retained existing post to be retained existing post to be retained existing post to be retained existing post to be retained existing post to be retained existing post be retained existing post to be retained existing post to be retained existing post to be retained existing post to be retained mechanical extract ductwork to run vertically through ceiling direction of joists over Existing slab to be retained slab condition to be checked on site by contractor and findings to be reported to BCO and Structural Engineer. Existing slab to be retained slab condition be checked on site by contractor and findings to be reported to BCO and Structural Engineer. Timber frame wall connector or equivalent at junction with existing wall together with vertical DPC All dimensions indicative only where existing construction to be retained final dimensions to be checked and confirmed on site. outline of foundations shown dashed Patio timber frame structure to spec direction of joists over FFL to line through existing post to be retained existing post to be retained Existing structure to be removed shown dashed grey. Contractor to investigate loadbearing and report findings to Engineer. surface water drainage to attenuation tank and pond Permeable Surface SVP IC4 window and timber frame panel infill in existing structural opening vertical timber weatherboard sliding door outline of foundations shown idicatively DG. 11 IW. 01 IW. 02 100 direction of joists over egress window safety glass to spec safety glass to spec safety glass to spec UP 100 1469 new post by strct. eng. shelving egress pocket door beam above by strct. eng. wood burning stove brick chimney breast by specialist post by strct. eng. post by strct. eng. post by strct. eng. 1505 215 910 215 885 new post by strct. eng. 190 new post by strct. eng. new post by strct. eng. Beam by strct. eng. Beam by strct. eng. direction joists over direction of joists over direction of joists over direction of joists over Beam by strct. eng. Beam by strct. eng. Beam by strct. eng. new post by strct. eng. Beam by strct. eng. provide guarding and handrail to stairs with openings between balustrades or railings not to exceed 100mm concrete slab construction by strct. eng. timber floor to spec Beam by strct. eng. Beam by strct. eng. Beam by strct. eng. Beam by strct. eng. direction of joists over direction of joists over direction of beam+block Staircase with total rise of 2385mm divided equally into 11no risers, goings to be approx 240.8mm, max pitch 42°. min. head-height to stair 2m. TOP OF SLAB DATUM 0.000 TOP OF BRICK PLINTH TBC +0.600 U/S WALL PLATE TBC +2.250 FF FFL TBC +2.450 TOP OF BRICK PLINTH TBC +0.600 U/S WALL PLATE TBC +2.250 TOP OF LOWER SLAB -0.180 U/S BARN HIP SOFFIT TBC +3.625 GF FFL +0.082 GF FFL +0.082 1 8 10 11 41° Staircase with total rise 2385mm divided equally into 11no risers, goings to be approx 240.8mm, max pitch 42°. min. head-height to stair 2m. provide guarding and handrail to stairs with openings between balustrades or railings not to exceed 100mm. 9 46 degree pitch 46 degree pitch 46 degree pitch solid floor construction to spec concrete slab construction by strct. eng. ED. 02 WG. 07 DG. 10 ED. 03 WG. 06 WG. 10 suitability of existing foundations to be checked on site and confirmed by structural engineer to BCO approval DPC DPC brick plinth existing brick plinth to be retained wood burning stove flue outlet located min 2300mm horizontally from roof weathered surface, min. as high as ridge and min. 1000mm from flue intersection with roof weathered surface clay tiles to match existing suitability of existing floor slab to be checked on site and confirmed by structural engineer BCO approval suitability of existing floor slab be checked on site and confirmed by structural engineer to BCO approval IW. 01 2348 TBC 2150 TBC 2000 2462 TBC floor joists by strct. eng. ceiling joists by strct. eng. rafters by strct. eng. ridge beam by strct. eng. Entrance Lobby Kitchen BAT LOFT existing roof structure to be retained T+G boarding T+G boarding over DPM over OSB deck supported by proprietary loft insulation pedestals open eaves open eaves 1736 as existing 140 TBC structural stud wall as per strct. eng. spec ashlar wall to strct. eng. spec ridge beam by strct. eng. DPC timber floor to spec DPC foundations shown indicative only final depth to be agreed by BCO suitability of existing foundations be checked on site and confirmed by structural engineer BCO approval TOP OF BRICK PLINTH TBC +0.600 U/S WALL PLATE TBC +2.250 TOP OF LOWER SLAB -0.180 U/S BARN HIP SOFFIT TBC +3.625 TOP OF SLAB DATUM 0.000 TOP OF BRICK PLINTH TBC +0.600 U/S WALL PLATE DOOR HEAD TBC +2.250 FF FFL TBC +2.450 GF FFL +0.082 GF FFL +0.082 clay tiles to match existing 2100 1100 2100 ED. 02 ED. 03 WG. 07 WG. 08 1000 440 1950 DPC DPC egress window safety glass to spec safety glass to spec safety glass to spec wood burning stove flue outlet located min 2300mm horizontally from roof weathered surface, min. as high as ridge and min. 1000mm from flue intersection with roof weathered surface Provide continuous ventilation at soffit over insulation to ventilate roof void. Provide continuous ventilation at soffit over insulation to ventilate roof void. 2462 horizontal timber weatherboarding to match existing brick plinth to match existing 1100 exactly 1100mm from FF FFL Balustrading to be 1100mm high above the finished floor level for guarding The balustrading to be at such centres so that 100mm sphere would be unable to pass through. Ensure the proposed guarding achieves the containment performance in BS 6180:2011. Manufactures details and justification is required not bespoke design. WF. 02 brick plinth to match existing horizontal timber weatherboarding to match existing 2100 TOP OF BRICK PLINTH TBC +0.600 U/S WALL PLATE TBC +2.250 TOP OF LOWER SLAB -0.180 U/S BARN HIP SOFFIT TBC +3.625 TOP OF SLAB DATUM 0.000 GF FFL +0.082 clay tiles to match existing 2100 471 1950 2100 900 925 46 degree pitch WG. 03 WG. 05 WG. 12 WF. 01 safety glass to spec safety glass to spec safety glass to spec safety glass to spec DPC DPC horizontal timber weatherboarding to match existing window and timber frame panel infill in existing structural opening vertical timber weatherboard egress window egress window wood burning stove flue outlet located min 2300mm horizontally from roof weathered surface, min. as high as ridge and min. 1000mm from flue intersection with roof weathered surface mechanical extract ductwork to run vertically through ceiling Provide continuous ventilation at soffit over insulation to ventilate roof void. Provide continuous ventilation at soffit over insulation to ventilate roof void. Provide continuous ventilation at soffit over insulation ventilate roof void. 2462 1100 exactly 1100mm from FF FFL 01 02 03 04
home.
cottage is located within the curtilage of a Grade II Listed farmhouse surrounded by agricultural land. The project involves the conversion and extension of a redundant oak frame hay storage barn into a country
finishes.
communicated directly with the clients, consultants and Building Control Officer. I prepared, submitted and acquired Building Control approval, produced all drawings and specifications, and assisted the Ecology consultant in obtaining all relevant permits associated with the presence of wildlife on the site.
The entire building features a bespoke solid oak frame and traditional vernacular external materials and
Throughout all of the stage 4 design process, I
floor ga plan 02-first floor ga plan 03-side elevation 04-detailed section AA
Retrofit C3 Dwellinghouse Biddenden Stage 4 Nov.19-Jan.20
Private
Development C3 Dwellinghouse
Shadoxhurst Stages 2+3 Apr.-May.19
The project is a new built, multi unit, private residential development aimed at retirees, comprising 34 units featuring a mix of flats and bungalows on a redundant rural site.
In collaboration with and under the guidance of a senior architect, I assisted with the development of the dwelling units’ design at stages 2 and 3.
I drafted the floor plans, elevations, street scenes and contributed to the final master plan production in preparation for the Planning Application package.
01-stage 3 south street scene
02-stage 3 east street scene
03-stage 3 west street scene
01 02 03
Development C3 Dwellinghouse Standen Stages 2+3 Oct-Nov.17
The project is a residential development consisting of the conversion of 2 existing derelict concrete frame barns into 2 luxury dwellings. The development is located in a rural area surrounded by sporadic farmhouses.
I developed the proposal throughout stages 2 and 3 under guidance and supervision from a senior designer, adhering to Permitted Development Class Q parameters. The units retain the form and volume of the original structures and are treated externally with natural timber cladding and a standing seam zinc roof. The dwellings feature ample airy mezzanine communal spaces.
I produced all drawings in preparation for a Lawful Development Certificate application.
01-unit
06-unit
08-unit
01 05 07 03 02 06 08 04 09 10 11 12
ground floor plan
first floor plan
2 first floor plan
1 front elevation
1 ground floor plan 02-unit 2
03-unit 1
04-unit
05-unit
2 front elevation
rear elevation
07-unit 1
2 rear elevation
prior project
built 12-unit
built
09-unit 2
10-unit 1 prior project 11-unit 1
2
Private Retrofit C3 Dwellinghouse Hawkenbury Stages 1+2+3
Jun.-Jul.19
Located within the expansive curtilage of a Grade II Listed farmhouse, surrounded by agricultural land, the project comprises the adaptation and extension of a redundant framed stable block into a private residential annexe, intended to serve as a luxury guesthouse.
I liaised directly with the client throughout stages 1, 2 and 3 to establish all crucial elements, including the schedule of accommodation, feasibility of desired features, the layout and design, planning permission route and principles of fabric retrofit.
The design features ample high clerestory glazing, an infill extension that transforms the stables into a symmetrical monolithic block, an internal courtyard and retention of the original shape and mass.
I developed the design, produced all drawings, prepared, submitted and successfully acquired planning permission.
01-stage 3 floor plan
02-stage 3 front elevation
03-stage 3 side elevation
04-stage 3 rear elevation
05-stage 3 side elevation
06-stage 3 key section
Lounge Dining Entrance rooflight rooflight rooflight Bathroom Bedroom Study Utility Kitchen Outdoor Courtyard Store rooflight Island Bi-fold Doors French Doors French Doors rooflight rooflight Clerestory Windows Clerestory Windows Clerestory Windows Master Bedroom Wardrobe En-suite Bedroom rooflight rooflight Parking Drive Path Garden Garden Garden Gate 01 06 04 03 02 05
Private Extension C3 Dwellinghouse Broomfield Stage 4 Aug.-Oct.20
The project is composed of the addition of a conservatory to the ground floor kitchen area, hosting a dining space and replacement of a leanto element with a larger extension, housing a utility room on a Grade II Listed house in a rural area.
During RIBA Stage 4, I directly collaborated with the client, consultants, and Building Control Officer to develop the design and prepared, submitted and ensured building control approval as well the successful discharge of all pre-commencement planning conditions.
I produced all technical drawings, details, documents and associated specifications for all statutory approvals and construction.
01-gutter and joinery section 02-conservatory section 03-conservatory section
04-utility room section
05-utility joinery plan
06-conservatory joinery plan
07-utility joinery section
08-conservatory corner post 09-general arrangement plan
S/D H/D C/M S/D H/D S/D A A B B C C Dining Kitchen Utility Bedroom Shower Room Living Store Study Snug Hall existing IC Patio Seating Area KEY mechanical extract ventilation smoke detector heat detector CO detector SVP soil vent pipe RWP rain water down-pipe IC inspection chamber surface water drain run foul water drain run ED W external door window existing walls to be demollished SP soil pipe BIG back inlet gulley RL roof light concealed RWP concealed RWP existing IC existing IC RWP structural support as designed by strct. eng. structural support as designed by strct. eng. structural support as designed by strct. eng. structural support as designed by strct. eng. structural support as designed by strct. eng. ED.01 ED.02 ED.03 W.01 W.02 W.03 post by strct. eng. post by strct. eng. post by strct. eng. post removed New masonry fixed via Ancon staifix starter profiles vertical DPC New masonry fixed via Ancon staifix starter profiles vertical DPC span of rafters Suitability of existing structural elements retained to be checked on site by structural engineer to BCO approval. All dimensions indicative only where existing construction to be retained final dimensions to be checked and confirmed on site. up up masonry wall to spec sw timber stud wall to spec RL.01 482 1400 mm RL.02 482 1400 mm RL.03 482 1400 mm RL.04 482 x 1400 mm structural support as designed by strct. eng. bi-fold doors safety glass spec bi-fold doors safety glass to spec bi-fold doors safety glass to spec up 100 4198 100 1638 1463 1472 x [825] 175 1340 797 x [825] 789 665 3219 x [2100] TBC 6036 2173 303 2475 TBC 100 5506 x [1950] 100 120 5706 100 3164 x [1950] 100 3364 3487 5949 15l/s 15l/s Surface and fowl water drainage position, design levels TBC on site and approved by BCO 120 745 x [1950] 100 1088 existing well be infilled line with strct. eng. specification and to BCO approval span rafters surface water drainage to connect to existing/new soakaway with position, design & levels TBC on site and approved by BCO up 150mm step up 150mm step retain existing door and frame protect during construction retain existing door and frame protect during construction new gas combi boiler to replace existing system under-floor heating system manifold be installed below work-top under-floor heating system spec under-floor heating system to spec under-floor heating system to spec 1912 337 1012 337 337 patio area to be extended as shown; pool area paving stone to be removed and re-layed as finish for the extended area french drain brick slot perimeter drain brick slot perimeter drain 3474 TBC 3762 TBC 1040 TBC 1195 TBC post by strct. eng. Span of Beam Block Floor Span of Beam Block Floor Span of Beam Block Floor structural support as designed by strct. eng. outline of new foundations shown dashed GF FFL/DATUM 0.000 SSL -0.150 TOP OF PARAPET +2.335 foundations shown indicatively only design by strct. eng. BCO approval ED.02 bi-fold doors safety glass to spec W.01 RL.02 482 1400 mm secret gutters formed suit falls code lead lead capping glass roof by specialist code lead flashing junction with existing FFL to line through with existing main house ensure new DPM linked existing DPM timber cornice rafters strct. eng. 1950 structural support strct. eng. walls below DPC spec existing lean-to extension floor removed safety glass spec insulated upstand brick slot perimeter drain structural support strct. eng. existing timber beam to be retained min. 150 beam and block floor by specialist ventilated void telescopic vent air brick cavity tray weepholes GF FFL/DATUM 0.000 SSL -0.150 TOP OF PARAPET +2.335 W.01 safety glass to spec secret gutters formed suit falls code lead lead capping glass roof specialist FFL to line through with existing main house ensure new DPM linked existing DPM brick plinth timber cornice structural support strct. eng. walls below DPC spec insulated upstand ED.01 safety glass spec 1950 1950 brick plinth walls below DPC to spec code lead flashing at junction with existing roof pitch structural support by strct. eng. insulated upstand lead capping timber cornice rafters by strct. eng. french drain brick slot perimeter drain brick min. 150 telescopic vent beam and block floor by specialist ventilated void telescopic vent air brick foundations shown indicatively only design by strct. eng. BCO approval foundations shown indicatively only design by strct. eng. BCO approval exist house FFL/DATUM 0.000 SSL -0.300 TBC U/S WALL PLATE +1.950 FFL -0.150 U/S EAVES +1.825 walls below DPC spec ensure new DPM is linked existing DPM 20° roof structure by strct. eng. structural support strct. eng. clay tiles match existing W.02 code lead flashing junction with existing provide min. 25mm continuous ventilation throughout entire roof DPC linked cavity tray masonry wall spec facing brick 150 roof construction spec Onduline Ondutile roof underlay system 150 ensure 50mm clear gap above insulation vented open eaves min.25mm continuous gap and insect mesh french drain foundations shown indicatively only design by strct. eng. BCO approval min. 150 beam and block floor specialist ventilated void telescopic vent air brick GF FFL/DATUM 0.000 SSL -0.150 TOP OF PARAPET +2.335 foundations shown indicatively only design strct. eng. to BCO approval ED.02 bi-fold doors safety glass spec W.01 RL.02 482 1400 mm secret gutters formed suit falls code lead lead capping glass roof specialist code lead flashing at junction with existing FFL line through with existing main house ensure new DPM linked to existing DPM 8° timber cornice rafters by strct. eng. 1950 structural support by strct. eng. walls below DPC to spec existing lean-to extension floor removed safety glass to spec insulated upstand brick slot perimeter drain structural support by strct. eng. existing timber beam be retained min. 150 beam and block floor specialist ventilated void telescopic vent air brick cavity tray weepholes GF FFL/DATUM 0.000 SSL -0.150 TOP OF PARAPET +2.335 W.01 safety glass spec secret gutters formed suit falls code lead lead capping glass roof by specialist FFL to line through with existing main house ensure new DPM linked to existing DPM brick plinth timber cornice structural support by strct. eng. walls below DPC spec insulated upstand ED.01 safety glass spec 1950 1950 brick plinth walls below DPC to spec code lead flashing junction with existing 8° roof pitch structural support by strct. eng. insulated upstand lead capping timber cornice rafters strct. eng. french drain brick slot perimeter drain air brick min. 150 telescopic vent beam and block floor specialist ventilated void telescopic vent air brick foundations shown indicatively only design strct. eng. to BCO approval foundations shown indicatively only design by strct. eng. BCO approval 228 53mm timber cill (inc. draft excluder) weather bar 75 80mm door head 100 55mm top rail 80 x 50mm bottom rail 50 170mm Outside Inside 12mm thick double glazed IGU 12mm thick double glazed IGU 35mm hardwood decorated fascia 215x50mm softwood treated former planed to form fall Code lead flashing 35mm hardwood fascia WRP hardwood moulding ref C682 150x350mm secret gutter formed to suit falls code lead finish over OSB3 deck insulated upstand 32.5mm insulated plasterboard beam by structural engineer glazed roof by specialist 12mm thick double glazed IGU powder coated aluminium frame brick plinth WRP timber moulding ref C896 WRP timber moulding ref S1223 WRP hardwood moulding ref D1163 timber rafters by structural engineer to receive chamfer at bottom and painted min. 25mm deep softwood firrings to create fall 228 53mm timber cill (inc. draft excluder) 80 x 50mm bottom rail 12mm thick double glazed IGU 80 x 50mm top rail 100 55mm window head 50x35mm horizontal glazing bar facing brick Outside Timber Door frame Ex. 100 55mm Inside Door Siderail Ex. 50 50mm 12mm thick double glazed IGU 12mm thick double glazed IGU 12mm thick double glazed IGU Door Siderail Ex. 50 50mm Door Siderail Ex. 50 50mm Inside door manufacturers cill extension 258 120x50mm softwood timber timber frame slimline double glazed bifold door 65mm square rain water pipe 25mm thick softwood timber fascia 37.5mm insulated plasterboard steel post as specified by structural engineer 20x20mm ovolo timber window bead outside inside 80 50mm side rail 100 x 55mm window jamb 12mm thick double glazed IGU 80 50mm stile external cill 50x35mm vertical glazing bar internal cill 80 50mm side rail 100 x 55mm window jamb facing brick 01 05 06 07 08 01 03 04 09
Private Annexe C3 Dwellinghouse Sissinghurst Stages 1+2+3 Nov.20-Jan.21
Situated within the curtilage of an isolated house surrounded by woodland, the project consists of the retrofit and extension of a redundant ancillary building into a residential annexe for use as a luxury guesthouse.
Throughout RIBA stages 1, 2 and 3, I liaised directly with the client to establish the layout, appearance, access, design, planning permission route and the principles of external fabric retrofit.
The design features an open plan kitchen dining living space, balcony terrace with a framed view towards the forest, en-suite bedroom and bedspace/ study area in the existing roof space. Externally, the building is treated with a mix of timber cladding and a lead roof for the extension.
I designed the scheme, produced all drawings, prepared, submitted and monitored the planning application process, resulting in the sucesfull approval of the project.
01-stage 3 rear elevation
02-stage 3 side elevation
03-stage 3 site plan
04-stage 3 ground floor plan
05-stage 3 key section
Parking log burner Bedroom 1 Kitchen Dining Shower Room Utility Pantry Store Living En-suite Wardrobe pocket door pocket door Cloaks Store ramp down garden sliding doors F/F Balcony flat roof lantern existing SVP pocket door A A Entrance Garden 02 01 03 04 05
Housing+Community Walworth London Sep.16-Jun.17
The project represents a response, critique and future speculation exercise regarding central urban developer housing trends that have coalesced over the last decade.
The proposal aims to establish a community based, built to rent council run housing estate. Its objective is to foster social interaction and facilitate the formation of long-term relationships among young, single individuals within a close-knit community setting.
The development consists of compact, affordable dwellings, offering essential amenities tailored to a micro-living environment.
01-scheme isometric view 02-central square view 03-dwelling cluster view 04-development concept model 05-spatial relationship model 06-dwelling cluster courtyard 07-scheme site section
01 02 06 04 05 03 07
Housing+Community Walworth London Sep.16-Jun.17
The scheme features its own water supply source with re-use and sustainable filtration systems. Coupled with rainwater harvesting, these systems effectively reduce on-site resource consumption and pollution. Interconnected canals and ponds serve as visual amenity features, establishing water as a unifying lifestyle choice for residents. All dwellings adhere to Passivhaus Standard principles, incorporating high-insulation levels and MVHR technology to enhance thermal comfort while minimizing fuel consumption and carbon dioxide emissions.
01-dwelling cluster plans
02-cella high level detail plan
03-scheme master plan
01 02 03
All content within this document, including images, text, logos and graphics is the property of Alex Marinescu [the document’s author] unless otherwise stated. The content may not be reproduced, distributed, transmitted, displayed, or otherwise used without the prior written permission of the author. This document is designed to be viewed and printed in A3 landscape format and may be printed, in whole or part thereof, by prospective employers for review and recruitment purposes only.
drawings and graphics produced by the author utilising Autodesk AutoCAD, Trimble SketchUp, Adobe Photoshop and Adobe InDesign. Original drawings produced by the author whilst employed at Kent Design Studio ltd. unless otherwise stated.
Front cover image - Tate Modern chimney brickwork detail - author’s own photograph.
©