PRINCE2
Answer: d) Focus on products
Answer:
c) Project Assurance
Answer:
c) Senior User
Que.: 04. ABC
experience of delivering training projects that respond to new legislation. Previous projects have had to change the acceptance criteria, due to further updates being made to legislation during the project.
What action should be taken to address this, and why?
Options:
a) Agree and prioritize the acceptance criteria during the initiation stage, because they can be amended through change control, if needed
b) Set the quality tolerances for the acceptance criteria in the product descriptions, because quality tolerances define the acceptable range
c) Agree and prioritize the acceptance criteria during the initiation stage, because these criteria will be used to determine if the project can be closed
d) Set the quality tolerances for the acceptance criteria in the product descriptions, because this would allow for additional changes in legislation
has
Answer:
a) Agree and prioritize the acceptance criteria during the initiation stage, because they can be amended through change control, if needed
Que.: 05. A change authority has been appointed for the project. During the development of the 'classroom-based training material', a large number of changes were proposed to the design of the 'e-learning course'.
Therefore, the change authority has decided to use the Moscow technique to prioritize changes based on the impact they will have on completing each stage on time. Is this an appropriate application of the Moscow technique, and why?
Options:
a) No, because it should define scope tolerances, supporting the management by exception principle
b) Yes, because it should be used to prioritize change based on the estimated impact on time
c) Yes, because it is a prioritization technique that should be used to prioritize a product's quality criteria
d) No, because it should be used to prioritize change based on the project's business justification
Answer:
b) Yes, because it should be used to prioritize change based on the estimated impact on time
Unique Features Continued….
● If a candidate wants to know about PRINCE2 Practitioner 6th Edition training detail, our website provides information about that too.
● A candidate is able to know about his performance depending on the result section of PRINCE2 Practitioner 6th Edition online test.
● Marks obtained could be a motivator factor to prepare more or less depending on the result.
● Last but not the least, we have a money back policy in our website,that makes us really unique.
● Testimonials written on the website, could be helpful to choose our website, as these are shared by our valuable users, who availed our online practice test.