Kilkenny City Bus Network Presentation

Page 1

Kilkenny City Bus Service

Presentation to Kilkenny City Municipal District Committee 16 th February, 2018 Simon Walton


Background and Introduction • Objective of KCC to support the introduction of a Kilkenny City Bus Service (Mobility Management Plan 2009) • Objective of NTA to expand public transport town services • NTA has determined that there is demand for regular public transport within Kilkenny City and that such demand cannot be met on a commercial basis • Kilkenny City Bus Service will be a Public Service Contract (4 to 5 years) i.e. fully subsidised by the State • Design of the Kilkenny City Bus Network has been completed by NTA in consultation with KCC


ROUTE DESIGN

Trips - Origins (yellow)/Destinations (purple)


ROUTE DESIGN Population density


ROUTE DESIGN Car Ownership


Red Route


Green Route


General Description of Routes

Green Route ( 8.5km, 16 stops, 2 buses/hour) Purcellsinch Business Park – Leggettsrath - Old Dublin Road – Johnswell Road – Beechlawns – Newpark Shopping Centre – Pennyfeather Way – O’Loughlin Road – McDonagh Jucntion – John St. Upper – Market Yard – Irishtown – Vicar Street – Banim Terrace – Sycamores – St. Lukes Hospital

Red Route (8.7km, 21 stops, 2 buses/hour)

Loughboy Retail Park – Watershed – Loughboy Shopping Centre – Laurel Drive – Larchfield – Waterford Road – Patrick Street – Ormonde Road – College Road – Old Callan Road – Gaol Road – Dominic Street – Dean Street – Irishtown – Markey Yard – John Street Upper – McDonagh Junction – Castlecomer Road – Newpark Hotel - Glendine


Key Provisions of the Kilkenny City Bus Service • Half hourly service • Monday to Friday 7am to 10.30pm • Saturday 8am to 10.30pm • 4 Buses 2 per route • Hourly Service • Sunday • 2 Buses

12pm to 5pm 1 per route

• Leap cards will be available but cash fares and DSP passes will also be accepted • A limited number of new stops will include bus shelters • Real Time Passenger Information is envisaged for the service


Timelines to Introduction • NTA o procure 4 busses from their National Framework for bus supplies. (2 buses to operate per route) Q1 – Complete o complete a 2 stage tender process to appoint an operator (4 or 5 year contract) for the two routes.  Pre-qualification (Stage 1) – Complete  4 Shortlisted Operators  Tender Documents for Stage 2 - Underway • KCC o introduce the 68 bus stops required for both routes, works to commence March/April 2018. • NTA/KCC o enable awareness raising and promotion of the new service Q2/Q3 2018 • Likely commencement date for service is Q4/2018 or Q1/2019


Thank You

Any questions?