In this portfolio I inserted some of the jobs that I was the main person in charge, or I was part of a development team. I worked in general in the Development of Project Design, in the Implementation of BIM Technology, acting as BIM Manager and Development of Technical Drawings for approval with public agencies. I also accompanied the whole process of Planning and Execution of the Works. I present here in general the Digital Prototypes of Projects. 2


3


4


Was the principal of the project. The Developer's interest was to develop a mixed-use Building, with residential/commercial/institutional. I started with the study of Local law, and possession of this information the next step was the Full Development of the project, with its Artistic and technical Designs and your computer model. Also was given the technical and economic feasibility study, to show that the expectations of the entrepreneur, would be being met. Has already been given the entry of Legal project, which is in the process of being approved by the municipality.

5


6


7


8


9


10


11


12


13


Was the principal of the project. Realized the technical feasibility studies, technical drawings and the development of the computer model. Has already been given the entry of Legal project, which is in the process of being approved by the municipality.

14


ACCESSES AND CONNECTIONS

15


STUDY OF LEGISLATION

16


INFRASTRUCTURE

17


INFRASTRUCTURE

18


DIGITAL PROTOTYPE

19


DIGITAL PROTOTYPE

20


DIGITAL PROTOTYPE

21


DIGITAL PROTOTYPE

22


In this Helicentro project, was the architect responsible for all its stages, which were: -Reference Designs study; -Study of the Local Legislation for the implementation of a project with so many quirks and restrictions; -Technical feasibility Study; -Elaboration of a program where needs were met the special needs of such a venture, while continuing to take into account your economic viability; -Development of Draft; -Simplified Legal Project; -Drainage project; Earth moving project; - Digital prototype construction (Mockup); -Planning of the work. For being a project with special features, a change in zoning Law, to restrict construction in your feedback. The land on which is built the Helicentro has passed by Earth moving phase and begins to have the first infrastructure works in progress.

23


ACCESS/PARKING/ED. ADM/HANGARAGE

DIGITAL PROTOTYPE CONSTRUCTION

ADMINISTRATIVE BUILDING

24


CONTROL ROOM/REFUELING STATION/PARKING BAY

DEPLOYMENT

ADMINISTRATION BUILDING/PAINTING HANGAR

25


APPROACH

STOP APPROACH OF AIRCRAFT

APPROACH

26


27


In the design of this Educational Complex, which will satisfy the Child, Fundamental levels l and ll until high school, I was member of a group of three architects, where I developed several tasks, including: - Field survey; - Technical feasibility study, Study and Study neighborhood impact; - Study of educational standards and for scaling buildings; - Preparation of the program of needs.; - Preparation of technical drawings and computer model; - Earth moving project; - Development of planning and schedule of work; - Meetings with employees of complementary projects (electrical, Structure, coverage, fireman, hydraulic) request for Entry of a building permit. Details of the project. The project is in the construction of your first stage, with completion scheduled for the end of this stage 2018.

28


29


30


31


32


33


34


35


36


In the design of this building Multifamily Residential (HIS), were respected all the assumptions imposed by edict of banking competition Planner. The legal restrictions passed where the same would be deployed, your feedback, the amount of housing units that should be contemplated, variations of the type of housing units to the type of material and construction system to be used in your future construction. The design intent was to give '' MOVEMENT '' to all its facades, integrating also the design of the building concepts of sustainability. The work of Legal Study and development of complete project was developed by me and another architect. We were not the chosen by the newsstand, but it was excellent opportunity.

37


38


39


40


41


In the design of this Venture was responsible for part of the technical feasibility Study, 2D and 3D images, and every computer model. The project is at the stage of Incorporation by the owner of the land and one of the Investors.

42


43


44


45


The project of this CHAPEL had the opportunity to work on all fronts work as possible. I was part of a team of Architects where I participated: - Making the field Survey of the land; - Participated in the program Study of needs and project Layout; - I developed the Executive design and Detailing; - I was part of the computer model; - I followed the process of approval with the city; - I was part of the team for planning and monitoring of execution of the Work.

46


47


48


49


50


51


52


53


54


55


56


No projeto deste Edifício Residencial fui responsável por fazer toda a Modelagem do Projeto em REVIT e SKETCHUP Foi modelado todo o projeto de Arquitetura, Estrutura, Hidráulica e seu Terreno Existente. Com esta modelagem fiz todo o Projeto Executivo e seu Detalhamento, também todo o Cálculo de Corte e Aterro de Movimentação de Terra e seu Projeto de Terraplanagem. Foi possível fazer também toda a compatibilização no NAVISWORKS entre as disciplinas de projeto citadas acima e antecipar as possíveis interferências, antes delas acontecerem em obra. Além dos desenhos técnicos, também foi possível obter as imagens internas e externas para a apresentação do projeto. Para isso foram usados softwares como o Lumion, Photoshop e Corel.

EDIFÍCIO COMPATIBILIZADO – MAQUETE ELETRÔNICA

57


PROJECT LOCATION

58


Apartment-Living Room

Apartment-Balcony Gourmet

Apartment-Pool

Coverage – Ballroom

ILLUSTRATIVE IMAGES

59


ACCESS TO THE ARCHIVES – BIM MODELING

60


LEGAL PROJECT

The Legal project, is the first design that the person responsible for compatibility in BIM have, to do the modeling project.

61


COMPLEMENTARY INFORMATION

01-list of project information

02-Descriptive Memorial

03-tables and Notes

62


MODELING AND RENDERING OF THE PROJECT IN REVIT

01-Legal project

02-Modeling in Revit

03- 3D Prototype completed-BIM

63


MODELING AND RENDERING OF THE PROJECT IN REVIT

04-BIM model error to be corrected

05-BIM Model fixed

64


MODELING AND RENDERING OF THE PROJECT IN REVIT

01-Legal project

03- 3D model

02-change in structural design

04 - Interference

05- Solution found

65


Structural Plant-Floor Type According to the phases of the project will evolve, the information and drawings posted at Autodoc for all designers, they come with more and more detailed information that the Legal project, see example above, which enables greater precision in the BIM model.

66


COVERAGE BOTTOM POOL

Superimposition of model Plants BIM, for interference detection and modeling of design disciplines.

TYPE FLOOR

UNDERGROUND PLANIALTIMÉTRICO

67


Some products obtained in modeling and Making BIM.

Tables Digital Prototype

Technical plants and detailing

3D cutting

68


COMPATIBILITY OF THE PROJECT IN AUTOCAD

Compatibility of the disciplines in DWG 69


COMPATIBILITY OF THE PROJECT IN AUTOCAD

Plant overlay– ARQ / ESTR / HID / PAIS

70


COMPATIBILITY OF THE PROJECT IN AUTOCAD

2- Specification of finishing materials of the facade

1 - Compatibility – ARQ/ESTR

3 – Hydraulic specification

4- Specification in the Foundation

71


COMPATIBILITY OF THE PROJECT IN NAVISWORKS

Importing Revit model to the Navis

Quickly and accurately, the Naviswork makes an analysis of all existing disciplines interference in the

72


COMPATIBILITY OF THE PROJECT IN NAVISWORKS

List of Conflicts pointed to by the program

Image finding exactly where the interference.

73


COMPATIBILITY OF THE PROJECT IN NAVISWORKS

List of Conflicts and visualization

Enlarged detail of interference found

74


In the design of this complex, was the architect responsible for the project. Since your feasibility study, until the application for approval of the project at City Hall for your construction. The project was conceived within the BIM TECHNOLOGY. Having his first studies being done in AutoCad, to then be forwarded for modeling in Revit. After the construction of the Digital Prototype in Revit, the template is forwarded to the LUMION, where adjustments were made, for the generation of images that would be used in your presentation.

75


76


77

DEPLOYMENT


78

ESTUDO DE VIABILIDADE E ACESSOS


79


80


81


82


83


84


85


86


87


88


89


90


91


92


93


94


95


96


97


98


99


100


101


102


103


104


105


106


107


108


109


110


111


112


113


114


115


116


117


118


119


120


121


122


123


124


125


126


127


128


129


130


131


132


133


134


135


136


137



Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.