Imagine the result
Bridges Statement of Qualifications
Statement of Qualifications Bridges
Picture on the frontside, Bridge ‘Trois Bassins’, France 2
Statement of Qualifications Bridges
Contents Introduction 7 Your challenges 9 Create a functional and stunning civic icon Mitigate construction risks Provide long-term viability
9 9 9
Our solutions
11
Research programs
11
What we deliver
12
Consultancy in the planning of large bridges Project and program management Project design and engineering Surveys Maintenance / rehabilitation / retrofit Large prestressed concrete bridges Steel bridges Cable supported bridges Maintenance and restoration Arch bridges
12 12 13 13 13 14 14 14 14 15
Why ARCADIS?
17
The design process
21
Selected references
22
Where can you find us?
31
Imagine the Result 3
Statement of Qualifications Bridges
Millau Bridge, Millau France 4
Statement of Qualifications Bridges
5
Millau Bridge, Millau France 6
Statement of Qualifications Bridges
About ARCADIS ARCADIS is an international company that delivers consulting, engineering and project management services for infrastructure, environment and buildings. For more than a century, we have stood apart from the competition because of our commitment to leave the environments, places and lives we touch better than we found them. We strive to create balance by establishing equality, harmony and stability between the creative and the functional, between nature and the built environment, between present needs and future legacy, and between imagination and results. What does this mean for you? As our client, you will benefit from our commitment to mobility, sustainability and quality of life. You will work closely with experts strategically drawn from our 15,000 proficient and dedicated professionals, each of whom understands the importance of providing tailored solutions to your unique goals and challenges. You will benefit from our local positions within a highly integrated global network, and consequently, you will have access to both the best of our worldwide knowledge and our region-specific expertise. Most importantly, you will receive a project that provides value - civic, financial, environmental, social, economic - today and well into the future.
Millau Viaduct Millau, France Imagine A bridge that can span the 2.5-kilometre wide Tarn Valley, 250-metres above the ground from Causse Rouge to Causse du Larzac. A design competition won by a team of engineers and architects under the technical leadership of ARCADIS. The Result An innovative, multiple-span cable-stayed bridge, breaking records and gaining international praise. The bridge carries the A75 motorway, with two lanes in each direction, and a total with of 27-metres. The deck is a unique multispan cable-stayed structure, comprising six 342-metres typical spans and two 204-metres side spans. Each pier is extended above the deck by a pylon carrying the cable stays.
7
Statement of Qualifications Bridges
Suspended Through Girder Bridge Terneuzen, The Netherlands 8
Statement of Qualifications Bridges
Your challenges Create a functional and stunning civic icon Bridges often become sources of community pride and landmarks capable of symbolizing the cities and regions in which they are located. For centuries, bridges in places from San Franscisco to Millau have been providing us with icons that are inextricable from the character and identity of their locales. The bridges that have achieved such noble status are those that reflect local history, complement the environment, and offer aesthetically striking design. At the same time, bridges are only as successful as their resilience and reliability. They must blend aesthetics with safety, durability and ease of access. They must undergo careful maintenance and/or retrofitting to increase capacity and improve safety and mobility for the community. They must be designed and constructed for effective planning, management, optimization and control.
Mitigate construction risks Large bridges push construction methods and materials to their limits. Civil engineers know that these structures pose the greatest risks and carry the heaviest loads during construction. For this reason, contractors who undertake such operations rely on highly skilled professionals, from concept through details, from risk assessment to maintenance. At all stages, they need creative engineers who are open to dialogue, able to consider or propose safe and efficient construction methods, and deliver within budget and on time.
Provide long-term viability Large bridge construction and operations are often awarded to concession companies that assume owner responsibilities, as well as contractor risks. Their needs and expectations are therefore a combination of the needs and expectations of owners and contractors, with a strong emphasis on long-term viability.
9
Statement of Qualifications Bridges
Van Starkenborgh Canal, Netherlands 10
Statement of Qualifications Bridges
Our solutions At ARCADIS, our leading bridge experts, engineers and technicians share a single vision that bridge design, more than any other type of civil work, requires the complete collaboration of structural engineering and architectural design at all stages of the process. We strongly believe that solid structural, aesthetic and functional design does not necessarily mean high costs and uncontrolled budgets. Rather, we are certain that superior and optimized structural design naturally leads to striking projects. Taking into account environment, aesthetics, economy, durability and sustainability, we advocate a holistic process, one that results in stunning and functional landmarks that stand the test of time. Our bridge specialists have devoted their careers to staying abreast of construction methods and materials; to working closely with architects, international consultants and top-notch contractors; and to delivering world-class projects, such as the Normandy Bridge, Vasco da Gama Crossing and Millau Viaduct. United by vision and passion, our professionals represent a range of disciplines, including environment, transportation, geotechnical engineering, construction economics and architecture.
Research programs ARCADIS participates in two research programs related to the bridge and structural engineering fields. Orthoplus research program with two main purposes: 1 Analyzing the fatigue behavior of orthotropic slabs under cyclic loading and verifying the influence of the overlay (no overlay, bituminous overlay). 2 Developing a new concept where the overlay is made of UHPFRC (ultra high performance fiber reinforced concrete) connected to the upper plate of the orthotropic slab. CEOS research program oriented towards the improvement of our knowledge of large concrete elements cracking generated by shrinkage and thermal variations. The main output expected is a potential reduction of passive reinforcement, which appears presently to be excessive when Eurocodes rules are applied.
Bridge over the Van Starkenborgh Canal Groningen, Netherlands Imagine A new double-track railway bridge of approximately 150-metres long over the Van Starkenborgh Canal. The addition of a second railway track on the Groningen Noord – Sauwerd route was the inspiration for the new bridge. Part of the project involved the replacement of a single-track steel truss bridge with a new double-track railway bridge. At the same time, the clearance height and width below the deck also had to be increased. The result The new railway bridge was designed as a steel arch bridge. As a result of the crossing angle, the arches are staggered slightly by a distance of 12.75-metres, which is equivalent to the hanger distance. The bridge deck sits at mid-height, and the bridge has an 89-metres central span and two unequal end spans of 28 and 36-metres. The ends of the arches are below the deck, as a result the primary horizontal loads are partially removed from the arch by an internal longitudinal tie placed at the same height as the bridge deck. At the point where it connects to the central pillars, the arch is supported by auxiliary trusses. The trusses are set at an angle of 45º and are joined to the main pillars creating a sturdy triangle.
11
Statement of Qualifications Bridges
What we deliver Our consultancy is continually being redefined. ARCADIS employees are value driven, cooperative, creative and willing to share responsibility. Value driven because we focus on project management and on creative solutions that enhance your end result. Cooperative because we work with you and your staff to provide seamless delivery. Creative because we always push boundaries. Willing to share responsibility because we know what we are doing; the quality of our large infrastructure services has been proven for more than half a century.
Consultancy in the planning of large bridges • • • •
Feasibility studies Safety requirement studies Conceptual design Risk analysis
Project and program management • • • • • • • • • •
12
Cost estimating and management Scheduling / programming Project management of the design and construction phases Risk management Bid document preparation Bid evaluation Bid procedure management Contract management Construction management and supervision Dispute and claim management
Statement of Qualifications Bridges
Project design and engineering • • • •
Preliminary design Final and detailed design Mechanical and electrical system design Independent design checking
Surveys • • • • •
Geological, geophysical and geotechnical surveys Hydrological and hydrogeological studies Meteorological surveys (wind) Environmental impact studies Monitoring program design and implementation
Maintenance / rehabilitation / retrofit • • • • •
Maintenance planning and supervision Inspections and diagnostics Damage assessments Rehabilitation consultancy Retrofit consultancy
All-Purpose Trail over Warner Road and Granger Road, Cleveland Ohio United States Imagine As part of their ongoing initiative to construct an urban pedestrian/bicycle trail to link downtown Cleveland with the Cuyahoga Valley National park, Cleveland Metroparks challenged ARCADIS to develop a structural design that reflects the Metroparks’ commitment to creating a presence for the area. The ARCADIS design team responded with a cable-stayed bridge concept that allows for longer spans and fewer supporting piers, giving the two bridges the desired look of openness and allow an unobstructed view for the adjacent business community. The result The two bridges, almost identical in size, are more than 213-metres-long. The cable stayed portions of the bridges are three-span structures with main spans of 66-metres and overall lengths of 132-metres. The 5-metres-wide superstructure consists of thru-pratt trusses fabricated from welded steel tubular members with steel floor beams and a concrete deck. The 21-metres-high H-shaped towers are constructed of steel tubular members. The towers are supported on concrete pedestal foundations with auger cast-in-place piles.
13
Statement of Qualifications Bridges
Large prestressed concrete bridges ARCADIS has designed numerous prestressed concrete box girder bridges, using a balanced cantilever method, either with precast or cast in-situ segments. Our engineers are well versed in the design and construction of these types of structures, particularly in the use of external post tensioning systems like those used during the construction of the “Trois Bassins” bridge on La Réunion Island. Our involvement with conceptual and detailed designs, as well as our technical leadership during construction, gives us a thorough knowledge of techniques and a real capacity to understand and consider each aspect of the project throughout its development. To illustrate our engineers creativity, Vecchio Bridge in Corsica is lightened with triangular openings cut into the box beam webs resulting in a unique, efficient and appealing project.
Steel Bridges Cast iron at the end of the 19th century, and iron and steel in the 20th century, the industrial revolution tremendously altered bridge design and engineering, under the leadership of engineers like Thomas Telford and Isambard Brunel in England, or Gustave Eiffel in France. During the second half of the 20th century, steel has seen a resurgence, with increased strength and quality, better protection against corrosion and improved welding methods. As a designer, ARCADIS has been instrumental in these new developments and has promoted architectural and technical innovation in this field with such projects as the bridge over the Wilhelmina canal in Tilburg (the Netherlands), Cernavoda bridge (Romania) and the Gustave Flaubert lift bridge in Rouen (France).
Cable-supported bridges The development of cable-stayed bridges began in Germany in the 1950s and 1960s and reached France in the 1970s with the opening of the Brotonne Bridge (1977). Many more followed. And ARCADIS’ expertise was there in the Calatrava bridge in The Netherlands, Mezcala Bridge in Mexico, Vasco da Gama Bridge in Portugal and, last but not least, the Millau Viaduct in France. ARCADIS engineers are at the forefront of innovation, whether its designing the first multiple cable-stayed spans in Mexico; slender decks of steel and concrete composite construction in Portugal using cantilever construction or the launching method and concrete or steel pylons to maximize efficiency. Our extensive expertise ensures our careful consideration and evaluation of all possible alternatives before selecting the most appropriate one.
Maintenance and restoration As traffic volumes, especially truck volumes, increase, owners and managers are faced with unexpected situations and cost. ARCADIS extensive expertise in bridges positions us well to help owners and managers handle these new challenges. For example: preparing maintenance plans, including organization and technical procedures; performing diagnostics; or proposing restoration or repairs based on state-of-the-art technology, like fiber reinforced polymer (FRP)reinforcements.
14
Statement of Qualifications Bridges
Arch bridges Arch bridges are timeless, epitomizing the ideal bridge. Although their features varied very little from the Roman Empire to the 18th century, there are several modern radial or crossed hangers, or struts. The arches can be vertical or inclined inward or outward. All these developments are reflected in the designs of ARCADIS engineers, like the Cernavoda tied-arch bridge in Romania with crossed hangers or the Gennevilliers rail bridge with radial hangers.
Bridges and overpasses over A2 motorway Romania Imagine A2 motorway, part of the 4th European large corridor, provides the best connection to the Black Sea coast. ARCADIS Eurometudes was involved in designing the 43-kilometres-long section Drajna-Fetesti and the rehabilitation of a 20 kilometres section of Fetesti-Cernavoda. The result The bridges have various statical scheme, according to the length of the obstacle and the requirements of the red line. The bridges were made of prestressed concrete and steel, which are traditional materials in the field of bridge construction. Concerning the cross sections of the deck, the project includes beams, continuous slab and ribbed slabs. To improve the safety of the traffic and also the structures, all the overpasses were conceived without the pier in the middle of the motorway. The bridges fully comply with the requirements of the client, trying by their aesthetic aspect to drive away the monotony of a motorway line. 15
Statement of Qualifications Bridges
Why ARCADIS? Our value At the core of every project we do are six key qualities inherent to our culture, our process and our results:
Quality We are committed to consistent service delivery across borders. All documents are reviewed by the project manager and are subject to ARCADIS’ strict quality assurance/quality control program.
Experience Since our beginnings in 1888, ARCADIS has delivered complex infrastructure projects that have withstood the test of time. Today, that longstanding knowledge expands and grows with each project, and guarantees solutions that will help minimize risks, optimize performance and strengthen our clients’ public image.
Cost efficiency We integrate stringent cost management methodology and systems into our design and planning procedures. Our project and cost management experts allow us to offer specialized construction management services.
Speed Once started, projects are planned and implemented with a sense of urgency and coordinated by a single ARCADIS project manager with full authority to marshal and coordinate resources globally.
Communication To facilitate dynamic, instant and ongoing communication, ARCADIS has established multinational groups to maintain networks of key project managers throughout our global network. All project team members are in constant communication with our project managers, who in turn keep our clients informed on issues that could have an impact on their projects as they arise.
16
Statement of Qualifications Bridges
Advocacy During every step of a project, we represent our clients’ goals and best interests. We view ourselves as an extension of our clients’ organizations.
Our people Recognizing that our people are our most valuable asset, we have created a work environment that nurtures innovation, fosters collaboration, and rewards entrepreneurship. United by a common set of values, our professionals are given tools they need to succeed and play a critical role in where we’re going as a company. We find that this approach to our people yields the best results for our clients. Our professionals are value-driven because we focus on project management and producing creative solutions that enhance our results. Our collaboration necessarily extends to you, our clients; we find that the best solutions and seamless delivery often arise from an open and communicative relationship throughout the entire process. The knowledge we give our employees reflects more than half a century of experience on large infrastructure projects. In addition to producing greater work for our clients, these tools provide our professionals with the confidence to share responsibility and lead projects from start to finish.
Our legacy ARCADIS’ competence in bridges began in France in the early 1960s. At that time, EEG was closely associated with the development of prestressed concrete, and eventually became the leader in bridge design and engineering in France. Through the merger of EEG and Simecsol, ARCADIS ESG (the blended company) inherited this proud tradition. With approximately 300 engineers and technicians working on bridge projects in six countries (France, Belgium, The Netherlands, Poland, Romania and the United States) ARCADIS is a key actor in this field, and has the capabilities to provide clients with all the necessary services for planning, developing and executing projects, ranging from project consultancy and architecture to structural engineering and detailed design.
Gustave Flaubert Bridge France Imagine A lift bridge with 80-metres / 160-feet-high towers that fit of the river. A bridge that meets the safety concerns of road and moterway traffic. The result An elegant and light structure, combining efficiency and simplicity. An innovative and ingenious butterfly-shaped, cross-leveraged system.
17
Statement of Qualifications Bridges
Noorderlaan bridge, Belgium 18
Statement of Qualifications Bridges
Cernavonda Bridge, Romenia 19
Statement of Qualifications Bridges
20
Statement of Qualifications Bridges
The design process At ARCADIS we design bridges in multidisciplinary teams made up of engineers, architects, landscape architects and town planners. Our design expertise is based on the creation of designs based on the existing context, and meeting the demands of tomorrow. In its designs, ARCADIS takes responsibility for a sustainable living environment and spatial quality both today and more importantly, also for the future. We therefore consider each issue, from vision through management, as a special assignment that calls for a tailor-made approach to the design process. This method is translated into a design geared to the specific situation. We provide for continuity in our processes by ensuring a seamless transition between design phase and preparation phase. ARCADIS has now accrued more than 40 years of experience working together across boundaries and disciplines with proven successful collaboration between engineers and designers. The result of close collaboration between specialists from different disciplines is the creation of an integrated design. Design teams are assembled on a broad basis to make the most of every challenge. ARCADIS designers are forever in search of innovative and sustainable solutions for the world of tomorrow. This complex design process is represented on this page, from project start through to the opening of the bridge. By making use of 3D models, the design can be visualised and assessed in every phase. The pedestrian/cycle bridge featured on this page is located in Dilsen-Stokkem, Belgium. The design is the result of collaboration between ARCADIS architects in the Netherlands and engineers from Belgium and the Netherlands.
21
Statement of Qualifications Bridges
Selected references Location
Year Description
Client
Antwerp, Belgium ongoing
Oosterweel link Antwerp. New high-way connection on the TV SAM ring of Antwerp with several bridges- and tunnels in it. Total cost about 1,8 billion euro.
Elbert County, Georgia, ongoing United States
SR 72 WB over Savannah River (Richard B. Russell Lake). Georgia Department of The widening of SR 72 from 2 to 4 lanes for a distance of Transportation approximately 11.6 km. The project includes a 620-m-long, 9 span two lane bridge. The proposed bridge will parallel the existing 2 lane bridge. A spliced bulb tee superstructure will be use. 3-m-diameter single column drilled shaft bents will support the bridge
2011 Ronse, Belgium Brugge, Belgium 2010
Project N60 Ronse. Technical reference design, project EIR AWV East Flanders and risk management.This is one of the missing high-way links in Belgium. Arcadis is making the tenderdesign in a DBFM-way. It is a new road with several bridges and tunnels in it and the connection with the existing high-way. A project with very difficult geotechnical conditions. A11. Conceptual design of the missing link in the main road network between the N49 in Westkapelle Knokke and the N31 in Brugge.
AWV West Flanders
Turnhout, Belgium 2010
Slow traffic bridge over the canal Dessel - Schoten. Cycling steel arch bridge.
Municipality of Turnhout
Houthalen-Helchteren, 2010 Belgium
North-South link in Houthalen-Helchteren. Project studies AWV Limburg (including: EIR, MSIP, SSR, design) for the construction. This is one of the missing high-way links in Belgium. ARCADIS is making the tenderdesing. It is a new road (more than 10 km long) with several bridges and tunnels in it including the connection with the existing high-way.
2010 Mechelen, Belgium
R6. Extension of the R6 around Mechelen. Several new bridges AWV Antwerp (Heisbroekweg, N1 and Liersesteenweg) for the ring road around the city of Mechelen. ARCADIS makes the structural and architectural design of all bridges.
2010 Antwerp, Belgium
Noorderlaan Bridge. New bridge across the Albert Canal. The bridge has 2 decks, one is a road bridge the other part is a ligth-rail bridge. The bridge has a main span of about 80 m. The bridge is a steel box-girder bridge.
BAM
Brugge, Belgium 2010 Pedestrian and cycle bridge over the Koning Albert l lane. Municipality of Roeselare Architectural and structural design of an pedestrian bridge with a length of about 500 m. The bridge has a steel box-girder deck. The bridge is one of the viewpoints when you enter the city of Brugge. Britanny, France 2010
22
Terenez Bridge. Innovative cable stayed curved bridge with a 245 m main span. Prestressed concrete deck with steel floor beams. Inclined pylons located outside the deck.
General Council (Finistère)
Statement of Qualifications Bridges
Location
Year Description
Client
2010 Compiègnes, France
Compiègnes Viaduct. 2190 m long Motorway Bridge with spans in the range of 50 to 66 m. Precast segmental deck incrementaly launched with a unique cable stayed temporary equipment.
French State
Lummen, Belgium 2009
Lummen traffic interchange. Prestressed plate bridges. ARCADIS made the feasibility study for the construction of the bridges by sliding the plate bridge.
Jan De Nul
Brugge, Belgium 2009 Restructuring N31. Lege Weg - Bevrijdingslaan. Concrete plate AWV West Flanders bridges (ca. 20 m span) over an open tunnel part of the N31-highway. Dendermonde, Belgium 2009
Vlasmarkt Bridge. Lege Weg Fixed steel bridge (span 10 m) and Waterwegen en Zeekanaal nv simple steel draw bridge (span 12 m). Conceptual design and detailed study of steel construction and concrete construction. Conceptual design of electromechanical equipement.
2009 Ho Chi Minh City, Vietnam
Phu My Bridge. 1730-m-long roadway bridge across Saigon River. The central part is a 705-m-long cable stayed bridge with a 380-m main span.
Phu My Corporation
South Korea 2009
Busan Geoje Link. Large cable stayed bridges, part of a 8.3-km-long link between the City of Busan and Geoje Island.
GK Fixed Link
Réunion Island, France 2009
Ravine Fontaine Bridge. Steel arch bridge carrying “Route des Tamarins” across a deep valley called “Ravine Fontaine”. The 160-m arch is a box beam of variable width and depth.
Regional Council
United States, Lake 2009 County, Ohio
LAK-2-3.63 - Reconstruction, rehabilitation, widening and safety upgrading of 18.5 km of SR 2 and includes 20 mainline bridges, 10 overhead bridges, 25 culverts and 7 interchanges. The existing four-lane divided highway will be widened to a six-lane facility.
Ohio Department of Transportation – District 12
Kent, Ohio, United States 2009
Crain Avenue Bridge Relocation. Realignment of 850 m of roadway on Crain Avenue from North Mantua Street to North Water Street. The project involved replacing of a 80-m utility bridge with pedestrain and bike facilities over the Cuyahoga River and CSX railroad tracks.
Ohio Department of Transportation – District 4
Wyszkow, Poland 2008
Bridge over Bug River. Prestressed continuous 9-span beam General Directorate for National twin structure along Wyszków bypass crossing the Bug river; Roads and Motorways geotechnical analysis, architectural and construction design, “for construction” design, author’s supervision during construction phase.
Réunion Island, France 2008
“Ravine des trois bassins”. Motorway viaduct over a deep Regional Council valley. Innovative extradossed prestressing. Total length 370 m, four spans of 40-75-104-126 m).
Rouen, France 2008
Gustave Flaubert Bridge. Motorway lift bridge across the River Seine. Largest bridge of this type in Europe with 120-m lifting spans and clearance of 55 m when opened to maritime traffic.
French State
Saendelft, 2008 The Netherlands
Brigde at railway station Krommenie-Assendelft. Steel walking bridge. Span 12 m and total length 42 m.
ProRail
23
Statement of Qualifications Bridges
Location
Year Description
Client
2008 Youngstown, Ohio, United States
Spring Common Bridge. Replacement of the existing in-filled Mahoning County, Ohio steel grid bridge deck on the tied-arch and thru girder spans, concrete repairs and placement of a microsilica overlay on the frame span, miscellaneous steel repairs, and painting of all structure steel.
Troup County, Georgia, 2008 United States
Kia Boulevard over I-85. Design Build a new interchange and Georgia Department of frontage road for the new Kia Motors Plant. Transportation Transportation enhancements that included approximately 8 km of new frontage roadway as well as a new interchange for access and egress to I-85 and included the design of two new bridges and several walls.
Fetesti, Romania 2007
Portal Bridge over A2 Motorway. Bridge with prestressed concrete deck, conception and design. Total length: 71.60 m. Height of the deck 1.10-1.70 m.
Fetesti, Romania 2007
Steel/concrete Bridge over A2 moterway. Continuous deck CNADNR (National Administration with steel beams and concrete slab over A2 motorway, of Roads - Romania) conception and design.Total length 111.25 m. Height of the deck: 1.75 m.
Cricov, Romania 2007 Fetesti, Romania 2007
Bridge Cricov. Bridge with simply supported prestressed Regional Authority of Prahova concrete beams and continuous overconcrete slab, conception County and design, Total length: 93.20 m. Overpass over A2 Motorway. Overpass with prestressed concrete continuous slab deck over A2 motorway, conception and design, Total length: 26+38+26 m=90 m
CNADNR (National Administration of Roads - Romania)
Tilburg, The Netherlands 2007
Bridge over Wilhelmina canal. Cycling Arch bridge. Span 57.5 m.
Municipality of Tilburg
2007 Amsterdam, The Netherlands
Utrechtboog. Two single-track railway-bridge at 15 m above ground level with concrete fly-overs with a length of 1.5 km each.
ProRail
Rotterdam, 2007 The Netherlands
Slow traffic bridge over railways Rotterdam Central ProRail Station. Box girder bridge on 7 colomns with a total length of 135 m and a width of 5 m.
Fulton County, Georgia, 2007 United States
5th Street Pedestrian Plaza Bridge over I-75/85, Design-Build. The new Fifth Street Bridge is a two-span bridge with lengths of 42 m (span 1) and 36.4 m (span 2). The bridge width is 68 m. Each side of the roadway has a 7.3 m-wide sidewalk. While the total bridge width is more than 68 m, more than 38 m are landscaped areas, with 23 m provided on the north side and more than 15 m provided on the south side.
Palestine, Texas, 2007 United States
LOOP 256. The proposed LOOP 256 project replaces both the Texas Department of existing Wells Creek and Union Pacific Railroad Bridges with Transportation, Tyler District a 7-span, 143-m bridge with Type C beams and 0.75-m drill shafts.
Lisbon, Portugal 2006
Lizeria Bridge. 12-km motorway bridge, with a main bridge over Tagus River and a tresle across a flood plain. Prestressed concrete decks. High seismic actions.
24
CNADNR (National Administration of Roads - Romania)
Georgia Department of Transportation
Brisa (concession company)
Statement of Qualifications Bridges
Location
Year Description
Client
2006 Valley View, Ohio, United States
Ohio and Erie Canal Towpath Pedestrian Bridges. Two cable-stayed bridges with main spans of 66 m and overall lengths of 132 m. The 4.9-m wide superstructure consists of thru-pratt trusses fabricated from welded steel tubular members with steel floor beams and a concrete deck. The 21-m high H-shaped towers are constructed of steel tubular members.
Cleveland Metroparks
Bielsko-Biala, Poland 2005
Overpass over expressway S1. One span overpass. Reinforced concrete integral bridge (frame structure) 47-m long. Architectural and construction design. Geotechnical analysis. Design during bid phase. Designer’s supervision during construction phase.
General Directorate for National Roads and Motorways
Ogrodzona, Poland 2005 Ogrodzona Bridge. Bridge crossing expressway S1 over valley General Directorate for National 25-m deep. Prestressed concrete beam bridge 314-m long. Roads and Motorways Architectural and construction design. Geotechnical analysis. Design during bid phase. Superstructure constructed with derrick scaffolding. Designer’s supervision during construction phase. Cieszyn, Poland 2005
Pedestrain Bridge over S1. Prestressed concrete frame General Directorate for National structure crossing expressway with one span. Architectural and Roads and Motorways construction design. Geotechnical analysis. Designer’s supervision during construction phase.
Noord-Brabant, 2005 Nature Bridge Groene Woud crossing highway. Nature bridge width a span of 52 m and a with of 50 m. The Netherlands
Rijkswaterstaat
DeSoto Parish, Louisiana, 2005 United States
U.S. 171 Sabine Parish Line to South Mansfield. Twin bridge structures in a horizontal curve that span two railroad tracks for the Mid Louisiana Rail Corporation. Bridges are comprised of AASHTO Type 3 and Skewed Type 4 PPC Girder Spans with reinforced concrete pile bents.
Louisiana Department of Transportation and Development
Palestine, Texas, United 2005 States
SH 154. A 170-m x 21-m, 14-span bridge with prestressed slab beams built on the existing centerline. For the upstream end, the proposed relief culvert will remove 4.3 m of existing concrete box culvert and be extended 30.5 m using 2 45-degree bend joints and a FW-45 (end treatment). For the downstream end, the proposed relief culvert will remove 2.1 m of existing concrete box culvert and extend 23 m using 1 45-degree bend joint and a Safety End Treatment (TY I)(3:1).
Texas Department of Transportation, Tyler District
Tarn, France 2004
Millau Viaduct. Exceptional multi-span cable-stayed bridge, carrying A75 motorway across the deep Tarn valley. Total length of 2460 m with 342-m typical spans. Concrete piers, up to 240 m tall, are among the tallest in the World. Steel box deck with orthotropic slab.
French State
Groningen, 2004 The Netherlands
Bridge over the Van Starkenborgh canal. Two-track steel arch bridge. Span 152 m over water.
ProRail
Hilversum, 2004 The Netherlands
Nature Bridge Crailo. Crossing railways 130-m long and 50-m wide natural bridge.
Gooisch Natuur Reservaat and ProRail
25
Statement of Qualifications Bridges
Location
Year Description
2004 Amsterdam, The Netherlands
Two slow traffic bridges over the East and West entrance to Amsterdam Central Station. Two steel arch bridges of 28- and 31-m length. Each bridge has a width of 2.5 m for pedestrains and a 3.5 m broad cycling lane.
Tilburg, The Netherlands 2004 Two slow traffic bridges near railway station Tilburg Reeshofweg. Two steel box girder bridges on 3 colomns with a total length of 35 m and 42 m and a width of 5.3 m.
Client Municipality of Amsterdam
Municipality of Tilburg
United States, DeKalb 2004 County, Georgia
410-m-long bridge over I-285 and Nancy Creek Tributary. This is pedestrian and bicycle friendly bridge. The 9-span bridge consists of five 1.83-m bulb tee spans and two two-span continuous composite curved steel plate girder units supported on concrete column bents and multiple 1.83-m drilled caissons.
2004 Gent, Belgium
R4 ring road around Ghent. Redesign of intersections 7 - 7b AWV East Flanders and 8
Zelzate, Belgium 2003
N49 / R4 in Zelzate. Construction of traffic interchange with several prestressed concrete bridges.
Brugge, Belgium 2003 Kanaaleiland phase 2. Redesign of cycle and pedestrian bridge. The bridge is a steel bow bridge with an architectural shape.
DeKalb County, Georgia
N.V. Cordeel AWV West Flanders
2002 Cernavoda, Romania
Cernavoda Bridge. Bowstring bridge over Danube-Black Sea Canal, conception and design. Total length: 172.5 m. Height of the arch at middle span: 28 m.
CNE Invest (Nuclear Power Plant Cernavoda)
2002 Terneuzen, The Netherlands
Through Gider Brigde Terneuzen. U-shape through bridge with a total length of 124 m. This steel bridge is built with an angle of 21o and a fly-over of 1.5 km. Bridge has a Movalbe Scafolding System.
NV Westerscheldetunnel
Amsterdam, 2002 The Netherlands
Railway Bridge over the West entrance of the railway yard ProRail of Amsterdam Central Station. Two steal railway bridges on 5 colomns each with a total length of 70 m and a width that varies between 5.2 and 13.9 m.
Eisden, Belgium 2001
Mine Eisden. Access route mine site- phase 1 + 2. Several concrete bridges with spans between the 20 and 30 m.
Municipality of Maasmechelen
1999 Strasbourg, France
Pierre Pfimlin Bridge. Motorway Bridge connecting France to Germany over the Rhine River. Prestressed box girder deck with a main span of 205 m.
French State
Corsica, France 1999
Vecchio Bridge. Roadway bridge crossing a deep valley in Corcica mountains. Innovative prestressed concrete box girder with triangular webs with a main span of 150 m.
French State
France 1999 Ventabren Viaduct. 1730-m railway bridge. Prestressed concrete box beam, 37 spans with a typical length of 45 m, incrementally launched. Zwolle, The Netherlands 1999
26
Twistvliet Bridge. This 175-m arch bridge is combined with bascule design.
RĂŠseau FerrĂŠ de France
Municipality of Zwolle
Statement of Qualifications Bridges
Location
Year Description
Client
Lisbon, Portugal 1998
Vasco de Gama Bridge. Main part of a 12-km motorway crossing Tagus estuary. It is a 830-m long cablestayed bridge with a 420-m main span. High seismic loading.
Novaponte (concession company)
Le Havre, France 1994
Bridge over Grand Canal Maritime du Havre. Motorway steel bridge with “V� piers and a main span of 180 m. The total length is 950 m.
General County (Seine Maritime)
Haut Rhin, France
Fessenheim Bridge. Roadway Bridge connecting France to Germany over the Rhine River. Composite deck 420 m long.
27
Statement of Qualifications Bridges
Vasco da Gama Bridge Lisbon, Portugal 28
28
Statement of Qualifications Bridges
29
Statement of Qualifications Bridges
Bridge Wyszk贸w, Poland
Cernavonda Bridge, Romenia 30
Statement of Qualifications Bridges
Where can you find us? Head office
Brazil
France
Spain
ARCADIS NV Nieuwe Stationsstraat 10 6811 KS Arnhem P.O. Box 33 6800 LE Arnhem The Netherlands Phone: +31 26 377 8911 E-mail: info@arcadis-global.com www.arcadis-global.com
ARCADIS Logos Ltda. São Paulo, Brazil Phone: +55 11 3117 3171 E-mail: logoseng@logoseng.com.br Contact: Julio Cesar Biezus Neves or José Carlos de Souza Valsecchi
ARCADIS ESG Le Plessis Robinson Cedex, France Phone: +33 1 4601 2481 E-mail: direction@arcadis-fr.com Contact: Michel Bastick
RTKL España, Sucursal en España Madrid, Spain Phone: +34 91 426 0980 E-mail: Madrid-Info@rtkl.com Contact: Jorge Beroiz
Chile ARCADIS Geotécnica SA Santiago, Chile Phone: +56 2 3816000 E-mail: arcadis@arcadis.cl Contact: Marcelo de Moras
United States ARCADIS U.S., Inc. Highlands Ranch Colorado, United States Phone: +1 720 344 3500 E-mail: arcadisgm@arcadis-us.com Contact: Steven Kramer or Gary Landschoot RTKL Associates Inc. Baltimore, Maryland United States Phone: +1 410 537 6000 E-mail: Baltimore-Info@rtkl.com Contact: Lance Josal www.rtkl.com
Germany ARCADIS Deutschland GmbH Darmstadt, Germany Phone: +49 6151 3880 E-mail: info@arcadis.de Contact: Josef Homola ARCADIS Immobilien Consulting GmbH Frankfurt, Germany Phone: +49 6979 5900 E-mail: frankfurt@arcadis.de Contact: Thomas M. Vogt
The Netherlands ARCADIS Nederland BV Amersfoort, The Netherlands Phone: +31 33 4771000 E-mail: info@arcadis.nl Contact: Leo van der Kemp PRC BV Bodegraven, The Netherlands Phone: +31 172 631414 E-mail: info@prc.nl Contact: Rob Lith
China ARCADIS Asia Shanghai, China Phone: +86 21 587 61 451 E-mail: info@arcadis.cn Contact: Theo Tombeur
ARCADIS Aqumen Arnhem, The Netherlands Phone: +31 40 2332 800 E-mail: info@aa-fm.com Contact: Jerry van Ulden
RTKL International Ltd. Shanghai, China Phone: +86 21 6122 7922 E-mail: Shanghai-Info@rtkl.com Contact: Jay Clark
Poland
Belgium ARCADIS Belgium Antwerp, Belgium Phone: +32 3 3608300 E-mail: info@arcadisbelgium.be Contact: Alain Bossaer
Czech Republic ARCADIS CZ, a.s. Praha, Czech Republic Phone: +42 296 330 111 E-mail: info@arcadispm.cz Contact: Pavel Havlicek
United Kingdom ARCADIS AYH plc London, United Kingdom Phone: +44 20 72161000 E-mail: info@arcadis-ayh.com Contact: Steve Didcott RTKL UK Ltd. London, United Kingdom Phone: +44 (0)20 7306 0404 E-mail: London-Info@rtkl.com Contact: Alan Morgan
United Arab Emirates ARCADIS Gulf Dubai, United Arab Emirates Phone: +971 4 335 8882 E-mail: info@apsgulf.ae Contact: Philip Gearing ARCADIS Gulf Abu Dhabi, United Arab Emirates Phone: +971 2 446 5775 E-mail: info@apsgulf.ae Contact: Peter Sykes RTKL UK Ltd. (Dubai Branch) Dubai, United Arab Emirates Phone: +971 4 311 7188 E-mail: London-Info@rtkl.com Contact: John Robertson
ARCADIS Polska Sp. z o.o. Warsaw, Poland Phone: +48 22 203 2000 E-mail: officeayhhomola@arcadis.pl Contact: Jan Paluch
Romania ARCADIS Eurométudes Bucharest, Romania Phone: +40 21 31 22699 E-mail: office@arcadis-ro.com Contact: Alexandrina Lulia Otelea
Photography Michiel Kievits Fotographie page 21 Pedro Damásio www.flickr.com/rolhas page 28/29
31
ARCADIS is an international company providing consultancy, design, engineering and management services in the field of infrastructure, environment and buildings. We aim to enhance mobility, sustainability and quality of life by creating balance in the built and natural environment. ARCADIS develops, designs, implements, maintains and operates projects for companies and governments. The company has an extensive international network that is supported by strong local market positions. We strive to leave the environments, the places and the lives we touch better than we found them. To achieve this, we create balance—in our world, in our projects and in our lives. We strive to find harmony, equality and stability between the creative and the functional, between nature and the built environment, between the innovative and the tried and true, between present needs and future legacy, and between imagination and results. For more information www.ARCADIS-global.com