Balfour Beatty UK Site Mobilisation Guide Balfour Beatty UK Site Mobilisation Guide “ Go Live” from 1 st July 2016
A word from our sponsors
Dean Banks, Managing Director for UK Construction Services “ Through the Site Mobilisation Hub service there has been a step change in the w ay the business approaches site set up and exit. The Site Mobilisation Hub has introduced a standard one stop shop for site mobilisation, and is a great example of Build to Last in action. Put simply it is about us w orking more effectively from day one, sharing best practice and ensuring w e meet and exceed our customer and internal expectations.”
Andy Ormerod, Managing Director for Plant & Fleet Services “ The Site Mobilisation Hub is making a big contribution to Balfour Beatty’s Build to Last transformation programme by driving lean efficiencies through our UK operations w ith a slick and standardised approach. Our Site Mobilisation Hub team is on hand to support every project manager to get up and running in the most efficient and seamless manner. More than £10m of recorded savings have already been achieved since the Mobilisation Hub w ent live in July 2016.”
SITE MOBILISATION GUIDE VERSION 2, 2018
2
Introduction The Hub has been set up to change our approach to mobilising and demobilising sites. This presents a great opportunity to save money by using in-house expertise, equipment and our comprehensive UK supply agreements. When you contact the Hub, the team w ill take you through a triage process. All sites are encouraged to make initial contact w ith the Hub. Our processes are detailed on the Business Management System (BMS) and in this booklet for your information. Getting site set -up right first time creates a safe and sustainable environment. Safety is our licence to operate. The Hub follow s the Gated Lifecycle and the Digital Briefcase to provide the governance and control of key stage gate documentation. The Site Mobilisation Hub is happy to support you. Please don’ t hesitate to call or email.
Lean – Using our in-house expertise and external partners allow s us to mobilise and demobilise efficiently, keeping cash in the company. Expert – Connecting employees w ith competent in-house specialists and external suppliers to successfully deliver, maintain and remove project facilities. Trusted – Using a planned and programmed approach to Mobilisation / Demobilisation, w ill enable us to accurately measure and report cost. Safe – Safety is at the heart of mobilisation through relentless collaboration, using in-house expertise ensuring our equipment is compliant and safe - helping to deliver Zero Harm.
0844 880 0090 mobilisationhub@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
3
Mobilisation and Demobilisation T-minus notification periods Mobilisation > 6 months
18 to 26 wks
PreSigning of Occupation Lease Survey Planning Application
3 rd Party Property Consent
-18 wks Tow er Cranes
-17 wks
-16
wks Cars and Vans
LCV and HGV
Tenancy Agreement
-15 wks
-14 wks
-13 wks
-12 wks Signing of Licence Operat or Licence
-11
-10
-9
-8
wks
wks
wks
wks
-7 wks
-6 wks
-5
Securit y
Craw ler Cranes
Temporary Accomm
Water and Sew erage
Generators
wks
Modular Accomm
Broadband
Fixed Fibre Gas and Electric
SITE MOBILISATION GUIDE VERSION 2, 2018
4
Demobilisation -4
-3
-2
-1
-12
wks
wks
wks
wks
wks
Structured Cabling
Telephony
Temporary Electrics
Sw eepers
Bulk Fuel
Nonoperated Plant
P-Card
Fleet
Waste Containex Accomm Furniture/ Asset Exchange
Signage / Fuel Cards Noticeboard
Viprinet Satellite / Satellite
PPE & Site Equipment
Fire Services
Building Materials
Multi Function Device
Driver Risk Management
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
wks
wks
wks
wks
wks
wks
wks
wks
wks
wks
IT removal
Security
Modular Accomm
Propert y Handover
General Plant
Temporary Accomm
Fire
Gas and Electric
Cont ainex Accomm
Propert y Handover
Project Demobilised
Office Supplies
Project Mobilised
Project Control Room
Modular Accomm
-11 wks
Generat ors Furnit ure/ Asset Exchange
Suction 4G Router Excavators
SITE MOBILISATION GUIDE VERSION 2, 2018
5
Contents The Site Mobilisation Hub process
8
Mobilisation: key elements
19
IT setup
42
What happens w hen you contact the Hub?
9
Health & Safety
20
Gas & electricity temporary connection
44
How does it fit into the Business Lifecycle?
10
Site layout
22
Tow er Cranes
46
Example site plan
23
Fleet
48
Project start up review
11
Accommodation options
24
Vehicle Operating Licence
50
T-Minus planning
12 Modular Accommodation
26
Site Security
52
Information distribution and requirements gathering
13 28
Workforce Management
54
Delivery to project plan
14
Temporary Accommodation (Cabins) Example cabin layouts
30
Third party consents
56
Standardised cabin layouts
32
Water and sew erage temporary connections
58
Pre-occupation site surveys
36
Craw ler cranes
62
Tenancy agreements
38
Temporary w orks planning
64
Planning applications
40
Temporary electrics
66
Clarify and agree Mobilisation programme
15
Handover and benefits realisation / preparation for Demobilisation
16
Transfer cost know ledge to Business Winning Community
17
SITE MOBILISATION GUIDE VERSION 2, 2018
6
Fire Services
68
Building materials
92
Tow er Cranes
112
Furniture and asset exchange
70
Non-operated plant
94
3 rd party property handback
114
Waste
72
Generators
96
116
Road Sw eepers
74
Electricity and gas temporary disconnections
Effluent empty servicing
98
Signage
76
Site security
118
Fuel cards 100
Furniture and asset exchange
120
78
Driver Risk Management 102
IT removal service
122
Project Control Room
80
Construction Logistics and Community Safety
104
Fire Services
124
Bulk fuel
82
Major Earthw orks
Non-operated plant collection
126
Contacts at a glance
128
Communication noticeboards
106 Purchasing cards
84
Demobilisation: key elements
107 Suction Excavators
86
PPE and site equipment
88
Office supplies
90
SITE MOBILISATION GUIDE VERSION 2, 2018
Modular Accommodation
108
Temporary Accommodation (cabins)
110
7
The Site Mobilisation Hub process
SITE MOBILISATION GUIDE VERSION 2, 2018
8
What happens when you contact the Hub? Requirement Identification
»
The process diagram outlines how the Site Mobilisation Hub w ill operate
»
Stage 1 (Requirement Identification) - Our Mobilisation Partners review the CRM platform to identify projects
»
Stage 2 (Triage) - Site Mobilisation Partner w ill contact Project Manager to go through mobilisation / demobilisation requirements (please note that for a sub-contractor order, this w ould need to be raised by the project’ s Quantity Surveyor or Buyer as per Balfour Beatty
Triage
policy – search PRC-PR-0003 on 360) »
Typically, if your project value is less than £250k and 6 months in duration you may be advised by the Site Mobilisation Hub to interact directly w ith the specialist contacts included throughout the guide
Requirements Gathering
»
Stage 3 (Requirements Gathering) – a Mobilisation Partner w ho engaged w ith you at stage 2 w ill gather all your site mobilisation / demobilisation requirements and proceed w ith the mobilisation of your project
Change Request Process 9
»
Stage 4 (Change Request) – if a major change in site mobilisation requirements occur that can be costed back to the client, please inform the Site Mobilisation Hub
Mobilisation/ Demobilisation
»
Stage 5 (Handover) – The Site Mobilisation Hub w ill provide a handover document to the Project Manager of all the commodities provided
» Our Site Mobilisation Partners will be happy to assist with any
Handover
Mobilisation / Demobilisation enquiries, please don’t hesitate to call or email Get in Touch: mobilisationhub@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
0844 8800 090
9
How does it fit into the Business Lifecycle? » Stage Gates 1 - 4 are the Win Business sales stage w hich transitions into the project delivery Stages 5-8 » Left of Stage Gate 5, the Site Mobilisation Hub
w ill have your project on their radar from CRM data » The Site Mobilisation Hub engages w ith project teams as early as Stage Gate 3 w ith a w atching brief all the w ay back to Stage Gate 1, w orking
closely w ith the w ork w inning community to input information collated post contract mobilisation to support bidding activity » At Stage Gate 4, the Site Mobilisation Hub’ s active service kicks in to support successful
contract aw ards
SITE MOBILISATION GUIDE VERSION 2, 2018
10
Project start up review » At Stage Gate 5 or earlier, w e need to introduce the discipline of a project start up review » To achieve this the Project Manager needs to
confirm the project programme is still achievable w ith the Strategic Business Unit (SBU) contract sponsor and effectively agree w hat success w ould look like at Stage Gate 7 » This project start up review should be held
betw een the project sponsor and the manager w ithin 30 days of contract aw ard
SITE MOBILISATION GUIDE VERSION 2, 2018
11
T-minus planning
» The Site Mobilisation Hub brings together our UK w ide expertise across a w ide range of functions required to mobilise or demobilise a site. This includes IT and phone connections, temporary accommodation, Plant & Fleet, commodity procurement, utility connections, property and site security » The Hub can provide a tailored service for any type of contract, including JVs. This facilitation service is free. By engaging w ith the Hub you’ ll be supported in finding the most cost effective solution for your project and you’ ll be proactively helped in making all the arrangements necessary to successfully mobilise and demobilise » Once w e are talking together about your mobilisation, w e probably already know you from the mobilisation plan created and out lined in Stage Gate 3 and updated and finalised during Stage Gate 4 SITE MOBILISATION GUIDE VERSION 2, 2018
12
Information distribution and requirements gathering
» Having gathered the projects detailed requirements
» A named member of the Site Mobilisation Hub
the information is automatically issued to all the
engages w ith all service providers to agree their
service providers that w ill be supporting the project
timescales and creates a single summary
» The service providers review the information and confirm the timescales for providing the service required by the project
SITE MOBILISATION GUIDE VERSION 2, 2018
programme for monitoring w ith the Project Manager, this can then be included w ithin the overall project programme
13
Delivery to project plan
» At this point, the project has an agreed
» The progress of your mobilisation delivery is
mobilisation schedule and all parties are
continuously monitored and aggregated across
w orking tow ards delivering the most cost
all mobilisation w orks and reports are produced
effective solution in line w ith agreed timescales
across all functions » Our Service Level Agreements for our supply chain and delivery partners can be found on the Business Management System
SITE MOBILISATION GUIDE VERSION 2, 2018
14
Clarify and agree Mobilisation programme
Âť All the elements required for a successful site mobilisation are delivered in line w ith the agreed programme under the superv ision of the Project Manager and the site team
SITE MOBILISATION GUIDE VERSION 2, 2018
15
Handover and benefits realisation
» Once mobilisation is complete, the Site Mobilisation Hub provide a handover pack to the Project Manager w ith an outline
Preparation for Demobilisation
» The Project Manager should engage w ith the Site Mobilisation Hub at least 12 w eeks before project end date
of the Mobilisation / Demobilisation of the project » By having a consistent and planned approach to M obilisation and Demobilisation, Balfour Beatty can gain cost savings and time efficiency, w e also maintain a consistent expert standard
SITE MOBILISATION GUIDE VERSION 2, 2018
16
Transfer cost knowledge to business winning teams
» Follow ing successful Demobilisation the Hub collates a
» At gate 7, the Mobilisation Partner gives the Project
checklist to remember and deliver this back to the bid team
Manager a prompt to close the project and archive all
for future learning
the associated documentation and metrics in the digital
» The end result is that w e collaborated relentlessly, all got left and delivered a lean service, safely, on-time and in a cost
effective manner
SITE MOBILISATION GUIDE VERSION 2, 2018
briefcase » This enables us to provide learning for future project
opportunities
17
SITE MOBILISATION GUIDE VERSION 2, 2018
18
Mobilisation Key Elements
SITE MOBILISATION GUIDE VERSION 2, 2018
19
Health & Safety – how to get it right Projects must be mobilised to a standard that provides everyone w ith the right impression of health and safety expectations
The site establishment should eliminate fatal risks
Balfour Beatty is committed to: “Safe - Our licence to operate” “Zero Harm – No injuries or ill health caused by our work activities” “Treat Health like Safety – The health and wellbeing of the workforce must be built into our site establishment”
The site establishment must go beyond legal compliance and demonstrate our zero harm commitment to our w orkforce
Site layouts should ensure safe interface and efficient movement of people, plant and materials
Health and Safety should be your first and last thought for every stage of the project lifecycle
SITE MOBILISATION GUIDE VERSION 2, 2018
20
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
Checklist to remember
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
The Project must not commence until “ fit for w ork” therefore suitable arrangements for the follow ing must be in place: » Vehicle movements including access, egress and parking
mobilisationhub@balfourbeatty.com 0844 8800 090
» Deliveries of plant and materials » Lighting appropriate to all seasons » Walkw ays to allow safe access in and around the site establishment » Induction & training facilities that create a good environment for all briefings » Welfare sufficiently sized for peak demand (e.g. toilets and drying rooms)
Balfour Beatty specialist contact: Craig McCallum Craig.McCallum@balfourbeatty.com
» Security relevant to the local environment preventing unauthorised access. » Access control allow ing the authorised access of competent people onto site
07766 423 158
» When using operated or non operated plant, please ensure you refer to the Plant Specifications Booklet
The arrangements must take into account the changing demands on the site establishment throughout the project lifecycle so it remains fit for w ork.
SITE MOBILISATION GUIDE VERSION 2, 2018
Plant Specifications booklet: https://w w w .balfourbeatty.com/media/ 164314/plant-specification-bookletjanuary-2017.pdf Or search HSF-RM-0046e on 360
21
Site layout – how to get it right Using a scale draw ing, determine the area available for site compound. It must include access and egress to the road and existing utilities
Add accommodation, cabins and any modular buildings w ith storage and w orking facilities required to the scale draw ing
Add parking area, site access roads and footw ays, paying particular attention to the segregation of people and vehicles / plant and equipment
Consider environmental and sustainability impact
SITE MOBILISATION GUIDE VERSION 2, 2018
22
Key Considerations » Plant and People segregation » Vehicle movement » Members of the Public interface » Lighting » Hand rails » Access and egress » Security » Access control » Water
» Canteen » Utilities » Proximity
SITE MOBILISATION GUIDE VERSION 2, 2018
23
Accommodation options Key Features
Typical Use
Mobile Welfare (Wheeled Self Contained Units)
» »
Integrated w elfare in one delivery Short lead-in time
»
During site set up activities (suggested up to 1 month)
Temporary Cabins
» » » » »
Know n fixed unit costs Minimal design required Basic specifications Short lead time Restricted floor plan options
»
Ideal for short to medium term use (suggested up to tw o years) Well suited to smaller projects
» » » »
Variable cost Standardised layout and design Open plan options More efficient use of floor space
»
Flexible (Containex) solution
» » » »
Quick lead times Installation 2-3 w eeks Very flexible (panel configuration) Open plan (central column for larger buildings)
» »
Ideal for any hire over 26 w eeks Ideal for urban locations
Serviced Permanent Office
» » » »
High and variable cost Short lead time Minimal set up required Flexible terms
»
Ideally suited for mobilising a project w hile w aiting for permanent site set up Short term use only (suggested less than one year)
» » »
Variable cost Bespoke use of floor space Medium lead time
»
Traditional Modular Buildings
Permanent Office Refurbishment
SITE MOBILISATION GUIDE VERSION 2, 2018
»
»
»
Ideal for medium to long term use (suggested over 18 months) Well suited for larger projects w ith higher staffing levels
Ideal for medium to long term use (suggested over one year)
24
What to consider when choosing accommodation Office Space
One desk per member of staff, although hot desks may be a more efficient option
If unsure about capacity required, it is better to overestimate as adding capacity during w orks can be difficult
Things to consider » Desk space for the client » Meeting rooms and breakout areas » Project Control room / lean centres » Induction and training rooms
Storage
Things to consider » A central PPE store may be useful » Traffic and pedestrian routes w ill impact on moving materials and plant from storage areas to site
Car Parking
Things to consider » Peak numbers of staff on site » Additional parking for visitors and the client » Safe w alking routes to and from the car park using a one w ay system
Welfare
Things to consider » The number of people on site includes office staff and operatives » Facilities need to accommodate peak numbers on site » First aid requirements » Mobility impaired people access may be required » A fire escape is required every 30 metres or five cabins w idths
SITE MOBILISATION GUIDE VERSION 2, 2018
25
Modular Accommodation – how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
Traditional Modular Building
Modular team contact site w ith options based on current stock or new build
Draw ings and quote are issued by the Modular team
Flexible (Containex) solution
Order placed by site and refurbishment w orks commence. Site visit arranged
Installation w orks commence and building is handed over to Project Manager
SITE MOBILISATION GUIDE VERSION 2, 2018
26
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
X
-4
-3
-2
X
Before engaging, please consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1 END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact:
Balfour Beatty Site Mobilisation Hub » Prepare detailed plans of temporary accommodation and compound to be covered. » Available footprint » Length of hire building required for (early off-hire charges can apply)
mobilisationhub@balfourbeatty.com 0844 8800 090
» Number of staff and/or operatives w ho w ill be using the building » Facilities required (e.g. Canteen, Induction Room, Meeting Rooms, First Aid Room) Balfour Beatty specialist contact: Checklist to remember: Modular Buildings » Standard layouts may be an advantage
01332 288 426
» Mobilisation period for cabins is generally around 6-8 w eeks, longer for larger
Modular.enquiries@balfourbeatty.com
buildings or buildings requiring significant w ork » Site installation w ill be 8-10 w eeks, longer for larger buildings » Site w ill need to ensure foundations and mains services are available prior to delivery to site » Don’ t forget to get the temporary w orks design for the Building Foundations and ground loadings for offloading using mobile cranes are the customers responsibility » The mobilisation period for Containex buildings is 2-4 w eeks SITE MOBILISATION GUIDE VERSION 2, 2018
27
Temporary Accommodation (cabins) – how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements.
Confirm date of site survey (if required)
The supply of temporary cabin units is through our sole supplier, A-Plant. A-Plant offer Balfour Beatty three standards of anti-vandal accommodation. » Fire rated for double stacked units in close proximity to other occupied buildings. » Amber for standard units » Green for ‘ Eco’ units w ith extra insulation, PIR lighting, w aterless urinals and double glazing.
Agree maintenance requirements
Final quotation provided by A -Plant
Project Manager to raise requisition for hire
SITE MOBILISATION GUIDE VERSION 2, 2018
28
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X Unit
Occupancy
Property compliance – Please engage w ith your local
Cabin A
5 people
health and safety representative, to ensure you have
Cabin B
4 people
taken appropriate advice to be compliant
Cabin C
20 people
Before engaging, please consider the following:
Cabin D
40 people
» Location of the hire
Cabin E
30 people 125 / 25 people
Cabin G
6 people 50 / 25 people
Cabin H
50 / 25 people
Cabin I
12 people
Cabin J
30 people
Cabin K
1 person
Cabin L
10x8 or 20x8 Secure Store
-8
-6
-5
-4
-3
-2
-1
First point of contact: Balfour Beatty Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
» Date and time of delivery and the estimated off hire date w here know n and including restrictions
Cabin F
-12
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
Balfour Beatty specialist contact:
Checklist to remember:
Construction, Major Projects
» Check for compliance to fire regulations.
csukplant@balfourbeatty.com
» Consider specifying a fire detection system and
0870 8444 888
enclosing the underside of cabins. » Ensure that the temporary w orks are in place for lifting operations » Place your order 20 w orking days prior to delivery to get best rates » Don’ t forget to get the temporary w orks design for the Cabin Foundation and Working Platform for offloading cranes
SITE MOBILISATION GUIDE VERSION 2, 2018
(select option 1, option 1, option 2 ) Gas & Water, Power T&D bbssplant@balfourbeatty.com 0870 8444 888 (select option 1, option 1, option 1 ) Rail, Living Places, Joint Ventures mobilisationhub@balfourbeatty.com 0844 8800 090
29
Example cabin layouts
Cabin A
Cabin D
SITE MOBILISATION GUIDE VERSION 2, 2018
Cabin B
Cabin E
Cabin C
Cabin F
30
Example cabin layouts
Cabin G
Cabin H
Cabin I
Cabin J
Cabin K
Cabin L
SITE MOBILISATION GUIDE VERSION 2, 2018
31
Standardised cabin layouts Cabin Type
Occupancy
Electrical Load
BB1
10 people (5 white collar, 5 blue collar )
15.5 kVA
BB2
20 people (5 white collar, 15 blue collar)
18.5 kVA
BB1
SITE MOBILISATION GUIDE VERSION 2, 2018
BB2
32
Standardised cabin layouts Cabin Type
Occupancy
Electrical Load
BB3
20 people (9 white collar, 20 blue collar)
24 kVA
BB4
30 people (9 white collar, 20 blue collar)
24 kVA
BB4 – DOUBLED STACKED BB3
SITE MOBILISATION GUIDE VERSION 2, 2018
33
Standardised cabin layouts Cabin Type
Occupancy
Electrical Load
BB5
30 people (9 white collar, 40 blue collar)
47.5 kVA
BB6
50 people (9 white collar, 40 blue collar)
47.5 kVA
BB7
100 people (18 white collar, 80 blue collar)
70.5 kVA
BB6
BB5
BB7
SITE MOBILISATION GUIDE VERSION 2, 2018
34
Standardised cabin layouts Cabin Type
Occupancy
Electrical Load
BB8
100 people (18 white collar, 80 blue collar)
70.5 kVA
BB9
150 people (27 white collar, 120 blue collar)
93.5 kVA
BB8
SITE MOBILISATION GUIDE VERSION 2, 2018
BB9
35
Pre-occupation site surveys – how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
To ensure condition surveys, ecological reports (e.g. Tree Protection Orders and Japanese Knotw eed) and contamination investigations are completed and necessary consents are processed prior to gaining occupation.
Property Team w ill liaise w ith Project Manager to agree preferred site location and key property requirements
Property Team w ill facilitate searches and carry out initial engagement w ith landlords
Property Team w ill highlight any issues relevant to these locations
Property Team w ill record and manage in line w ith timescales
SITE MOBILISATION GUIDE VERSION 2, 2018
36
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
» Site details, type and size of property » Duration of occupation » Details of site use and transportation issues, including any changes likely during the
mobilisationhub@balfourbeatty.com 0844 8800 090
project Checklist to remember:
Balfour Beatty specialist contact:
» Refrain from agreeing informal or local arrangements w here risk is not controlled
Property Team
» Conduct adequate research on adjacent property / land ow nership including over-
property.services@balfourbeatty.com
sailing rights » Carry out condition surveys before and after residency » Utilities: obtain utility draw ings for the area including telecoms, gas and w ater, electric, sew erage and fuel pipelines both above and below ground. » Consider environmental impact issues » Ensure condition surveys, ecological reports (e.g. Tree Protection Orders and Japanese Knotw eed) and contamination investigations are completed and necessary consents are processed prior to gaining occupation. SITE MOBILISATION GUIDE VERSION 2, 2018
37
Tenancy agreements - how to get it right
Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
Property Team agree preferred site and prepare legal documents
When legal documents are completed, at the time of occupation Property Team archive and record break clauses
SITE MOBILISATION GUIDE VERSION 2, 2018
38
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following: » Define your requirements – size, type, location, period required for etc.
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
» Forecast the expenditure in your budget
mobilisationhub@balfourbeatty.com
Checklist to remember:
0844 8800 090
» Ensure adequate lead time for instruction to negotiate tenancy typically 14 w eeks if you have identified a property and 22 w eeks if a search is required » Avoid entering into non-professional agreements w ith third parties, as these can increase cost and liabilities » Conduct initial conditions survey
Balfour Beatty specialist contact:
Property Team 0114 232 9677 property.services@balfourbeatty.com
» Ensure steps have been taken to set up payments rent, business rates, utilities etc. » Inform Property Services if you intend to undertake any alterations to the premises so that Landlord consent can be obtained » Agree and record method of reinstatement obligations before undertaking w ork » Make adequate provision for dilapidation costs. You may be liable for reinstatement and repair costs if the property is not returned in good condition, especially if alterations have been undertaken w ithout consent SITE MOBILISATION GUIDE VERSION 2, 2018
39
Planning applications - how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
The process to determine planning requirement for site set up of land and buildings.
Property Team w ill liaise w ith the Project Manager to agree required planning route, appoint planning consultants and submit applications
Project Manager creates a traffic and access statement and environmental plan for submission w ith the planning application
Property Team w ill deal w ith local planning office requests and gain consent
SITE MOBILISATION GUIDE VERSION 2, 2018
40
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
Before engaging with us, consider the following:
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
» Tenancy agreement must be completed before Planning Applications can be submitted » Project Manager should have an informal discussion w ith local authority to determine
mobilisationhub@balfourbeatty.com 0844 8800 090
if planning consent is required, considering; » Duration of project and occupation » All intended site use and transportation issues
Balfour Beatty specialist contact:
Checklist to remember:
Property Team property.services@balfourbeatty.com
» Property Team may appoint planning consultants to prepare and submit applications, the costs w ill fall to the project. » The ow ner of land is not responsible for submitting application – it is the occupier » Consider hoarding and fencing requirements and conditions. There have been instances of developers/ builders being fined for breaching regulations » Adhere to conditions such as noise and w orking time restrictions. Note: This also applies to taking occupation on a client site under the terms of their planning consent. SITE MOBILISATION GUIDE VERSION 2, 2018
41
IT setup - how to get it right
Site Project Manager defines requirements
Site Project Manager contacts the Site Mobilisation Hub, w ho w ill assign a Mobilisation Partner to your project
Mobilisation Partner w ill agree IT requirements and arrange a suitable installation date / time
SITE MOBILISATION GUIDE VERSION 2, 2018
42
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following: Define requirements including deliverables, lead times, key dates, service requirements, budgets and site contacts. The Mobilisation Partner w ill w ork w ith you to capture the detail required. Checklist to remember
-1
-12
-8
-6
-5
-4
-3
-2
First point of contact: Balfour Beatty Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
» Allow sufficient IT budget in tender
Balfour Beatty specialist contact:
» Clearly define requirements – w hat tools / functions do the staff need as part of
IT Site Setup Office
project delivery? (CAD / BIM / Document control systems / client specified systems / 360 access) Lead in times » Temporary communication – 12 w orking days » Permanent communication – 120 w orking days * *
Subject to survey and receipt of approval
» IT equipment for new starters should be requested through the On and Off Boarding
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
To raise initial request https://balfourbeattyukitss.servicenow.com/nav_to.do?uri=%2Fsp Click on ‘IT Services – Order Or Request Something – Services and Access – Site Setup Services – Then Site Setup Services again.’ IT Site setup how to guide:
https://home360.balfourbeatty.com/it/Documents/ High%20Level%20Site%20Steup%20Guide.pdf Or search ‘High Level Site Setup Guide’ on 360 Queries to the dedicated IT team
team via Employee Services (0800 030 4127) sitesetup@balfourbeatty.com 0191 228 2991
SITE MOBILISATION GUIDE VERSION 2, 2018
43
Gas & electricity temporary connections – how to get it right
Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
Project Manager w ill complete a Utility Requirements questionnaire provided by the Site Mobilisation Hub
If you require a new supply; the Site Mobilisation Hub w ill initiate a new requirement w ith a preferred supplier and w ill commence the set up. Costs w ill be incurred at this stage
SITE MOBILISATION GUIDE VERSION 2, 2018
44
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
-1
-12
-8
-6
-5
-4
-3
-2
-1
Before engaging with us, consider the following:
First point of contact:
» Project code
Balfour Beatty Site Mobilisation Hub
» Strategic Business Unit
mobilisationhub@balfourbeatty.com
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
» Full site address including postcode, Meter Point Administration Number (MPAN) or (Meter Point Reference Number (MPRN)
0844 8800 090
» Site contact name and contact details » Purchase Order Number Checklist to remember: » Do not contact any other provider directly. This w ill cause confusion and potential non-compliance w ith legal requirements » Pay invoices w ithin established time scale – provider w ill issue disconnection letters if they are not paid w ithin the agreed payment terms » All new gas and electricity supplies must be fitted w ith Automatic Meter Readers (AMRs) that are Day+ 1 capable. Having these fitted during site set -up is significantly cheaper than doing so retrospectively
» Often the connection betw een the boundary and the accommodation distribution board w ill need to be installed by the site team SITE MOBILISATION GUIDE VERSION 2, 2018
45
Tower Cranes - how to get it right
Project Manager should assess w hether the project is likely to require Tow er Cranes and liaise w ith the Site Mobilisation Hub to discuss requirements
Plant & Fleet Services w ill liaise w ith site to develop a Tow er Crane Solution that meets the requirements of the Project
Plant & Fleet Services w ill procure or use from existing Fleet, a Tow er Crane for the Project and put in place the appropriate measures to mobilise the Crane.
SITE MOBILISATION GUIDE VERSION 2, 2018
46
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
-1
-12
-8
-6
-5
-4
-3
-2
-1
Before engaging with us, consider the following:
First point of contact:
» The lifting radiuses and corresponding capacity required at each radius.
Balfour Beatty Site Mobilisation Hub
» The traffic management plan for install, w ho w ill develop this (many councils w ill
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
mobilisationhub@balfourbeatty.com
require a minimum of 8-12 w eeks notice for closure) » Any site constraints (over sailing, access, height restrictions etc.)
0844 8800 090
» Luffing jib lead times to hire – 16-20 w eeks » Saddle jib lead times to hire – 16-20 w eeks Balfour Beatty specialist contact: Checklist to remember: » Allow ing sufficient time for base design and cat III checking (30 days minimum) » Tow er crane pow er supply, either mains or generator. » Any traffic management plans required must be communicated and discussed w ith Tow er Crane Services as soon as possible
Simon Armstrong 07854 058036 0870 8444 888 (Select Option 1, Option 5) tow ercranes@balfourbeatty.com
» Temporary w orks design for the Tow er Crane Base and Working Platform for erection cranes (base completion hand over certificate). » In the event of purchases, a purchase order is required to procure a new crane so please take into account the lead times mentioned above. SITE MOBILISATION GUIDE VERSION 2, 2018
47
Fleet - how to get it right
Is your Project going to require LCV’ s or HGV’ s
Contact the Fleet Service desk on 0845 602 7064 LCV: Option 1, then Option 4 or 5 HGV: Option 2, then Option 3 or 4
Our expert Fleet Team w ill w ork w ith you to agree the right solution to meet your vehicle requirement
SITE MOBILISATION GUIDE VERSION 2, 2018
48
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
X
-3
-2
-1
-12
-8
-6
-5
-4
-3
-2
-1
Before engaging with us, consider the following:
First point of contact:
» What are the Project requirements (i.e. Chapter 8 Livery, Tow bar)
Balfour Beatty Site Mobilisation Hub
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
» How long w ill the vehicles be required for » Are there specialist vehicles that must be on the Project » Are there any legal requirements that must be complied w ith
mobilisationhub@balfourbeatty.com 0844 8800 090
» Does the w orkforce have the competency to operate the vehicles Checklist to remember:
Balfour Beatty specialist contact: Fleet Service desk
» When w ill I need the vehicles and how long w ill they be required
» Delivery locations must be know n (and appropriate project / task codes)
Lead Times » Short Term Hire LCVs / HGVs – 4-72hrs (specification dependant) » Long Term Hire LCVs – 16-20w ks (specification dependant) » Long Term HGVs – 20+ w ks (specification dependant)
SITE MOBILISATION GUIDE VERSION 2, 2018
01332 476071/ 0845 602 7064 fleetservicedesk@balfourbeatty.com BMS Link: https://home360.balfourbeatty.com/g horeferencecentre/Group%20BMS/Pa ges/FleetCust.aspx Or search ‘ Plant and Fleet’ , then ‘ Fleet’ on the BMS
49
Vehicle operating licence – how to get it right
Do you need to operate Heavy Goods Vehicles (HGV) from the site?
Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
Operating centre licences are required w here Heavy Goods Vehicles (HGV, Vehicles greater than 3.5 ton Gross Vehicle Weight) are operated from the site. Authorisation is required from the Office of the Traffic Commissioner to become an “ Operating Centre” . Balfour Beatty Fleet Services team w ill process the application and payment including the statutory notice publication in local press. It is likely that the site w ill be subject to a visit by Department for Transport officials. The application may be subject to challenge by local residents and businesses also from Statutory Objectors.
Contact Fleet Services team
SITE MOBILISATION GUIDE VERSION 2, 2018
50
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following: » Full postal address of the site » If the site is not ow ned or formally leased by Balfour Beatty you w ill need a letter from the land lord authorising the company to use the site as operating centre for
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
the purpose of operating the required number of HGVs » Scale site plan show ing parking area, access/egress points and adjacent roads Balfour Beatty specialist contact: Checklist to remember: Group Transport & Compliance Manager » Plan for the peak number of HGVs operating from site
Adrian Wanford
» Leave sufficient space available to park the number of vehicles to be specified in the
07967669535
application
FleetCompliance@bbfleetservices.com
» If operations are likely to involve coupling or uncoupling of articulated vehicles make sure suppliers are aw are of Balfour Beatty requirements for automatic trailer braking and cab handbrake alarms [HGV not Vehicle Operating Licence specific issue]
SITE MOBILISATION GUIDE VERSION 2, 2018
51
Physical Security Services – how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
Security Team w ill contact the Site Team to discuss security requirements and arrange potential site visits
Core Services Standardised Access Control
CCTV & Alarm Based Systems
» On site for more than 6 months w ith a site boundary – The Standardised Access Control is for you
» CCTV & Alarm based systems can greatly improve your security defences and provide w arning of an intrusions
» Time & attendance for both safety & commercial benefit
» Deployed systems can be mobile, battery or mains pow ered and monitored externally
» CSCS Card Integration
» Cost effective Solution
» Online dashboard reporting / roll call
Security Team submit proposals from approved supply chain and agree solution
Project Team raise orders for preferred supplier
Manned Guarding
Automated Gates, Barriers & Blockers
» Manned Guarding provides a strong visible deterrent by physical presence on site
» Prevents vehicle and pedestrian access through roadw ays
» Can be statistic covering one site or mobile covering multiple sites miles apart
» Can be remotely controlled , linked to ANPR or proximity readers
Implement Security Measures
SITE MOBILISATION GUIDE VERSION 2, 2018
52
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
-1
-12
-8
-6
-5
-4
-3
-2
-1
The security team offer the follow ing support:
First point of contact:
»
Focus on applying security risk management to all w orks
Balfour Beatty Site Mobilisation Hub
»
Identify primary security risks and provide mitigations
»
Site security design from tender to contract aw ard
»
Scope and costed security solutions across project milestones
»
Technical advice on security products and solutions
Before engaging with us, consider the following: » Please have ready site details/ type/ size of property, duration of occupation and
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
mobilisationhub@balfourbeatty.com 0844 8800 090
Balfour Beatty specialist contact: SecurityServices@balfourbeatty.com
security services possibly required. Checklist to remember:
John Barrie (Security Operations Manager)
» Engage w ith the security team early to avoid a poorly scoped security solution and
07967 689451
possible missed savings opportunities » Procurement of suppliers w ithout engaging the team, potentially increases risk exposure to Balfour Beatty
SITE MOBILISATION GUIDE VERSION 2, 2018
https://home360.balfourbeatty.com/secu rityservices Or search ‘ Security Services’ on 360
53
Workforce Management - how to get it right? Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements of units
The new Balfour Beatty UK w ide standardised Site Access Control system is delivered through our strategic partner Human Recognition Systems. It ensures the right people are on site, at the right time w ith the right qualifications. It is a cloud based platform meaning that reports are easily accessible. This system delivers:
Security Team w ill liaise w ith the Project Manager to discuss requirements and arrange potential site visits
Security team w ill agree number and type of units to be installed and quote w ill be provided
»
Time and attendance
»
Qualifications and inductions / training
»
Deliveries to site
»
Data on labour levels and attendance
»
CSCS card readers to ensure w orkforce are compliant
»
Logistics management
Engineer w ill install the units on site and a trainer w ill assist in using the online system
SITE MOBILISATION GUIDE VERSION 2, 2018
54
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X Before engaging with us, consider the following: » Please have ready site details/ type/ size of property and duration of occupation
Checklist to remember:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
» Ensure Site Survey carried out by M-site or Security Team capture all your requirements and is safe » Understand your IT connectivity for optimal performance, connect to local BB netw ork w here possible
Balfour Beatty specialist contact:
» Identify logistics challenges for delivery of Pods, inform M -site if plan changes 2 w eeks
before delivery date » Ensure commercial buy in before and after the quote is agreed and signed off
SecurityServices@balfourbeatty.com
For any other queries with the system:
» Identify and nominate at least one M -Site champion to receive full training on system » Ensure the nominated M-site champion(s) have completed the online Data Protection
support@hrsid.com
training » Brief all blue and w hite collar staff about the on-boarding process » Ensure all BB staff and subcontractors are enrolled, pre-enrolment helps w ith completing this before they arrive on site » Capture Biometric finger prints on site as per the “ 4 Must Do’ s for enrolment”
SITE MOBILISATION GUIDE VERSION 2, 2018
55
Third party consents - how to get it right
Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and establish key areas of activity
For consents of third party and statutory authorities for easements and notices/licences. Refer to Property Section if legal agreement for access or storage means gaining consent from a third party adjacent to a main site. Easements for utilities should be undertaken by the utility provider, refer to the Gas & Electric section. Refer to the IT setup section if easements are required for communications.
Project Manager should identify consents required, Site Mobilisation w ill direct to Property Services or IT
Property Service / IT records and manages information in line w ith timescales
SITE MOBILISATION GUIDE VERSION 2, 2018
56
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact:
Balfour Beatty Site Mobilisation Hub
» Site details / type / size of property » Duration of mobilisation / occupation » Information on all intended site use and materials / transportation issues
mobilisationhub@balfourbeatty.com
0844 8800 090
Checklist to remember:
» Agree information or local arrangement w here risk is not controlled » Consider land use and access agreements – possible w ayleaves and easements to agree w ith third party. Property to advise on land ow nership and legal requirements » Consider overhand and party w all issues and agreements. Failure to information and
Balfour Beatty specialist contact: Property Team property.services@balfourbeatty.com
agree w ith site neighbours could result in trespass and damages claims
» Consider all proposed discharges – w aste, soil and effluent. Seek advice from contract environmental team, and Property Team if third party consent required » Access onto public highw ay – consents/signage etc. Contract team to determine w hat requirements are needed and make applications to relevant authority
SITE MOBILISATION GUIDE VERSION 2, 2018
57
Water and sewerage temporary connections - how to get it right Water supply needs to be arranged directly by the project w ith relevant local provider. Details can be found on the w ebsite w ater.org.uk. Early engagement is important as there may be a requirement for surveys, draw ings, local council approvals and legal approvals. The service and processes differ betw een providers.
Project Manager should contact the Site Mobilisation Hub, w ho w ill jointly agree the best course of action
SITE MOBILISATION GUIDE VERSION 2, 2018
Bottled w ater dispensers and coolers should only be used if a mains portable w ater supply is unavailable. The supply and plumbing can be tested to prove the w ater is safe to drink.
58
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
Before engaging with us, consider the following:
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
» Full site address including postcode » Site contact name and number
mobilisationhub@balfourbeatty.com
Checklist to remember:
0844 8800 090
» Use the correct specification for installation of pipew ork required by the provider e.g. “ Sew ers for Adoption” w hen installing w aste pipew ork and ensure that inspections are arranged w ith the provider
Water Supplier Information w w w .w ater.org.uk
» All new w ater supplies must be fitted w ith meters. Having these fitted during site set-up is significantly cheaper than doing so retrospectively and can help w ith billing disputes » Burying or insulating w ater piping w ill aid in avoiding the piping being heated by the sun and complaints about the w ater not being cool enough
SITE MOBILISATION GUIDE VERSION 2, 2018
59
SITE MOBILISATION GUIDE VERSION 2, 2018
60
Water and wastewater
Local water and wastewater
Water only
Anglian Water (Hartlepool Water) w w w .anglianw ater.co.uk
Albion Water w w w .albionw ater.co.uk
Affinity Water w w w .affinityw ater.co.uk
Džr Cymru – Welsh Water w w w .dw rcymru.com
Independent Water Netw orks w w w .iw nl.co.uk
Bristol Water w w w .bristolw ater.co.uk
Northern Ireland Water w w w .niw ater.com
Peel Water Netw orks w w w .peel.co.uk/utilities/w ater
Cambridge Water w w w .cambridge-w ater.co.uk
Northumbria Water w w w .nw l.co.uk
Thames Water Commercial Services w w w .thamescommercial.co.uk
Cholderton and District Water w w w .choldertonw ater.co.uk
Scottish Water w w w .scottishw ater.co.uk
Veolia Water Projects http://w w w .veolia.co.uk/our-services/ourservices/w ater-services
Dee Valley Water w w w .deevalleyw ater.co.uk
Severn Trent Water w w w .stw ater.co.uk South West Water w w w .southw estw ater.co.uk Southern Water w w w .southernw ater.co.uk Thames Water w w w .thamesw ater.co.uk United Utilities w w w .unitedutilities.com Wessex Water w w w .w essexw ater.co.uk Yorkshire Water w w w .yorkshirew ater.com
SITE MOBILISATION GUIDE VERSION 2, 2018
Essex and Suffolk Water (Northumbrian Water) w w w .esw ater.co.uk Hartlepool Water (Anglian Water) w w w .anglianw ater.co.uk Portsmouth Water w w w .portsmouthw ater.co.uk Bournemouth Water w w w .bournemouthw ater.co.uk South East Water w w w .southeastw ater.co.uk South Staffs Water w w w .south-staff-w ater.co.uk Sutton and East Surrey Water w w w .w aterplc.com
61
Crawler Cranes – how to get it right
Is your project likely to require craw ler cranes?
If yes, call BPH Equipment w ith details of your likely requirements and w e w ill identify a suitable crane for your project
BPH Equipment w ill mobilise the crane solution for your project
SITE MOBILISATION GUIDE VERSION 2, 2018
62
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following: » Details of all BPH Cranes are available on the w ebsite (w w w .bphequipment.co.uk)
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Jim Peck (Technical Sales Manager)
» Is the access suitable for a craw ler crane?
jim.peck@bphequipment.co.uk
» Can the load be lifted to the required location w ith a craw ler crane?
07967 667045
» Is the hire duration greater than 2 w eeks? » Does your AP have the appropriate qualifications to operate the crane?
Rob Jensen (Head of BPH) rob.jensen@bphequipment.co.uk
Checklist to remember: » The Appointed Person assessing, planning and executing the operation of the crane must
07738 000854
meet the relevant regulations
» The size of crane required or alternatively identify the load to be lifted and at w hat radius
Balfour Beatty specialist contact:
» Type of boom required i.e. Lattice or Telescopic » Number of cranes required » Any environmental restrictions applicable i.e. Engine tier or biodegradable oil » Sufficient notice available to plan the mobilisation
Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
» Length of boom required » Are there any site access restrictions? » Don’ t forget to get the temporary w orks design for the Working platform (including offloading and rigging location) SITE MOBILISATION GUIDE VERSION 2, 2018
63
Temporary works planning - how to get it right
Link up w ith the local Temporary Works Design office
Temporary Works are an Engineered Solution to enable the construction of the w orks. They include items such as scaffolds, formw ork, platforms etc. All Temporary Works on site needs to be designed and checked to ensure that they are safe adequate to perform the w orks.
Appoint a Temporary Works Co-ordinator
Identify Temporary Works items needed on the project and create a Schedule
Design & Check Temporary Works items ready for building on site
SITE MOBILISATION GUIDE VERSION 2, 2018
64
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following: » Identify the Bid Temporary Works Schedule and budget allow ance
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub mobilisationhub@balfourbeatty.com
» Think about how you w ant to set up site and your method for building project 0844 8800 090
Checklist to remember » Cranes and hiabs lifting on site need to have platforms beneath to spread the load from outriggers. » Underground services need to be diverted or protected from site activities » Formw ork and falsew ork needs to be designed and checked.
» ENG-PR-0009 – Temporary Works Design and Checking Procedure needs to be adhered to at all times.
Balfour Beatty specialist contacts: Ian Donaldson (Regional North & Midlands) ian.donaldson@balf ourbeat t y.com 07767 311813 Mark Beeston (Regional Scotland) mark.beest on@balf ourbeat t y.com 01698 647609 Grant Tolley (Major Projects & Regional South) grant .t olley@balf ourbeat t y.com 07872 005548 Steve Harper (Rail Services) st eve.harper@balf ourbeat t y.com 07970 235144
Lead in times
Ravi Panesar (Regional London) rpanesar@balf ourbeat t y.co.uk 07968 615675
» At least 2 w eeks for design & check
Adrian Llew ellyn (Pow er T & D) adrian.llew ellyn@balf ourbeat t y.com 07791 926639
(don’ t forget to add on procurement and installation time)
SITE MOBILISATION GUIDE VERSION 2, 2018
James Latham (Gas & Water) james.lat ham@balf ourbeat t y.com 07967 689371
65
Temporary electrics - how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
Our subcontract partner w ill develop a specification and design w ith agreed timescales
Temporary pow er, temporary lighting, temporary fire alarms, Data Points w ithin the units, Plumbing (w ater & w aste), utilities monitoring, grey/rainw ater harvesting, site accommodation bases. Services include: Temporary pow er and plumbing scheme design for bids and projects, including associated costs and sustainability options. Early engagement is preferable to enable value engineering. Attendance on site is possible for connection in 3-7 days, if accurate information is provided. For further Electrical Safety guidance see Mechanical & Electrical Safety 360 page: https://home360.balfourbeatty.com/UKHealthandSafety/Pages/Electricity.aspx
Project Manager w ill need to confirm order
Delivery and installation schedule agreed
SITE MOBILISATION GUIDE VERSION 2, 2018
66
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
» Be sure to have your project number at hand » Send details of temporary electrics
mobilisationhub@balfourbeatty.com 0844 8800 090
» Send details of the programme requirements (e.g. tow er crane, lifts, hoists) Checklist to remember:
Michael Walsh (Procurement) Michael.Walsh@balfourbeatty.com
» The specification of LED lighting should be encouraged on all projects but especially w here the duration is over 12 months. These fittings significantly reduce energy consumption and maintenance costs. » Ensure that there is early engagement w ith the Netw ork Operators to obtain a mains feed to site at the earliest opportunity to minimise the use of generators. The hire and supply of fuel w ill be far more expensive than a netw ork on most occasions. » Ensure that prior to any site w elfare units being inhabited; on conclusion of electrical supply installation, the follow ing are actioned; » Supply cabling to all units - w hether plug and play / hard w ired – are tested and recorded before energisation. » The internal electrical installation is Inspected as per IET BS7671 Regulations prior to supply being energised – any failings are remedied before pow er is sw itched on. » Once supply is energised, supply cable AND internal installation is tested as per IET BS7671
Balfour Beatty specialist contact: WysePower Paula Callaway (London and the South East) paula.callaw ay@w ysegroup.co.uk Annie Rush (West London and South West) annie.rush@w ysegroup.co.uk Rob Arnold (Midlands and Bristol) rob.arnold@w ysegroup.co.uk Mark Staunton (Scotland) mark.staunton@w ysegroup.co.uk Lee Davey (Leeds and North East) lee.davey@w ysegroup.co.uk Ian Green (Manchester and North West) ian.green@w ysegroup.co.uk Makhan Uppal Makhan.Uppal@w ysegroup.co.uk
Regulation, and test results recorded and copy left at site at that point – minimum of hand w ritten result MUST be left at site at the time of tests being carried out. » Note – all Inspection and Testing MUST be carried out be qualified and competent Electricians
SITE MOBILISATION GUIDE VERSION 2, 2018
Wingate Matt Cummings matt.cummings@w ingate.co.uk
67
Fire Services - how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill request a quotation. Alw ays attach a detailed site plan to include cabin layout
Final quotation provided by the Fire team
Fire Services team w ill confirm date of required delivery w ith the Project Manager
Project Manager w ill need to raise a purchase order on quotation
Fire Team and Project Manager to agree maintenance requirements
SITE MOBILISATION GUIDE VERSION 2, 2018
68
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
X
Before engaging with us, consider the following: » Prepare detailed plans of site cabins and compound to be covered.
-3
-2
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
» Size of building in square meter
mobilisationhub@balfourbeatty.com
» Types of buildings (w arehouse, office, hospital, school)
0844 8800 090
» Is there electricity on site? » When do you require fire services to install extinguishers and signs? » When do you require fire services to carry out a f ire risk assessment?
Balfour Beatty specialist contact:
» When do you require fire services to carry out a f ire alarm installation? Plant & Fleet Services 0870 8444 888 (option 3) Checklist to remember:
fireservices@balfourbeatty.com
» Include site plans to include cabin layout to provide a quote against » Include R12 Purchase Order Number
SITE MOBILISATION GUIDE VERSION 2, 2018
69
Furniture and asset exchange – how to get it right
Identify materials that you need that may be available from other projects and contact the Site Mobilisation Hub, w ho w ill assess your requirements
This service has been created to enable the exchange of surplus materials and furniture betw een project sites across the group, helping to reduce w aste, avoid land fill and achieve cost savings. It helps you connect w ith other parties to exchange materials, then you make the deal directly w ith them.
Log on to materials exchange and register a “ w ant” and look at w hat is already there
Link up w ith interested parties and complete transfer
SITE MOBILISATION GUIDE VERSION 2, 2018
70
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
» Be sure that you know your address and postcode » Determine w hat materials and equipment you need
mobilisationhub@balfourbeatty.com
» Are you w illing to pick up items from another site?
0844 8800 090
» If advertising furniture, advise on an accurate demobilisation date. Tips for using the Materials
Balfour Beatty specialist contact:
» Ensure that you register your “ w ant” as early as possible to maximise the number of
Phillip Dumelow
people w ho w ill see your entry » Review the database regularly to see if anything you need has come on
020 7963 2323 phillip.dumelow @balfourbeatty.com
» Register for updates to new items Checklist to remember:
To access the Project Portal: http://portal.balfourbeatty.net
» Make certain that any material transfers conform w ith legislation
To access the Project Portal How To
» Ensure any furniture or assets sourced are suitable in terms of cost, distance and
Guide:
quality for the project you are w orking on. If this is deemed unsuitable for your
http://portal.balfourbeatty.net/help/Cos
project, the Hub w ill contact you and discuss your options.
ts%20-%20Hub%20User.pdf
SITE MOBILISATION GUIDE VERSION 2, 2018
71
Waste - how to get it right
Project Manager should contact the relevant supplier for the type of skip required
Project Manager needs to raise a purchase order and book delivery
Reconomy is currently our supplier for solutions in general, concrete, w ood, plasterboard, inert and cardboard w aste. CF Booth are our supplier for metal skips, w ith Moulding Solutions supplying plastic skips. How ever, they w ill not deliver to Scotland. Therefore, Reconomy should then be the first option. Reconomy support teams are available for on-site support in optimal w aste segregations. Their helpdesk is open betw een 08:00 and 17:30, Monday to Saturday. Order before 16:00 for next day service.
Ensure invoice is correct and approve payment
Approved order is sent to the respective supplier
SITE MOBILISATION GUIDE VERSION 2, 2018
72
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Reconomy
» Your w aste plan identifying expected w aste streams and anticipated quantities early in the process – Reconomy can support w ith this » Check for any take back / recycling schemes w ith suppliers and utilise » Direct arrangements w ith scrap metal merchants are appropriate w here large high value quantities of scrap metal are anticipated Checklist to remember:
balfourbeatty@reconomy.com 0800 0282 290 CF Booth (Metal Skips) scm.pow er@balfourbeatty.com Moulding Solutions (Plastic Skips) shaun@moulding-solutions.co.uk
» Liaise w ith the sustainability team in your Strategic Business Unit to optimise w aste solutions
Balfour Beatty specialist contact:
» Consider the cost of w aste per yard w hen selecting skip size
Site Mobilisation Hub
» Consider requesting a site visit to assess requirements and optimise disposal
mobilisationhub@balfourbeatty.com
» Do not contaminate – charges may be incurred. If in doubt contact the Site
0844 8800 090
Mobilisation Hub for assistance » Do not overfill – additional charges refusal to service may occur » Report any complaints to avoid the creation of delays and decrease in the quality of response. SITE MOBILISATION GUIDE VERSION 2, 2018
73
Road Sweepers – How Do You Get It Right?
Is your project likely to require a road sw eeper?
If yes, w e w ill w ork w ith the project team to understand requirements and current site facilities
We w ill confirm arrival dates and complete all other necessary actions to support the hire and ensure a smooth mobilisation.
SITE MOBILISATION GUIDE VERSION 2, 2018
74
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
X
Sweeper Checklist:
-2
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact:
» Number of units?
Balfour Beatty Site Mobilisation Hub
» Does the site have clean w ater facilities or w ater bow sers?
mobilisationhub@balfourbeatty.com
» Are tipping/ w aste disposal facilities available onsite? » Is the hire duration greater than 3 months?
0844 8800 090
» Sufficient notice available to plan the mobilisation (w e source local drivers) » Are there any site access restrictions? » Shift patterns (day/ night & hours)
Balfour Beatty specialist contact:
» Work specific detail (road crossing/ gully sucking/ tarring)
Tom Pearson (Operations Manager) 07580 998998
SITE MOBILISATION GUIDE VERSION 2, 2018
75
Signage - how to get it right
Project Manager should create account on Lyreco w eb portal
This includes signage for temporary street w orks, permanent road signage, Balfour Beatty branded and all bespoke signage requirements. Lead time for standard stocked products is next w orking day. For nonstocked and bespoke signage requirements allow for a tw o w eek lead time follow ing initial engagement.
Project Manager to find products on the Lyreco Balfour Beatty database
Each project must have a noticeboard or folder. There are various types and sizes of noticeboard available from Lyreco, using the details below.
Project Manager w ill need to confirm order
Agree delivery to site
SITE MOBILISATION GUIDE VERSION 2, 2018
76
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Mobilisation Hub
» Make sure you have a Lyreco account, Site Mobilisation Hub can arrange this for you. Please allow 48 hours for your new account to be created » Have your site details to hand, inclusive of any project numbers/cost centres,
mobilisationhub@balfourbeatty.com 0844 8800 090
delivery points » Check w ith your health and safety contact in Balfour Beatty for required signage (minimum Fatal Risks, Golden Rules, Observation cards, H&S Law poster, Briefing
Balfour Beatty specialist contact:
Boards) Joseph Griffiths Checklist to remember:
07666 542 650 joseph.griffiths@balfourbeatty.com
» Check your customer contract for special requirements or limitations w ith regard to hoarding and signage » Ensure all legal notices are displayed e.g. F10, Health and Safety Law Poster.
HS&E team HSE@balfourbeatty.com
Contact your local HS&E advisor for further information
SITE MOBILISATION GUIDE VERSION 2, 2018
77
Communication noticeboards - how to get it right Every site is required to have a Communications noticeboard or folder. Project Manager should create account on Lyreco w eb portal
These can be procured from Lyreco, using the details on the preceding page. Once you have your noticeboard or folder, a member of the team must take responsibility for making sure it is updated. To do this, they need to email communications@balfourbeatty.com to register.
Project Manager to find products on the Lyreco Balfour Beatty database
Once registered, they w ill receive new s items via e mail that they must print and display on the noticeboard or in the folder.
Project Manager w ill need to confirm order
Agree delivery to site
SITE MOBILISATION GUIDE VERSION 2, 2018
78
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Mobilisation Hub
» Make sure you have a Lyreco account, Site Mobilisation Hub can arrange this for you. Please allow 48 hours for your new account to be created » Have your site details to hand, inclusive of any project numbers/cost centres,
mobilisationhub@balfourbeatty.com 0844 8800 090
delivery points » Check w ith your health and safety contact in Balfour Beatty for required signage (minimum Fatal Risks, Golden Rules, Observation cards, H&S Law poster, Briefing
Balfour Beatty specialist contact:
Boards) communications@balfourbeatty.com Checklist to remember: » Email communications@balfourbeatty.com to register to receive noticeboard/ folder content » To update the content in a timely manner
SITE MOBILISATION GUIDE VERSION 2, 2018
79
Project Control Room - how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the project requirements
Project control rooms employ visual management tools and short interval control on our projects. Combined w ith appropriate training and discipline of use, they are used to deliver best practice in communication, control and project management.
Determine project control room location
Template signs are available from BPP in a number of styles to suit a range of project requirements, and have a one w eek lead time.
Training can be arranged w ith our in house experts or you can use the online
w ebinar. Project Manager to order boards through BPP
Both parties to arrange training session for site team
SITE MOBILISATION GUIDE VERSION 2, 2018
80
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
-1
-12
-8
-6
-5
-4
-3
-2
-1
Project control rooms employ visual management tools and short interval control on our
First point of contact:
projects. Combined w ith appropriate training and discipline of use, they are used to
Balfour Beatty Site Mobilisation Hub
deliver best practice in communication, control and project management. Before engaging with us, consider the following:
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
mobilisationhub@balfourbeatty.com 0844 8800 090
» Define requirements: view the project board options available. Options can be view ed on BPP’ s online interactive catalogue
Balfour Beatty specialist contact:
» Determine location of the Project Control Room – a dedicated room if available or combined w ith an induction or meeting room Checklist to remember:
Andrew Dodsw orth
07474 294423 andrew .dodsw orth@balfourbeatty.com
» Install at the beginning of the project – these tools are most effective if used w ith discipline from the outset of the project » Use the training resources available to ensure your project gets the most benefit from the visual management tools
SITE MOBILISATION GUIDE VERSION 2, 2018
81
Bulk fuel - how to get it right
Identify fuel requirements
For the supply of bulk fuels, specifically gas oil, diesel, low sulphur gas oil and lubricant products, please refer to the group supplier agreement guide on page 104 for more details.
Project Manager should complete fuel form and send to Hall fuels to confirm the project requirements
Hall Fuels w ill provide Project Manager w ith an account number, w hich w ill then need to be quoted in future interactions
SITE MOBILISATION GUIDE VERSION 2, 2018
82
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact:
Hall Fuels » Assess planned fuel usage for period » Produce access plan
01784 248659
» Confirm site details including address and project code
balfourbeatty@hallfuels.co.uk
Checklist to remember: Balfour Beatty specialist contact: » Engage w ith the Site Mobilisation Team to notify them about specific health and safety requirements that occur on your site » Provide suitable fuel and lubricant storage facilities (double skinned tanks, separation from w atercourses, fire fighting measures, safe refuelling arrangements, etc.)
SITE MOBILISATION GUIDE VERSION 2, 2018
Michael Walsh 07966 991 014 Michael.Walsh2@balfourbeatty.com
83
Purchasing cards - how to get it right Purchasing Cards (Non-travel and expenses) are an alternative to a standard purchase order w ith a set monthly limit. They should be used for low value, high volume requirements. When you use it w ith Apply for a purchasing card by completing PRC-SF-0004A form
enabled suppliers, it reduces administration costs, lets you see line by line w hat you' re spending and pays our suppliers quicker.
Keep records and receipts
SITE MOBILISATION GUIDE VERSION 2, 2018
84
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
How to get a purchase card
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Balfour Beatty Site Mobilisation Hub
Complete form PRC-SF-0004A available on 360 and send to purchasing.card@balfourbeatty.com
mobilisationhub@balfourbeatty.com
An application w ill be sent to the bank on your behalf, you w ill then receive the card
0844 8800 090
and be provided w ith training. How to get a corporate card An application can be requested from the Expenses team cscpettycash_pcards@bbw orksmart.com How will transactions be posted to the project I am working on?
Balfour Beatty specialist contact: Purchasing Card Team 08000 304 127 | option 7 | option 1 CorporateCards@balfourbeatty.com
All transactions w ill appear on the banks online system ‘ MiVision’ , usually w ithin 48 hours after transacting w ith a supplier. The Project Manager or someone w ho has delegated responsibility for the card e.g. Site Administrator, can log in to MiVision and
allocate transactions accordingly.
SITE MOBILISATION GUIDE VERSION 2, 2018
85
Suction Excavation – how to get it right
Is your project likely to require suction excavators?
If yes, w e w ill liaise w ith the project team to detail and adapt our suction excavator proposition to suit requirements of site and available facilities
We w ill confirm arrival dates and complete all other necessary actions to support the hire and ensure a smooth mobilisation
SITE MOBILISATION GUIDE VERSION 2, 2018
86
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
X
Suction Excavator Checklist to remember:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact:
» Be compliant, w ith Balfour Beatty Suction Excavator procedures?
Balfour Beatty Site Mobilisation Hub
» Speak to the BBPFS Suction Excavator hire desk for advice?
mobilisationhub@balfourbeatty.com
» Provide excavation details, length, w idth, depth, ground/soil type? » Provide the distance from rear of vehicle to the start of the excavation?
0844 8800 090
» Do you know that, w e can extend the reach of the suction hose by 100 metres by fitting extension pipes and these pipes can go round bends? » What are the site access/egress details? » Do you have, on site tipping for the excavated material? » Do you have plant/people segregation, sufficient barriers to establish a safe w orking exclusion zone? » Do you require debris netting? » Arrange a site visit from the BBPFS operational team, only operational staff w ith years of experience w ill assess the w ork, no sales staff? » What is your anticipated hire duration, talk to the hire desk and w e can share our
Balfour Beatty specialist contact:
Suction Excavation Steve Goodw in (Head of Specialist Plant) 07967 669447 Kevin Smith (Hire Manager) 07583 063 423
Will Fantom (Operations Manager) 07967 669 481
experience and help you plan?
SITE MOBILISATION GUIDE VERSION 2, 2018
87
PPE and site equipment – how to get it right
Project Manager should contact Direct Corporate Clothing via telephone or email
Direct Corporate Clothing (DCC) is the group supplier for PPE.
Place your order and ensure you confirm delivery
Ensure invoice is correct and approve payment
SITE MOBILISATION GUIDE VERSION 2, 2018
88
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
-12
-8
-6
-5
-4
-3
-2
-1
Before engaging with us, consider the following:
First point of contact:
» P-card if available
Direct Corporate Clothing (DCC)
» Details of PPE requirements and replacement needs
bbg.helpdesk@directcorporate.co.uk
» Details of any stock you need to keep in storage on site
0121 543 1339
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
Checklist to remember: » Contact the marketing team if you require a non-standard design e.g. adding a new
Balfour Beatty specialist contact:
logo – Contact details of Marketing communications manager- w ho w ill need to give
Joseph Griffiths
approval - Patrick.gallagher@balfourbeatty.com
07966 542 650
» Consolidating requirements w ill help to avoid carriage charges (on orders less than
Joseph.Griffiths@balfourbeatty.com
£50) Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
SITE MOBILISATION GUIDE VERSION 2, 2018
89
Office supplies – how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the initial requirements
Site Mobilisation Hub can create an order on Lyreco' s w eb portal and pass the details to the Project Manager to order directly
This covers office supplies, first aid suppliers, catering and hygiene, IT consumable, print and office furniture. Orders can be placed w ith the dedicated Balfour Beatty Customer Services Team. Orders placed by 17:30 are guaranteed for next w orking day delivery across all stocked lines. Some catalogue furniture w ill have a five w orking day lead time. Lyreco’s Webshop stocks Balfour Beatty products. Before you engage w ith the Site Mobilisation Hub, check internal resources via the Materials Resources Exchange.
Project Manager should confirm order
Project Manager to oversee delivery to site
SITE MOBILISATION GUIDE VERSION 2, 2018
90
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
-12
-8
-6
-5
-4
Before engaging with us, consider the following:
First point of contact:
» Make sure you have a Lyreco account. If you do not, please allow 48 hours for a
Lyreco
new account to be created » Have your site details at hand, inclusive of any project numbers / cost centres.
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
uk.balfourbeatty@lyreco.com 0845 603 9044
Please also be clear on preferred payment method along w ith the relevant purchase order details or P-card information Checklist to remember: » Provide clear delivery instructions
» Consolidate orders to reduce the number of deliveries required
Balfour Beatty specialist contact: Joseph Griffiths 07966 542 650 Joseph.Griffiths@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
91
Building materials - how to get it right Project Manager should contact the Site Mobilisation Hub, w ho w ill conduct a Triage and assess the project requirements
Procure via P-Card or complete requisition and send to Mobilisation Partner
Mobilisation Partner to raise Purchase Order w ith Travis Perkins, Jew son or Arnold Laver w here transaction cannot be facilitated by P-Card
Materials delivered and documents sent to site support to allow timely processing of the invoice
SITE MOBILISATION GUIDE VERSION 2, 2018
General building materials for site mobilisations should be procured from the follow ing Balfour Beatty supply chain: • • • •
For General Building Materials (Heavy, Light and Civils): Tier 1 – Travis Perkins Tier 2 – Jew son For General Timber: Tier 1 – Travis Perkins/ Arnold Laver Tier 2 - Jew son
Benefits of utilising the agreement w ith Jew son include: • Travis Perkins have over 700 branches across the UK • Jew son (Inc. Build Centre) have over 600 branches including 55 Civils depots across the UK Both off next day delivery on any ‘ Core’ items ordered the previous day • Travis Perkins – ordered before midday • Jew son – ordered before 4pm Timber. All products supplied meet the criteria of the Balfour Beatty Sustainable Timber Procurement Policy (FSC/ PEFC and Chain of Custody). 92
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
Before engaging with us, consider the following: » Check internal resources via the Asset Exchange Project Portal » Consider pre-ordering specific sizes to avoid the requirement to dry cut on site » Consider delivery and offloading requirements e.g. crane or forklift offloading
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Jon Dean 07970 698 951 Jon.Dean@balfourbeatty.com
facilities and palletised loads » Consider manual handling controls and packaging materials
Balfour Beatty specialist contact:
» Consider temporary w orks design procedure requirements (hoarding design, shoring for pipe installation) » Please utilise P-Card w here possible or engage w ith your local procurement hub team w ho w ill place the order from your requisition
SITE MOBILISATION GUIDE VERSION 2, 2018
Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
93
Non-operated plant - how to get it right
Project Manager should contact the Plant hire service centre
Various non-operated plant and equipment hire from fencing to lighting tow ers.
Please raise the requisitions w ith the Plant Hire teams using the contact details opposite. Project Managers requirements are identified
The approximate lead time for your plant can vary betw een eight w orking hours to a w eek. Be sure to check w ith the hire desk how long delivery w ill take and if there is a faster option if required.
Project Manager w ill need to raise online requisition via email or phone
Hire desk w ill acknow ledge request w ithin one hour
SITE MOBILISATION GUIDE VERSION 2, 2018
94
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
Before engaging with us, consider the following:
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Construction, Major Projects
» Project code (contract site reference) » Estimated off-hire date » A competent and qualified user, if required » Delivery or collection address » Detail of any delivery requirements Checklist to remember:
csukplant@balfourbeatty.com 0870 8444 888 (select option 1, option 1, option 2) Gas & Water, Power T&D bbssplant@balfourbeatty.com 0870 8444 888 (select option 1, option 1, option 1)
» Check w hat accessories are required on the project » Consider the fuel cost and add the item to the bulk fuel delivery schedule
Rail, Living Places, Joint Ventures mobilisationhub@balfourbeatty.com
» Site restrictions on delivery and maintenance
0844 8800 090
» Ensure there is sufficient budget in the tender allow ance » Provide appropriate general and task lighting Balfour Beatty specialist contact: Plant Specification booklet: https://w w w .balfourbeatty.com/media/164314/plant -specification-booklet-january2017.pdf Or search HSF-RM-0046e on 360 SITE MOBILISATION GUIDE VERSION 2, 2018
Site Mobilisation Hub
mobilisationhub@balfourbeatty.com 0844 8800 090
95
Generators - how to get it right
Project Manager to identify plant / equipment requirements and contact the Mobilisation Hub. by using the generator selector and discuss w ith the Plant team specialists
In some cases it is more cost -efficient over the hire period to use a combination of a low er specification generator and a firefly / pow er cube or to run generators in parallel. Please contact your hire desk for more information. It is best practice if a generator is required to run 24/7 to have a second smaller generator installed to run during periods of low er demand. Generators up to 300kVA have a lead time of 12 w orking hours and generators over 1400kVA have a lead time of 20 w orking hours.
Project Manager w ill need to raise a requisition via email or phone
Breakdow ns should be attended and assessed w ithin four w orking hours. All orders processed via the Site Mobilisation Hub, w ill be passed onto the Energy Management Unit that can help size your generator for you.
Hire desk w ill confirm the order w ithin one hour
SITE MOBILISATION GUIDE VERSION 2, 2018
96
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
-12
-8
-6
-5
-4
-3
-2
-1
Before engaging with us, consider the following:
First point of contact:
» Will you use your generators for 40 hours a w eek or 20 hours a day?
Construction, Major Projects
» Would a small generator be sufficient for night use?
csukplant@balfourbeatty.com
Please have ready:
0870 8444 888
» Project and task codes (contract site reference)
(select option 1, option 1, option 2)
» Estimated off-hire date
Gas & Water, Power T&D
» Delivery or collection address
bbssplant@balfourbeatty.com
» Details of any delivery requirements
0870 8444 888
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
(select option 1, option 1, option 1) Checklist to remember: » Procure fuel for the generators from Halls Fuel » Apply for installation on a combinational service (using a smaller generator for low
Rail, Living Places, Joint Ventures mobilisationhub@balfourbeatty.com 0844 8800 090
demand periods) » Ensure there are provisions for emergency stand-by pow er » The correctly sized generators are used to avoid significantly increased fuel costs, noise levels and local air pollution
SITE MOBILISATION GUIDE VERSION 2, 2018
Balfour Beatty specialist contact: Energy Management Unit: EMUmobilisation@balfourbeatty.com
97
Effluent empty servicing – how to get it right
Project Manager should contact BioMarsh to enquire about tankemptying / w ater refill services
BioMarsh w ill provide a quote w ithin 24 hours
Services required w ill be carried out on site
SITE MOBILISATION GUIDE VERSION 2, 2018
98
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
Before engaging with us, consider the following:
» What services do you require? » What is the number of w elfare facilities on site?
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact:
balfourbeatty@biomarsh.com 0800 0285942
» What is the frequency of your requirements? Checklist to remember:
Key Account Manager: Brian Driver
» When requesting tank refills or empties remember to send PO number, project number, site contact name, telephone number and email address, full site address,
07812 235060 brian.driver@biomarsh.com
site opening times and unit number » Aborted services w ill incur a charge of £50 » All projects w ithin AB and PH postcode catchment areas w ill incur a £75
additional charge due to geographical location
Balfour Beatty specialist contact: Balfour Beatty Site Mobilisation Hub
» All projects w ithin IV, KW, HS, ZE and Northern Ireland postcode catchment areas w ill be priced as P.O.A due to geographical location
mobilisationhub@balfourbeatty.com 0844 8800 090
SITE MOBILISATION GUIDE VERSION 2, 2018
99
Fuel cards - how to get it right
Apply for the fuel card by contacting Fleet Helpdesk on 0845 602 7064
The Allstar Discount Diesel fuel card is accepted across the UK, including all major oil brands. The Allstar netw ork includes all the main supermarket and oil company forecourts as w ell as independent forecourts. The Discount Diesel fuel card can be used at over 1,700 forecourts. Dow nload the Allstar mobile app our app to find your nearest fuel station.
Keep records and receipts
SITE MOBILISATION GUIDE VERSION 2, 2018
100
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
The Allstar Discount Diesel fuel card is accepted across the UK, including all major oil brands. The Allstar netw ork includes all the main supermarket and oil company forecourts as w ell as independent forecourts.
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Fleet Helpdesk 0845 602 7064 (option 3)
The Discount Diesel fuel card can be used at over 1,700 forecourts.
Dow nload the Allstar mobile app our app to find your nearest fuel station.
01332 288 580 fuelcard@bbfleetservices.com
Before engaging with us, consider the following: » Visit the Allstar fuel station netw ork w ebpage to find details of fuel stations near your projects: https://w w w .allstarcard.co.uk/services/allstar-fuel-station-netw ork/ Checklist to remember: » Plan your journey and know fuel stations in relevant locations in advance » Fill up w hen you have betw een ¼ and ½ tank, not w hen already on red » Never fill up w ith premium fuel » A minimum of 5 w orking days are required to order and receive fuel cards
SITE MOBILISATION GUIDE VERSION 2, 2018
101
Driver Risk Management - how to get it right
Will your contract be using commercial vehicles?
Our team of experts focus on reducing driver related risk, providing comprehensive behavioural safety training supported by in-depth know ledge of the latest technology solutions.
This allow s us to examine driver risk level by review ing and understanding the situational, behavioural and attitudinal risk factors unique to each driver. Using the results of the assessment, w e develop bespoke programmes designed to deliver specific objectives. Balfour Beatty vehicle driver policy requires compliance w ith the permit to drive scheme.
Contact Driver Risk Management to arrange the installation of telematics to the commercial vehicles and the enrolment to the Permit to Drive scheme for your drivers.
SITE MOBILISATION GUIDE VERSION 2, 2018
102
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
X
As per the commercial vehicle policy, the installation of telematics into commercial vehicles is mandatory. All commercial vehicle drivers must also be enrolled and undertake the Permit to Drive scheme before driving on behalf of the business.
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
First point of contact: Permit to Drive enquiries Driverrisk@balfourbeatty.com
Telematics can be installed into a commercial vehicle w ith a minimum of 5 days notice. The request for drivers to be enrolled onto the Permit to Drive scheme should be sent 48 hours before they’ re required to drive on company business.
01332 288 192/01332 288 183
Telematics enquiries
Before engaging with us, consider the following:
telematics@bbfleetservices.com
» Will the driver you’ re requesting to be enrolled onto the Permit to Drive meet the
01332 288 204
minimum eligibility requirements to drive company vehicles? Checklist to remember: » All commercial vehicles should be fitted w ith telematics » All commercial vehicle drivers must hold a valid Permit to Drive » A minimum of tw o w orking days are required to enrol a driver and for them to
complete the required actions. » A minimum of 5 w orking days are required to order and install telematics into a commercial vehicle.
SITE MOBILISATION GUIDE VERSION 2, 2018
103
Construction Logistics and Community Safety (CLOCS) – how to get it right Will Heavy Goods Vehicles (HGV) be operated from the site? And/or w ill HGV’ s be making deliveries to site?
Create Construction logistics plan • Site suitability • Access and egress • Traffic routing • Control of traffic • Ensuring Supply chain compliance
Communicate out the plan to drivers and supply chain. Enforce the requirements
Balfour Beatty is a CLOCS Champion Company and committed to embedding the CLOCS standard across all UK sites. The CLOCS standard is most relevant to Heavy Goods Vehicles (HGV, Vehicles greater than 3.5 ton Gross Vehicle Weight) that both operate from and deliver to sites. The aim of CLOCS is to reduce death and injury to vulnerable road users that share the roads w ith construction industry traffic. A construction site logistics plan should be in place, communicated to Balfour Beatty drivers together w ith subcontractors, suppliers and their delivery drivers. The construction site logistics plan should include: • Suitability of access / egress points, signage, clear of obstacles • Ground conditions • Published instruction on best routes to and from site considering peak times, difficult junctions, low , w eight limits, Schools, hospitals and any other areas of high foot fall e.g. shopping centres, bus & train stations • Designated segregated areas for loading/unloading (off the road) • Designated areas for parking (off the road) • Control of site traffic - PVMP plan in place • CLOCS Gate checks for inbound traffic Please contact Adrian Wanford for more details on CLOCS: 07967669535, Adrian.Wanford@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
104
CLOCS – affects all suppliers CLOCS Adoption – What do I have to do?
1 2 3 4 5
Clients
Sites and Mainplan contractors Create Construction logistics • Site suitability • Access and egress • Traffic routingSpecialist contractors • Control of traffic Tier compliance 1 & Tier 2 • Ensuring Supply chain Materials suppliers
HGV operators
SITE MOBILISATION GUIDE VERSION 2, 2018
• Contractually require the main contractors to operate CLOCS • Ensure they are capable of doing this and ensure they do • Ensure all subcontractors are supplied only by suppliers who can make CLOCS compliant deliveries • Manage CLOCS compliance at site • Ensure all materials are only by supplied by suppliers who can make CLOCS compliant deliveries
• Ensure your in-house fleet or your 3rd party transport firm can make CLOCS compliant deliveries • You must be a member of FORS (Bronze minimum) • Your HGVs must have minimum Vulnerable Road User (VRU) safety equipment • Your drivers must be trained in VRU safety – Safe Urban Driving course 105
Major Earthworks Plant – internal self delivery
Does your project have medium-long term requirement for operated heavy plant?
Balfour Beatty have internal capability for operated: • Wheeled / Tracked Excavators = > 15t • ADTs 25-30t • Medium-sized tracked Dozers • Rubber Tyre Self Propelled Rollers 13-15t
Get in touch w ith the team to see how w e can support your project
SITE MOBILISATION GUIDE VERSION 2, 2018
David Walton, Strategic Assets
Site Mobilisation Hub
david.w alton@balfourbeatty.com
mobilisationhub@balfourbeatty.com
07980 911945
0844 8800 090
106
Demobilisation Key Elements
SITE MOBILISATION GUIDE VERSION 2, 2018
107
Modular Accommodation –how to get it right Project Manager should inform Modular team & Site Mobilisation Hub of intended off -hire date at least 12 w eeks in advance
Project Manager should check RAMS are in line w ith changes to site specification
When off-hiring modular accommodation, the Project Manager should contact the Modular team and the Site Mobilisation team. As you plan to demobilise your site, please post any materials that can be reused on the Materials Exchange including furniture.
Complete dilapidation report
Both parties to agree time for building removal
SITE MOBILISATION GUIDE VERSION 2, 2018
108
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
Before engaging with us, consider the following: » Confirm date and time of off -hire » Communicate any site opening / closing times or traffic restrictions
-4
-3
-2
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact: Balfour Beatty Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
Checklist to remember: » Empty the building of furniture at the end of the project
Balfour Beatty specialist contact:
» Remove all signage before returning all accommodation » Ensure all services are disconnected prior to collection » Minimum off -hire period is 12 w eeks
Modular Buildings 01332 288 426 Modular.enquiries@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
109
Temporary Accommodation (cabins) – how to get it right
Project Manager should inform the Site Mobilisation Hub of the date you w ill vacate the premises
When off-hiring temporary accommodation, contact the Site Mobilisation Hub and quote the site address and fleet numbers.
Project Manager to check RAMS are in line w ith changes to site specification
If the accommodation is to remain in place and the client or another contractor takes over its use, you must negotiate this ahead of our off -hire date and in conjunction w ith the Plant Hire Desk and A-Plant.
Both parties to agree collection time for cabin removal
Complete off -hire inspection form provided by A-Plant collection driver
SITE MOBILISATION GUIDE VERSION 2, 2018
110
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact: Balfour Beatty Site Mobilisation Hub
» Confirm date and time of off -hire » Confirm any alterations, missing furniture or damages to disclose to A -Plant
mobilisationhub@balfourbeatty.com
» Communicate any site opening / closing times or traffic restrictions
0844 8800 090
Checklist to remember:
Balfour Beatty specialist contact:
» Empty the toilets/effluent tanks prior to collection
Construction, Major Projects
» Return accommodation w ith all floors sw ept, bins emptied and w indow s secured
csukplant@balfourbeatty.com
» Ensure you have removed all Balfour Beatty signage
0870 8444 888
» Adhere to notice provisions w hich w ould result in additional costs
(select option 1, option 1, option 2)
» Remove all fixtures and fittings prior to collection (including notice boards to provide
Gas & Water, Power T&D
vacant possession)
bbssplant@balfourbeatty.com 0870 8444 888 (select option 1, option 1, option 1) Rail, Living Places, Joint Ventures mobilisationhub@balfourbeatty.com 0844 8800 090
SITE MOBILISATION GUIDE VERSION 2, 2018
111
Tower Cranes – how to get it right
Project Manager should inform the Site Mobilisation Hub and Tow er Crane Manager of intended off -hire date at least 12 w eeks in advance
When off-hiring Tow er Cranes, the Project Manager should contact the Site Mobilisation Hub.
Keep both parties updated on any slippage of the dismantle date so appropriate rescheduling dates can be booked.
Both parties to agree finalised dismantle date and taken aw ay by Tow er Crane Services.
SITE MOBILISATION GUIDE VERSION 2, 2018
112
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
Before engaging with us, consider the following: » Confirm date and time of off -hire
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact: Balfour Beatty Site Mobilisation Hub
» Hirers usually require a minimum of 12 w eeks’ notice of the intended off hire date
mobilisationhub@balfourbeatty.com
» Communicate any site opening / closing times or traffic restrictions
0844 8800 090
» Communicate any slippage to the dismantle date as soon as possible Checklist to remember: » Dismantle lead times can be longer if taking place during a road closure (up to 12 w eeks) or at the w eekend, or if Netw ork Rail or other agency have to approve method statements and methodology » Planning to remove the crane is as detailed as the installation - w here w ill the mobile crane stand, w here is the lay dow n area for the jib and other crane parts
SITE MOBILISATION GUIDE VERSION 2, 2018
Balfour Beatty specialist contact:
Simon Armstrong 07854 058036 0870 8444 888 (Select Option 1, Option 5) tow ercranes@balfourbeatty.com
113
3 rd party property handback – how to get it right Project Manager should inform the Site Mobilisation Hub of the date you w ill vacate the premises (minimum of 12 w eeks before break date)
When handing property back to the ow ner, dilapidations can be settled by an agreed figure that reflects the damages or by undertaking the w orks required.
Property Team w ill inform the landlord w ho may issue a dilapidation survey
Agree w hether to undertake any remedial w orks or pay a financial settlement to the landlord
Contract Team to sign-off handover w ith the landlord’ s representatives, Property Services to attend if high risk
SITE MOBILISATION GUIDE VERSION 2, 2018
114
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact: Balfour Beatty Site Mobilisation Hub
» Confirm hand back timescales » Confirm any alteration or damages to disclose to landlord for surveyor to note and record
mobilisationhub@balfourbeatty.com
0844 8800 090
Checklist to remember: Balfour Beatty specialist contact: » Forw ard any correspondence from landlord regarding dilapidations to Property Services » Comply w ith dilapidation rules w hen carrying out damage repairs at the end of the
Property Team property.services@balfourbeatty.com
project. » Agree dilapidations before vacating the premises – otherw ise this can make you liable for the landlords loss of rent w hilst putting damages right
SITE MOBILISATION GUIDE VERSION 2, 2018
115
Electricity and gas temporary disconnections – how to get it right When de-mobilising your site, there are tw o options for electricity and gas: Contact Site Mobilisation Hub to inform them of disconnection / transfer date
1. 2.
Transfer of ow nership to, for example, the client Disconnection of the supply
Demobilisation has to be w ith the Site Mobilisation Hub. Decommissioning lead time for gas is 6-8 w eeks and for electricity is 4-6 w eeks. For transfer of ow nership it is 28 w orking days. Project Manager to agree final billing arrangements
Confirm decommissioning date
SITE MOBILISATION GUIDE VERSION 2, 2018
116
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact: Balfour Beatty Site Mobilisation Hub
» Your project code » Strategic Business Unit
mobilisationhub@balfourbeatty.com
» Full site address including post code, MPAN or MPRN
0844 8800 090
» Site contact details including name and telephone number Checklist to remember:
Balfour Beatty specialist contact:
» Avoid contacting any provider directly. This w ill create confusion and potential non-
Michael Walsh
compliance to legal requirements such as the Carbon Reduction Commitment (CRC)
07800 514309
and Energy Savings Opportunity Scheme (ESOS) legislation
Michael.Walsh2@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
117
Physical Security Services – how to get it right
Project Manager should inform Site Mobilisation Hub of the planned end date for w orks
When nearing Demobilisation, please contact the Site Mobilisation Hub, w ho w ill liaise w ith security services team to arrange off hire and facilitate possible collection dates for equipment
Inform security services of project end date ready for off hire / removal
Inform suppliers w ith end date maintaining security
Agree collection date
SITE MOBILISATION GUIDE VERSION 2, 2018
118
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
Before engaging with us, consider the following: » Please have available site details
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact: Balfour Beatty Site Mobilisation Hub
» Are the security items hired or ow ned?
mobilisationhub@balfourbeatty.com
Checklist to remember:
0844 8800 090
» Some of the Standardised Access Control equipment and CCTV can take up to 4 w eeks to arrange collection and off hire.
Balfour Beatty specialist contact: SecurityServices@balfourbeatty.com
John Barrie (Security Operations Manager) 07967 689451
SITE MOBILISATION GUIDE VERSION 2, 2018
119
Furniture and asset exchange - how to get it right Waste Reduction Prevention
As your project approaches completion, there are several steps that you can take to reduce the amount of w aste sent to landfill.
1. Furniture and Asset Exchange Reuse
As you plan to demobilise your site, please post any furniture or assets that can be reused on the Furniture and Asset Exchange. You must be signed up to be able to use the Furniture and Asset Exchange. The Furniture and Asset Exchange allow s you in include availability dates for your excess materials to allow the site receiving the assets to plan appropriately.
Recycle
Please note that the Furniture and Asset Exchange includes all assets –including office equipment, building materials and TV’ s. You should allow six w eeks to find a match for your left over materials.
Energy Recovery
Disposal
SITE MOBILISATION GUIDE VERSION 2, 2018
Please Note: As you plan to demobilise your site, you must create an inventory of assets you have and include as much detail as possible. This can include pictures, condition of the asset and any measurements you have.
Search Project Portal on our 360 site.
120
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
2. Supplier take back and collection services
First point of contact:
Check w ith your suppliers to see if they have a take back and collection service that applies to left over materials and packaging. If they do, engage w ith them early to allow time to arrange for collection of materials and packaging in the final w eeks of the project.
Balfour Beatty Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
3. Recycling If reuse of a project or material is not possible, be sure to segregate w aste as much as is feasible. This w ill help you maximise off -site recycling and avoid landfill taxes.
If you have any questions regarding w aste management, please contact your local environment or sustainability manager or Reconomy. Details for Reconomy can be found on page 59. 4. Disposal The final option is for w aste is to dispose of it via skips. Shipping to landfill should alw ays be avoided but you also need to make sure that you leave your site in an acceptable condition. How the client receives the site w ill be a major factor in their overall satisfaction and is important for securing future w orks.
Please Remember: The Furniture and Asset Exchange is a core aspect that can provide Balfour Beatty w ith the opportunity to determine market rate cost savings w hen assets have been sourced from and are utilised on other projects. To access the Furniture and Asset Exchange, please use the follow ing link: http://portal.balfourbeatty.net To access the Project Portal How To Guide: http://portal.balfourbeatty.net/help/Costs % 20-% 20Hub% 20User.pdf
SITE MOBILISATION GUIDE VERSION 2, 2018
121
IT removal service - how to get it right
Include a project disclosure date into the project delivery plan
Maintain communications betw een the Site Mobilisation Hub and Project Manager
The IT Site Set Up (SSU) project delivery team manage the controlled closure, shut dow n and removal of IT services from project sites, as part of Demobilisation.
The first point of contact is the Site Mobilisation team w ho w ill liaise w ith the SSU team to scope your requirements and assign a SSU Delivery Manager. For IT removal and Verizon cancellation, please allow a minimum four w eek notice period.
Project Manager should inform Site Mobilisation Hub of the date you w ill vacate the premises
Complete closure of project and services
SITE MOBILISATION GUIDE VERSION 2, 2018
122
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
Before engaging with us, consider the following:
-2
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact: Balfour Beatty Site Mobilisation Hub
» Produce a clear scope of w orks to discuss mobilisationhub@balfourbeatty.com Checklist to remember:
0844 8800 090
» Ensure that you have allow ed a sufficient lead time to conduct the removal of IT solution.
Balfour Beatty specialist contact:
» Include provision for demobilisation costs in the project budget » Clearly communicate requirements
IT site set-up team office 0191 228 2800 sitesetup@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
123
Fire Services – how to get it right
Project Manager should inform Site Mobilisation Hub of the date you w ill vacate the premises
When nearing Demobilisation, please contact the Site Mobilisation Hub, w ho w ill liaise w ith the Fire Services team to schedule a collection date.
Inform fire services of decommissioning date ready for collection at least 10 days before in advance
Check fire safety procedure to ensure correct fire safety levels are maintained follow ing collection
Agree collection date
SITE MOBILISATION GUIDE VERSION 2, 2018
124
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
Before engaging with us, consider the following: Âť Please check decommission date required and inform the Site Mobilisation Hub at least 10 days prior to collection being required. Checklist to remember:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact: Balfour Beatty Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090
Âť Please check the site fire risk assessment and procedures to ensure that there is appropriate fire cover on site once the fire equipment has been decommissioned.
Balfour Beatty specialist contact: Plant & Fleet Services 0870 8444 888 (option 3) fireservices@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
125
Non-operated plant collection- how to get it right
Project Manager should inform Site Mobilisation Hub of the date you w ill vacate the premises (minimum of 12 w eeks before contract end date)
To terminate the hire of an item and request for it to be collected, please contact the Site Mobilisation Hub. All plant w ill be collected w ithin 48 hours, if collection is required quicker than this then you need to negotiate this w ith the hire desk. Make sure you sign collection documents – this confirms the condition of the plant w hen collected.
The Site Mobilisation team w ill liaise w ith the Plant Hire Desk to arrange for the plant to be collected w ithin 48 hours
The supplier w ill communicate any damages w ithin 72 hours.
Site representative signs collection documents
SITE MOBILISATION GUIDE VERSION 2, 2018
126
1826
-18
-17
-16
-15
-14
-13
-12
-11
-10
-9
-8
-7
-6
-5
-4
-3
-2
Before engaging with us, consider the following:
-1
-12
-8
-6
-5
-4
-3
-2
-1
END
>6m ths
DEMOBILISATION PROJECT DELIVERY
SITE MOBILISATION
X
First point of contact:
Construction, Major Projects » Project and task codes (contract site reference number) » Fleet number and/or Purchase order number Checklist to remember:
csukplant@balfourbeatty.com 0870 8444 888
(select option 1, option 1, option 2) Gas & Water, Power T&D
» Refuelling – if the item needs to be returned w ith fuel in it, check if it is cheaper to
bbssplant@balfourbeatty.com
fill on site or at the suppliers
0870 8444 888
» Location – if the item has changed location, has the supplier been informed?
(select option 1, option 1, option 1)
» Accessories – make sure all are included w hen returning the item
Rail, Living Places, Joint Ventures mobilisationhub@balfourbeatty.com
» Damaged items – make sure that you take any photos of any damaged items
0844 8800 090
Balfour Beatty specialist contact: Site Mobilisation Hub mobilisationhub@balfourbeatty.com 0844 8800 090 SITE MOBILISATION GUIDE VERSION 2, 2018
127
Contacts at a glance Building Materials Jon.Dean@balfourbeatty.com Bulk Fuel Balfourbeatty@hallfuels.co.uk Cranes tow ercranes@balfourbeatty.com rob.jensen@bphequipment.co.uk
Modular Buildings Modular.Enquiries@balfourbeatty.com John.Moore3@balfourbeatty.com Non Operated Plant csukplant@balfourbeatty.com bbssplant@baflourbeatty.com
Fire Services FireServices@balfourbeatty.com
PPE and Site Equipment bbg.helpdesk@directcorporate.co.uk Wise.cs.tlc@lyreco.com Joseph.Griffiths@balfoubeatty.com
Fleet fleetservicedesk@balfourbeatty.com
Purchasing Cards Purchasing.Card@balfourbeatty.com
Fuel Cards fuelcard@bbfleetservices.com
Property Property.Services@balfourbeatty.com
Gas and Electricity Michael.Walsh@balfourbeatty.com
Signage/Noticeboards/ Office Supplies and Furniture Wise.cs.tlc@lyreco.com Joseph.Griffiths@balfourbeatty.com
Energy Management EMUmobilisation@balfourbeatty.com Generator csukplant@balfourbeatty.com bbssplant@balfourbeatty.com mobilisationhub@balfourbeatty.com HS&E Team HSE@balfourbeatty.com IT Site Set-Up and Removal Sitesetup@balfourbeatty.com Materials Resource Exchange Portal Philip.Dumelow @balfourbeatty.com mobilisationhub@balfourbeatty.com
SITE MOBILISATION GUIDE VERSION 2, 2018
Security Services SecurityServices@balfourbeatty.com Temporary Accommodation and Plant Csukplant@balfourbeatty.com Bbssplant@balfourbeatty.com mobilisationhub@balfourbeatty.com Temporary Electrics Paula.Callaw ay@w ysegroup.co.uk Matt.Cummings@w ingate.co.uk
Temporary Works Tom.New ton@balfourbeatty.com Ian.Donaldson@balfourbeatty.com Mark.Beeston@balfourbeatty.com Grant.Tolley@balfourbeatty.com Vehicle Operating Licences Fleetcompliance@bbfleetservices.com Waste Balfourbeatty@reconomy.com Water and Sew erage w w w .w ater.org.uk
Supply Agreements User Guide Click Here Or search “ Supply Agreements User Guide” on 360 Any feedback on this guide, should be sent to: MobilisationHub@balfourbeatty.com
Expert Capabilities Brochure: Click here Or search “ BB Expert Capabilities” on 360
128
Notes
SITE MOBILISATION GUIDE VERSION 2, 2018
129
Notes
SITE MOBILISATION GUIDE VERSION 2, 2018
130
Scan QR code to view an introduction to the Site Mobilisation Hub