DEFENCE Capability questions for the next government Hon Dr Wayne Mapp looks to the past in order to explore the maritime acquisition landscape of the future, focusing on the Offshore Patrol Vessel and Frigate replacement decisions facing the next government. The first two years of the Coalition government have been a pleasant surprise for those interested in defence matters. They have a coherent defence story, particularly well set out in the 2019 Capability Plan, which builds on the work of the previous National government. They have been able to make the big multibillion-dollar procurement decisions, something that eluded the previous government. The Coalition government has even managed to gain some degree of acceptance from the Green Party about the direction of defence policy.
Dr Wayne Mapp QSO was New Zealand’s Minister of Defence and Minister of Science and Innovation from 2008 to 2011 18
It is now time to look forward, particularly beyond 2020. No big defence decisions will be made in election year. They will all be carried forward to the next term of government, whoever that government might be. As I have said in a number of my previous articles, the next big decisions will be about naval capability. This might be thought to be mostly about the frigate replacement. In fact, it is broader than that. By 2030 many of the major platforms will need replacing. The multirole ship, the Canterbury will be over 20 years old. So will the two offshore patrol vessels, the Wellington and the Otago. These ships have had a hard life, and 20 years or so would seem to be a reasonable service life. The two ANZAC frigates, Te Mana and Te Kaha will be over 30 years old. The frigates should make it to 2035 due to their current midlife upgrade, but they also have the longest procurement timeline. So, between 2020 and 2023, it could be expected the government will need to make the key naval procurement decisions. The past provides a guide. In the early 2000s the Clark government wanted to reorient naval capability. Project Protector was the result. The capability planning process took nearly two years. The Maritime Patrol Review commenced in June 2000 and was released in February 2001, followed by the ship specific Maritime Forces Review released in January 2002.
In July 2002 the government sought expressions of interest from shipbuilders. It took nearly another two years to April 2004 to select Tenix as the supplier. The multi role ship was delivered in 2008, though it had immediate problems. As Minister, I spent much of 2009 sorting out these problems, which resulted in an $86 million settlement in early 2010 with BAE Systems who had acquired Tenix. All the Project Protector ships were finally properly in service in 2010. Thus, a process to deliver quite modest ships took a full 10 years from initial planning to actual delivery into service. There is no reason to think it will be much different this time, although there is probably a clearer understanding of what maritime capability is required than there was twenty years ago. It is almost certain the Navy will press the government for more capable ships than the current Project Protector fleet. The tight financial constraint of $500 million for the whole of the Project Protector fleet meant that corners were cut. The government was warned about this at the time. It meant New Zealand got a oneoff multi role ship without a well deck, even though there were well proven designs with such capabilities available at the time at not much more cost. Experience has shown that the offshore patrol vessels should be larger to be able to effectively cope with the southern ocean. Line of Defence