DEVELOPMENT MILESTONES The completed milestones and development schedule for The Coral resor t, Nor theast Brazil


Completed Milestones The main boulevard at Lago do Mar, May 2013

2008

Site

selection and ownership in 2008

Conceptual

master plan approved

The Coral has already achieved many key development milestones since its conception. Most importantly, the resort has been granted planning approval and ground works to build the road infrastructure onsite is progressing well.

Best Development in Brazil 2009

in 2009

Planning approval

BEST DEVELOPMENT BRAZIL The Coral Lake & Beach Resort by BRIC Group

regranted in September 2013

Best DeVelopMent BrAzil the coral lake & Beach resort by Bric Group

Best Development in Brazil 2010

The Coral won the 5-star award for Best Residential Development in Brazil by the America Property Awards 2014-2015. The resort also won highly commended awards for Mixed Use Development, Architecture Single Residence for its Rustic villa design and Property Single Unit for it Modern villa design.

Ground works

started in January 2014

2015

2

WINNER OF

WINNER OF

WINNER OF

WINNER OF

RESIDENTIAL DEVELOPMENT AWARD in BRAZIL

ARCHITECTURE SINGLE RESIDENCE AWARD for the RUSTIC VILLA

PROPERTY SINGLE UNIT AWARD for the MODERN VILLA

MIXED USE DEVELOPMENT AWARD in BRAZIL

Sand dunes before Sunrise Beach, July 2014


As the development progresses through its development plan and

Price Increases

accomplishes key development milestones, plots at The Coral will be subject to price rises as the value of land increases.

Panoramic view of the road layout at Sunrise Beach, August 2014

The planned price increases for 450sqm plots is as follows: APRIL 2014

OCTOBER 2014

JANUARY 2015

Price rise to: US$34,100

Price rise to: US$36,175

Price rise to: US$37,260

Prices increased when infrastructure and utility

A price increase coincides with the licence approval

A price increase is expected to coincide with

building works were well underway.

and commencement of the show home build.

completion of the infrastructure and utility ground works.

3


Water drainage pipes between quadras 7 and 5, September 2014

Development Schedule

INFRASTRUCTURE & UTILITY WORKS

SHOW HOME CONSTRUCTION

Estimated completion February 2015

Estimated completion April 2015

The infrastructure work plan includes ground

• Site of the show home to be on Plot 22 in quadra 5

works, roads, electricity and other utilities, such as: • Topography • Services infrastructure • Landfill • Transportation equipment • Excavation, loading, transporting and removal ground works to level the land

• Completion of the licence application to build the show home in October 2014 • Construction expected to begin November 2014 • Estimate build time to completion is 6 months

• Spreading, wetting and compacting of red sand for road foundations

The main boulevard throughout the site looking towards the lagoon, July 2014

4

Ground works on the main boulevard at Lago Doce, April 2014

Works on the main boulevard at Lago Doce in the direction of the lagoon, April 2014


Ground works on quadra 31, April 2013

Development Schedule APARTMENT CONSTRUCTION

HOTEL AND ONSITE FACILITIES

Estimated launch date June 2015

Estimated launch date July 2015

• Architect designs begin in November 2014

• Construction of hotel, gymnasium, spa, retail and other onsite facilities

•D esign plans and blue prints pre-study to be completed by January 2015 • Licence application for apartment complex in quadra 3 with the beach club to be submitted February 2015 • Off-plan sales to start upon licence confirmation • Construction of first apartment complex scheduled to begin once 35% sold

• Architect designs begin in November 2014 • Design plans and blue prints to be completed by January 2015 • Licence application for the hotel in quadra’s 20 and 22 to be submitted February 2015 • Hotel suite sales to commence upon licence confirmation • Construction of hotel scheduled to begin once 35% sold LAGOON CLUBHOUSE Estimated construction mid-end 2015 The lagoon clubhouse will be one of the last onsite amenities to be completed.

5

Building works on the main boulevard at quadra 47, April 2013

Ground works on quadra 45, May 2013


Building of the main boulevard through quadra 45, April 2013


Global Perspective on Local Real Estate

www.bric-investment.com info@bric-investment.com UK Freephone: 0203

399 9439

USA Freephone: (+1)

321 247 6897

Rest of World: +34

952 810 711

USA

BRAZIL

SPAIN

HUNGARY

DUBAI

109 N Brush Street Suite 160 Tampa FL 33602

Av. Dom Luis, 1200 SLR 1304/1305 Torre 1 Business Ed. Patio Dom Luis Meireles Fortaleza, Ceara, Brazil +(55) 85 3013-1111

Centro de Negocios Puerto Banus, Oficina 39 29660 Nueva Andalucia Marbella, Spain

Mammut II - 3rd floor Lรถvรถhรกz utca 2-6. 1024 Budapest

Suite 2210 Bayswater Tower Business Bay (Consulting office)

(+34) 952-810-711

(+36) 1 345-8211

(+971) 44 275-072

(+1) 813 315-3885

Disclaimer : The information contained herein is solely for informational purposes and does not constitute an offer by BRIC Group to sell, rent or lease real estate. All information provided is believed to be accurate and correct at the time of publishing and is given in good faith. BRIC Group disclaims any warranties or representation concerning the accuracy, correctness or reliability of the information contained within this document and instructs you to independently verify the accuracy of the information provided. All intellectual property rights are retained by their owners. All content including text, images and logos are the proper ty of BRIC Group. It is not permitted without the express prior consent of BRIC Group to transfer, copy, distribute or compile in whole or par t any of the content contained herein.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.