SCOPE
Locations Yangon, My. Duration 1 Day Cargo Storage tanks x 2 Dimensions (m)
18 Tonne W2.5xH15
Equipment Used Mobile crane Tailing crane
100 Tonne 30 Tonne
CEA Project Logistics Myanmar was contracted for the transportation and installation of two 18 Tonne vertical storage tanks at a Yangon brewery. The project would prove complex due to two cranes being required to operate in a very narrow location outside the facility.
Services Used Project Engineer Project Manager Special Projects Team
PROJECT TEAMS PREPARE THE INSTALLATION SITE
CASE STUDY Brewery Tanks Installation
CS024 1/2
BREWERY TANKS INSTALLATION
BREWERY TANKS INSTALLATION
Before the arrival of the tanks, CEA teams prepared the installation area and affixed anchor bolts to each concrete tank base. After the first tank had arrived both the 100 Tonne mobile crane and 30 Tonne tailing crane positioned themselves either side of the trailer in the narrow alley. All required slings were attached to both ends of the tank and the cranes began the lift. In advance of this operation, CEA Engineering submitted highly detailed lift plans for approval by the client.
CONCRETE BASE LOCATION FOR THE TANKS
Due to working in such a confined space each tank had to be lifted above and clear of the adjacent buildings, the crane then turned and lowered each tank onto its concrete base allowing for final alignment and the anchor bolts to be fixed.
ON-SITE SAFETY TOOLBOX TALK
BREWERY TANKS INSTALLATION
TAILING CRANE BEGINS LIFT
FINAL ALIGNMENT
CEA PROJECT LOGISTICS G-18 PEARL CONDO KABAR AYE PAGODA ROAD BAHAN TOWNSHIP YANGON MYANMAR +959 421 031 286 100 TONNE MOBILE CRANE MOVES THE FIRST TANK INTO POSITION
www.ceaprojects.com
CASE STUDY Brewery Tanks Installation
CS024 2/2