![](https://assets.isu.pub/document-structure/230110180219-607f28800f933b20e4f3f7ccff31559f/v1/0ceb0a6090cde0cf0cdd4e271e19c725.jpeg?width=720&quality=85%2C50)
3 minute read
Requesting relief under construction contracts: best practices
Requesting relief under construction contracts:
BEST PRACTICES
Our firm was recently asked to provide thoughts on best practices in pursuing additional compensation and/ or adjustments to the schedule to complete work on construction contracts (“Relief”) .
Recognizing that the terms “changes” and “claims” are typically addressed in contracts, we are sharing some of the observations that we have heard clients voice over the years .
These observations relate to concerns that have impacted the process of issue resolution during project delivery and often obstructed relationships between key stakeholders .
The following are the concerns and our specific suggestions for the “top 10” best practices, recognizing that contracts and situations differ .
1 BASIS
Concern: “We don’t know the contractual basis…”
Best Practice: Establish the contractual basis and the specific provisions being relied upon in seeking relief .
2 NOTIFY
Concern: “We were not notified…”
Best Practice: Provide a contractual notice that is complete, timely and compliant with the specific requirements of the contract .
3 RESERVE
Concern: “If only we knew…”
Best Practice: Even if the matter may not lead to Relief, notify the other party, and retract in the future if Relief is not required .
4 UPDATES
Concern: “We could have taken measures…”
Best Practice: Provide regular updates and interim submissions during the progress of the work, including any mitigation actions put in place to enable the other party to make informed decisions .
5 MAINTAIN
Concern: “If only you would have kept sufficient information…”
Best Practice: Maintain and compile sufficient schedule and cost information that can support the pursuit of the request .
6 DETAILS
Concern: “We have not been provided with sufficient information…”
Best Practice: Provide sufficient details and substantiation, including any contractual substantiation requirements to enable the other party to understand and address the Relief being sought .
7 SUBSTANTIATE
Concern: “There are no supporting records…”
Best Practice: Ensure that the request is supported by relevant contemporaneous records that support the details provided .
8 CONSOLIDATION
Concern: “We are receiving the information at the end of the project…”
Best Practice: Avoid consolidating requests into one submission . Notify, update, and provide details on an individual, progressive, and timely basis .
9 CAUSATION
Concern: “We cannot link the cause to the effect…”
Best Practice: Link events or documents to effects and demonstrate a causal link in a manner that will assist in the review and resolution .
10 PRESENTATION
Concern: “We don’t fully understand what is being sought and why…”
Best Practice: Present the request for relief in a manner that is clear, concise, and supported by records/substantiation .
About the authors
Daniel Josiah, PGDip, PQS, MRICS, MCIArb, is Director, Contracts & Commercial with Lakeland Consulting Inc ., where he provides services to a wide range of clients in the private and public . Daniel has a particular expertise in issues around scope, schedule, and cost, and has prepared expert reports for the purposes of negotiation, alternative dispute resolution, and litigation . In 2020, Daniel was selected by On-Site Magazine and SitePartners in inaugural edition of the 40 under 40 in Canadian Construction .
Zain Ghaffur, LL .M ., BSc (Hons), MCIArb, is a Senior Contracts & Commercial Specialist with Lakeland Consulting Inc . Zain advises clients on all phases of projects, particularly in relation to matters of contractual claims and disputes . He is currently working on a large-scale infrastructure project supporting the review and resolution of complex contractual issues .
Note: The above is provided for informational purposes only and does not constitute legal or other advice or an opinion of any kind or a substitute for legal counsel. The reader of this paper is advised to seek specific legal advice regarding any specific legal issues or concerns.
Construction Claims & Dispute Resolution
![](https://assets.isu.pub/document-structure/230110180219-607f28800f933b20e4f3f7ccff31559f/v1/b0371ea6fe521fca7e4eb626ba1a6ff0.jpeg?width=720&quality=85%2C50)
CAUSE EFFECT ENTITLEMENT SUBSTANTIATION
SCHEDULE DELAY AND DISRUPTION
![](https://assets.isu.pub/document-structure/230110180219-607f28800f933b20e4f3f7ccff31559f/v1/8293bbd9031185b8f6cb0b12d666d80d.jpeg?width=720&quality=85%2C50)
LOSS OF PRODUCTIVITY / EARNED VALUE
CUMULATIVE IMPACT OF CHANGE
DAMAGES QUANTIFICATION
PROJECT ADVISORY
Combines the experience of both in-house and external counsel
![](https://assets.isu.pub/document-structure/230110180219-607f28800f933b20e4f3f7ccff31559f/v1/90ea1ae48606ed6e3bee921b7f0ebd20.jpeg?width=720&quality=85%2C50)
ADJUDICATION, LITIGATION, ARBITRATION COURSE OF PROJECT ADVICE – DISPUTE AVOIDANCE CONTRACT DRAFTING AND NEGOTIATION COLLABORATIVE CONTRACTING TRAINING
jmargie@margiestrub.com jstrub@margiestrub.com www.margiestrub.com 647-792-0010
MARTIN HOEY | Practice Lead, Construction Claims martin.hoey@envistaforensics.com