Cottage Grove Strategic Plan implementation 2016 17

Page 1

Implementation Schedule

2016 Lead Staff

16‐Q1

16‐Q2

2017 16‐Q3

16‐Q4

17‐Q1

17‐Q2

Positioning for Growth Hire ED Director Revised Position Description Solicited and Advertised Position Reviewed Applications

Completed Completed Completed

Interviewed 4 Candidates ‐ First Round

Completed

Final Interview with Council ‐ 2 Candidates Make Job Offer and Run Background Check

Completed Completed Completed 02/2016

Hire New ED Director Develop Business Retention & Christine Costello Expansion (BR&E) Plan Develop Successful Business Park Plan Jennifer Levitt Review Transitional Growth Area and determine new boundaries of the Jennifer, Burbank, McCool, Christine Business Park Mass site grade 60 acres for shovel Jennifer, Ryan ready pads Prepare an agreement with WAG Trust for the ongoing land deal (Dog Park & Jennifer, Kori Compost Site) Review EDA Bylaws and Policies ‐ Joint Christine, Kori, Robin Council/EDA Workshp Survey surrounding communites for Christine expedition process Review Business Subsidy Policy Robin Prepare a policy for SAC Credits Robin, Christine Develop a marketing strategy BRT Station Planning Review code related to building materials Space Needs Study for PW & Parks Budget for Space Needs Study Review Equipment, Storage, and Staffing needs at full build out Develop a Subcommittee with Public Works and Parks

Target Date of Completion: August 2016

Jennifer Levitt

Aug. 2016 Target Date of Completion: July 2017 Review as part of Comprehensive Plan Summer 2016 July 2016 May 2016 Apr.‐May 2016 May 2016 May 2016 Completed by October 2016

Christine, Sharon Jennifer, Burbank

Summer 2016

McCool, Burbank

Summer 2016

Les Burshten Les/Zac

Target Date of Completion: January 2017 ‐ Ongoing May 2016

Adam

Aug. 2016

Les/Zac

Oct. 2016

Page 1

2018

2019


Implementation Schedule

2016 Lead Staff

Prepare an RFP for a Space Needs Study Receive Proposals for a Space Needs Study Public Services Commission Review and Adopt Space Needs Study Identify land for expansion Conference with Developers, Real Estate Brokers, and Land Owners Select Topics for Real Estate Brokers Forum Select Speakers for Real Estate Brokers Forum Conduct a Real Estate Brokers Forum Developer Forum/Event (River Boat/Golf/Other) Landowners Forum (Education/Outreach) Finalize RRCC BRT Stations Gateway North/Jamaica Business Feedback ‐ Survey Host Business Park Meeting to Gain Feedback Comp Plan Steering Committee Chamber Lunch Event ‐ Educate and Gain Feedback Red Rock Commission Final Acceptance of Station Locations

16‐Q1

16‐Q2

2017 16‐Q3

16‐Q4

Ryan/Adam

Oct. 2016

Les

Dec. 2016

17‐Q1

Les

Feb. 2017

Jennifer Levitt

Mar. 2017 Target Date of Completion: January 2017

Christine Costello Christine

April 2016

Christine

May 2016

Christine

Nov. 2016

Christine

Aug./Sept. 2016

Jennifer, McCool, Burbank

Oct. 2016 Target Date of Completion: July 2017

Jennifer Levitt April 2016 May 2016

April‐July 2017 May 2016 Oct. 2016 Reforming Organizational Culture

Training and Travel Committee Solicit Interest Begin Meeting Review and Make Recommendations Prepare Costs for Budget Consideration Implement Changes Evaluate Benefits Review Parental Paid Leave Policy Review HAS Funding Levels and When

Joe Fischbach Joe Fischbach Joe Fischbach

Committee Committee Committee

Target Date of Completion: September 2016 April 2016 April 2016 May 2016 June 2016 Jan. 2017 Target Date of Completion: September 2016

Joe Fischbach Joe Fischbach

May 2016

Joe Fischbach

May 2016

Page 2

17‐Q2

2018

2019


Implementation Schedule

2016 Lead Staff

Make Changes if feasible Implement Changes Health and Wellness Committee First Meeting of Committee Set Goals and Objectives of Wellness Committee Set Priorities for 2016 Future Meeting Dates/Frequency Budget ‐ Calendar of Events Evaluate Effectiveness of Program by Determined Benchmarks Emphasize Career Path Options

16‐Q1

16‐Q2

Joe, Charlene Joe, Charlene Joe Fischbach/Becky Ahlvin

2017 Budget for 3 Firefighters/Paramedics

17‐Q2

Feb. 2016 Wellness Committee

Feb. 2016

Wellness Committee Wellness Committee Wellness Committee

Feb. 2016 Feb. 2016 June 2016 Annually

Wellness Committee

Target Date of Completion: Janyary 2017 ‐ Ongoing

Joe Fischbach/Department Heads April 2016

July 2016 Nov. 2016 Target Date of Completion: End of 2017

Joe Fischbach Joe, Becky Joe, Becky Joe, Becky Joe, Becky

March 2016 April 2016 May 2016 July 2016

Joe, Becky

Jan. 2017 Target Date of Completion: November 2016

Chief Redenius/Director Woolery

Plan and Articulate Staffing Rationale

May 2016

Submit Budget Request Documents

June 2016

Council Workshops (Budget) Final Adoption of Budget Park Improvement Plan SWC Athletic Facility Needs Study Adopted by Council Develop Budget Implications Align Expectations with ISD 833 Amend CIP Implement Project According to CIP

17‐Q1

Jan. 2017 Target Date of Completion: Janyary 2017 ‐ Ongoing

Supervisor Training on Use of Forms

Budget Approval ‐ Start/End

16‐Q4

Sept. 2016

Update Performance Appraisal Forms to Include Training Goals/Plans and Mid‐ Year Check‐In

Deploy Updated Assessments Compensation Plan for 2018 Develop RFP Send Out RFPs Review RFPs Develop Budget for 2017

2017 16‐Q3

July 2016

Zac Dockter

Dec. 2016 Make Cottage Grove a Recreation Destination Target Date of Completion: Nobember 2016 Completed 02/2016 March 2016 April 2016 May 2016 Ongoing 2017

Page 3

2018

2019


Implementation Schedule

2016 Lead Staff

River Oaks Business Plan Council Adopt Business Plan for River Oaks Assessment of River Oaks River Oaks Active Management Partnership Staff Realignment Add Service Options Create Marketing Strategy Create Mississippi River Access

16‐Q1

16‐Q2

River Oaks Task Force (Councilmember Dennis and Mayor Bailey)

2017 16‐Q3

16‐Q4

17‐Q1

17‐Q2

2018

2019

Target Date of Completion: Summer 2016 Completed 02/2016 Summer 2016 Ongoing March 2016 Summer 2016 Summer 2016 Target Date of Competion: October 2016

River Oaks Task Force, Sharon Zac Dockter

River Oaks Scenic Overlook Park Design Hire Landscape Designer Solicit Community Input Design Master Plan Draft Draft Review Finalize Master Plan and Budget Add to CIP Incoporate with Pavement Management Plan Boat Launch on Mississippi River Contact Mississippi River Boat Launch Leaser and DNR about Reopening Access Contract Negotiations Sign Contract Hire Facilitator for Community Engagement

Zac Dockter Zac, Designer, Parks Commission, Engineer Zac, Designer Commission, Council Commission, Council Zac Dockter

Aug. 2016 Aug. 2016 Sept. 2016 Oct. 2016 May 2018

Zac Dockter

2019 April 2016

Zac Dockter Zac, Charlene, Attorney May 2016 Zac, Charlene, Attorney June 2016 Engaging the Community and Forming the Vision Target Date of Completion: June 2016

Sharon Madsen Completed 02/2016 Completed 03/2016

Draft RFP Issue RFP Proposals Due Possible Oral Interviews Contract Award

April 4, 2016 April 2016 May 2016 May‐June 2016

Community Visioning Process Begins Develop Communications Plan

June 2016

Target Date of Completion: September 2016

Sharon Madsen

Page 4


Implementation Schedule

2016 Lead Staff

Identify key stakeholders Identify potential questions;

16‐Q4

17‐Q1

17‐Q2

June 2016 Jan. 2017 Ongoing Sharon Madsen

Sharon Madsen

Target Date of Completion: September 2016 May‐June 2016 June‐Aug. 2016 Target Date of Completion: November 2016 ‐ Ongoing TBD

Create Based on Facilitator Feedback Develop Community Plan

2017 16‐Q3

April 2016

Based on Facilitator Implement Changes Gather Community Input

16‐Q2

March 2016 March/April 2016

Answer why and develop key messages Promote Engagement Strategies Implement Changes Promote results from Community Engagement Develop Engagement Strategies

16‐Q1

Target Date of Completion: May‐June 2016

Sharon Madsen

Based on results from community input

TBD

Implement Changes

TBD

Page 5