Lanotte Park Second Public Input Meeting June 21, 2022
• • • • • •
Park Location Park Inventory & Views Proposed Plan Proposed Amenities Estimated Cost Action Plan
2
• 4.06 acres acquired in 2006 & 2012.
Sunrise Park
• Neighborhood Park: Serves residents within a ¼ mile to ½ radius.
3
• Open space and wooded areas • Major drainage channel • Explorer gas line • A top Priority for the 2019 Parks & Open Space Master Plan • $1.385 million budgeted in Park Bonds for FY 2022/23
4
5
6
Playground area and Canopy with picnic tables
Existing parking 1/3-mile 8 ft wide paved trail
North 7
Shade canopy with four tables
Trail with bench seating
8
Small playground with swings 9
• • • • • • •
Demolition, hardscape, canopy $440,000 Park Amenities $260,000 Landscape $210,000 Lighting & Electrical $375,000 Engineering & Inspection $ 69,000 General Conditions $107,000 Total $1.46 million
• Budgeted
$1.385 million 10
– Public Input Meeting – Public Plan Review – Park Board Endorsement – Construction documents – Bids for construction – Construction complete
March 1, 2022 June 21, 2022 August 8, 2022 Summer, 2023 Winter 2023/24 Summer 2024 11
North 12