Project review—Remedial, facade and concrete repairs to Telstra Exchange—by Dapcor Built in the 1970s, the Ipswich Telstra Exchange was due for remedial, facade and concrete repairs. The aim of the project was to maintain the integrity of the building envelope without disrupting Telstra operations. Risk of falling material The building façades had become a potential hazard with the risk of materials falling to the pavement below. An assessment revealed the need for concrete repairs to window reveals, brick and blockwork repairs, sealant repair and tiling. Particular challenges of the project included working on a live Telstra Exchange Building and working over high-traffic public footpaths. Remedial repairs delivered on time, to budget Our solution required a mix of access equipment including scissor lifts, boom lifts and rope access works. The project was completed on time and to budget without disrupting Telstra operations. The result? The removed risk to the public. Win-win!

Project Details SECTOR—Remedial LOCATION—Ipswich, QLD CLIENT—BGIS/Telstra VALUE—$342,000 PROGRAM—7 Weeks

COMPLETION—June 2019

www.dapcor.com.au Email: sales@dapcor.com.au 15


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.