7 minute read
Irish Cement celebrates 85 years of making high-quality cement
Irish Cement is tremendously proud its unique heritage and the work done by previous generations. It also recognises the responsibility of this current generation to ramp up further the pace of change and address industry carbon emissions.
The world has transformed over the past 85 years. Think back to Ireland of the 1930s, when our grandparents tell tales of walking to school barefoot, ponies and traps, black bicycles, and very few cars on the roads. By and large, they recall simpler times when the pace of life seemed more relaxed. There were very few telephones, let alone smartphones. Instead, there were telegrams, letters, and messenger boys, no urgent emails demanding an immediate response. Farming was as vital in Ireland then as it is now, and the Electricity Supply Board had been established just a decade earlier. Rural electrification was transforming communities throughout Ireland, and today we all recognise the important role electricity plays in our daily lives. There is something else from that era, which is vital to our daily lives but is often overlooked.
Advertisement
Founding Of Irish Cement
On 23 May 1938, Sean Lemass, then Minister for Industry and Commerce, surrounded by other dignitaries, pushed an oversized red button and two cement factories, one on the banks of the Boyne in Drogheda, the other in Mungret outside Limerick, sprang into life. The location of the Cement Ltd (later to become Irish Cement) factories had been carefully chosen to be close to abundant supplies of limestone, ports for the importation of fuel, and centres of the population for the sale of its product. From that day on, cement used in concrete and mortar has been one of the key ingredients in the foundations of the Irish State. Irish Cement has been at the forefront of manufacturing high-quality cement since 1938, and cement continues to be a critical ingredient in our modern economy. During those eight and a half decades, Irish Cement has transformed its operations through upgrades and continuous investment in the most energy-efficient cement manufacturing technology.
Irish Cement Today
Today’s workforce in Irish Cement is tremendously proud of that unique heritage and the work done by previous generations. They also recognise the responsibility of this current generation to ramp up further the pace of change. That change is to address the carbon emissions from the cement industry and to further improve the resource efficiency of its operations. The cement sector has committed to being carbon neutral by 2050, and progress is well underway. Already, a typical bag of Irish Cement has a 20% lower carbon footprint compared to the 1990s. It is still the same great cement that delivers the same great performance, but you can have confidence knowing its production had less impact on our environment, both in terms of climate change and circular economy.
These reductions have been achieved through energy efficient investments, which need less energy to make each tonne of cement; the introduction of lower carbon CEM II cements, Ireland’s most popular cement; and the replacement of imported fossil fuels using locally sourced alternative fuels. Continuous investment in training and development of the workforce has underpinned these developments.
The Future Of Irish Cement
Maintaining quality and cement performance for customers remains the top priority as the company innovates and becomes more sustainable in the way it makes cement. In 15 years, when Irish Cement will celebrate 100 years in business, the way cement is manufactured will be radically different from today. To achieve those improvements, further investment will be made to reduce fossil fuel consumption and make operations more resource efficient. Irish Cement is committed to maintaining its leadership position as Ireland’s highquality cement maker through innovation, collaboration and a recognition of its unique heritage.
HENRY HATHAWAY outlines the principle behind a Deed of Novation and suggests that when it comes to projects where design obligations are being transferred to the contractor, the appropriate instrument must be implemented.
Ausual feature of construction projects is a scenario where the employing party will undertake designs and then generate the specifications for a project with the consultant team prior to engaging with contractors for tendering.
Generally, the consultant team will set out the performance specifications and take the design to a developed stage according to its agreement. Contractors will then tender on the designs and specifications that have been produced. Where the contractor is to take responsibility for further design or implementation, it then has a choice, it may employ its own design teams directly, or it may decide, usually through agreement with the employer, that it will retain the original design team given the fact that there is a familiarity with the scheme or that it is convenient to carry through with the designs that are in development.
Deed Of Novation
One particular way to facilitate this mechanism is to proceed with a ‘Deed of Novation’. Essentially, a novation is the transfer of all obligations under one agreement between two initial parties
(employer and consultant) to an incoming party (the contractor) and allows for the designs to continue. The incoming party takes the place of the original party, usually the employer, and so the process of design development continues, hopefully seamlessly.
A question then arises. If a contractor that had based its entire tender pricing on the designs and specifications by the consultant when it was retained during the time with the employer later finds out that the design was wrong or perhaps negligently performed, then what can the contractor do about this scenario?
To explain further, a contractor who costed its tender against drawings and specifications that were either not developed correctly or are unworkable might turn to the employer and set out that the contractor merely followed the designs and specifications at the time of tendering and relied upon the information that was provided at the time but later found to be wrong.
DESIGN & BUILD CONTRACTS
This is a scenario that was evident in the
Scottish case of ‘Blyth & Blyth Limited v Carillion Construction Limited’ in 2001. Carillion was the design and build contractor and agreed to enter into a novation agreement of the engineer’s appointment that was originally with the employer. Carillion subsequently found that the tender drawings were wrongly prepared for the employer prior to the novation. If Carillion were to return to the employer, the employer would certainly have stated that it no longer was a contracting party with the engineer and that redress should be direct from the consultant. Carillion then pursued Blyth & Blyth, the engineer and stated that the engineer had underestimated the scope and quantity of work and suffered loss, having caused Carillion to undervalue the works. Carillion relied on broad wording of the novation, but the court found that the wording was insufficient to give Carillion a right to pursue for losses pre-novation. It found that no greater loss had been suffered by Carillion than the employer, and given the fact that the employer had not, in fact, suffered any loss (it was released from the contract and arguably was in benefit because Carillion had under-priced the works), then no greater loss could be claimed by Carillion above what the employer had suffered. It is known as the no-loss principle.
If the above sounds difficult, it is because it was a difficult position. It emerged to be a “black hole” but essentially derives from loss.
In my previous articles and lectures, I will have spoken about a claim requiring a coincidence of breach and loss with the required factual and legal causation.
Organising The Transfer Of Obligations
Since this case, the remedy was in drafting and organising the transfer of obligations. There are, in essence, two types of novation generally accepted, ab-initio, where an imaginary scenario is provided that the incoming party was always the contracting party or a switch agreement. The above scenario in Blyth & Blyth is catered for through a “no loss clause” in drafting.
The key takeaway is to ensure that the appropriate instrument is implemented where obligations are, in effect, being transferred.
However, pragmatically, many other issues arise for all of the parties, be they consultants, employers or contractors and need to be considered.
In the first instance, where there is a transfer, and the contractor has relied upon the developed design to that point in order to provide a cost, it ought to be identifiable to what extent the design has been progressed to and whether the employer’s requirements can be adequately met.
Scope Of The Original Services
A further point arises as to payment and to consider what scope of the original services have been undertaken by the consultant, whether payments are up to date and what scope of services are required to be completed. A consultant can find itself in difficulty when an incoming contractor may seek to value engineer or make changes, and the consultant must be alive to this in terms of its own previous work and whether or not adequate sums have been allowed for to carry out any further designs.
At the outset of any such agreement, a developed set of schedules are required to be incorporated, which set out the performed scope and detailed costs as well as prospective work and fees along with the programme development. Any deviations or methods to be proposed by the contractor at this point should be contained within its proposals and the underlying construction contract.
Given the complexity of the case in Blyth & Blyth and the theories related to the underlying problems that can arise, it is best advised to stay clear of such arguments.
The case of Blyth & Blyth is examined and discussed in detail in training and development courses offered by Henry Hathaway Solicitors and pragmatic steps provided to assist in avoiding the circumstances that can arise.
Henry Hathaway is a solicitor who practices in both Ireland and England and Wales and specialises in construction law. He is a qualified civil engineer and spent 12 years working in the industry. He regularly advises on contract formation and provides practical advice when entering construction contracts and regularly provides training and seminar days to companies to assist knowledge and application in order to assist them in avoiding disputes in construction.
If you require further information in relation to contract formation or would like to discuss training and development in this area, contact henry.hathaway@hathawaysolicitors.ie
Our services
We offer years of experience shaping concrete and cutting holes and conduits in solid floors and walls
Diamond Core Drilling
Wire Sawing
Concrete Cutting Walls
Concrete Cutting Floors
Wall Chasing
Brokk Remote Demolition
About Us
Ralkore Ltd is a company specialist in core drilling and concrete cutting services
Based in Dublin, Ireland, we are able to provide nationwide services, including the North of Ireland, and also UK, 24 hours a day and 7 days per week.