On behalf of the developer, we provide you with the latest updates as of July 2018 from the Aura construction site.
taken place below: • Reduced level excavations / rock break out to Phase 1 + 2 complete • Phase 1 + 2 foundations complete, lift base and retaining walls ongoing • Phase 1 lift core complete, retaining wall works complete & lift shaft works ongoing • Phase 2 + 3 lift core base ongoing • Phase 1 steelwork installation complete to Level 6 • Phase 2 steelwork installation complete to Level 6 • Phase 1 metal decking and concrete upper floor works complete to Level 6 • Phase 2 metal decking works ongoing • Drainage installations to Phase 1 due to commenced • Tower crane 1 operational • Tower crane 2 to be erected in September 2018 The key dates for construction are: Phase 1 • Demolition
Complete
• Practical Completion
Q3 2019
Phase 2 + 3 • Demolition
Complete
• Practical Completion
Q1 2020
www.csiprop.com
Dear Investor,
Work is continuing well on the Aura site. Please see a summary of the works that have
Student Accommodation
Progress Update July 2018
www.csiprop.com
AURA
Student Accommodation
Progress Update April2018 2018 July
www.csiprop.com
AURA