Retos de la planificación de instalaciones de energías marinas en el Mediterráneo

Page 1

Jornada de Planificación Marítima Espacial en el sector de las Energías Renovables Marinas 16 de mayo de 2018

Retos en la planificación de instalaciones de energías marinas en el Mediterráneo Pedro Mayorga /Ana Mayorga Jornada de Planificación Marítima Espacial en el sector de las Energías Renovables Marinas 16 de mayo de 2018


EnerOcean Introduction 37.5

• •

100 metros

37

50 metros

36.5 20 metros

0 metros

36 -7.5

-7

-6.5

• –

• • • •

• Horizon 2020

-6

-5.5


EnerOcean Introduction

• •

• • • – – –


– – –


The Prize

– –



W2Power: Snapshot Today ▪

W2Power is a patented technology that uses proven platform technology and offshore wind turbines available today. This allows major de-risking of wind power in deep waters.

Can be built, installed, maintained and repaired world-wide, at any sea depth.

Platform is wind-vaning, eliminates turbine yaw, lower cost and increased uptime

Industry leading power per foundation and mooring/connection point: 12 MW - More efficient use of foundation, cabling, installation, operation & maintenance, decommissioning - Lower LCoE than any other known contenders (on specific sites) - Excellent multi-use capability for additional economic activities

A prototype will be demonstrated at sea in Canary Islands: Project DEMOWIND WIP10+


W2Power Key dimensions • Large but light-weight semi-submersible: up to 12 MW wind power on one foundation. • Uses commercial WT’s for optimised mass & torque distribution, e.g. 2 x SWT-6.0 • Extensive testing in MARINET • TRL 6 project on-going . Has completed TRL advancements using 8 test campaigns in 4 laboratories in 3 countries

• 1 : 6 Scale prototype to be sea tested at PLOCAN (Canary Islands)

Main Dimensions − Hub height: 90 m

− Distance between tower bases: 90m − Beam during construction: 72m − Power: up to 2 x6 MW (aprox 132 m rotor diameter) − Operational draft: 15 m − Displacement: 7500 m3, near 4000 tn of ballast


W2Power Economics and benefits ❖ The best 12MW platform solution is to use two 6MW turbines: Lower loads (static and dynamic) on the floater ▪ Benefits of platform self orientation ➢ Elimination of active yaw system in the turbines, responsible for long downtime periods and expensive single breakdowns.

➢ Self-orientation of the platform means less absolute misalignment (no yaw threshold). Platform allows for up- or downwind turbines. ➢ Allows closely spaced turbines on leaning towers (smaller platform) ▪ Benefits of leaning towers and twin wind turbines

➢ Allows for smaller floating platform (< rotor diameter) and vertical reach of nacelle from a barge (cheaper O&M) without crane vessels ➢ Smaller wind turbines for the same power • Lower cost per MW and today’s technology

• Lower height. Cheaper assembly and maintenance ▪ Benefits of a light but big semi-submersible platform, ➢ You can have smaller volume and draft in the columns for the same stability (reduces construction steel need)


Step by step development

Leader Spanish Partners

UK Partner



W2Power Prototype : WIP10+ Project Status â–Ş

The design phase is completed, prototype detailed structural design:


W2Power Prototype : WIP10+ Project Status The design phase is completed, Mooring design:

0 -2

heave plate front X (m)

â–Ş

-4 -6 -8 -10 -12 -14

0

500

1000

1500 2000 Time (s)

2500

3000

3500


W2Power Prototype : WIP10+ Project Status â–Ş

The design phase is completed, electrical systems, wind turbines control:


W2Power Prototype : WIP10+ Project Status ▪

The design phase is completed, full size subsystems predesign…


W2Power Prototype : WIP10+ Project Status â–Ş

The design phase is completed, adaptation to prototype scale:


W2Power Prototype : WIP10+ Project Status ▪

Installation requirements at PLOCAN: PREVIOUSLY • • • •

• • • •

DEFINITION OF SPECIFIC PROTOTYPE PLACEMENT, SITE RESERVATION AT TEST BENCH PROCEDURES TO INSTALL AND UNINSTALL MAINTENANCE PLAN (INCLUDING PREVENTIVE M. PLAN), ACCESS PROCEDURES PERMITS: • GRID CONNECTION (STATE AND REGIONAL • ENVIRONMENTAL (EIA if needed, including Environmental Monitoring Plan) • “MARITIME-TERRESTRIAL PUBLIC DOMAIN” OCCUPATION PERMIT COMMUNICATIONS INFRASTRUCTURE WITH BASE INFRASTRUCTURE BEACONING/ MARKING PLAN TOWING PLAN INSURANCE (covering damage to others, contamination, recovery, …)

• ECONOMIC SOLVANCY FOR THE PERIOD

AFTER INSTALLING • COMMUNICATION TO MARITIME AUTHORITIES ( Navigation Charts and Marine Notice) • COMMUNICATION OF “MARITIME-TERRESTRIAL PUBLIC DOMAIN” OCCUPATION DURING TEST/DEMO ENVIRONMENTAL MONITORING PLAN EXECUTION MAINTENANCE PLAN EXECUTION


W2POWER MULTIUSE PLATFORMS EnerOcean was a member of the FP7 Project TROPOS (2012-2015), led by PLOCAN, Ocean of Tomorrow call, previous to current BLUE GROWTH. TROPOS focused in the development of multiuse solutions that: Suitable for : • Mediterranean Sea • Subtropical Seas • Tropical Seas

Integrate aspects related to: • Transport • Energy • Aquaculture • Leisure

Have modular design: • Central unit with internal and external modules • Multiple satellites to provide energy and to produce offshore aquaculture products


W2POWER MULTIUSE PLATFORMS 3 Conceptual designs and four implentations were considered: Leisure Island Modules: • Visitors Center • Food & Beverage • Accommodation • Nautical Activities & Marina • Safety & Environmental Monitoring • Photovoltaic Plant (large external) • Energy Storage

Green & Blue ‘Crete’ Modules: • Fish Aquaculture • Algae Aquaculture • Processing Plant • Substation • Quick Reaction Maintenance Base (small external) Satellite Units: • Wind + PV + fish cage + algae floater

Green & Blue ‘Taiwan’ Modules: • Fish Aquaculture • Algae Aquaculture • Processing Plant • OTEC plant (small external) Satellite Units: • Submersible fish cage + algae floater

Sustainable Production Concept Potential Modules (various designs): • Bunkering • LNG • Repair Terminal • Security, Surveillance and Anti-Piracy • Container Terminal


W2POWER MULTIUSE PLATFORMS Green and Blue from concept to engineering design:


W2POWER MULTIUSE PLATFORMS

SILO 2

BLOWER 2

BLOWER 1

- Aquaculture fishcage & PV cover (25000 m3 y 300 kW PV), option for algae. - Columns use for additional auxiliary equipment

SILO 1

FLUIDS AND FEED CONDUCTIONS Loads elevator

PUMP

SILO 1 4 m DIAM.x 4 m

5m

PERMANENT BALLAST

COLUMN C

SILO 2

FLUIDS AND FEED CONDUCTIONS

PUMP

VARI DOSER

PUMP

10m

CONTROL CABINET

30-60 Satellites x 8-12 MW wind

Stairs

AIR COOLER

Sea Water Control Ballast

PUMP

AIR COOLER 15m

VARI DOSER 30 kW Emergency Gen-Set

LOW VOLTAGE CABLING

COLUMN C LOW LEVEL (15.5 m over keel, 0.5 m over MWL) PUMPS, VARI-DOSER AND AIR COOLING LEVEL HEIGHT 4.0 m (Max height: 3.045 m) Total Weight: 4 x 500 kg (Pumps) + 950 kg (Genset) + 1500 kg (Varidoser + air cooling) = 4500 kg


W2POWER MULTIUSE PLATFORMS

SILO 2

BLOWER 2

SILO 1

Loads elevator

15m

FLUIDS AND FEED CONDUCTIONS

SILO 1 4 m DIAM.x 4 m

PERMANENT BALLAST

CONTROL CABINET

5m

SILO 2

AIR COOLER

Stairs

FLUIDS AND FEED CONDUCTIONS

AIR COOLER

VARI DOSER

PUMP

PUMP

10m PUMP

Sea Water Control Ballast

PUMP

▪ Funciones (control de modulos, trafo, silos alimentación, Depósito CO2 para algas, grupos electrógenos emergencias, …) ▪ Distribución de pesos (lastre) y volúmenes ▪ Conexión, accesos y autonomía

BLOWER 1

Integración de módulos en las columnas:

VARI DOSER 30 kW Emergency Gen-Set

LOW VOLTAGE CABLING

COLUMN C COLUMN C LOW LEVEL (15.5 m over keel, 0.5 m over MWL) PUMPS, VARI-DOSER AND AIR COOLING LEVEL HEIGHT 4.0 m (Max height: 3.045 m) Total Weight: 4 x 500 kg (Pumps) + 950 kg (Genset) + 1500 kg (Varidoser + air cooling) = 4500 kg


W2POWER MULTIUSE PLATFORMS Performance and interactions Validation : -

Test at UCC-BEAUFORT (HMRC) - National Ocean Wave Basin in Cork (Ireland) . April/june 2014


W2POWER BLUE&GREEN CONCEPT Studied initally as one of the case of energy and other uses in FP7 MARINA Platform project (power and fish aquaculture, Norway case) Deeply studied in FP7 TROPOS project for the Mediterranean Sea (near Crete, power, fish and algae production). Synergies with Wind and PV exploitation

Tank testing of platform and fish cage combination at 1:100 scale. Currently at TRL 4 Very good economics and use of the free space and volume available. Up to 120m – 130 m long and 30-35 m deep cages. Up to 40000 m3. 5000 – 7000 Tn/year of fish Potential use of a base port , central semi (TROPOS) or factory ship (freezer trawler) as central processing unit with 20-50 platforms.

Benefits as an Multiuse platform • Significant revenues addition in the same sea space (2050%more), access to cleaner seas for fish farming, lower concentration of fish and their waste (lice and infections risks). • Better economic cycle of the joint investment (CAPEX/OPEX share timing). Sharing of OPEX costs

• Sharing of mooring (floating line and submerge lines ) and very stable access platform offshore. Big space between columns allow for fully assembled cage float in and out • Better access to power for ancilliary services (grid connected). No risk of fuel spilling. • High feedstock storage capacity into the columns. Reduced number of travels.


W2Power for multiuse ❖ Platform designed for Multi-Use from start ▪ Different Hybrid power production: ➢ Wind and wave energy production (grid connected or near offshore consumption

➢ Wind and PV (mainly for the shadow effect for aquaculture ▪ Different energy and aquaculture species and products combinations: ➢ Wind/wave/PV and/or Salmon, seabream/bass, amberjack, meagre, ¿tuna? ➢ Seeweed, microalgae

▪ Enabling additional research on multi-use energy applications, e.g. ➢ Integration with electrical sub-station ➢ On-board energy storage ( ICAES, flow batteries, …) ➢ Offshore desalination ➢ Environmental monitoring, surveillance. ➢ Vessel support ➢ …


ERM

MSP

BLUE GROWTH

• OFFSHORE WIND • TIDAL & WAVE

• Reserved Space: pilot proyect// farms • Grid • Procedures

• Employment • Climate change • Green House

From: “Maritime Spatial Planning (MSP) for Blue Growth”

Jornada de Planificación Marítima Espacial en el sector de las Energías Renovables Marinas. Murcia 16 Mayo 2018


Fuente: Future trends of main maritime sectors. Source: Piante C., Ody D., 2015. Blue Growth in the Mediterranean Sea: the Challenge of Good Environmental Status. MEDTRENDS Project. WWF-France. 192 pp.

Jornada de Planificación Marítima Espacial en el sector de las Energías Renovables Marinas. Murcia 16 Mayo 2018


Jornada de Planificación Marítima Espacial en el sector de las Energías Renovables Marinas. Murcia 16 Mayo 2018


From: “Maritime Spatial Planning (MSP) for Blue Growth” Jornada de Planificación Marítima Espacial en el sector de las Energías Renovables Marinas. Murcia 16 Mayo 2018


From: “Maritime Spatial Planning (MSP) for Blue Growth” Jornada de Planificación Marítima Espacial en el sector de las Energías Renovables Marinas. Murcia 16 Mayo 2018


Jornada de Planificación Marítima Espacial en el sector de las Energías Renovables Marinas 16 de mayo de 2018

Thank you for your attention, any question?

Pg. 31


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.