1 minute read
5: PRELIMINARY MASTER PLAN CONCEPT
CHAPTER 3 // PUBLIC ENGAGEMENT AND DRAFT PLAN
EXHIBIT: 5 PRELIMINARY MASTER PLAN CONCEPT
The preliminary site plan included the revitalization of existing shelter, picnic, and signage facilities, as well as the addition of two viewing decks, a lookout tower, natural play area, walking paths, bouldering areas, and a stage. The stage concept was ultimately rejected by the steering committee.

Stakeholder Meetings and Draft Plan

PUBLIC PRESENTATION AT THE DOWNTOWN BOONE ANNUAL MERCHANTS MEETING (AUGUST 21, 2018)
In August of 2018, the consultant team presented the final park master plan at a public meeting that also focused on a meeting of downtown Boone merchants. More than 50 local business owners were in attendance and the group generally supported the plan. A full list of public comments from this meeting can be found in Appendix B.
Planning consultant Cody Mitchell discusses key plan features with a local business owner.