EXHIBIT 03: CELEBRATING SUCCESS IN LAKE LURE

New boat slips and the accompanying boardwalk at the Lake Lure Marina have provided for a new functional connection between the marina and beach area. The cost of this infrastructure improvement was approximately $1 million, which has been offset by new revenues from rental boat slips and a $100,000 contribution from the RCTDA.

LAKE LURE STRATEGIC ACTION QUICK FACTS

LL1. MORSE PARK PARKING EXPANSION & VISITOR CENTER

BudgetEstimate: $3 - $4 million CurrentStatus: Financial Analysis

Secured Funding (including projections through 2025):

Rutherford County Tourism Development Authority: $300,000 Lake Lure: $300,000

Key Grant/ Financial Opportunities:

Parks and Recreation Trust Fund (provided recreation amenities are added to the project scope) Private Restaurant Operator & Partner

Strategic Action Steps and Target Completion Dates:

1. Visitor Center Financial Analysis (Council Review): Summer 2022 2. Visitor Center Floor and Elevation Plan: Fall 2022 3. Pitch Deck to Solicit Private Partner: Spring 2023 4. Preliminary Engineering for Parking and Visitor Center: 2023-2024