Student Internship Report Student Name: Diana Enab Student ID: 1057895 Internship Company Name: AEC Internship Semester: Summer 2021-2022 Internship Total Hours: 240 hrs (6 weeks) Faculty Supervisor: Mohamed Elkaftangui
Content 1- Introduction 2- Internship Sheets 3- Internship Tasks 4- Conclusion
Introduction
About Company
01
I. Company Birth
III. Company Supervision
AEC is one of The Leading Architectural and Engineering Consultancy Offices in UAE and has been in the Local Market since 1982.
Eng. Maher Lamie Founder of the company.
II. Vision A.E.C.’s philosophy of providing innovative architectural solutions with consistently high levels of service and competence results in the clear communication of alternatives and recommendations so that sound decisions are made with confidence to the best interest of the client. - AEC maintains and commits to an integrated management system to facilitate the reduction of the impact/risk and hazards associated with its operations, activities, products, and services. We continuously strive to Identify materials, processes or products that may cause harm to humans and the environment.
Eng. Ahmed KamelDesign Operations Manager in AEC & my Internship Company Supervisor. IV. Branches and Projects scope Currently having 2 branches in Al Ain and Cairo besides the head office in Abu Dhabi. Projects completed by A.E.C. in the U.A.E., Egypt, France, UK, Oman, Qatar, Saudi Arabia, Seychelles, Tanzania, China, Pakistan and Libya reflect contemporary architectural theory and encompass modern conveniences while maintaining classic functionality.
01
About Company
About Company
01
V. Area of Expertise:
III. Area of Expertise Architecture Design
Landscape architecture
Structural Engineering
Master planning
Interior Design
Feasibility studies
Urban Planning
Value engineering
Quantity Surveying
Tendering & Construction
Project Supervision
Project management
Road related engineering
Civil work & transportation
02
Company Projects
Company Projects
02
1. Company Project Categories
I. Categories
Commercial
Recreation
Cultural
Religious
Educational
Office Buildings
Governmental
Multistory Bldg
Health
Local Consultant
Hotels
Interior Design
Industrial
Master Planning
Company Project
02
II. Company Project Examples
Internship sheets
Internship Tasks
Internship Timeline Week 1
Architectural Drawings: Project Title: [C46]: Residential & Commercial Building
Week 2 Week 3
Toilets & Bathroom Details: Project Title: [C44]: Residential & Commercial Building [C47]: Hotel Apartment Building
Week 4
Flats & Retails Area:
Week 5
Project Title: [C10]: Residential & Commercial Tower Fire & Life Safety Strategy Drawings: [C46]: Residential & Commercial Building [C1]: Coptic Church
Week 6 Architectural Modifications: Project Title: [C11]: Residential & Commercial Tower [C15]: Residential & Commercial Tower
01
Architectural Drawings: Project Title: [C46]: Residential & Commercial Building Understanding Architectural Drawings * Entrances * Circulation * Divisions * Levels * Annotation * Hatches * Openings
Assigning Print Layout Settings according to Company Code: * Paper Size * Scale and Units * Plot Style (Pen Assignments)
Assigning Proper Documents Settings for Submission: * Proper Drawings Titles * Revision name and code * Plot Number * Authorities logo & sign
List
Internal Finishes
Typical Plans
Roof Plan
Elevations
Sections
Stairs
Preparation of Compiled Architectural Drawings for Submission (to get approval from bank):
Site Plan
01
Architectural Drawings: Project Title: [C46]: Residential & Commercial Building
*Proper sheet Order & format *Proper scale, updates, etc.
02
Architectural Drawings: Project Title: [C46]: Residential & Commercial Building Checked Format of Project Submission to Tanasok, Abu Dhabi Municipality: *Project Description *Selected Criteria *Street view Perspectives (both daytime and night time), *Roof view Perspectives *Elevations *Site Location at Google maps *Photographs of current site *Environmental Studies *Sun & Shade Studies Checked Format of Feasibility Study Report submitted to ADCE (Abu Dhabi Commercial Engineering Services): *Conceptual Area Breakdown *Conceptual Cost Estimate *Projected Returns on Investments *Conceptual Design Drawings Checked Municipality regulations & building codes
03 04
Toilets & Bathroom Details: [C44]: Residential & Commercial Building & [C47]: Hotel Apartment Building Producing Toilets & Bathroom Detailed Drawings * Sections * Plans * List * Materials * Annotation * Hatches *Light *Furniture
Key plan to link toilets & bathrooms location & title
Material: Fixation, Dimensions, Thickness, Type
Application of Lights considers centering the light fixture at room area, surrounded by ceiling tiles at same dimensions, and filling the rest with gypsum board.
-Including details of drawing according to scale for all building floors (Ground, Mezzanine, Typical and Roof): Plans: Brickwork, Finishes, Floor Tiles, Wall Tiles, Hatches, Centering Furniture according to Dimensions, Door, Skirting, Covers, and Drainage. Section: Brickwork, Finished, Floor Tiles, Wall Tiles, Hatches, Centering Furniture according to Dimensions, Door, Skirting, Covers, False Ceiling and Lighting Fixtures
05
Flats & Retails Area: [C10]: Residential & Commercial Tower
* AREAS ARE BASED ON CARPET AREA ONLY.
Unit
Flats
Living Room / Foyer / Dining
Living Room Balcony
Corridor
Maid room
Corridor FR Lobby
Maid Toilet
Powder Room
Kitchen Balcony
Kitchen
M. Bedroom
M Bedroom Toilet
Master Bedroom Balcony M. Bedroom 2
M Bedroom Toilet Master Bedroom 2 M. Bedroom 3 2 Balcony
M Bedroom Toilet Master Bedroom Bed Room 3 3 Balcony
Bed Room Balcony
4 GR-BR 01
6.1 (shared with living room) GR-BR 01
4.1 FR-BR 02
6.2 FR-BR 03
3 FR-BR 01
6.1 FR-BR 03
7.2 FR-BR 03
Bed Room Balcony 2
Bed Room 2
Bathroom
Iron/Dryer
Jan.
Store
Laundry
Total; Area -
G01 Duplix
29.7
-
-
5.2
14.1
10.2
G02 Duplix
29.7
-
-
7.9
11.5
G03 Duplix
22.2
-
-
6.3
G04 Duplix
22.2
-
-
G05 Duplix
22.2
-
-
G06 Duplix
23.2
-
-
101 2 BR
6.7 (shared 19 with Bedroom2)
102 2 BR
20
103 2 BR
23.7
104 1 BR
22.4
105 1 BR
22.4
106 1 BR
26.6
107 1 BR
21.9
11.1 7.1 (shared with Master Bedroom) 7.1 (shared with Master Bedroom) 7.1 (shared with Master Bedroom) 8.8
2.8
2.6
11.1
- 18.6 GR-BR 01
-
-
2.4
6.1 (shared 14.6 with living room)
13
-
-
2.2
10.1
- 15.5 GR-BR 01
4.4 GR-BR
6.3
13
-
-
2.2
10.1
- 15.5 GR-BR 01
4.4 GR-BR
6.3
13
-
-
2.2
10.1
- 15.5 GR-BR 01
4.4 GR-BR
5.8
12.5
6.7
3.6
2.2
10.7
- 15.5 GR-BR 01
4.4 GR-BR
20 FR-BR 03
8.7 (shared with living room) GR-BR 01 8.7 (shared with living room) GR-BR 01 8.7 (shared with living room) GR-BR 01 8.7 (shared with living room) GR-BR 01
9.4
3.5
-
-
2.5
11
-
23.3
4.7
9.7
3.7
-
-
2.8
10.6
-
23.1
4.8
13.2
2.4
-
-
2.8
10.4
-
20.1
5.6
-
5.8
-
-
2.6
11
-
22.8
4.5
-
5.8
-
-
2.6
11
-
17.9 FR-BR 02
-
-
21 FR-BR 03 -
7.3 FR-BR 03 -
22.4 FR-BR 01 -
16.1 FR-BR 01
-
6.3
3.1
1.9
2.1
79.5
23.6 FR-BR 02
6.6 FR-BR 02
14.3 FR-BR 02
-
-
-
-
-
6.9
3.2
-
1.9
65.8
19.3 FR-BR 02
3.9 FR-BR 02
-
23.6 FR-BR 01
6.6 FR-BR 01
14.3 FR-BR 01
-
-
-
-
-
6.9
3.2
-
1.9
65.8
19.3 FR-BR 01
3.9 FR-BR 01
-
23.6 FR-BR 02
6.6 FR-BR 02
14.3 FR-BR 02
-
-
-
-
-
6.9
3.2
-
1.9
65.8
19 FR-BR 02
3.9 FR-BR 02
-
27.8 FR-BR 01
6.0 FR-BR 01
14.3 FR-BR 01
-
-
-
-
-
-
-
-
1.9
66.6
3.3
-
-
6.8
-
4
-
-
5.8
0.8
102.6
4
-
-
6.1
-
121.5
6.7 (shared with 19.3 living room)
-
-
-
-
-
-
-
6.2 (shared with Living Room)
-
-
-
-
-
-
-
-
-
0.8
69.9
22.8
6.2 (shared with Living 4.5 Room)
-
-
-
-
-
-
-
-
-
0.8
69.9
-
-
-
-
-
-
-
-
-
-
68
-
-
-
-
-
-
-
-
-
-
85.6
-
-
-
-
-
-
-
-
-
0.8
64.6
-
-
-
-
-
-
-
-
-
0.7
64.5
-
-
-
-
-
-
-
-
-
0.8
66.5
20
4.8
6.9
-
-
-
-
-
-
1.9
109
-
-
-
-
-
0.7
80.1
4.3
-
-
6.8
-
6.5
-
6.3
-
-
2.1
9.1
-
19.1
-
6.4
-
-
2.3
7.2
-
25.6
6.6
6.8 11.4 (shared with Living 6.2 Room) 9.6 (shared with Living 6 Room) 6.9 (shared with Living 6.1 Room)
6.7 (shared with 17.3 Master Bedroom) 15.6 -
-
6.7
-
-
2.4
8.5
-
19.5
7
-
-
2.3
7.9
-
19.6
110 1 BR
21.7
-
-
7
-
-
2.3
7.9
-
20.7
-
12.2
6.8
-
2.5
8.1
-
18.9
5
-
6.2
-
-
2.6
12.4
-
22.4
4.5
-
-
-
-
-
9.4
3.5
-
-
2.5
11
-
23.3
4.7
-
-
-
-
19.3
20
204 1 BR
21.7
205 1 BR
22.4
206 1 BR
26.6
207 1 BR
21.9
9.7 (shared with Kitchen) 11.1 7.2 (shared with Master Bedroom) 7.1 (shared with Master Bedroom) 7.1 (shared with Master Bedroom) 8.7
9.6
3.7
-
-
2.8
-
13.6
-
-
2.8
-
6.4
-
-
2.6
-
5.8
-
-
2.6
11
11
-
-
23
4.8
19.9
5.6
22.8
4.5
-
6.2 (shared with Living Room)
-
-
-
-
-
22.8
6.3 (shared with Living 4.5 Room)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
68
-
-
-
-
-
-
-
-
-
-
86
-
-
-
-
-
-
-
-
-
0.8
64.7
-
-
-
-
-
-
-
-
-
0.7
64.6
-
-
-
-
-
-
-
-
-
0.8
66.4
20
4.8
6.5
-
-
-
-
-
-
1.9
108.6
-
-
-
-
0.7
4.3
-
-
6.8
-
-
6.3
-
-
2.1
9.1
-
19.1
-
6.4
-
-
2.3
7.2
-
25.6
6.6
7.3 11.3 (shared with Living 6.2 Room) 9.5 (shared with Living 6 Room) 7.4 (shared with Living 6.1 Room)
-
-
6.7
-
-
2.4
8.5
-
19.5
-
7
-
-
2.3
7.9
-
19.6
210 1 BR
21.6
-
-
7
-
-
2.3
7.9
-
20.7
-
12.2
6.8
-
2.5
8.1
-
18.9
5
20
303 2 BR
23.7
304 1 BR
21.7
305 1 BR
22.4
306 1 BR
26.6
307 1 BR
21.9
10 (shared with Kitchen) 10.5 7.2 (shared with Master Bedroom) 7.2 (shared with Master Bedroom) 7.1 (shared with Master Bedroom) 8.7
6.5
6.2 (shared with Living 4.8 Room)
-
302 2 BR
5.7 (shared with Living Room)
0.8
102.5
6.1
-
119.2
-
-
-
-
0.8
69.8
-
-
-
-
0.8
69.9
-
-
2.6
12.4
-
22.4
4.5
-
-
-
-
-
-
-
2.5
11
-
23.3
4.7
-
-
-
-
19.3
9.6
3.7
-
-
2.8
23
4.8
-
-
-
-
13.6
-
-
2.8
19.9
5.6
-
-
-
-
6.4
-
-
2.6
22.8
4.5
6.2 (shared with Living Room)
-
-
-
-
-
22.8
6.3 (shared with Living 4.5 Room)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
68
-
-
-
-
-
-
-
-
-
-
85.5
-
-
-
-
-
-
-
-
-
0.8
64.7
-
-
-
-
-
-
-
-
-
0.7
64.5
-
-
-
-
-
-
-
-
-
0.8
66.5
20
4.8
6.9
-
-
-
-
-
-
1.9
109
-
-
-
-
-
0.7
80.2
4.3
-
-
6.8
-
-
5.8
-
-
2.6
11
11
-
-
6.7 (shared with Bedroom2 ) 6.6
-
6.3
-
-
2.1
9.1
-
19.1
6.2 (shared with Living 4.8 Room)
-
6.4
-
-
2.3
7.2
-
25.6
6.6
6.8 11.4 (shared with Living 6.2 Room) 9.6 (shared with Living 6 Room) 6.9 (shared with Living 6.1 Room)
-
-
6.7
-
-
2.4
8.5
-
19.5
-
-
7
-
-
2.3
7.9
-
19.6
310 1 BR
21.7
-
-
7
-
-
2.3
7.9
-
20.7
-
12.2
6.8
-
2.5
8.1
-
18.9
5
-
6.2
-
-
2.6
12.4
-
22.4
4.5
-
-
-
-
-
9.4
3.5
-
-
2.5
11
-
23.3
4.7
-
-
-
-
19.3
5.7 (shared with Living Room)
6.5 (shared with living room)
6.5 (shared with 17.3 Master Bedroom) 15.5 -
21
401 2 BR
5.9
-
6.2
20.6
312 1 BR
-
-
3.5
308 1 BR
13.4 (shared 21.9 with Master Bedroom) 22.6 8.8 6.7 (shared 19 with Bedroom2)
-
4
-
6.8 (shared 10.6 with Living Room) 10.4 -
-
4
9.4
309 1 BR
311 2 BR
103.8
-
20.6
301 2 BR
6.6 (shared with 17.3 Master Bedroom) 15.5 -
-
21.1
212 1 BR
6.7 (shared with Bedroom2 )
6.6 (shared with living room)
-
208 1 BR
13.4 (shared 21.9 with Master Bedroom) 22.6 8.8 6.7 (shared 19 with Bedroom2)
5.7 (shared with Living Room)
-
209 1 BR
211 2 BR
102.8
-
-
23.7
77.2
-
-
203 2 BR
1.5
-
-
202 2 BR
-
-
6.7 (shared with Bedroom2)
6.2 (shared with Living 4.8 Room)
6.8 (shared 10.6 with Living Room) 10.4 -
4 FR
-
3.9 FR-BR 04
21
201 2 BR
-
16.2 FR-BR 02
-
3.9 FR-BR 01
20.5
112 1 BR
4.2 FR
19.2 FR-BR 04
108 1 BR
13.3 (shared 21.9 with Master Bedroom) 22.6 8.7 6.7 (shared 19 with Bedroom2)
-
19.3 FR-BR 01
109 1 BR
111 2 BR
-
6.5 (shared with living room)
80.2 103.8
4
-
-
5.9
0.8
102.5
4
-
-
6.1
-
118.7
-
-
-
-
0.8
69.8
-
-
-
-
0.8
69.9
103.8
05
Flats & Retails Area: [C10]: Residential & Commercial Tower *Filling in Areas for Ground+ 13 Floors building, each with 12 apartments. Process: AutoCad for polyline creation of spaces, Excel for filling in Figures and comparing flat areas and room usage. Reviewing previous Excel Area Sheets from other projects to match the layout & work flow.
Notes on Excel Table: *Classifying flats through color in table. *Annotation with Rooms tag *Adding meaningful notes where needed for Area Estimation Table sheet. *Dividing Area according to rooms, to verify a meaningful division of usage.
Preparation of Document Submission for Civil Defense 3
2
5
4
6
7 8
NO RT H
9
24
.3
4m 15.2
1
8m
C4
6
OFFICE - 3 GFA = 81 M2
1200
N 2709867.8343 E 233604.1800
2500
3800
NO LPG
Fire Reserve Water Tank shall be calculated according to the building type and Civil Defense requirement and shall be submitted in shop drawing submittal.
5.
4.
8. 9.
SMOKE EXTRACTION SHAFT WITH 6 TO 10 AIR CHANGES PER HOUR
X E
C D
FD90
3.
N 2709882.3713 E 233623.7556
7.
IT
P+++
Fire Pump capacity shall be calculated according to the building type and civil defense requirement and shall be submitted in shop drawing submittal.
PLOT LIMIT
P++
-2
2500 1250
STAIRCASE-1
All items in these documents are guidance only: detailed of Fire Alarm, Fire Fighting and all ventilation system in all items shall be submitted in shop drawing submittal.
2.
6.
P+++
1200
1.
FD90
90
3280 5680
1250
1200
3080
+4.55
1765
B
STAIRCASE-2
1200 100 1200
FD
PLOT LIMIT
A
There are no installations for LPG central system in these building. All gas piping (LPG central system) shall be exposed on the outside elevations filling line and risers if the system is provided. Determine the total area of the opening between adjacent façade of two different buildings as percentage as per UAE fire and life safety code and international codes. All Stairways shall be provided with marking signs. All Smoke Management System and Elevators shall be interlocking with the alarm system. All horizontal and vertical opening on external façade, on internal, shafts or voids shall be fire rated according to the rating degree of the compartment within the building or on elevation.
00
ISSUED FOR APPROVAL
July 2021
10. All portable fire extinguishers shall be provided as per UAE fore and life safety code and NFPA 10 11. Emergency light and exit signs shall be provided according to UAE fire and life safety code and NFPA 101 12. All structure elements shall have the fire resistance rating according to NFPA 5000 and other international standards. 13. All stairways shall be provided with two ways fire telephone communication. 14. All portions of these buildings and common and services areas shall be fully cover by smoke detections and fully covered by voice announcement system according to NFPA 72.
FHC
P++
+4.37
15. All portions of these building shall be fully protected by automatic sprinklers system according to NFPA 13.
FH C
05
Fire & Life Safety Strategy Drawings: [C46]: Residential & Commercial Building
16. Standpipe system shall be provided in these building according to NFPA 14. 17. All Fire Door and Windows shall be according to NFPA 80.
NO LPG
NO LPG
18. All types of smoke management systems (include pressure difference between adjacent zones) shall be following NFPA 90A, NFPA 92A, NFPA 92B and other international codes and standards and shall be submitted in shop drawing submittal.
E
19. All interiors finishing material shall be provided as UAE fire and life safety code and NFPA 101. 20. Fire command center room shall be provided according to UAE fore and life safety code and NFPA requirement. 21. Carbon monoxide detector shall be provided to detect the CO concentration.
SMOKE EXTRACTION SHAFT WITH 6 TO 10 AIR CHANGES PER HOUR
22. Central battery system for emergency lighting systems and other system shall be provided. 23. Internal roads indicating how fire-men emergency tracks will maneuver on the site and occupants assemblies areas. 24. Total duration time of full evacuation of the building at discharging level, up to assemblies' areas assemblies' areas shall be sized according total number of occupants. 25. All curtain walls and cladding insulations, exterior wall cladding and roofing system shall be provide as UAE fire and life safety code annexure A.1.21 and international codes and standards, after tender is approved bring shop drawing and support information for civil defense approval.
F
26. Fire pump and fire water tank shall be listed and tested according to civil defense requirement and international standards.
PLOT LIMIT
PLOT LIMIT
N 2709855.5968 E 233613.2669
N 2709870.1338 E 233632.8425
28. Fire or smoke damper shall be provided in these building on all duct shaft according to UAE fire and life safety code and NFPA 90A, NFPA90B and shall be submitted in shop drawing submittal. 29. All penetrations through fire resistance rated walls shall be protected by approved fire stop system and materials, installed and tested in accordance with ASTM E 814 or UL 1479. 30. All means of egress components details and dimensions shall be provided and constructed according to UAE fire and life safety code and NFPA 101 and 5000.
MEZZANINE FLOOR PLAN
31. Consultant and contractor shall comply with UAE fire and life safety code chapter 12 in terms of requirements of building under construction.
SCALE 1:100
OFFICE - 2 GFA = 71.51 M2
27. All open space floors shall be used as a single tenant floor only, if it used as a multiple tenancy, then fire rated corridor not less than one hour shall be connected to the bath staircase.
32. Emergency action plan shall be implementing in these buildings according to UAE annexure B2 in the UAE Fire and Life Safety Code.
OFFICE - 1 GFA = 71.79 M2
33. Consultant and contractors shall comply with UAE fire and life safety annexure B.1 in terms of the requirement of balcony, terrace and windows. 34. Private Fire Hydrants shall provide around these building as per UAE Fire and Life Safety Code. 35. Consultant and contractors must comply with the general notes and applicable codes and standards even if the code requirement was missed during plan review.
TABLE : 1 OCCUPANCY LOAD AS PER UAE FIRE CODE 2018 ,TABLE No.3.14 PAGE No.311&312 NAME OF BUILDING
NAME OF FLOOR
AREA
OCCUPANT FACTOR
COMMERCIAL APARTMENT
MEZZANINE FLOOR
OFFICE-1
BUSINESS
71.79 m²
9.3m² / PERSON
8 PERSON
1 EXIT
COMMERCIAL APARTMENT
MEZZANINE FLOOR
OFFICE-2
BUSINESS
71.51 m²
9.3m² / PERSON
8 PERSON
1 EXIT
COMMERCIAL APARTMENT
MEZZANINE FLOOR
OFFICE-3
BUSINESS
81.00 m²
9.3m² / PERSON
9 PERSON
1 EXIT
TOTAL:- 25 PERSON
1 EXIT
TYPE OF OCCUPANCY
NAME OF ROOM
NUMBER OF PEOPLE NO. OF EXIT
FIRE FIGHTING LEGEND: SYMBOL
FHC
TABLE : 2A STAIRCASE SCHEDULE AS PER UAE LIFE SAFETY CODE 2018 PAGE No.311&312 NAME OF BUILDING
NAME OF FLOOR
NUMBER OF STAIR
WIDTH OF EACH STAIR IN (mm)
FACTOR OF STAIR IN (mm)
COMMERCIAL APARTMENT
MEZZANINE FLOOR
EXIT STAIR-1
1200mm
7.6mm
158 PERSONS
COMMERCIAL APARTMENT
MEZZANINE FLOOR
EXIT STAIR-2
1200mm
7.6mm
158 PERSONS
MEZZANINE FLOOR FIRE & LIFE SAFETY STRATEGY LAYOUT
F104
5 KG Co2 FIRE EXTINGUISHER
TOTAL PERSON FOR TOTAL NUMBER OF COMPLY PEOPLE IN THIS FLOOR EACH STAIR 25 PERSONS
DESCRIPTION FIRE HOSE REEL CABINET. 1 No. Ø25x30 MTR. LONG HOSE REEL. 1 No. Ø25mm GATE VALVE & PRV. 1 No. 4.5KG. DCP FIRE EXTINGUISHER 1 No. 5KG. CO2 FIRE EXTINGUISHER. 1 No. Ø65mm LANDING VALVE.
5 KG DRY POWDER FIRE EXTINGUISHER
YES
1:100
2.5 KG DRY POWDER FIRE EXTINGUISHER
TOTAL NUMBER OF PEOPLE WHO CAN USE THESE STAIR : 316 PERSONS
4 WAY BREECHING INLET FIRE BLANKET
TABLE :3 MEANS OF EGRESS AS PER UAE FIRE CODE 2018 TABLE No.3.16 CHAPTER 3 PAGE No.321 NAME OF BUILDING
NAME OF FLOOR
COMMERCIAL APARTMENT
MEZZANINE FLOOR MEZZANINE FLOOR
COMMERCIAL APARTMENT
MEZZANINE FLOOR
COMMERCIAL APARTMENT
NAME OF ROOM
TYPE OF OCCUPANCY
ALLOWED DEAD END
ALLOWED COMMON PATH
ALLOWED TRAVEL DISTANCE
APPLIED DEAD END
APPLIED COMMON PATH
OFFICE-1
BUSINESS
15.00m
30.00m
8.36 m
-
10.40m
14.80m
YES
OFFICE-2
BUSINESS
15.00m
30.00m
8.36 m
-
12.50m
15.65m
YES
OFFICE-3
BUSINESS
15.00m
30.00m
8.36 m
-
12.00m
19.25m
YES
2 HOUR (120min.) FIRE RATED WALL
APPLIED COMPLY TRAVEL DISTANCE
1 HOUR (60min.) FIRE RATED WALL EXIT STAIRWAY FD60 FD90
TABLE : 5 FIRE PROTECTION SYSTEM AS PER UAE FIRE CODE 2018 ,CHAPTER 9 NO. OF BUILDING 1
NAME OF BUILDING
TYPE OF OCCUPANCY
COMMERCIAL APARTMENT
RESIDENTIAL (GROUP A)
AREA OF BUILDING (SQ.M)
BASEMENT BASEMENT BASEMENT GROUND MEZZINE -3 -2 -1 FLOOR FLOOR 550.00m²
550.00m²
550.00m²
371.61m²
371.61 m²
60 mins FIRE RATED DOOR 90 mins FIRE RATED DOOR DEAD END TRAVEL DISTANCE
FIRST to 15th TYPICAL FLOOR
ROOF FLOOR
TOTAL
TYPE OF FIRE PROTECTION SYSTEM
436.17x15 = 6542.55 m²
177.23 m²
9113.00 m²
SPRINKLER SYSTEM + WET RISER SYSTEM + EXTINGUISHER
TYPE OF FIRE ALARM SYSTEM DETECTOR
COMMON PATH EGRESS PATH FIRE ESCAPE ROUTE
P P++
P+++
NOMINAL LEVEL (AT FLAT / OFFICES) PRESSURE LEVEL (AT CORRIDOR LOBBIES) PRESSURE LEVEL (AT MAIN STAIRCASE'S & FIRE LIFT SHAFT)
P17
05
45 8
MIT
P16
P15
P14
P12
P11
Fire & Life Safety Strategy Drawings: [C46]: Residential & Commercial Building N 2709884.4182 E 233624.4154
BUILDING ENTRANCE
+0.20
BASEMENT LIMIT
R.C.C WALLS PLOT LIMIT
2500
1200
PROTECTED WITH FOAM WATER SPRAY SYSTEM
1800
1200 100 1200
C D
3000
P++
1540
2500
1515
P+++
FD90
+0.35
FHC +0.35
FD90
+0.35
PROTECTED WITH CLEAN AGENT SYSTEM
PROTECTED WITH CLEAN AGENT SYSTEM
E
FIRE FIGHTING W. TANK (1st,2nd&3rd. BASEMENT) R.C.C. TANK V=170.5m3 CAPACITY - 37500 IG.
EP
PROTECTED WITH CLEAN AGENT SYSTEM
MOKE EXTRACTION AFT WITH 6 TO 10 AIR HANGES PER HOUR
+0.35
JP
PROTECTED WITH CLEAN AGENT SYSTEM
+0.35
FIRE FIGHTING PUMP SET 750 GPM
DP
+0.35
+0.35
F
968 69
SHOP GFA = 48 M2
IMIT
P1
P2
P3
P4
P5
PLOT LIMIT
4WAY EACH 2 NO OF BREECHING INLET BOX ONE FOR FIRE TANK FILLING ONE FOR SPRINKLER SYSTEM FEEDING
24380
P6
P7
GROUND FLOOR PLAN
SCALE 1:100
P8
-Preparing a proper Fire & Life Safety Strategy Drawing Layout: *Travel Distance, *Common Path Distance *Exit Separation Distance *2hr FireC47 Rated Wall vs 1hr Fire Rated Wall *60 mins fire rated door vs 90 mins fire rated door stais *Exit Stairway *Fire Blanket *Fire Hose Reel Cabinet *Dry Powder Fire Extinguisher *Co2 Extinguisher *Dead End *Fire Escape Route *Egress Path.
SMOKE EXTRACTION SHAFT WITH 6 TO 10 AIR CHANGES PER HOUR
FD90
2100
15240
1050
STAIRCASE-1 1200
1200
1400 6300
1200
3360
+0.35
5230
R.C.C WALLS
2520
P+++
B
N 2709882.3713 E 233623.7556
EXIT-2
STAIRCASE-2
A
343 00
68 2
P13
P9
N 2709870.1338 E 233632.8425
P10
BASEMENT LIMIT N 2709863.7105 E 233639.7918
Link of study to UAE Fire and Life Safety Code of Practic
SCALE
DATE
REVISION
REMARKS
Fire Pump capacity shall be calculated according to the building type and civil defense requirement and shall be submitted in shop drawing submittal. Fire Reserve Water Tank shall be calculated according to the building type and Civil Defense requirement and shall be submitted in shop drawing submittal.
LIST OF DRAWINGS
F000
N.T.S
4. 5.
28-04-2021
00
F001
FIRE CODE STUDY
N.T.S
28-04-2021
00
03
F002
PERSPECTIVE
N.T.S
28-04-2021
00
04
F003
SETTING LAYOUT PLAN
N.T.S
28-04-2021
00
05
F100
THIRD BASEMENT FLOOR PLAN
1:100
28-04-2021
00
All gas piping (LPG central system) shall be exposed on the outside elevations filling line and risers if the system is provided.
All Stairways shall be provided with marking signs.
8.
All Smoke Management System and Elevators shall be interlocking with the alarm system.
9.
02
There are no installations for LPG central system in these building.
Determine the total area of the opening between adjacent façade of two different buildings as percentage as per UAE fire and life safety code and international codes.
7.
All horizontal and vertical opening on external façade, on internal, shafts or voids shall be fire rated according to the rating degree of the compartment within the building or on elevation.
10. All portable fire extinguishers shall be provided as per UAE fore and life safety code and NFPA 10 11. Emergency light and exit signs shall be provided according to UAE fire and life safety code and NFPA 101 12. All structure elements shall have the fire resistance rating according to NFPA 5000 and other international standards. 13. All stairways shall be provided with two ways fire telephone communication. 14. All portions of these buildings and common and services areas shall be fully cover by smoke detections and fully covered by voice announcement system according to NFPA 72. 15. All portions of these building shall be fully protected by automatic sprinklers system according to NFPA 13. 16. Standpipe system shall be provided in these building according to NFPA 14. 17. All Fire Door and Windows shall be according to NFPA 80. 18. All types of smoke management systems (include pressure difference between adjacent zones) shall be following NFPA 90A, NFPA 92A, NFPA 92B and other international codes and standards and shall be submitted in shop drawing submittal. 19. All interiors finishing material shall be provided as UAE fire and life safety code and NFPA 101.
0.20
06
F101
07
F102
08
F103
09
F104
10
F105
SECOND BASEMENT FLOOR PLAN
1:100
28-04-2021
00
FIRST BASEMENT FLOOR PLAN
1:100
28-04-2021
00
GROUND FLOOR PLAN
1:100
28-04-2021
00
BUILDING ENTRANCE
20. Fire command center room shall be provided according to UAE fore and life safety code and NFPA requirement. 21. Carbon monoxide detector shall be provided to detect the CO concentration. 22. Central battery system for emergency lighting systems and other system shall be provided. 23. Internal roads indicating how fire-men emergency tracks will maneuver on the site and occupants assemblies areas. 24. Total duration time of full evacuation of the building at discharging level, up to assemblies' areas assemblies' areas shall be sized according total number of occupants. 25. All curtain walls and cladding insulations, exterior wall cladding and roofing system shall be provide as UAE fire and life safety code annexure A.1.21 and international codes and standards, after tender is approved bring shop drawing and support information for civil defense approval. 26. Fire pump and fire water tank shall be listed and tested according to civil defense requirement and international standards.
MEZZANINE FLOOR PLAN
1:100
28-04-2021
00
1st to 4th FLOOR PLAN
1:100
28-04-2021
00
11
F106
5th to 8th FLOOR PLAN
1:100
28-04-2021
00
12
F107
9th to 12th FLOOR PLAN
1:100
28-04-2021
00
13
F108
13th & 14th FLOOR PLAN
1:100
28-04-2021
00
14
F109
15th FLOOR PLAN
1:100
28-04-2021
00
15
F110
ROOF FLOOR PLAN
1:100
28-04-2021
00
16
F111
TOP ROOF PLAN
1:100
28-04-2021
00
27. All open space floors shall be used as a single tenant floor only, if it used as a multiple tenancy, then fire rated corridor not less than one hour shall be connected to the bath staircase. 28. Fire or smoke damper shall be provided in these building on all duct shaft according to UAE fire and life safety code and NFPA 90A, NFPA90B and shall be submitted in shop drawing submittal. 29. All penetrations through fire resistance rated walls shall be protected by approved fire stop system and materials, installed and tested in accordance with ASTM E 814 or UL 1479. 30. All means of egress components details and dimensions shall be provided and constructed according to UAE fire and life safety code and NFPA 101 and 5000. 31. Consultant and contractor shall comply with UAE fire and life safety code chapter 12 in terms of requirements of building under construction. 32. Emergency action plan shall be implementing in these buildings according to UAE annexure B2 in the UAE Fire and Life Safety Code. 33. Consultant and contractors shall comply with UAE fire and life safety annexure B.1 in terms of the requirement of balcony, terrace and windows. 34. Private Fire Hydrants shall provide around these building as per UAE Fire and Life Safety Code. 35. Consultant and contractors must comply with the general notes and applicable codes and standards even if the code requirement was missed during plan review.
EMEREGENCY COMMAND CENTER
CHAPTER 1, Clause 2.9.3 of the UAE Fire and Life Safety Code of Practice -2017 The emergency command centre shall be fire separated from the remainder of the building with construction achvieing a fire rating of no less than 1 hour and be proided with an automatic sprinkler system in accordance with NFPA13 The clear space to be provided shall be no less than 8.9 s.q.m in narea with internal dimention less than 2440mm The emergency command centre shall contain the following controls -
.C WALLS
17
A01-A200
ELEVATION - 1 (FRONT)
1:100
28-04-2021
00
18
A01-A201
ELEVATION - 2 (RIGHT)
1:100
28-04-2021
00
19
A01-A202
ELEVATION - 3 (REAR)
1:100
28-04-2021
00
20
A01-A203
ELEVATION - 4 (LEFT)
1:100
28-04-2021
00
SECTION A-A
1:125
28-04-2021
00
22
A01-A301
SECTION B-B
1:125
28-04-2021
00
A01-A302
SECTION C-C
1:125
28-04-2021
00
24
A01-A303
SECTION D-D
1:125
28-04-2021
00
1200 100 1200
25
STAIRCASE-2
23
2500
1:50
28-04-2021
00
A01-A401
SECTION 1-1 PART-1 ( STAIRCASE-1 )
1:50
28-04-2021
00
27
A01-A402
SECTION 1-1 PART-2 & HANDRAIL DETAIL ( STAIRCASE-1 )
1:50
28-04-2021
00
EXIT-2 STAIRCASE - 2 DETAILED PLAN
the fire pump is accessible directly from the outside and shall be protected with an automatic sprinkler system in accordance with NFPA 13-2011
N 2709884.4182 E 233624.4154
28
A01-A403
1:50
28-04-2021
00
29
A01-A404
SECTION 2-2 PART-1 ( STAIRCASE-2 )
1:50
28-04-2021
00
30
A01-A405
SECTION 2-2 PART-2 & HANDRAIL DETAIL ( STAIRCASE-2 )
1:50
28-04-2021
00
ETISALAT & DU ROOM ( TELEPHONE ROOMS )
As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017, the Etisalat and Du Room shall be provided with fire extinguisher system
HV & LV ROOM
ACCESS AND EGRESS VIA PLANTROOMS
Pursuate to Clause 40.2.5.2 of NFPA 101 - 2011, walkways that serve as a component in the means of egress shall be no less than 560mm in width and be provided with a minimum headrooms clearance of no less than 2030mm
EMERGENCY POWER SUPPLY SYSTEM
GENERATOR ROOM
BASEMENT LIMIT TABLE - 3 CONSTRUCTION RATING AS PER NFPA 5000 TABLE No. 7.2.1.1 & CONSTRUCTION ELEMENTS
FIRE RATING FOR TYPE II (222) CONSTRUCTION
FIRE RATING FOR FIRE RATING FOR TYPE II (111) TYPE II (000) CONSTRUCTION CONSTRUCTION
FIRE RATING FOR TYPE I (442) CONSTRUCTION
4 hours
0 hours
4 hours
0 hours
4 hours
0 hours
4 hours
2
INTERIOR BEARING WALLS
3
COLUMNS
proided with secondary power and include independent ductwork serving other parts of the building The following shall be provided within the emergency command centre -
(b) Emergency oice / alarm communication system unit (c) Fire detection and alarm system unit (d) Annuniciator isually indicating the location of elevator and their operation
4
The emergency command centre shall be provided with emergency lighting
TWO WAY EMERGENCY COMMUNICATION SYSTEM CHAPTER 7, Table 7.2 Page no:489 of the UAE Fire and Life Safety Code of Practice -2017 Two way, Clause emergency communication system shall be provided between the emergency command centre and the following areas-
(b) All fire fighting related mechanical equipment rooms inclusive of the sprikler pump room , switch rooms and generator rooms (c) All rooms housing smoke control equipment (d) All lift machine rooms (e) Fire lifts (g) Air handling control rooms
EMERGENCY VOICE EVACUATION AND COMMUNICATION SYSTEM One way emergency voice evacuation and communication system as well as emergency centre shall be provided for high rise building as per CHAPTER 7, Table 7.3 Page no:491 of the UAE Fire and Life Safety Code of Practice -2017
FIRE SERVICE OPERATION REQUIREMENTS CHAPTER 1, Clause 2.6 Page no:224 of the UAE Fire and Life Safety Code of Practice -2017 The maximum parking distance of a Civil Defense vehicle from not less than one building is less than 15mm The maximum road grade of the Civil Defense ehicle access shall no exceed 10% A suitable access pathway shall be provided to enablefire fighters to inspect all elevations of the building being paved or gravel type no less than 1 m in width As per Table 2.6 Clause 13 of Chapter 2. of the UAE Fire & Life Safety Code of Practice -2011 the largest floor area of the development is the ground floor with an area between 4,000ms.q.m and 8000m2 only 1/4 of the perimeter of the building is required to be provided with perimeter accesways The perimeter of the building has an approximate dimension of 368m and requires no less than 92m of an accessible perimeter The development is provided with a fire perimeter access way that exceeds 200m
Supporting more than one floor, columns or other bearing walls
2 hours
1 hours
Supporting one floor only
2 hours
Supporting a roof only
1 hours
0 hours
3 hours
1 hours
1 hours
0 hours
3 hours
Supporting more than one floor , columns or other bearing walls
2 hours
1 hours
0 hours
4 hours
Supporting one floor only
2 hours
1 hours
0 hours
3 hours
Supporting a roof only
1 hours
1 hours
0 hours
3 hours
Supporting more than one floor, columns or other bearing walls
2 hours
1 hours
0 hours
4 hours
Supporting one floor only
2 hours
1 hours
0 hours
2 hours
Supporting a roof only
1 hours
1 hours
0 hours
2 hours
FLOOR / CEILING ASSEMBLIES
2 hours
1 hours
0 hours
2 hours
6
ROOF / CEILING ASSEMBLIES
1 hours
1 hours
0 hours
2 hours
7
INTERIOR NONBEARING WALLS
0 hours
0 hours
0 hours
0 hours
0 hours
0 hours
0 hours
0 hours
PLOT LIMIT 8
EXTERIOR NONBEARING WALLS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
CODES/STANDARDS
UAE FIRE AND LIFE SAFETY CODE OF PRACTISE - 2017 NFPA 101 LIFE SAFETY CODE 2012 EDITION NFPA 10 STANDARD FOR PORTABLE EXTINGUISHERS,2013 EDITION NFPA 13 STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS,2013 EDITION NFPA 14 STANDARD FOR THE INSTALLATION OF STANDPIPE AND HOSE SYSTEMS , 2013 EDITION NFPA 15 STANDARD FOR WATER SPARY FIXED SYSTEMS FOR FIRE PROTECTION ,2012 NFPA 16 STANDARD FOR THE INSTALLATION OF FOAM -SPRINKLER AND FOAM -WATER SPARY SYSTEM ,2011 EDITION NFPA 20 STANDARD FOR THE INSTALLATION OF STATIONARY PUMPS FOR FIRE PROTECTION ,2013 EDITION NFPA 22 STANDARD FOR WATER TANKS FOR PRIVATE PROTECTION NFPA 72 NATIONAL FIRE ALARM AND SIGNALING CODE ,2013 EDITION NFPA 92 STANDARD FOR SMOKE CONTROL SYSYTEMS,2013 EDITION NFPA 110 STANDARD FOR EMERGENCY AND STANDBY POWER SYSTEM,2010 EDITION NFPA 2001 STANDARD ON CLEAN AGENT FIRE EXTINGUISHING SYSTEM,2012 EDITION NFPA 500 BUILDING CONSTRUCTION AND SAFETY CODE , 2012 EDITOR NFPA 664 STANDARD FOR THE PREVETION OF FIRES AND EXPLOSION IN WOOD PROCESSING AND WOOD WORK FACILITIES, 2012 EDITION NFPA 654 STANDARD FOR THE FIRE PREVENTION OF FIRE AND DUST EXPLOSION FROM COMBUSTIBLE PARTICULATE SOLIDS,2013 EDITION NFPA 24 - STANDARD FOR THE INSTALLATION OF PRIVATE FIRE SERVICESMAINS AND APPURTENANCE , 2011 EDITION NFPA 30 FLAMMABLE AND COMBUSTABLE LIQUIDS CODE , 2011 EDITION NFPA 33 - STANDARD FOR SPARY APPLICATION USING FLAMMABLE OR COMBUSABLE MATERIALS , 2011 EDITION NFPA 34- STANDARD FOR DIPPING , COATING AND PRINTING PROCESS USING FLAMMABLE OR COMBUSTIBLE LIQUIDS , 2011 EDITION NFPA 51B - STANDARD FOR FIRE PREVENTION DURING WELDING , CUTTING AND OTHER HOT WORK , 2011 EDITION NFPA68- STANDARD ON EXPLOTION PROTECTION BY DEFLAGRATIONENTING , 2013 EDITION NFPA 69- STANDARD ON EXPLOSION PREVENTION SYSTEM , 2008 EDTION NFPA 80 - STANDARD FOR FIRE DOORS AND OTHER OPENING PROTECTIVE , 2013 EDITION NFPA91 - STANDARD FOR EXAUST SYSTEM FOR AIR CONVEYING OF VAPOURS , GASES , MISTS AND NON COMBUSTIBLE PARTICULAR SOLID, 2013 EDITION NFPA 90A- STANDARDFOR THE INSTALLATION OF AIR- CORDITIONING AND VENTILATING SYSTEM , 2012 EDITION NFPA 204- STANDARD FOR SMOKE AND HEAT VENTING , 2012 EDITION NFPA 220 - STANDARD ON TYPE OF BUILDING CONSTRUCTION , 2012 EDITION NFPA 221- STANDARD FOR HIGH CHALLANGE FIRE WALLS , FIRE WALLS AND FIRE BARRIER WALLS NFPA 2113 -STANDARD FOR LIGHTING PROTECTION SYSTEM 2011 EDITION NFPA 2113 - STANDARD IN SECTION , CARE USE AND MAINTENANCE OF FLAME RESISTANT GARMENTS FOR PROTECTION OF INDUSTRIAL PERSONNEL AGAINST FLASH FIRE , 2012 EDITION
N 2709882.3713 E 233623.7556 25 26 27 28 29 30 31
ENCLOSED EQUIPMENT/AUH PLANT ROOM
As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017, the Enclosed Equipment /AUH Plant Room shall be provided with Automatic Sprinkler System
LIFT MACHINE ROOM As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017, the Lift Machine Room shall be provided with Pre-action Sprinkler System Automatic Sprinkler System
Table 3.2 Chapter 3 of the UAE Fire & Safety Code of Practise-2017 Doors providing access to and are in the path of travel to an exit from rooms that have an area not exceeding 6.5 m2 and are not required to be occupied by disabled persons shall be provided with a door leaf dimension of at least 610mm The clear and unobstructed width of doorways that provide access to the fire escape stairways shall not less than 915mm At least one leaf of a double leaf doorway set shall be no less than 810mm in clear width
EXTERNAL CLADDING
External cladding and roofing system shall comply with Chapter 1 ,Section 4, Cladding and facade system
FIRE CODE STUDY
The system shall be approved during the shop drawing submission stage
Shop Drawings to be submitted to Abu Dhabi Civil defense for approval shall be based on the following Codes/Standards ITEM
ELECTRICAL ROOM
As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017,the Electrical Room shall be provided with fire extinguisher System
DOOR WIDTHS
BEAMS, GIRDERS, TRUSSES & ARCHES
5
(h)Emergency and standby power status indicators (i)Fire pump status indicators
SERVER ROOM As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017, the Server Room shall be provided with Clean Agent System
EXTERIOR BEARING WALLS 0 hours
(a) Building plans indicating the typical floor plans and details the location of the building exit stairways,
As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017, the central battery room shall be provided with Clean Agent System with Automatic Sprinkler System
As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017,the IT Room shall be provided with Clean Agent System
WASTE/RECYCLE ROOM (GARBAGE ROOM )
CHAPTER 1 OF THE UAE FIRE AND LIFE SAFETY CODE OF PRACTICE - 2017,TABLE 1.6
1 hours
GENERAL
with Automatic Sprinkler System
IT ROOM ( SERVER ROOM )
Table 3.2 , chapter 3 , Page no 217 of the UAE FIRE & LIFE SAFETY CODE OF PRACTICE _2017 Thresholds at doorways shall not exceed 13mm and where a threshold is between 6.3mm and 13mmit shall be bevelled with a slope not sleeper than 1:2
1 hours
(k)Puplic address system
As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017, the closet having heaters or furnaces shall be provided with
THRESHOLDS
1 hours
(l)Control for smoke management system
ETS ROOM ( ELECTRIC THERMAL STORAGE )
CENTRAL BATTERY ROOM
1 hours
(j)Generator superision devices and manual star and transfer features
As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017,the Generator Room shall be provided with Foam Sprinkler System
ELEVATOR HOISTWAY PROTECTION
Sidewall spray sprinklers shall be installed at the bottom of each elevator hoist way , nor more than 6100mm above the floor of the pit as per clause 8.15.5.1 of NFPA 13 standard for the Installation of Sprinkler System
2 hours
fire fighting equipments and fire department access
TRANSFORMER ROOM As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017,the Transformer Room shall be provided with fire extinguisher system
Type 60, class 1, Leel 1 Standby power system in accordance witg Article 701 of NFPA 70, National Electric Code and NFPA 110, Standard for Emergency and Standby power system shall be provided in this building,(page 47 General Directorate of Civil Defense Safety and Prevention Department Plan Reiew Manual ) Further , the standby power shall have a capacity to provide power for the following essentials functions: (a) Life safety illumination (b) Fire detection and alarm system (c) Elevators (d) Fire Pumps (e) Puplic safety communications system (f) Industrial processes wher current interruption would production serious life safety or health hazards. (g) Essential ventilation and smoke removal system
CONSTRUCTION OF EXIT STAIRWAYS
Chapter 3 of the UAE FIRE & LIFE SAFETY CODE OF PRACTISE -2017 Exit stairways shall be no less than 2 hours fire rated and Constructed of Reinforced Concrete (RCC) AND PROVIDED WITH 90 minute self -closing fire rated door sets
F001
RISERS, SHAFTS & PASSAGEWAYS
Chapter 1, Table 1.9 ,Page no 113 of the UAE Fire & Life Safety Code of Practice - 2017 Vertical shafts -
2 hour with 90 minute access openings
Elevators Exit Access Corridors -
2 hour with 90 minute lift landing doors 1 hour with 1 hour self- closing fire rated door sets
Exit passageways -
2 hour with 90 minutes self - closing fire rated door sets
LIST OF DRAWINGS FIRE & LIFE SAFETY STRATEGY LAYOUT
1:100
TABLE-2 TYPE OF CONSTRUCTION AS PER NFPA 5000 TABLE NO:- 7.4.1,PAGE NO:-101UAE FIRE CODE 2018, CHAPTER 1, TABLE 1.7 SL. NO
NAME OF BUILDING
1
COMMERCIAL
TYPE OF OCCUPANCY
RESIDENTIAL
AREA OF BUILDING (PER STOREY)
TYPE OF CONSTRUCTION
436.00m²
TYPE I(332)
m²
APPLIED MAXIMUM ALLOWABLE ALLOWABLE HEIGHT (m) HEIGHT (m) UNLIMITED
67.70
MAXIMUM ALLOWABLE NO. OF STOREY UNLIMITED
APPLIED ALLOWABLE NO.OF STOREY
MAXIMUM ALLOWABLE AREA PER STOREY(sq.m)
APPLIED ALLOWABLE AREA PER STOREY(sq.m)
COMPLY
15
UNLIMITED
436.00m²
YES
F-000
SPRINKLER SYSTEM + WET RISER SYSTEM + EXTINGUISHER
DETECTOR
N-T.S
Fire Hose Reel Cabinet
Preparation for Drawings Submission
1515
P++
+0.35
FD90
SMOKE EXTRACTION SHAFT WITH 6 TO 10 AIR CHANGES PER HOUR
FD90
FHC +0.35
15240
FD90
ISSUED FOR APPROVAL
As per Table 9.3 Chapter 9 page no 826 of the UAE Fire & Life safety Code of Practise -2017, the HV & LV Room shall be provided with Clean Agenty System
The egress paths indicated are indicative only. The contractor shall ensure compliance with the prescriptiv requirements of this clausesuch that access from any part of the roof ( both internal and external ) is maintained at all times
2 hours
(f) Fire fighting stairways
26
Chapter 3 of the UAE FIRE & LIFE SAFETY CODE OF PRACTISE -2017 Doors in the means of egress shall be side hinged or pivoted swinging type and shall be capable of swinging to the full required width of the opening
Doors accommodating more than 50 persons , doors in exit enclosures and doors serving high hazard areas shall swing in the direction of egress The forces required to fully open any door manually in a means of egress shall not exceed 67N to release the latch, 133N to set the door to the minimum required width
CHAPTER 9.3, TABLE 9.18 PAGE NO:773 OF THE UAE FIRE AND LIFE SAFETY CODE OF PRACTICE -2017
Supporting a roof only
(a) Every fire fighting lift lobby including the ground floor
STAIRCASE - 1 DETAILED PLAN
SWING & FORSE
and pressure according to the hydraulic calculation to supply fire demand of the system
FIRE PUMP ROOM
Supporting one floor only
exit routes, protected corridors,fire protection systems,fire compartments,fire fighting equipments,
July 2021
Emergency Evacuation Diagrams and Actions plan shall be provided prior to occupation of the building in accordance with ANNEXURE_B2. EMERGENCY ACTION PLANS of the UAE Fire & Life Safety Code of Practise - 2017
5230
P+++
1800
ISSUED FOR APPROVAL
FIRE PUMP
(g) Sprinkler valve and waterflow detector display panels
A01-A300
in ASCE ( American society of civil engineers) and any other structure requirements for a top rail
Supporting more than one floor , columns or other bearing walls
(d) All terminals and superisory / control equipment of the building fireprotection /detection system
C46
Chapter 3 of the UAE FIRE & LIFE SAFETY CODE OF PRACTISE -2017
AS PER CHAPTER 9.3, TABLE 9.18 PAGE NO:773 OF THE UAE FIRE AND LIFE SAFETY CODE OF PRACTICE -2017 , The fire pump set shall consist of one main electrical driven pump , one standby diesel driven pump and electric jocky pump having minimum flow
1
8m
Enclosed stairways shall be rovided with markings that indicate the floor level, the terminus of the top and bottom of the stair enclosure, the identification of the stair enclosure and the floor level of , and the direction to , the exit discharge The signage shall be located inside the enclosure approximately 1525mm aove the floor landing in a position that is visible when the door is in the open or closed position and in lettering no less than 25mm high The stairway identification letters shall be located at the top of the sign in minimum 25mm high lettering
As per , CHAPTER 9, Table 9.3 Page no:637of the UAE Fire and Life Safety Code of Practice -2017 the fire water shall be stored in a water tank having two compartments or in two tanks with total effective fire water reserve to cater the pumping demand of the system which shall be no less than 60 minutes
S.No.
.3
STAIRWAY IDENTIFICATION
(c) Engineered smoke control system (e) Air conditioning and mechnical ventilation required for the emergency command centre shall be
24
and a safety factors of 4 shall be used Enclosed stairways shall be rovided with markings that indicate the floor level, the terminus of the top and bottom of the stair enclosure, the Each handrail or guard section shall be supported by a minimum of three glass balusters, or shall be otherwise supported to remain in place if one baluster panel fails, and either an attached handrail or guard shall be provided or the glass balusters shall laminated glass with two or more glass piles of equal thickness and the same glass type , and the panels shall be designed to withstand the loads specified
(b) Emergency voice communication
(f) Controls for unlocking electromagnetic or access control stairway doors
21
A01-A400
FIRE WATER TANK
BALUSTRADE PANELS Chapter 1 , Section 2.17, UAE FIRE & LIFE SAFETY CODE OF PRACTISE -2017 The panels and their support system shall be designed to withstand the loads specified in ASCE(American Society of civil Engineers)
A minimum of two breeching inlets per wet riser at remote locations shall be provided (a) Shall be visible from the fire engine access road (b) The distance of the breeching inlet to the fire engine access road shall not exceed 18m (c) The connectionsshall be located and arranged so that the hose lines can be readiily and conveniently attached to the the inlets without interferrence from any nearby object , including building , fences or posts (d) Each breeching inlet connection shall be prvided with signage in raised or engraved letters at least 25.4mm in height on a plate or fitting (e) The sign shall indicate the service for which the connection is intended (f) A sign at inlets shall be provided indicating the pressure required to deliver the greatest system demand a valve shall (g) Breeching inlet shall be adequately illuminated be installed in the hydrant connection
(a) Fire Lifts
(e) Status indicator and control of air handling system
28-04-2021
BREECHING INLET
As per CHAPTER 1, Table 2.2 Page no:256 of the UAE Fire and Life Safety Code of Practice -2017 benching inlet shall be a 4 way connection having 150mm diameter flanged outlet with 4 nos of 65mm diameter instantaneous male coupling inlets
00
DRAWING NAME
2. 3.
6.
01
P11
External fire hydrant locations are indicative only and shall be subjected to ADCD approval during the shop drawing submission
All items in these documents are guidance only: detailed of Fire Alarm, Fire Fighting and all ventilation system in all items shall be submitted in shop drawing submittal.
00
SERIAL
DRAWING NUMBER
P12 1.
15.24m
P14
P13
LIST OF FIRE & LIFE SAFETY STRATEGY DRAWINGS
C47
July 2021
Preparation of Document Submission for Civil Defense LAND KEY :
FIRST FLOOR PLAN
1.
All items in these documents are guidance only: detailed of Fire Alarm, Fire Fighting and all ventilation system in all items shall be submitted in shop drawing submittal.
2.
Fire Pump capacity shall be calculated according to the building type and civil defense requirement and shall be submitted in shop drawing submittal.
3.
Fire Reserve Water Tank shall be calculated according to the building type and Civil Defense requirement and shall be submitted in shop drawing submittal.
4. 5.
A
B
C
D
F
E
G
6.
H
7. 31000 100
6200
2600
4600
8.
4000
4600
2600
6200
100
9.
NO LPG SYSTEM IN THIS BUILDING
There are no installations for LPG central system in these building. All gas piping (LPG central system) shall be exposed on the outside elevations filling line and risers if the system is provided. Determine the total area of the opening between adjacent façade of two different buildings as percentage as per UAE fire and life safety code and international codes. All Stairways shall be provided with marking signs. All Smoke Management System and Elevators shall be interlocking with the alarm system. All horizontal and vertical opening on external façade, on internal, shafts or voids shall be fire rated according to the rating degree of the compartment within the building or on elevation.
10. All portable fire extinguishers shall be provided as per UAE fore and life safety code and NFPA 10 11. Emergency light and exit signs shall be provided according to UAE fire and life safety code and NFPA 101
GENERAL NOTES :
12. All structure elements shall have the fire resistance rating according to NFPA 5000 and other international standards. W05
13. All stairways shall be provided with two ways fire telephone communication.
W05
W02
W02
W02
W02
A
4200 W02
FD90
D01
S01
D01
F.H.C
CORRIDOR
D02
1800
STORE
1
STAN
5M 12.3 CE=
2180
OFFICE-1 W02
VE TRA
L DI
D01
D01 S01 FD90
ELEC.
D02
LIFT-1
FD90 S01
W02
D01
CORRIDOR
D01
W02
F.H.C
OFFICE-8 W02
20. Fire command center room shall be provided according to UAE fore and life safety code and NFPA requirement.
9 Ltr. WET CHEMICAL EXTINGUISHER
21. Carbon monoxide detector shall be provided to detect the CO concentration.
2.5 KG CO2 FIRE EXTINGUISHER
W. TOILET
W04
1
W04
W04
W04
CUBICLES PARTITION
M 4.38 0M TH= =10.8 N PA NCE MO DISTA COM VEL TRA
A800
W03
D01
D01
D03
STORE
TRA VE
L DI
STAN
W02
CE= 12.3 5M
OFFICE-9
W02
5. FOR SIZES OF COLUMNS AND SHEAR WALLS AND ANY OTHER STRUCTURAL ELEMENTS, REFER TO STRUCTURAL DRAWINGS. 6.THE CONTRACTOR SHALL BE RESPONSIBLE FOR PRODUCING A COMPLETE SET OF COORDINATED SHOP DRAWINGS FOR ALL ELEMENTS OF THE WORK FOR APPROVAL PRIOR TO COMMENCEMENT OF WORKS. APPROVAL OF SHOP DRAWINGS BY THE CONSULTANT DOES NOT RELIEVE THE CONTRACTOR OF HIS RESPONSIBILITY FOR COMPLYING WITH ALL REQUIREMENTS OF THE CONTRACT DOCUMENTS.
5KG CO2 EXTINGUISHER
7. DRAWINGS ARE IN PART DIAGRAMMATIC AND DO NOT NECESSARY SHOW COMPLETE DETAILS OF CONSTRUCTION, WORK, OR MATERIALS, PERFORMANCE OR INSTALLATION.
FIRE BLANKET
25. All curtain walls and cladding insulations, exterior wall cladding and roofing system shall be provide as UAE fire and life safety code annexure A.1.21 and international codes and standards, after tender is approved bring shop drawing and support information for civil defense approval.
8. CONTRACTOR SHALL STRICTLY ADHERE TO APPLICABLE CODES, RULES, AND REGULATIONS GOVERNING BUILDING CONSTRUCTION AS SET BY THE AUTHORITY HAVING JURISDICTIONS.
2 HOUR (120min.) FIRE RATED WALL
9. CONTRACTOR TO CHECK ALL DIMENSION AND LEVELS ON SITE AND DISCREPANCIES ARE TO BE REFERRED TO THE ARCHITECTS / ENGINEERS FOR DECISION.
1 HOUR (60min.) FIRE RATED WALL
27. All open space floors shall be used as a single tenant floor only, if it used as a multiple tenancy, then fire rated corridor not less than one hour shall be connected to the bath staircase.
OFFICE-10
W03
4. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH WITH RELEVANT (ARCHITECTURAL, STRUCTURAL, MEP, AND, SPECIFICATION THE CONTRACTOR SHALL COORDINATE THESE DRAWINGS AND NOTIFY ANY DISCREPANCY FOR CLARIFICATION BEFORE COMMENCEMENT OF WORKS.
2.5 KG DCP FIRE EXTINGUISHER
24. Total duration time of full evacuation of the building at discharging level, up to assemblies' areas assemblies' areas shall be sized according total number of occupants.
26. Fire pump and fire water tank shall be listed and tested according to civil defense requirement and international standards. M. TOILET
O.T.S
2
19. All interiors finishing material shall be provided as UAE fire and life safety code and NFPA 101.
22. Central battery system for emergency lighting systems and other system shall be provided.
OFFICE-11
CUBICLES PARTITION
COM MON OFFICE-13 PATH TRAV =4. EL DI 38M STAN CE= 10.8 0M
OPEN DUCT @ F.F SLAB D
FHR
18. All types of smoke management systems (include pressure difference between adjacent zones) shall be following NFPA 90A, NFPA 92A, NFPA 92B and other international codes and standards and shall be submitted in shop drawing submittal.
23. Internal roads indicating how fire-men emergency tracks will maneuver on the site and occupants assemblies areas.
D01
B
4420 W02
STAIR-2
+4.20
CORRIDOR
D01
W02
D01
W02
EXIT-2
C
a
D01
+4.20 OFFICE-2
16. Standpipe system shall be provided in these building according to NFPA 14.
M .81 5M =5 9.1 ATH NCE= NP MO ISTA OFFICE-7 COM AVEL D TR
OFFICE-6
OFFICE-5
STAIR-1
D01 W02
12800
OFFICE-4
3. ALL LEVELS INDICTED ARE FINISHED FLOOR LEVEL (FFL) UNLESS OTHERWISE INDICATED.
FIRE HOSE REEL CABINET. 1 No. Ø25x30 MTR. LONG HOSE REEL. 1 No. Ø25mm GATE VALVE & PRV. 1 No. 5KG. DCP FIRE EXTINGUISHER 1 No. 2.5KG. CO2 FIRE EXTINGUISHER.
17. All Fire Door and Windows shall be according to NFPA 80.
A
TRA COMM O VEL DIS N PATH TAN =5 CE .81 OFFICE-3 = M 9.1 5M
M .63 =4 .88M TH 12 PA CE= ON MM ISTAN CO D VEL TRA
W02
2. THE DRAWING SHOLUD NOT BE SCALED, USE WRITTEN DIMENSIONS AS SHOWN.
DESCRIPTION
SYMBOL
15. All portions of these building shall be fully protected by automatic sprinklers system according to NFPA 13.
A400
W02
1. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METER.
FIRE FIGHTING LEGEND:
14. All portions of these buildings and common and services areas shall be fully cover by smoke detections and fully covered by voice announcement system according to NFPA 72. ( if applicable)
1 W02
100
NORMAL WALL
28. Fire or smoke damper shall be provided in these building on all duct shaft according to UAE fire and life safety code and NFPA 90A, NFPA90B and shall be submitted in shop drawing submittal.
10. FEATURES NOT FULLY SHOWN ON PLANS OR DETAILS ARE TO BE PROVIDED AS INDICATED FOR SIMILAR CONDITIONS. CONSTRUCTION METHODS AND MATERIALS NOT EXPLICITLY INDICATED OR IMPLIED ARE INCIDENTAL TO THE WORK AND ARE VARIATION FROM THE DIMENSIONS AND / OR CONDITIONS SHOWN ON THESE DOCUMENTS. ANY SUCH VARIATIONS SHALL BE APPROVED PRIOR TO PROCEEDING WITH THE WORK, OR THE CONTRACTOR SHALL ACCEPT FULL RESPONSIBILITY FOR COST TO RECTIFY THE SAME.
EXIT STAIRWAY
29. All penetrations through fire resistance rated walls shall be protected by approved fire stop system and materials, installed and tested in accordance with ASTM E 814 or UL 1479.
FD60
60 mins FIRE RATED DOOR
30. All means of egress components details and dimensions shall be provided and constructed according to UAE fire and life safety code and NFPA 101 and 5000.
FD90
90 mins FIRE RATED DOOR DEAD END
31. Consultant and contractor shall comply with UAE fire and life safety code chapter 12 in terms of requirements of building under construction.
TRAVEL DISTANCE
32. Emergency action plan shall be implementing in these buildings according to UAE annexure B2 in the UAE Fire and Life Safety Code.
COMMON PATH
33. Consultant and contractors shall comply with UAE fire and life safety annexure B.1 in terms of the requirement of balcony, terrace and windows.
EGRESS PATH
34. Private Fire Hydrants shall provide around these building as per UAE Fire and Life Safety Code.
FIRE ESCAPE ROUTE
35. Consultant and contractors must comply with the general notes and applicable codes and standards even if the code requirement was missed during plan review.
INTERNAL ACCESS
EXISTING CHAPEL TABLE : 1 OCCUPANCY LOAD AS PER UAE FIRE CODE 2018 ,TABLE No.3.13 PAGE No.285 to 287
3
NAME OF FLOOR
NAME OF ROOM
AREA
OCCUPANT FACTOR
CHAPEL EXTENSION
1st & 2nd FLOOR
OFFICE- 01, 02
BUSINESS
43.63m²
9.3m² / PERSON
5 PERSON
2 EXIT
Rev
CHAPEL EXTENSION
1st & 2nd FLOOR
OFFICE- 03
BUSINESS
23.04m²
9.3m² / PERSON
3 PERSON
2 EXIT
OWNER :
CHAPEL EXTENSION
1st & 2nd FLOOR
OFFICE- 04 ,05 ,06
BUSINESS
50.53m²
9.3m² / PERSON
6 PERSON
2 EXIT
CHAPEL EXTENSION
1st & 2nd FLOOR
OFFICE- 07
BUSINESS
23.04m²
9.3m² / PERSON
3 PERSON
2 EXIT
CHAPEL EXTENSION
1st & 2nd FLOOR
OFFICE- 08 , 09
BUSINESS
43.63m²
9.3m² / PERSON
5 PERSON
2 EXIT
CHAPEL EXTENSION
1st & 2nd FLOOR
OFFICE- 10 , 11
BUSINESS
33.00m²
9.3m² / PERSON
4 PERSON
CHAPEL EXTENSION
1st & 2nd FLOOR
OFFICE- 12 , 13
BUSINESS
32.00m²
9.3m² / PERSON
NAME OF BUILDING
4
5
TYPE OF OCCUPANCY
NUMBER OF PEOPLE
NO. OF EXIT
2 EXIT
4 PERSON
2 EXIT
TOTAL:- 30 PERSON
2EXIT
00
ISSUED FOR APPROVAL
July. 2021
Description
Date
COPTIC CHURCH
LEAD CONSULTANT :
STRUCTURAL :
TABLE : 2A STAIRCASE SCHEDULE AS PER UAE LIFE SAFETY CODE 2018 PAGE No.285 to 287
6
NAME OF FLOOR
NUMBER OF STAIR
WIDTH OF EACH STAIR IN (mm)
FACTOR OF STAIR IN (mm)
TOTAL PERSON FOR EACH STAIR
CHAPEL EXTENSION
1st & 2nd FLOOR
EXIT STAIR-1
1200mm
7.6mm
157 PERSONS
CHAPEL EXTENSION
1st & 2nd FLOOR
NAME OF BUILDING
7
EXIT STAIR-2
1200mm
7.6mm
TOTAL NUMBER OF PEOPLE IN THIS FLOOR 30 PERSONS
157 PERSONS
COMPLY
PROJECT NAME :
COPTIC CHURCH
YES ZONE :
AL KHAREER - WADI AL AIN - AL AIN SECTOR NO. :
NAME OF BUILDING
9
10
FD90
STAIR-3
NAME OF ROOM
TYPE OF OCCUPANCY
ALLOWED DEAD END
ALLOWED COMMON PATH
ALLOWED TRAVEL DISTANCE
APPLIED DEAD END
APPLIED COMMON PATH
APPLIED TRAVEL DISTANCE
COMPLY
1st & 2nd
OFFICE- 01, 02
BUSINESS
15.00m
15.00m
60.00m
-
0.00m
11.97m
YES
CHAPEL EXTENSION
1st & 2nd
OFFICE- 03
BUSINESS
15.00m
15.00m
60.00m
-
0.00m
8.34m
YES
CHAPEL EXTENSION
1st & 2nd
OFFICE- 04 ,05 ,06
BUSINESS
15.00m
15.00m
60.00m
-
0.00m
13.08m
YES
CHAPEL EXTENSION
1st & 2nd
OFFICE- 07
BUSINESS
15.00m
15.00m
60.00m
-
0.00m
8.73m
YES
CHAPEL EXTENSION
1st & 2nd
OFFICE- 08 , 09
BUSINESS
15.00m
15.00m
60.00m
-
0.00m
12.43m
YES
CHAPEL EXTENSION
1st & 2nd
OFFICE- 10 , 11
BUSINESS
15.00m
15.00m
60.00m
-
0.00m
12.03m
YES
CHAPEL EXTENSION
1st & 2nd
OFFICE- 12 , 13
BUSINESS
15.00m
15.00m
60.00m
-
0.00m
12.01m
YES
PROPOSED MODIFICATIONS - TO EXISTING PUBLIC BUILDING (CHURCH) - (G+2+R) CONSISTING OF CHURCH EXTENSION AND ACCOMMODATION BUILDING & 1 MECH. ROOMS, ON (SECTOR WADI AL AIN -1 , PLOTS (22-01-085-1) AL KHAREER - WADI AL AIN - AL AIN DRAWING TITLE :
( CHAPEL EXTENSION ) FIRST FLOOR PLAN
DRAWING NO. :
FD90
STAIR-4
1
CHAPEL EXTENSION
TYPE OF OCCUPANCY BUSINESS (GROUP B) OFFICE
SUBMISSION DATE :
AREA OF BUILDING (SQ.M)
GROUND FLOOR
1st Floor
405.00m²
405.00m²
00
2nd Floor
ROOF FLOOR
TOTAL
TYPE OF FIRE PROTECTION SYSTEM
405.00m²
13.90 m²
1228.90 m²
SPRINKLER SYSTEM +FHR, WET RISER SYSTEM + EXTINGUISHER
TYPE OF FIRE ALARM SYSTEM
FIRE ALARM SMOKE DETECTION SYSTEM
SCALE :
1/150
07/07/2021 PROJECT ID:
DRAWING SIZE :
B2S-2018-000739 FOR OFFICIAL USE ONLY:
12
REVISION NO. :
F6-101
TABLE : 5 FIRE PROTECTION SYSTEM AS PER UAE FIRE CODE 2018 ,CHAPTER 9 NAME OF BUILDING
(22-01-085-1)
PROJECT DESCRIPTION :
CHAPEL EXTENSION
NO. OF BUILDING
11
NAME OF FLOOR
PLOT NO. :
WADI AL AIN -1
TABLE : 3 MEANS OF EGRESS AS PER UAE FIRE CODE 2018 TABLE No.3.16 CHAPTER 3 PAGE No.293 to 295
8
335.3
06
Fire & Life Safety Strategy Drawings: [C1]: Coptic Church
A1
Preparation of Document Submission for Municipality LAND KEY :
LANDSCAPING SHOWN BEYOND THE PLOT LIMIT IS FOR GUIDANCE ONLY, WHICH SHALL BE DONE BY MAIN DEVELOPER.
X1
N QI
X2
X3
+7.77
N 2705396.229 E 254604.988 X4
1
LINE OF CANOPY
A303
+8.17
1
2
3
4500
N 2705394.530 E 254596.319
4200
7 4200
53356
4200
+8.36 +8.46
+8.46 FHC-R
5075
ONT
SMDB
8100
1
L.V ROOM +8.46
A310
+8.41
SMDB
SMDB
FOR GROUND FLOOR MAIN ENTRANCE DETAILS REFER TO DRAWING NUMBER A713-A714 (MAIN ENTRANCE FLOORING LAYOUT, RCP, SECTIONS AND DETAILS)
F.F PUMP ROOM
SHAFT
MECH.
4000
+8.46
1 A301
A491
+8.46
CORRIDOR
DB
FIREMEN LIFT
4
DB
DB
A491
ED OU TDOOR AREA
+8.46
+8.36
REINFORCED CONCRETE WALL/COLUMN
+8.46
+8.41
PERFORATED FIBER CEMENT CLADDING
AWCS ROOM (GARBAGE) 01.h
GENERATOR
SERVICE ENTRANCE
ELEC.
A312
SER. LO BBY-3
EXTERNAL INSULATED BLOCKWALL
STORE
STORE
SHAFT
+8.46
SHAFT2 ELE VATION -1 4
DEPRESSED SLAB
BICYCLE PARKING SER. LOBBY-2
+8.46
5
4
6
A310
A801
A310
+8.41
DD FHC-R
6 A405
PLOT LIMIT ACK LIN E
LOAD
+8.36
+8.36
ING ARE A
SETB
UP
J
AREA
4
SHAFT 4
STAIR-1
4200
7 A491
EMPLOYER : 2401 2000
LIFT-4
K
300
LIFT LOBBY (T.HOUSE)
A205
A491
3 4 1 ELEVATION-1 A311 MECH. SHAFT-
+8.46
150
+8.41
A311
1900
ELE C.
+8.46 01.i
SMDB
01.i
JAN.
FHC-R
SMDB
STAIR
LAUNDRY LOBBY
LOBBY
G. WC
M. BATHROOM
M. BATHROOM
JAN.
G. WC
O.T.S.
KITCHEN DB
KITCHEN
AL DANA NORTH
STAIR
LAUNDRY
LOBBY
AV-6 AV-5
+2.64
TERRACE
ARCHITECTURAL MODIFICATIONS WITHOUT ADDITION & WITHOUT STRUCTURAL MODIFICATIONS
KITCHEN
G. WC SHAFT M. BATHROOM
AV-4
LIVING / DINING
KITCHEN
BEDROOM
TERRACE
TERRACE
LIVING / DINING
LIVING/DINING
TERRACE
BUILDING LIMIT
C11
STAIR
LAUNDRY
LIVING/DINING LIVING/DINING
2 A313
PLOT NO. :
RBW8 PROJECT DESCRIPTION :
72 00
LIVING/DIN ING TERRACE
SECTOR :
ﺗﻌﺩﻳﻼﺕ ﻣﻌﻣﺎﺭﻳﺔ ﻓﻘﻁ ﺑﺩﻭﻥ ﺇﺿﺎﻓﺔ ﻭﺑﺩﻭﻥ ﺗﻌﺩﻳﻼﺕ ﺇﻧﺷﺎﺋﻳﺔ
ONT
KITCHEN
BEDROOM
ONT
LOBBY
SETBACK LINE
+8.46
BEDROOM
DB
G. WC
JAN.
ONT
BEDROOM
SMDB
01.i
IRON./DRYER RM.
ONT
BEDROOM
DB
EXTRACT AIR
O.T.S.
01.i
IRON./DRYER RM. SMDB
JAN.
LIVING/DIN ING
AV-1
+8.46
STAIR
DB
LOBBY
ZONE :
01.e
IRON./DRYER RM.
LAUNDRY
G. WC
COMMERCIAL / RESIDENTIAL TOWER AV-7
LINE SETBACK
TERRAC E
IRON./DRYER RM.
LAUNDRY
SMDB
STAIR
M. BATHROOM
KITCHEN DB
LOUVER
DB
KITCHEN
G. WC
ONT
BEDROO M
LOBBY
MAID'S BR
DB
JAN.
ONT
SHAFT3 ELE VATION -1
O.T.S.
PROJECT NAME :
200MM BLOCK WALL (BOUNDERY WALLC) WITH INTERMEDIATE CONCRETE POSTS AT EVERY 4000MM
WC 01.i
SMDB
STAIR
LOBBY JAN.
A311
ENT.
01.i
ONT
G. WC
HOUSE
+8.46
SMDB
GARB.
CONSULTANT :
1 A304
5 A311
00 40
M. BATHROOM 2
+8.41
TOWN
W/M
+5.77
A310
2
CORRDO R (T.HOUSE)
FHC-R
01.i
IRON./DRY ER RM.IRON ./DRYER RM.
LAUNDR Y
SHAFT
+8.41 200
CORRDO R (T.HOUSE)
1 ELEVATION-2 MECH. SHAFT-
AV-7
+8.41
7
+8.46
STAIR
ALDAR OWNER :
0 00
00 60
A310
+7.34
67932
A310
BARRIER
ED OU TDOOR
09 JUN 2021 17 MAY 2021 01 OCT 2018 DATE
BARRIER
+7.62
A315
7500
SHAD
ISSUED FOR APPROVAL ISSUED FOR APPROVAL ISSUED FOR APPROVAL DESCRIPTION
MASTER DEVELOPER : 1
4
AV-6
2 1 0 REV. NO.
SETBACK LINE PG-15
2500
58181
LINE SETBACK
7
01.e
H
MECH.
SET BACK LINE PLOT LIMIT
LINE OF CANOPY
3
00
DD
A304
A313
60
BULK STO RE
G
+4.21
INTERNAL BLOCKWALL (100/150/200)
+8.41
+8.46
CCTV ROOM
E.C.C ROOM A-312 A312
WALL LEGEND :
CC
SER. LOBBY-1
2
LIFT 1, 2 & 3
SHAD
BB
STAIR-2
7 A402
FHC-R
FOYER
2800
+8.46
TEL.
ONT
LIFT LOBBY
SHAFT
E
SHAFT
+8.46
AS WET ARE
MECH. MECH. SHAFT-2 ELEVAT *ADM SHA FT-(SIZ ION 2 ELE E A0) VATION -2 -2
ME CH.
SMDB
DB
FUTURE
4200
2
SETBACK LINE
AV-2
4. CONTRACTOR MUST VERIFY ALL DIMENSIONS & MEASUREMENTS ON SITE & UNDERTAKE ANY ADDITIONAL OR NEW SURVEY AS NECESSARY TO CONFIRM SITE CONDITIONS. 5. ALL DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL OTHER PROJECT DOCUMENTS (I.E. ARCHITECTURAL, STRUCTURAL, MEP DRAWINGS, SPECIFICATION & BOQ SHOULD BE ALL READ TOGETHER FOR CONSISTENCY). 6. IF ANY DISCREPANCIES ARE FOUND BETWEEN DRAWINGS OR DOCUMENTS, THE CONTRACTOR MUST BRING THE SAME TO THE ATTENTION OF THE ENGINEER & SUBMIT PROPOSED SOLUTIONS DURING SHOP DRAWINGS STAGE, SUBJECT TO ENGINEER'S CONSENT & APPROVAL.
SLAB
SED DEPRES
HATCH INDICATE SLAB AT 3.20 METER HIGH
A490 3 A312
1
2. ALL LEVELS ARE IN METERS UNLESS OTHERWISE NOTED. 3. DO NOT SCALE OFF ANY DIMENSIONS FROM THE DRAWINGS.
+8.36
+8.46
TRENCH
+8.46
F
4300
1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE NOTED.
TRENCH
5
AV-3
GENERAL NOTES :
TRANSFORMER
TRENCH
MAIN ENTRANCE LOBBY
RETAIL
+8.46
A312
A313 4
6680
SETBACK LINE
TRENCH
+8.61
+8.42
AA0
CC
4400
GAS
TRENCH
4
AV-4
C11
A801
+8.37
+8.41
BB
AV-5
N 2705374.480 E 254653.585
+8.01
AA0
D
4100
CE VEHICULAR ENTRAN
9 5474
H.V ROOM
5 A801
ON STREET SHOPPING /
1
8
PLOT LIMIT
FOYER
E LIN
K AC TB SE
01.g
A301
A801
A405
+8.17
4.81%
SETBACK LINE
C
6 A310
6
4200
34
+7.77
3393
5
4200
4 A801
A
+8.17 88
A
B
4
3875
5 A310
BL
+8.17
+8.01 5
PLOT LIMIT
5408
06
Architectural Modifications: [C11]: Residential & Commercial Tower
DRAWING TITLE : +8.41
GROUND FLOOR PLAN
AV-3
TERRACE
AV-2
DRAWING NO. :
REVISION NO. :
3
A104 3 A310
AV-1
2
1276
A302
11 JULY 2021
1
PLOT LIMIT
A303
16747
ML-2
PROJECT ID :
5423
ML-1
N 2705347.649 E 254561.863
SUBMISSION DATE :
B1N-2018-000258-P02-M03
ML-3 ML-4
OFFICIAL USE ONLY : ML-5 ML-6
ML-7
80785
ML-8 ML-9
OFFICIAL USE ONLY : ML-10 YYYY
ML-11
ML-12
ML-13
ML-15
ML-16
PLOT LIMIT
N 2705309.721 E 254633.066
SCALE :
1 : 100 DRAWING SIZE :
A0
06
Architectural Modifications: [C11]: Residential & Commercial Tower Basement Floors
LANDSCAPING SHOWN BEYOND THE PLOT LIMIT IS FOR GUIDANCE ONLY, WHICH SHALL BE DONE BY MAIN DEVELOPER. X3
2
4500
3
3875
5
A310
A310
4
4200
5
4200
6
4200
7
4200
8
4200
9
5474
53356
N 2705394.530 E 254596.319
88
A
C11
34
5075
MECH.SHAFT-1
6680
+3.56
FAN ROOM
23
3393
01.b
B
22
21
20
19
18
17
16
GENERAL NOTES :
+3.56
15
STORE
AA0
CONTROL ROOM
PARKING
5213 8100
00
14
11
54
55
A405
PARKING
WALL LEGEND :
TYPICAL ROAD HUMPS AS SPECIFIED AND AS PER TYPICAL DETAIL
+3.31 +3.56
G SYSTEM SHORIN
2000
OWNER :
WHEEL STOPPER (TYPICAL)
57
EMPLOYER :
300
+3.66
STAIR-1
SMDB
50
58
40
00
3
01.d
SMDB
+3.56
+3.56
ELEC.
SMDB
36
DB
DB
400
41
42
0
2000
00
2
40
FHC-R
+3.56
0
TION-1
10 40 0
-3 ELEVA
TYPICAL ROAD HUMPS AS SPECIFIED AND AS PER TYPICAL DETAIL
44
UP TO GROUND FLOOR
45
GARB.
PROVISION OF MEP SERVICES
A313
AV-5 76
PARKING
43
3
AV-2
+4.15
+4.15
+4.15
5408
+4.15
PROVISION OF MEP SERVICES
AV-3 01.g
HIGH END RESTAURANT / SHOP 03
AV-2 01.f
+4.15
+4.15
+4.15
DRAWING NO. :
DB
1.17° 1276
DB
ML-1
+4.00
1.17°
ML-2
2
ML-3
1.10°
UP
A302
7.43°
1.10°
1
ML-6
UP
A303
ML-8
ML-7
N 2705309.721 E 254633.066
80785
ML-10 YYYY
ML-11
ML-12
ML-13
ML-15
+2.80
SHAFT
+56.91
MECHANICAL
+56.91
01.r
JACUZZI KIT +57.86
ø
1
STAIR-2
A301
DN
A
+56.76
+57.86
6. IF ANY DISCREPANCIES ARE FOUND BETWEEN DRAWINGS OR DOCUMENTS, THE CONTRACTOR MUST BRING THE SAME TO THE ATTENTION OF THE ENGINEER & SUBMIT PROPOSED SOLUTIONS DURING SHOP DRAWINGS STAGE, SUBJECT TO ENGINEER'S CONSENT & APPROVAL.
CC
ACCESS CONTROL DOOR
STORE
20 50
JACUZZI
WALL LEGEND :
DN
SHAFT SHAFT
01.s
+56.91
A310
+56.91
+56.91 01.p
01.s
01.p
01.p
01.s
DD
DD
01.j
+55.56
DISABLE LIFT
7
GLASS PARTITION
4300
8
ACK LINE
ROOF
A310
UP
2 1 0 REV. NO.
SMDB
SHAFT
+8.46
ISSUED FOR APPROVAL ISSUED FOR APPROVAL ISSUED FOR APPROVAL DESCRIPTION
4
DB
DB
AREA
GENERATOR
+8.36
REINFORCED CONCRETE WALL/COLUMN
+8.46
+8.41
PERFORATED FIBER CEMENT CLADDING
AWCS ROOM (GARBAGE) 01.h
EXTERNAL INSULATED BLOCKWALL
STORE +8.46
SERVICE ENTRANCE
ELEC.
A491
5 A310
+8.46
+8.41
4
6
A801
A310
DD
7
6 A405
PLOT LIMIT LOAD
+8.36
+8.36
ING AREA
SETB
AREA
SHAFT
40
OWNER :
00
60 00
STAIR
4200
7 A491
-1
EMPLOYER :
2000
LIFT-4
K
300
LIFT LOBBY (T.HOUSE) +8.41
7
+8.46
A205
A491
A311 3 4 ELEVATION-1 A311 MECH. SHAFT-1
+8.46
150
+8.41
ELEC.
1900
AV-1
2 A302
PROJECT ID :
N 2705309.721 E 254633.066
ML-8 ML-9
ML-10 YYYY
ML-11
ML-12
ML-13
ML-15
ML-16
OFFICIAL USE ONLY :
200
JAN.
STAIR
IRON./DRYER RM.
LAUNDRY LOBBY
LOBBY
G. WC
M. BATHROOM
M. BATHROOM
O.T.S.
DB
KITCHEN
LIVING/DI NING
STAIR
LAUNDRY
LOBBY
AV-4
TERRACE
LIVING/DININ G
LAUNDRY
5408
LIVING / DINING
LIVING/DINING
KITCHEN
BEDROOM
TERRACE
TERRACE
LIVING / DINING
LIVING/DINING
TERRACE
ﺗﻌﺩﻳﻼﺕ ﻣﻌﻣﺎﺭﻳﺔ ﻓﻘﻁ ﺑﺩﻭﻥ ﺇﺿﺎﻓﺔ ﻭﺑﺩﻭﻥ ﺗﻌﺩﻳﻼﺕ ﺇﻧﺷﺎﺋﻳﺔ
ONT
TERRACE
BUILDING LIMIT
DRAWING TITLE : +8.41
GROUND FLOOR PLAN
AV-3
TERRACE
3
AV-2
DRAWING NO. :
REVISION NO. :
3
A104
SCALE : 3
1 : 100 DRAWING SIZE :
A0
A310
AV-1
2
1276
A302
11 JULY 2021
1
PLOT LIMIT
A303
ML-1
N 2705347.649 E 254561.863
SUBMISSION DATE :
16747
ML-2
PROJECT ID :
B1N-2018-000258-P02-M03
ML-3 ML-4
OFFICIAL USE ONLY : ML-5
OFFICIAL USE ONLY :
C11
ARCHITECTURAL MODIFICATIONS WITHOUT ADDITION & WITHOUT STRUCTURAL MODIFICATIONS
KITCHEN
LIVING/DI NING
2 A313
PLOT NO. :
RBW8 PROJECT DESCRIPTION :
72 00
M. BATHROOM
KITCHEN
BEDROOM
AV-5
SECTOR :
STAIR
G. WC SHAFT
+8.46
BEDROOM
AV-6
SETBACK LINE
JAN.
ONT
KITCHEN
ZONE :
AL DANA NORTH
ONT
LOBBY
G. WC
DB
BEDROOM
DB
IRON./DRYER RM. JAN.
G. WC
SMDB
01.i
SMDB
O.T.S.
01.i
DB
JAN.
FHC-R
SMDB
STAIR
LOBBY
ONT
BEDROOM
MAID'S BR +8.46
IRON./DRYER RM.
LAUNDRY
G. WC
COMMERCIAL / RESIDENTIAL TOWER AV-7
01.e
SMDB
SMDB
M. BATHROOM
KITCHEN
PROJECT NAME :
200MM BLOCK WALL (BOUNDERY WALLC) WITH INTERMEDIATE CONCRETE POSTS AT EVERY 4000MM
WC 01.i
IRON./DRYER RM.
LAUNDRY
ONT
DB
STAIR
ONT
ONT
TION-1
-3 ELEVA
G. WC
CONSULTANT :
1 A304
5 A311
E ENT.
5423
B1N-2018-000258-P02-M03
1
LOBBY
+2.64
REVISION NO. :
A117 11 JULY 2021
ML-4
KITCHEN
AV-1
DRAWING NO. :
SUBMISSION DATE : ML-1
JAN.
BEDROO M
TERRAC E
ROOF PLAN
AV-2
A303
3 A313
DRAWING TITLE : AV-3
A203
+4.21
AV-2
O.T.S.
DB
ﺗﻌﺩﻳﻼﺕ ﻣﻌﻣﺎﺭﻳﺔ ﻓﻘﻁ ﺑﺩﻭﻥ ﺇﺿﺎﻓﺔ ﻭﺑﺩﻭﻥ ﺗﻌﺩﻳﻼﺕ ﺇﻧﺷﺎﺋﻳﺔ
JAN.
HOUS
+8.46
LINE SETBACK
LINE SETBACK
AV-1
AV-3
MECH . SHAFT
A313 4
AV-4 ARCHITECTURAL MODIFICATIONS WITHOUT ADDITION & WITHOUT STRUCTURAL MODIFICATIONS
01.i
A311
01.i
STAIR
LOBBY
LOUVER
PROJECT DESCRIPTION :
AV-2
G. WC
A310
EXTRAC T AIR
AV-3
M. BATHROOM 2
C11
RBW8
W/M GARB.
YER RM.
+5.77
AV-4 PLOT NO. :
SECTOR :
TOWN
01.i
YER RM.IRON./DR
+8.41
00
AV-5
SETBACK LINE
IRON./DR
LAUNDR Y
2
R (T.HOUSE )
40
AL DANA NORTH
AV-6
X4
FHC-R
01.i
STAIR
ZONE :
CORRDO
SMDB
COMMERCIAL / RESIDENTIAL TOWER
+8.46
DB
AV-7
AV-4
SHAFT
+8.41
R (T.HOUSE )
SMDB
K
CORRDO
+7.34
ELEVATION-2
AV-6 AV-5
MECH. SHAFT-1
AV-7
CONSULTANT :
ML-7
ALDAR
BARRIER
ED OUTD OOR
2401
PROJECT NAME :
ML-6
67932
UP
4
09 JUN 2021 17 MAY 2021 01 OCT 2018 DATE
BARRIER
+7.62
A315
0 250
SHAD
4 A310
ISSUED FOR APPROVAL ISSUED FOR APPROVAL ISSUED FOR APPROVAL DESCRIPTION
MASTER DEVELOPER : 1
1
ML-5
2 1 0 REV. NO.
SETBACK LINE PG-15
750 0
A304
ML-3
SET BACK LINE PLOT LIMIT
BULK STORE
01.e
OWNER :
01.p
ML-2
00
FHC-R
A310
X3
60
DEPRESSED SLAB
BICYCLE PARKING SER. LOBBY-2
DD
X1
X2
INTERNAL BLOCKWALL (100/150/200)
+8.41
+8.46
CCTV ROOM
STORE DB
FIREMEN LIFT
WALL LEGEND :
CC CORRIDOR
LINE OF CANOPY
09 JUN 2021 17 MAY 2021 01 OCT 2018 DATE
EMPLOYER :
AV-7
1 A301
SER. LOBBY-1
+8.46
SHAFT
+8.46
ED OUTD OOR
BB
STAIR-2
7 A402
E.C.C ROOM A-312 A312
SER. LOBB Y-3
J
4200
. SHAFT
-2 ELEVA TION-1 4
SHAD
PAVING TILES AND SWIMMING POOL FURNITURE LAYOUT REFER TO LANDSCAPE
AV-6
N 2705347.649 E 254561.863
SHAFT
TEL.
01.p
+55.56
F.F PUMP ROOM
SHAFT
SMDB
DB
+8.46
FHC-R
FOYER
A304
ALDAR 8 A310
+55.96
A310
+8.41
2 A491
A312
SETBACK LINE
01.p
J
K
AV-5
+8.46
+8.46
LIFT LOBBY
LIFT 1, 2 & 3
5
MECH.
58181
4100
MECH
E
H
ING POOL
4. CONTRACTOR MUST VERIFY ALL DIMENSIONS & MEASUREMENTS ON SITE & UNDERTAKE ANY ADDITIONAL OR NEW SURVEY AS NECESSARY TO CONFIRM SITE CONDITIONS. 5. ALL DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL OTHER PROJECT DOCUMENTS (I.E. ARCHITECTURAL, STRUCTURAL, MEP DRAWINGS, SPECIFICATION & BOQ SHOULD BE ALL READ TOGETHER FOR CONSISTENCY). 6. IF ANY DISCREPANCIES ARE FOUND BETWEEN DRAWINGS OR DOCUMENTS, THE CONTRACTOR MUST BRING THE SAME TO THE ATTENTION OF THE ENGINEER & SUBMIT PROPOSED SOLUTIONS DURING SHOP DRAWINGS STAGE, SUBJECT TO ENGINEER'S CONSENT & APPROVAL.
SED SLAB 1
L.V ROOM
A490 3 A312
MASTER DEVELOPER :
SWIMM
UP
DEPRES
TRENCH
2
1
2. ALL LEVELS ARE IN METERS UNLESS OTHERWISE NOTED. 3. DO NOT SCALE OFF ANY DIMENSIONS FROM THE DRAWINGS.
+8.36
+8.46
A202
01.p
POOL LADDER POOL DECK
+56.66
+54.54
TRANSFORMER
TRENCH
+8.41
G
SETB
H
C11
GENERAL NOTES :
1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE NOTED.
TRENCH
HATCH INDICATE SLAB AT 3.20 METER HIGH
4
SET BACK LINE
SETBACK LINE
TRENCH
+8.61
+8.42
+8.46
FOR GROUND FLOOR MAIN ENTRANCE DETAILS REFER TO DRAWING NUMBER A713-A714 (MAIN ENTRANCE FLOORING LAYOUT, RCP, SECTIONS AND DETAILS)
+8.46
A312
PLOT LIMIT
+8.01
A801
LINE SETBACK
+55.56
N 2705374.480 E 254653.585
PLOT LIMIT
VEHICULAR ENTRANCE
9 5474
+8.37
GAS
AA0
PERFORATED FIBER CEMENT CLADDING
LINE SETBACK
SHAFT
A201
A801
MAIN ENTRANCE LOBBY
RETAIL
CC
1
8
H.V ROOM
5
F
OPEN SHOWER
UP G
LINE
BB
A301
A801
TRENCH
AA0
D
REINFORCED CONCRETE WALL/COLUMN
+56.91
4400
A304
01.p
01.p
SHAFT 1
4200
A405
+8.17
A310
7 4200
53356
FOYER
ACK LINE
F
C
6
4 A801
6 4200
+8.36 +8.46
ON STREET SHOPPING /
EXTERNAL INSULATED BLOCKWALL
ROOF OF TOWER
5 A310
5 4200
+8.17
01.g
INTERNAL BLOCKWALL (100/150/200)
4000
7
LINE OF CANOPY
4 4200
+8.46
K AC TB SE
4000
ROOF OF TOWER
OPENING IN SLAB
E
3 3875
FHC-R
SETBACK LINE
B
4300
OPENING IN SLAB CC 4200
BB
2 4500
4100
D
1 A301
5. ALL DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL OTHER PROJECT DOCUMENTS (I.E. ARCHITECTURAL, STRUCTURAL, MEP DRAWINGS, SPECIFICATION & BOQ SHOULD BE ALL READ TOGETHER FOR CONSISTENCY).
01.r
SHAFT
X4
1 A303
1
34
2800
+56.91
BB
PLOT LIMIT
88
A +7.77
4400
8100
4. CONTRACTOR MUST VERIFY ALL DIMENSIONS & MEASUREMENTS ON SITE & UNDERTAKE ANY ADDITIONAL OR NEW SURVEY AS NECESSARY TO CONFIRM SITE CONDITIONS.
+8.01
+8.17
N 2705394.530 E 254596.319
+8.17
5
SMDB
3. DO NOT SCALE OFF ANY DIMENSIONS FROM THE DRAWINGS.
+53.31
OPEN BELOW
N 2705396.229 E 254604.988
SMDB
2. ALL LEVELS ARE IN METERS UNLESS OTHERWISE NOTED. +53.31
+56.91
+7.77
ONT
1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE NOTED.
AA0
+56.66
C
X3
ONT
GENERAL NOTES :
N QIB LA
X2
FUTURE WET AREAS
8100
+56.66
ø 300 0
5075
B
200
LAND KEY :
LANDSCAPING SHOWN BEYOND THE PLOT LIMIT IS FOR GUIDANCE ONLY, WHICH SHALL BE DONE BY MAIN DEVELOPER.
X1
6680
OPENINGININSLAB SLAB OPENING
12600
OFFICIAL USE ONLY :
16747
4.81%
AA0
K AC TB SE
A0
OFFICIAL USE ONLY :
ML-16
+2.80
MECH . MECH SHAFT-2 ELEVA . SHAFT *ADM (SIZE -2 ELEVA TION-2 A0) TION-2
C11
SETBACK LINE
1 : 100 DRAWING SIZE :
B1N-2018-000258-P02-M03
ML-5
3393
9 5474
3 SCALE :
11 JULY 2021 PROJECT ID :
ML-4
5075
8 4200
REVISION NO. :
A103 SUBMISSION DATE :
+4.00
1.17°
8100
7 4200
LINE
AV-1
ONT
1.17°
UP
BASEMENT-1 PLAN
STORE
LOBBY ONT
3
N 2705394.530 E 254596.319
C11
DRAWING TITLE :
PROVISION OF MEP SERVICES
01.f
01.g
HIGH END RESTAURANT / SHOP 02
DB
A310
A
PLOT NO. :
ARCHITECTURAL MODIFICATIONS WITHOUT ADDITION & WITHOUT STRUCTURAL MODIFICATIONS
AV-4
DN
01.g
HIGH END RESTAURANT / SHOP 01
ONT
+4.00
4200
6 4200
PE
5423
5
SLO
RBW8 PROJECT DESCRIPTION :
CONVEX MIRROR
6% = 16.
ﺗﻌﺩﻳﻼﺕ ﻣﻌﻣﺎﺭﻳﺔ ﻓﻘﻁ ﺑﺩﻭﻥ ﺇﺿﺎﻓﺔ ﻭﺑﺩﻭﻥ ﺗﻌﺩﻳﻼﺕ ﺇﻧﺷﺎﺋﻳﺔ
1.17°
N 2705374.480 E 254653.585
4200
+3.81
SLOPE= 8.33 %
2
QIB LA
4 4200
+3.56
+3.56
PROVISION OF MEP SERVICES
A313
Typical Plans
Roof Plans
3
AL DANA NORTH SECTOR :
79
STORE AV-1
N
3875
COMMERCIAL / RESIDENTIAL TOWER ZONE :
AV-6 +3.56
MECH . SHAFT
AV-3
CONSULTANT :
PROJECT NAME :
AV-7
00
+3.56
00
2 A310
A313 4
A204
2
40
1
10
AV-4
1 A304
1 TO
0 800
X3
4500
5
4
BASEMENT RAMP FROM FLOOR GROUND
SMDB
LAND KEY :
1
400 0
200
200 150
4200
+3.56
AV-7
AV-6 AV-5
ML-9
SETBACK LINE
09 JUN 2021 17 MAY 2021 01 OCT 2018 DATE
ALDAR
LIFT LOBBY-2
+1.50
X4
ISSUED FOR APPROVAL ISSUED FOR APPROVAL ISSUED FOR APPROVAL DESCRIPTION
6 51
LIFT-4
UP
1
2 1 0 REV. NO.
56
32
FHC-R
8
38
+3.56
34
01.a
9
MASTER DEVELOPER :
BICYCLE PARKING
7
33
35
10
STORE
TYPICALCORNER GUARD IN ALL COLUMNS AS PER SPECIFIED AND AS PER DETAILS
+3.56
29
+3.56
PARKING
67932
EXISITN
0 400
34 TYPICALCORNER GUARD IN ALL COLUMNS AS PER SPECIFIED AND AS PER DETAILS
A405
+3.56
PARKING
32
33
+2.80
A303
SET BACK LINE PLOT LIMIT
+3.56
+1.50
X2
PERFORATED FIBER CEMENT CLADDING
6 REGULATORY ARROW
35
J
UP
X1
EXTERNAL INSULATED BLOCKWALL REINFORCED CONCRETE WALL/COLUMN
DD
MECHANICAL MECH.SHAFT-3 MECH.SHAFT-4
7
BASEMENT 1 PARKING: 58 CARS +3.56
28
K
INTERNAL BLOCKWALL (100/150/200)
1 A315
20
TOP LEVEL
3
31
BY DEVELO PER
4300
36
2
CONVEX MIRROR
11199
+3.56
27
85
58181
RAMP FROM BASEMENT-2
SLOPE= 16.6 % 41
G RAMP/S TAIRS WITH EXISTIN
4000
COORD
30
20
4100
TYPICAL ROAD HUMPS AS SPECIFIED AND AS PER TYPICAL DETAIL
+3.56
G RAMP
H
53
PARKING
TO BE
4400
A304
G
52
00 40
DD
+3.66
01.d
SLOPE= 8.33 %
ROAD MARKING (TYPICAL)
STORE FHC-R
29
INATED
F
CC
72
4200
12
13
LIFT 1, 2 & 3
6. IF ANY DISCREPANCIES ARE FOUND BETWEEN DRAWINGS OR DOCUMENTS, THE CONTRACTOR MUST BRING THE SAME TO THE ATTENTION OF THE ENGINEER & SUBMIT PROPOSED SOLUTIONS DURING SHOP DRAWINGS STAGE, SUBJECT TO ENGINEER'S CONSENT & APPROVAL.
BB 1 A301
5
00 40
FIREMEN LIFT
1
FHC-R
STAIR-2 LIFT LOBBY-1
27
28
5. ALL DRAWING SHOULD BE READ IN CONJUNCTION WITH ALL OTHER PROJECT DOCUMENTS (I.E. ARCHITECTURAL, STRUCTURAL, MEP DRAWINGS, SPECIFICATION & BOQ SHOULD BE ALL READ TOGETHER FOR CONSISTENCY).
2800
2775
26 CC
E
4. CONTRACTOR MUST VERIFY ALL DIMENSIONS & MEASUREMENTS ON SITE & UNDERTAKE ANY ADDITIONAL OR NEW SURVEY AS NECESSARY TO CONFIRM SITE CONDITIONS.
+3.56 612
TYPICALCORNER GUARD IN ALL COLUMNS AS PER SPECIFIED AND AS PER DETAILS
BB
1
3. DO NOT SCALE OFF ANY DIMENSIONS FROM THE DRAWINGS.
A310
STORE
25
A301
2. ALL LEVELS ARE IN METERS UNLESS OTHERWISE NOTED.
1
ETS ROOM +3.56
F.F WATER TANK
D
1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE NOTED.
AA0
+3.56
24 C
N 2705347.649 E 254561.863
N 2705396.229 E 254604.988
N 2705374.480 E 254653.585
1
X4
1 A303
1
N QIB LA
X2
20
*Gaining an understanding on the importance of setting a proper Travel Distance to the nearest exits in case of fire. *Coordinating Revision Clouds with proper legend description, and setting proper hatching for its print layout. *Editing submission sheets layout when needed.
LAND KEY : X1
N 2705396.229 E 254604.988
ML-6
ML-7
80785
ML-8 ML-9
OFFICIAL USE ONLY : ML-10 YYYY
ML-11
ML-12
ML-13
ML-15
ML-16
PLOT LIMIT
N 2705309.721 E 254633.066
SCALE :
1 : 100 DRAWING SIZE :
A0
Preparation of Document Submission for Municipality TABLE : 1 OCCUPANCY LOAD AS PER UAE FIRE CODE 2017 ,TABLE No.3.14 PAGE No.311&312 NAME OF BUILDING
NAME OF FLOOR
NAME OF ROOM
COMMERCIAL APARTMENT
BASEMENT-3
PARKING AREA
TYPE OF OCCUPANCY ENCLOSED PARKING
AREA
OCCUPANT FACTOR
2600.00m²
27.9m² / PERSON
93 PERSON
TOTAL:- 93 PERSON
LAND KEY :
TABLE : 5 FIRE PROTECTION SYSTEM AS PER UAE FIRE CODE 2017 ,CHAPTER 9
NUMBER OF PEOPLE NO. OF EXIT 2 EXIT
2 EXIT
NO. OF BUILDING 1
NAME OF BUILDING
TYPE OF OCCUPANCY
COMMERCIAL APARTMENT
RESIDENTIAL (GROUP A)
AREA OF BUILDING (SQ.M)
BASEMENT BASEMENT BASEMENT GROUND -3 -2 -1 FLOOR 3591.00m²
3591.00m²
3617.64m²
1 st FLOOR
2 nd FLOOR
3rd FLOOR
4 th FLOOR
5 th FLOOR
2752.95m² 2752.95m² 1603.00m² 1576.00m² 1533.60m² 1533.60m²
6 TH FLOOR
7 TH FLOOR
8 TH FLOOR
9 TH FLOOR
10 TH FLOOR
11 TH FLOOR
12 TH FLOOR
ROOF FLOOR
TOP ROOF FLOOR
TOTAL
1535.70m²
1533.60m²
1530.00m²
1418.50m²
1418.50m²
1418.50m²
1418.50m²
1397.80m²
1397.80m²
35620.64m²
TYPE OF FIRE PROTECTION SYSTEM SPRINKLER SYSTEM + FHC , WET RISER SYSTEM + EXTINGUISHER
TYPE OF FIRE ALARM SYSTEM
FIRE ALARM SMOKE DETECTION SYSTEM
NO LPG SYSTEM IN THIS BUILDING
TABLE : 2A STAIRCASE SCHEDULE AS PER UAE LIFE SAFETY CODE 2017 PAGE No.311&312 NAME OF BUILDING
NAME OF FLOOR
NUMBER OF STAIR
WIDTH OF EACH STAIR IN (mm)
FACTOR OF STAIR IN (mm)
TOTAL PERSON FOR EACH STAIR
COMMERCIAL APARTMENT
BASEMENT-3
EXIT STAIR-1
1300mm
7.6mm
171 PERSONS
BASEMENT-3
COMMERCIAL APARTMENT
EXIT STAIR-2
1300mm
7.6mm
TOTAL NUMBER OF PEOPLE IN THIS FLOOR 93 PERSONS
171 PERSONS
C15
COMPLY
YES
33600
TABLE : 3 MEANS OF EGRESS AS PER UAE FIRE CODE 2017 TABLE No.3.16 CHAPTER 3 PAGE No.321 NAME OF BUILDING
NAME OF FLOOR
NAME OF ROOM
TYPE OF OCCUPANCY
ALLOWED DEAD END
ALLOWED COMMON PATH
ALLOWED TRAVEL DISTANCE
APPLIED DEAD END
APPLIED COMMON PATH
APPLIED TRAVEL DISTANCE
COMPLY
COMMERCIAL APARTMENT
BASEMENT-3
PARKING AREA
ENCLOSED PARKING
15.00m
15.00m
60.00m
-
0.00m
45.20m
YES
COMMERCIAL APARTMENT
BASEMENT-3
PARKING AREA
ENCLOSED PARKING
15.00m
15.00m
60.00m
-
0.00m
45.60m
YES
COMMERCIAL APARTMENT
BASEMENT-3
PARKING AREA
ENCLOSED PARKING
15.00m
15.00m
60.00m
-
0.00m
23.50m
YES
4200
4200
4200
4200
4200
4200
4200
4200
FIRE FIGHTING LEGEND: SYMBOL
FHC
DESCRIPTION FIRE HOSE REEL CABINET. 1 No. Ø25x30 MTR. LONG HOSE REEL. 1 No. Ø25mm GATE VALVE & PRV. 1 No. 4.5KG. DCP FIRE EXTINGUISHER 1 No. 5KG. CO2 FIRE EXTINGUISHER. 1 No. Ø65mm LANDING VALVE.
P+++
PRESSURE LEVEL (AT MAIN STAIRCASE'S & FIRE LIFT SHAFT)
4.5KG DRY POWDER FIRE EXTINGUISHER 5KG CO2 EXTINGUISHER 2 HOUR (120min.) FIRE RATED WALL 1 HOUR (60min.) FIRE RATED WALL EXIT STAIRWAY FD60 FD90
45000 GALLONS
60 mins FIRE RATED DOOR 90 mins FIRE RATED DOOR DEAD END TRAVEL DISTANCE
FHC
COMMON PATH 1300
2800
1300
R.C.C WALLS
1200
FD90
1100 EXIT-2
P+++
2800
FIRE ESCAPE ROUTE
1200
EGRESS PATH
5400
03
FOR AUTHORITY APPROVAL
02
FOR AUTHORITY APPROVAL
23-05-2021
00
FOR AUTHORITY APPROVAL
19-06-2018
DESCRIPTION
DATE
REV. NO.
04-07-2021
MASTER DEVELOPER : P+++
ALDAR
FHC
OWNER:
FHC
CONSULTANT :
EMPLOYER : A FHC
1100
PROJECT NAME : 1200
1300
FD90 1200
2.
Fire Pump capacity shall be calculated according to the building type and civil defense requirement and shall be submitted in shop drawing submittal.
3.
Fire Reserve Water Tank shall be calculated according to the building type and Civil Defense requirement and shall be submitted in shop drawing submittal.
4.
There are no installations for LPG central system in these building.
5.
All gas piping (LPG central system) shall be exposed on the outside elevations filling line and risers if the system is provided.
6.
All Stairways shall be provided with marking signs.
8.
All Smoke Management System and Elevators shall be interlocking with the alarm system.
9.
2800
COMMERCIAL / RESIDENTIAL TOWER ZONE :
PLOT NO :
C15
AL DANA NORTH SECTOR NO :
RBW8
RAMP ( SLOPE 8%)
Determine the total area of the opening between adjacent façade of two different buildings as percentage as per UAE fire and life safety code and international codes.
7.
P+++
A
2800
All items in these documents are guidance only: detailed of Fire Alarm, Fire Fighting and all ventilation system in all items shall be submitted in shop drawing submittal.
5400
R.C.C WALLS 1.
1300
06
Architectural Modifications: [C15]: Residential & Commercial Tower
PROJECT DESCRIPTION :
INTERNAL MODIFICATIONS TO MATCH THE ARCHITECTURAL DRAWINGS
All horizontal and vertical opening on external façade, on internal, shafts or voids shall be fire rated according to the rating degree of the compartment within the building or on elevation.
FHC
10. All portable fire extinguishers shall be provided as per UAE fore and life safety code and NFPA 10
ﻟﻣﻁﺎﺑﻘﺔ ﺍﻟﻣﺧﻁﻁﺎﺕ ﺍﻟﻣﻌﻣﺎﺭﻳﺔ
ﺗﻌﺩﻳﻼﺕ ﺩﺍﺧﻠﻳﺔ
11. Emergency light and exit signs shall be provided according to UAE fire and life safety code and NFPA 101
DRAWING TITLE :
12. All structure elements shall have the fire resistance rating according to NFPA 5000 and other international standards. 13. All stairways shall be provided with two ways fire telephone communication. 14. All portions of these buildings and common and services areas shall be fully cover by smoke detections and fully covered by voice announcement system according to NFPA 72.
BASEMENT 3 FIRE & LIFE SAFETY STRATEGY LAYOUT
15. All portions of these building shall be fully protected by automatic sprinklers system according to NFPA 13. 16. Standpipe system shall be provided in these building according to NFPA 14. 17. All Fire Door and Windows shall be according to NFPA 80.
20. Fire command center room shall be provided according to UAE fore and life safety code and NFPA requirement.
SUBMISSION DATE :
21. Carbon monoxide detector shall be provided to detect the CO concentration.
26. Fire pump and fire water tank shall be listed and tested according to civil defense requirement and international standards. 27. All open space floors shall be used as a single tenant floor only, if it used as a multiple tenancy, then fire rated corridor not less than one hour shall be connected to the bath staircase. 28. Fire or smoke damper shall be provided in these building on all duct shaft according to UAE fire and life safety code and NFPA 90A, NFPA90B and shall be submitted in shop drawing submittal. 29. All penetrations through fire resistance rated walls shall be protected by approved fire stop system and materials, installed and tested in accordance with ASTM E 814 or UL 1479. 30. All means of egress components details and dimensions shall be provided and constructed according to UAE fire and life safety code and NFPA 101 and 5000. 31. Consultant and contractor shall comply with UAE fire and life safety code chapter 12 in terms of requirements of building under construction. 32. Emergency action plan shall be implementing in these buildings according to UAE annexure B2 in the UAE Fire and Life Safety Code. 33. Consultant and contractors shall comply with UAE fire and life safety annexure B.1 in terms of the requirement of balcony, terrace and windows. 34. Private Fire Hydrants shall provide around these building as per UAE Fire and Life Safety Code. 35. Consultant and contractors must comply with the general notes and applicable codes and standards even if the code requirement was missed during plan review.
SCALE :
04-07-2021
22. Central battery system for emergency lighting systems and other system shall be provided. 23. Internal roads indicating how fire-men emergency tracks will maneuver on the site and occupants assemblies areas. 24. Total duration time of full evacuation of the building at discharging level, up to assemblies' areas assemblies' areas shall be sized according total number of occupants.
03
F100
19. All interiors finishing material shall be provided as UAE fire and life safety code and NFPA 101.
25. All curtain walls and cladding insulations, exterior wall cladding and roofing system shall be provide as UAE fire and life safety code annexure A.1.21 and international codes and standards, after tender is approved bring shop drawing and support information for civil defense approval.
REVISION NO:
DRAWING NO :
18. All types of smoke management systems (include pressure difference between adjacent zones) shall be following NFPA 90A, NFPA 92A, NFPA 92B and other international codes and standards and shall be submitted in shop drawing submittal.
SMOKE EXTRACTION SHAFT WITH 6 TO 10 AIR CHANGES PER HOUR
PROJECT ID :
1:150@A1
B1N-2018-000265-CD03
FOR CIVIL DEFENSE APPROVAL :
Editing Key Legend according to needed revisions
TABLE : 1 OCCUPANCY LOAD AS PER UAE FIRE CODE 2017 ,TABLE No.3.14 PAGE No.311&312 NAME OF BUILDING
NAME OF FLOOR
NAME OF ROOM
COMMERCIAL APARTMENT
BASEMENT-3
PARKING AREA
TYPE OF OCCUPANCY ENCLOSED PARKING
AREA
OCCUPANT FACTOR
2600.00m²
27.9m² / PERSON
TABLE : 5 FIRE PROTECTION SYSTEM AS PER UAE FIRE CODE 2017 ,CHAPTER 9
NUMBER OF PEOPLE NO. OF EXIT 93 PERSON
TOTAL:- 93 PERSON
2 EXIT
2 EXIT
NO. OF BUILDING 1
NAME OF BUILDING
TYPE OF OCCUPANCY
COMMERCIAL APARTMENT
RESIDENTIAL (GROUP A)
AREA OF BUILDING (SQ.M)
BASEMENT BASEMENT BASEMENT GROUND -3 -2 -1 FLOOR 3591.00m²
3591.00m²
3617.64m²
1 st FLOOR
2 nd FLOOR
3rd FLOOR
4 th FLOOR
5 th FLOOR
2752.95m² 2752.95m² 1603.00m² 1576.00m² 1533.60m² 1533.60m²
6 TH FLOOR
7 TH FLOOR
8 TH FLOOR
9 TH FLOOR
10 TH FLOOR
11 TH FLOOR
12 TH FLOOR
ROOF FLOOR
TOP ROOF FLOOR
TOTAL
1535.70m²
1533.60m²
1530.00m²
1418.50m²
1418.50m²
1418.50m²
1418.50m²
1397.80m²
1397.80m²
35620.64m²
TYPE OF FIRE PROTECTION SYSTEM SPRINKLER SYSTEM + FHC , WET RISER SYSTEM + EXTINGUISHER
TYPE OF FIRE ALARM SYSTEM
FIRE ALARM SMOKE DETECTION SYSTEM
TABLE : 2A STAIRCASE SCHEDULE AS PER UAE LIFE SAFETY CODE 2017 PAGE No.311&312 NAME OF BUILDING
NAME OF FLOOR
NUMBER OF STAIR
WIDTH OF EACH STAIR IN (mm)
FACTOR OF STAIR IN (mm)
TOTAL PERSON FOR EACH STAIR
COMMERCIAL APARTMENT
BASEMENT-3
EXIT STAIR-1
1300mm
7.6mm
171 PERSONS
COMMERCIAL APARTMENT
BASEMENT-3
EXIT STAIR-2
1300mm
7.6mm
171 PERSONS
TOTAL NUMBER OF PEOPLE IN THIS FLOOR 93 PERSONS
COMPLY
YES
TABLE : 3 MEANS OF EGRESS AS PER UAE FIRE CODE 2017 TABLE No.3.16 CHAPTER 3 PAGE No.321 NAME OF BUILDING
NAME OF FLOOR
COMMERCIAL APARTMENT COMMERCIAL APARTMENT COMMERCIAL APARTMENT
NAME OF ROOM
TYPE OF OCCUPANCY
ALLOWED DEAD END
ALLOWED COMMON PATH
ALLOWED TRAVEL DISTANCE
APPLIED DEAD END
APPLIED COMMON PATH
APPLIED TRAVEL DISTANCE
BASEMENT-3
PARKING AREA
ENCLOSED PARKING
15.00m
15.00m
60.00m
-
0.00m
45.20m
YES
BASEMENT-3
PARKING AREA
ENCLOSED PARKING
15.00m
15.00m
60.00m
-
0.00m
45.60m
YES
BASEMENT-3
PARKING AREA
ENCLOSED PARKING
15.00m
15.00m
60.00m
-
0.00m
23.50m
YES
33600 4200
4200
4200
4200
4200
4200
4200
4200
COMPLY
FIRE FIGHTING LEGEND: SYMBOL
FHC
DESCRIPTION FIRE HOSE REEL CABINET. 1 No. Ø25x30 MTR. LONG HOSE REEL. 1 No. Ø25mm GATE VALVE & PRV. 1 No. 4.5KG. DCP FIRE EXTINGUISHER 1 No. 5KG. CO2 FIRE EXTINGUISHER. 1 No. Ø65mm LANDING VALVE.
P+++
PRESSURE LEVEL (AT MAIN STAIRCASE'S & FIRE LIFT SHAFT)
4.5KG DRY POWDER FIRE EXTINGUISHER 5KG CO2 EXTINGUISHER 2 HOUR (120min.) FIRE RATED WALL 1 HOUR (60min.) FIRE RATED WALL EXIT STAIRWAY
45000 GALLONS
60 mins FIRE RATED DOOR 90 mins FIRE RATED DOOR DEAD END TRAVEL DISTANCE COMMON PATH 1300
2800
1300
P+++ FD90
P+++
*Attaching key legend to each plan and providing needed modifications as revisions with their tags. *Hatch of revision plans indicates non modified part of drawings. FHC
A
5400
2800
FIRE ESCAPE ROUTE
1200
EGRESS PATH
1200
FD90
FHC
FD60
1100 EXIT-2
06
Architectural Modifications: [C15]: Residential & Commercial Tower
Conclusion
Skilled applied/learned
Knowledge gained:
*AutoCAD for Drafting and Preparing Paper space according to company’s layout, and printing settings.
*Setting Layers properties are essential in all drafting process.
*AutoCAD for Drafting and Area Estimation.
*Shortcuts and few tricks in using some AutoCAD commands.
*AutoCAD for Applying Fire fighting Studies.
*Municipality Regulations and Building codes.
*AutoCAD for Revision clouds.
*Scale setting of the drawings while preparing for print layout.
*Word for editing Legend Keys.
*Format of Project Submission to Tanasok, Abu Dhabi Municipality.
*AutoCAD for Drafting and Preparing Paper space according to company’s layout, and printing settings, including pen assignments.
*Format of Feasibility Study Report submitted to ADCE (Abu Dhabi Commercial Engineering Services).
*Excel for filling in Figures and comparing flat areas and room usage.
*Coordinating Revision Clouds with proper legend description, and setting proper hatching for its print layout.
*A drawing should be easily communicated through use of current line weights, line type, and color.
*Proper Fire & Life Safety Strategy Drawing Layout.
*Coordinating details with key drawings.
Thank you Diana Enab