2014-2015
Government of Nepal Ministry of Federal Affairs and Local Development
ANNUAL PROGRESS REPORT FY 2071/72(2014/15)
Local Governance and Community Development Programme
(LGCDP –II) Regional Coordination Unit (RCU) Dhangadhi
Local Governance and Community Development Program (LGCDP-II)
Regional Coordination Unit (RCU) Dhangadhi Kailali Tel.:+977-91 523240/525301
Fax No.:+977-91 523039
Executive Summary Annual Progress Report of the fiscal year 2071/72 (2014/15) covers the progress status and achievement of LGCDP Phase II of Far Western Development Region (FWDR). The progress report is analysed based on output 1-7 of District Development Committees (DDC), Municipalities and Village Development Committees (VDC). It also highlighted the problems, issues, way forward and some recommendations observed during site visit, backstopping, monitoring and supervision at all level of programme in the Far Western Development Region. The key achievements have been highlighted in this report. Empowered citizen and community organization: Till the FY 2071/072 (2014/015),
Social Mobilization activity has been implementing in all 328 VDCs (2944 Ward) and all 21 Municipalities (271 Ward). SM activities has been implemented in the technical support of 58 LSPs, 444 SMs and 30 D/MCCs in the region. Under this activity, 3210 WCFs and 468 CACs have been formed in VDCs and Municipality Wards; in which more than 74554 members, including 46% female, have been mobilized in community. Similarly, VDCs and Municipalities ward have been a good platform of more than 12666 members representing from 468 CACs. Out of total CAC members, 88% women represents from ultra-poor and under-privileged group. The CAC members are now being empowered and able to coordinate with VDCs and other service providers through REFLECT classes, training/exposure's in local level. The program has initiated to provide LIP grant support of Rs.100, 000 to each CACs. Till the date (069/70 to 071/72) Total of 424 VDCs and Municipality CACs have received LIP grants Rs. 42900000 for income generating activities for better livelihood. The total of 2004 member's of 424 CACs have been benefited so far. Only 176 CACs are remaining to receive LIP grants. Established accountability mechanism at local level: LGAF provides assistance to the CSOs with the objective institutionalized the downward accountability system to strengthen the good governance system at local level. The CSOs have been started implementing the program from February 2015. Out of 9 i
DDCs, 8 DDCs and 14 Municipalities have been supported by 8 CSOs in the region. Out of 328 VDCs, 62 VDCs and 169 Municipalities ward has been covered so far. The CSOs are facilitating on the three areas of intervention (1) coordination with local bodies (2) Facilitation (3) Monitoring of the service delivery system. Access to resource increased : Regarding this output, programme has made effort to
increase the internal revenue of LBs. In order to increase the internal revenue of LBs MoFALD Internal revenue management training at DDC level and integrated property tax system training at municipality level were held during the reporting period. However no countable progress has been made to increase the resources in the region. Only 3 (Kailali, Kanchanpur and Doti DDCs), 14 municipalities and 42 VDCs has increased their internal revenue by 10%. Moreover, The result of MCPM shows that Dadeldhura and Kanchanpur DDCs and Tikapur Municipality have received additional grant by 15% and 10% and 20% respectively. In case of VDCs only 211 VDCs out of 328 have qualified the MC this year. Public Financial management system improved: In order to strengthen the capacity of financial management the programme have organised VDC accounting software training and support resources to internal audit section in all 9 districts. In this training 283 VDC staffs have been trained. As per the LBs report 57 VDCs have adopted VDC accounting software and made functional, 45 VDCs have introduced simplified expenditure system from this fiscal year. Similarly, four municipalities and nine DDCs have been practicing of e-bidding system and 14 Municipalities and nine DDCs have prepared procurement plan in this year. Capacity strengthening in Local bodies: Capacity development a major cross-cutting area of the programme. CD activities are mandated to LBs for making more accountable and effective service delivery through institutional and human resource development.
Therefore, programme have supported on demand based and non-
demand (Contextual) based CD activities to the LBs. Local Level Planning training in two districts was directly supported by MoFALD, in this training 1685 WCF members were participated of which 46% were women. And 427 Social Mobilizers have received SM training from all districts. The trainings were organized by National Service Provider/LDTA.
Access to and quality of local infrastructure and other socio economic administered by LBs are improved This output address and ensure their effectiveness and efficiency while delivering of services related to infrastructure development, vital events registration, social security payments and community mediation. ii
In FY 2071/72, there are 10981 different types of project completed in LBs (DDC 1435, Municipality 2544 and VDCs 7002) of this region, which have benefitted 2392853 population (DDC45105, Municipality 618154 and VDC 1323694) respectively. Similarly the total cost of the completed project is Rs.1219395000 (DDC 252130, Municipality 372361, VDC 594904) Out of total benefitted population In DDC 54% from Disadvantaged groups. So far target group wise budget allocation and implementation is concerned; DDC by and large followed the blended guideline meeting the target as mentioned. Similarly 2544 different project completed in 21 municipalities which have 618154 population of the region. Likewise 7002 different project completed at 238 VDCs of Far –west region the total population benefited at VDCs projects 1323694. In addition, Community Infrastructure Development Grant
schemes were implemented and focused in directly income generation and livelihood development of CAC members. Till the date (069/70 to 071/72) total of 362 CACs received grant sum of Rs. 124341812 to implement 3595 income generating schemes at VDCs and Municipality level. Out of total 251 CACs of VDCs received grant Rs. 88576302 for 2277 community and individual schemes, where has 111 CACs of Municipalities received grant of Rs. 35765510 for 1318 community and individual schemes. The total benefited members of those 362 CACs are 55546 (male 26640 and female 28906) so far. Out of total 36761(male 17448 and female 19313) members from VDC and 18785 (male 9192 and female 9593) members from Municipality have been benefited.
Strengthen integrated planning, budgeting, monitoring, evaluation and coordination amongst local governance actors Now it is a regular practice that all LBs are following the Local Bodies Resource Mobilization and Management Guidelines 2069 during the planning, monitoring and implementing process. Integrated Planning Formulation and supervision and monitoring committee are functional and Result Based Monitoring (RBM) is introduced by LBs. Project wise Monitoring & Supervision Committee were formed and carried out monitoring at field level. The political leaders have also been mobilized to monitor the projects. In addition, MoFALD has been occasionally involved in the monitoring process, where the regular monitoring, supervision backstopping has been made by Regional Coordination Unit. During the year Baitadi, Kanchanpur, Kailali, Bajura, Achham, Bajhang and Doti district has completed the District Periodic Plan with the support of MoFALD and other development partners. Darchula district is in the line of completing of DPP where has Dadeldhura could not start so for.
iii
Cross cutting theme: All LBs have allocated 35% target budget for Women, Children and DAG community. All the nine DDCs have formed Gender Responsive Budget committee (GRBC) and Gender Equality and social Inclusion Implementation Committee (GESIIC) Overall in the
case of FWDR six DDCs out of nine and six old Municipalities have conducted GESI audit. Eight DDCs out of nine, 257 VDCs out of 328 and 13 Municipalities out of 21 have adopted CFLG, whereas remaining one DDC Darchula have also decided for CFLG adoption from DDC council. Seven DDCs, 272 VDCs and 9 Municipalities have conducted child gathering in this year which is 42% increased by last. Report six DDCs namely Dadeldhura, Kailali, Baitadi, Achham, Kanchanpur and Bajura and four Municipalities Api, Lamki-Chuwa, Bheemdutta and Dashrathchand have formed EFLG coordination committees. Similarly, four DDCs and seven Municipalities have Environment Management Plan Information & Communication Technology (ICT) LGCDP Phase -II provides the system, procedures, structures, tools and capacities for the facilitating the transformation of the local bodes into local government entities. MoFALD and UNV have set up new polite initiative, 'University Youth ICT Volunteers' for LGCDP-II. This component aims to digitalize the working procedure of government of Nepal as well as strengthen and maintain the IT infrastructure of LBs (DDCs/Municipalities). This report includes ICT activities and achievements performed at region FY 71/72 (2014/15) and positive change and need of ICT. Also includes future scope of ICT and E-governance for effective public service delivery of LBs. During the year MOFALD/LGCDP provided budget Rs.11700000 to all DDCs and 6 Municipalities to procure desktop server, hybrid solar along with required networking devices and utilized received budget. The basic IT infrastructure setup are being utilized with optimize resources with the best possible.
iv
List of Acronyms/Abbreviations ADB ASIP
Asian Development Bank Annual Strategic Implementation Plan
CAC
Citizen Awareness Center
RCU
Regional Co-ordination Unit
CD
Capacity Development
CFLG
Chile Friendly Local Governance
CSO
Civil Society Organization
DAG
Disadvantaged Group
DDC
District Development Committee
DGE
District Governance Expert
DP
Development Partner
DSMC
District Social Mobilization Committee
EMP
Environment Management Plan
GESI
Gender Equality and Social Inclusion
GIZ
(German Society for International Cooperation)
I/NGOs
International/Non-Government Organization
IGA
Income Generating Activity
IEC
Information, Education and Communication
LB
Local Body
LBFC
Local Body Fiscal Commission
LGAF
Local Governance & Accountability Facility
LGCDP
Local Governance & Community Development Programme
LIP
Livelihood Improvement Programme
LLP
Local Level Planning
LSP
Local Service Provider
M&E
Monitoring & Evaluation
MoFAL D ICT
Ministry of Federal Affairs and Local Development
ICTV
Information Communication Technology Volunteers
Information Communication Technology
v
Contents Introduction..................................................................................................................................... 1 1.1 Program Background ................................................................................................................. 1 1.2 LGCDP at Far Western Region................................................................................................ 1 1.3 Topography of Far Western Region ....................................................................................... 2 1.4 Socio-economic condition of Region ..................................................................................... 3 1.5 Local Development Bodies in Nepal ...................................................................................... 3 1.5.1 District Development Committees ................................................................................. 3 1.5.2 Municipalities .................................................................................................................. 4 1.5.3 Village Development Committees .................................................................................. 4 CHAPTER I ........................................................................................................................................ 5 Compilation of Sector Report ......................................................................................................... 5 OUTPUT 1......................................................................................................................................... 5 Citizen and Community Organization are empowered to Actively Participated and Assert their Right in Local Governance............................................................................................................... 5 1.1 Social Mobilization .................................................................................................................... 5 1.1.1 Overall status of Social Mobilization (SM) Coverage: ..................................................... 5 1.1.2 Ward Citizen Forum (WCF) ............................................................................................. 6 1.1.3 Citizen Awareness Center (CAC) ..................................................................................... 7 1.1.4 Capacity Building under Social Mobilization: .................................................................. 8 1.1.5 Access of WCF in LBs Planning Process. .......................................................................... 9 1.1.6 CAC Graduation Status:................................................................................................. 10 1.7 District/Municipal Social Mobilization Coordination Committee .................................... 11 1.1.8 Local Service Provider (LSP) .......................................................................................... 11 1.1.9 Social Mobilizers ........................................................................................................... 12 1.1.10 Conduction of Underlying Causes of Poverty Analysis (UCPA) in wards or VDCs ....... 12 Harmonization and Linkage of CACs: ..................................................................................... 12 1.2 Livelihood Improvement Programme .................................................................................. 13 OUTPUT 2....................................................................................................................................... 18 Accountability Mechanism for Local Governance are in place.................................................... 18 2.1 Local Governance & Accountability Facility (LGAF) ............................................................. 18 OUTPUT 3....................................................................................................................................... 21 Local Bodies Access to Resource Increased .................................................................................. 21 3.1 MCPM of District development committee (DDC) .............................................................. 21 3.2 MCPM of municipalities ....................................................................................................... 22 OUTPUT 4....................................................................................................................................... 23 Public Finance Management System Improved ........................................................................... 23 4.2 GESI responsive Budgeting and Auditing Practices at LBs ................................................... 23
vi
4.2.1 GESI and GRB adoption ................................................................................................. 23 4.2.2 GESI auditing progress: ................................................................................................. 24 OUTPUT 5....................................................................................................................................... 25 Institutional and Human resource Capacities of LBs and Central Level Agency Involved in Local Governance ................................................................................................................................... 25 5.1 Capacity development ......................................................................................................... 25 5.2 Information & Communication Technology (ICT) and Capacity Development of LBs ............. 26 Activities..................................................................................................................................... 27 Progress Status........................................................................................................................... 27 Remarks ..................................................................................................................................... 27 5.3 Demand Based Capacity Development................................................................................ 29 OUTPUT 6....................................................................................................................................... 30 Access to and quality of local infrastructure and other socio economic administered by LBs are improved........................................................................................................................................ 30 6.1 Status of Project Funding Matrix ......................................................................................... 31 6.1.1 District level .................................................................................................................. 31 6.1.2 Municipality Level ......................................................................................................... 33 6.1.3 VDC Level ...................................................................................................................... 36 6.2 Budget Expenditure vs Benefitted Population..................................................................... 37 Project vs Benefitted population ............................................................................................... 38 6.3 Community Infrastructure Development Grants: ................................................................ 39 6.4 Social Security & Vital Registration ...................................................................................... 42 6.5 Community Mediation ......................................................................................................... 43 OUTPUT 7....................................................................................................................................... 43 Strengthen integrated planning, budgeting, monitoring, evaluation and coordination amongst local governance actors ................................................................................................................ 43 7.2 Financial Delivery ................................................................................................................. 44 7.3 Gender and Social Inclusion (GESI) ...................................................................................... 44 7.4 Child Friendly Local Governance .......................................................................................... 47 7.3 Environment Friendly Local Governance (EFLG) .................................................................. 51 Visitors ........................................................................................................................................... 54 Issues, Challenges-way forward and Recommendation .............................................................. 55 Recommendations for further actions ......................................................................................... 60
vii
Annexes: Annex Annex Annex Annex Annex Annex Annex Annex Annex Annex Annex Annex Annex Annex Annex Annex
1: 2: 3: 4: 4a: 4a: 4a: 6a: 6b: 6C: 7: 8: 9: 10: 11: 12:
Result Based Monitoring (RBM) Social Mobilization Livelihood Improvement Program (LIP) Public Financial Management (PFM) - DDCs PFM – Municipality PFM – VDCs Demand Based Capacity Development Project Funding Matrix DDC Project Funding Matrix Municipalities Project Funding Matrix VDC Community Infrastructure Development Grants Social Security & Vital Registration Financial Delivery of LGCDP Gender and Social Inclusion (GESI) Environment Friendly Local Governance (EFLG) Child Friendly Local Governance (CFLG)
viii
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
Introduction 1.1 Program Background The Government of Nepal (GoN) is committed to improving people’s standards of living through the citizen-centric governance and effective service delivery based on democratic values and right based development approach. After the significant achievement in implementing first phase of the Local Governance and Community Development Programme (LGCDP), a national programme in the area of local governance and community development. The importance of this programme is ensuring the accountability on delivery of local services through established institutions and systems and the commitments being expressed for its continuation, by the GoN and the LGCDP development partners (DPs). LGCDP Phase I, successes while it has addressed its emerging challenges, demonstrating value for money and practicing effective risk management in a transitional and politically uncertain environment. LGCDP I activities were planned to achieve three overarching outcomes related to citizen empowerment, local government operations and local government policy making and execution. Together they aimed to strengthen the demand and supply sides of local governance by empowering citizens to actively engage with local government bodies and to increase the capacity of the government to deliver basic public services through a devolved system of local government. The vision for the programme calls for LGCDP II to act as a key support mechanism to the GoN’s poverty reduction efforts. By the positive experience of Phase I, LGCDP II will make pathways with a number of changes in focus and approach. As describe above; LGCDP - a national programme of Government of Nepal and is under implementation across the country from the last five years. Ministry of Federal Affairs and Local Development (MoFALD) is the executive agency for this programme and has implemented its activities in community level through the Local Bodies with financial support from a range of Development Partners. In order to co-ordinate/facilitate LGCDP's activities in local level and provide technical backstopping support to implementing agencies (LBs), LGCDP has established a Regional Co-ordination Unit (RCU) in development region.
1.2 LGCDP at Far Western Region The Far Western Development Region of Nepal covers 19,539 km2 out of 147, 181 km2 area of the country. It has nine districts with the regional headquarters at Dipayal of Doti district. The Far Western Region is remote and developmentally challenged. About
1
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
44% of people in the Far-West Hills and 49% in the Himalayan districts live beneath the poverty line. The region has limited access to basic service delivery and increasing service delivery is always challenging because of its difficult topography. The region has complex socio-economic structures and there is both widespread gender and caste based discrimination. Traditional systems associated with religion, culture and customs also have a great impact on overall development. It has two zones: i.e. Mahakali and Seti. The main cities are; Dhangadhi is the district headquarter of Kailali District of Seti Zone. Mahendranagar is the district headquarter of Kanchanpur District in Mahakali Zone. It is located on the bank of Mahakali River, 6 km north of the India border. Kanchanpur is inhabited by people of various races, including the indigenous Tharu people. Dipayal Silgadhi municipality is the headquarter of Doti district as well as regional centre of Far-Western Region. It is within trekking distance of Khaptad National Park. Dipayal is also the name of the scenic valley of Seti River. Amargadhi is the district headquarter of Dadeldhura district. The LGCDP II, Regional Coordination Unit, Dhangadhi is responsible for facilitating, monitoring and backstopping of 9 District Development Committees, 21 Municipalities and 328 VDCs being existed in the region. The RCU also serves as a link between the Programme Co-ordination Unit (PCU)/MoFALD and the LBs. Additionally, RCU is responsible in carrying out regular monitoring of field level activities and ensuring timely delievery of services along with preparing periodic and annual plan and progress reports. This report describes the major activities implemented by LBs under LGCDP-II in the region on Fiscal year 2071/72 (2014/15).
1.3 Topography of Far Western Region Far Western development region is a smallest development region of Nepal. The eastern boundary of the Far- western Development Region is Karnali River and its western boundary is Mahakali river. The region is influenced by the monsoon wind which is coming from the North West which brings enough rainfall in winter. Thus, FarWestern Development Region gets more rainfall in winter than in summer. Hence, the
2
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
Region is comparatively less dry than other Region. During the summer season extremely hot wind called Loo blows from the Thar deserts of India towards the terai of Nepal. Such winds affect Mahendranagar, Dhangadhi and even Dipayal in the north.
1.4 Socio-economic condition of Region Far-Western Development Region is least economically backward in comparison to other Region. Most of the remote areas of the districts are not accessed by transportation and facing problems. However district headquarter's of all 9 districts are nearly linked with the roads, which makes people easy access to find job market to Nepal and India. But the condition of women is miserable in FarWestern Development Region. Tharus live in different part of terai. They earn their living by agriculture, animal rearing, fishing, etc. Besides, other groups of people also live here like Brahmin, Chhettri, etc. The main crops grown in FarWestern Development Region are millet, barley, wheat and oil seeds. Paddy is mostly cultivated in the terai. The important tourist centers are Shuklaphanta Wildlife Reserve, Khaptad National Park, Mount Api and Saipal. Because of less infrastructures and distance from the capital city, that very few tourists are visiting the Region. As from socio-economic indicators, about 44 % of people of Hills and 49% in the Himalayan districts is living below the poverty line. The region has limited access to basic services and to increase the service delivery is also challenging due to difficult topography. It has complex socio-economic structures and there is both widespread gender and caste-based discrimination. Traditional systems associated with religion, culture and customs also have a great impact on overall development of the region. Opportunities are in far western Nepal, thousands of people can cross the border at Kanchanpur / Kailali on their way to Bardia. As there is a good road network, have water supply and electricity, and plenty of natural beauty on offer the districts can easily attract transit passengers to stay over. Exclusive products like rice wine, banana wine, allo (a local fibre), and Tharu and Rana handicraft just need better branding to capture a wider international market.
1.5 Local Development Bodies in Nepal 1.5.1 District Development Committees
District development committee (DDC) is a leading organization for district level development activities. It is considered as the central point of the local development. There are many government and non-government agencies in district for the integrated development. DDC plays an important role for coordinating all the development initiatives implemented by line agencies and I/NGOs. District Council is the supreme body for the formulation of district development plan. The Council should ratify the
3
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
plans and programmes of line agencies, which are prepared following participatory planning process. District Development Committee is the executive body of the District Council. The Committee conducts its activities in accordance with the decisions and direction of the District Council. The DDC implements its programme within the framework of district periodic plan. We have 75 districts i.e. 75 district development committees are in functional now. 1.5.2 Municipalities
A municipality is usually an urban administrative division having corporate status and usually powers of self-government or jurisdiction. The term municipality is also used to mean the governing body of a municipality. A municipality is a general-purpose administrative subdivision, as opposed to a special-purpose district. Currently, there are 191 municipalities in Nepal. 1.5.3 Village Development Committees
It is the lower administrative part of district having with several VDCs, similar to municipalities but with greater public-government interaction and administration. Currently, there are 3,276 village development committees in Nepal. A VDC is further divided into wards; the number depends on the population of the district: the average is nine wards.
4
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
CHAPTER I Compilation of Sector Report OUTPUT 1 Citizen and Community Organization are empowered to Actively Participated and Assert their Right in Local Governance 1.1 Social Mobilization Social Mobilization is one of the major component of LGCDP which is more focused on the empowerment of citizens especially women children and disadvantage group by strengthening their institutions like Citizen Awareness Center (CAC) at settlement level and Ward Citizens Forum (WCF) at ward level of all VDCs and ward of Municipalities. It is aimed to engage these institutions through Local Service Providers (LSPs) in the local governance process to ensure the most disadvantaged groups are well informed about their rights and their demands are included in the LBs planning process. WCF is taken as the major vehicle for facilitating the community in settlement level planning process, social harmony, social reform and civic oversight functions. Hence, more focus is given in reformation of old WCF and formation of new WCF in all wards of municipalities. 1.1.1 Overall status of Social Mobilization (SM) Coverage:
LGCDP was begun one year later (2009/10) than the LGCDP programme implemented in the country (2008/09). Till the FY 2071/072 (2014/015), Social Mobilization activity has been implementing in all 328 VDCs (2944 Ward) and all 21 Municipalities (271 Ward). SM activities has been implementing in the technical support of 58 LSPs, 444 SMs and 30 D/MCCs in the region. Under this activity, 3210 WCFs and 468 CACs have been formed in VDCs and Municipality Wards; in which more than 74554 members, including 46% female, have been mobilized in community. Similarly, CACs in VDCs and Municipalities ward have been a good platform for more than 12666 members representing from 468 CACs. Out of total CAC members, 88% women represents from ultra-poor and under-privileged group. The CAC members are now being empowered and able to coordinate with VDCs and other service providers through REFLECT classes, training/exposure's in local level.
5
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
WCFs and CACs become the most bottom level structure of Local Governance. WCF and CAC have been gradually empowered through training/exposure with the support of SMs/LSPs at local level. /LSPs. WCFs with technical support from the trained social mobilisers have already played a significant role in local level planning process; especially in such transition period of Nepalese political situation. What is further needed is to get coordinated closely with VDC and locally available Line Agencies and other service providers for its institutional development and making WCF as entry point for all sorts of development intervention in local level. 1.1.2 Ward Citizen Forum (WCF)
WCF have been formed with the technical support and facilitation of SMs/LSPS at ward level. Thus, WCFs become the most bottom line structures of government in grass root level for local governance process. Till end of FY 2071/072 (2014/015), all together 3210 WCF have been formed. Out of total; WCF 2944 WCF formed at 328 VDCs ward and 266 WCF formed at 21 Municipalities Ward respectively. Almost all WCFs are gender friendly and socially inclusive as envisaged by the programme. The total members of WCFs are 74554. Among the total members 67922 members (36873 male 54% and 31049 WCF members at Mun. Level
WCF Member at DDC level
female 46%) are engaged at VDC level. Similarly
Female 44%
Male 56%
Female 46%
Male 54%
6632
members
(3684
male
56%
2948
and
female 44% are engaged at Municipality level. The ethnicity composition of members at VDC level comprised 20% Dalit, 9% Janajati/Madeshi/Muslim, and 69% are others. Similarly at Municipality level 23% Dalit, 20% Janajati, and 53% are others. During the reporting period 2727 WCFs have been reformed at 2680 wards of VDC and 46 ward of Municipality respectively. Altogether 26870 WCF members (male 55% and female 45%) were replaced. In addition, total of 236 new WCF are formed at municipality where has 211 WCF represents from new municipalities.
6
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
1.1.3 Citizen Awareness Center (CAC)
CAC has been established in each VDCs of the entire districts of the region (328 VDCs); in which more than 8 thousand members including 84 % female are directly involved and are taking participation in REFLECT class. The composition of CAC members seem to be inclusive as dalits represent 63%, Janajati represent 3% and remaining 34% is covered by other castes. Likewise in the Municipality as per policy of 1 CAC formation in each ward, CACs have been formed in 140 wards out of total 271 wards of Municipalities. Out of total 3923 CAC members, 97% are female; which Seems quite encouraging. Social classification wise membership distribution in Municipalities CAC is of 58% dalit 12% Janajati and CAC Member's at VDC level
remaining 30% are others. During the reporting
Male 16%
period the coverage Municipality ward of Dhangadi, Depayal Silgadi, Dashrathchand, Amargadi, LamkiChuha has been completed. Besides, there are other
Female 84%
agencies who have already been working in transformational SM approach and have formed
CAC Member's at Mun. Level
Male 3%
CACs. CARE/RRN-CSP, UNICEF and Action Aid are the key implementing agencies who are working in various districts of the region. Altogether 451 CACs
Female 97%
have been formed by respective agencies like CARE/RRN-CSP: 373; UNICEF: 41 and Action Aid: 3 respectively.
7
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
1.1.4 Capacity Building under Social Mobilization:
During the reporting period Till the end of
FY
2071/072
(2014/015)
the
following training has been organized by RCU and NSP/RDTC to enhance capacity of Social Mobilizers, Local Service Provider SM coordinators, Members of WCFs and CACs, Members of Political Party/IPFC, VDC secretary and LBs staff in the local level planning, Reflect Social
LLP Training participants at Beldadi VDC, Kanchanpur
Mobilization, Business plan development, EFLG, CFLG, GESI Crus-Cutting issues. Total of 56 events of LLP training were conducted in 2 districts (Kailali+Kanchanpur) 49 events and 7 events in municipalities. Altogether of 2216 participants including (43% 956 female) representatives from WCF/CAC members, IPFC members and political parties' were trained on Local Level Planning and civic
LLP&SM Training Participants
oversight process. Out of the total participants,
there
were
68.14%
participants from WCF, 23.51% from IPFC member of VDCs/political parties and remaining 8.34% were from CAC.
3000 2000 1000 0
No of Participa nts Series1 2770
Male
Female
2258
512
By ethnicity the Janajati 46%, Dalit 11% and remaining 43% were from others. As social mobilizes are the front lines of the programme for the transformational social change in the community, the capacity of the social
mobilizes
should
be
upgraded
periodically. In this regards 18 events of Social Mobilization Training were conducted in 9 DDCs including 21 Municipalities support of NSP/RDTC Doti. Altogether 517 participants
SM Training in RDTC Doti
8
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
from SMs, LBs staffs, SM coordinators of LSPs have participated in the training. Out of total participants 41% were female. During the training the concept of Transformational Social Mobilization, UCPA, LIP/CIG and concepts of CFLG, EFLG, GESI, and accountability tools were widely discussed and practiced. Before conducting the LLP and SM trainings at district level a Master ToT was conducted at central and regional level to develop the Resource Person. The resource persons were nominated by the concerned districts. During the M-ToT altogether 37 RPs including 22% female has participated in LLP and SM training. 1.1.5 Access of WCF in LBs Planning Process.
During the F/Y: 2071/072, all LBs (VDC, Municipality and DDC) have
Participants Detail at Ward Level Planning
prepared their annual plan for the F/Y: 2072/073 as per the provision made in Local Bodies Resource Mobilization
M 71896
52345 15471
and Management Guideline 2069. Almost all 14 steps of planning
F
VDC
9010
MUN
process has been applied while preparing the annual plan. More than 86% LBs has conducted ward level planning workshop and total of 148722 citizens with 41% female have participated. Similarly during the council of LBs (DDC, Municipalities and VDCs) total of 45990 citizens with average of 40% female have participated. The ratio of female participants, Municipalities seem higher in comparison of DDC and VDC. During the year total approved projects were 12278 by LBs council (VDC/Municipality) out of 30858 projects demanded by WCFs. The ratio of demand vs approved is 40% only. The percentages show that less projects approved by LBs in comparison of demanded projects by WCF. However, the total cost of projects Rs. 1037773193 is allocated by LBs in their annual plan is higher in comparison of LBs annual grant usually received from government. Similarly the total number of projects included in LBs annual plan which is demanded by WCF. So the actual ratio of included projects in LBs annual plan is more than 85%.
9
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
The impact of LLP training was seen
positive
in
Kailali
and
Kanchanpur district. The demand vs approved projects ratio is calculated more than 90%. While analyzing targeted sector projects (women, children and DAG) the average percentages of approved projects is 44% of total
CAC members demanding to VDC Secretary
demand projects through WCF where has women 38%, children 51% and DAG 43% by the local bodies respectively. Similarly the average of approved budget for target group is 36% of total budget where has women 11%, Children 10% and DAG 15% respectively. The above figure shows that WCF has played vital role in LBs planning process. WCFs are now gradually becoming grass root level institution to claim their right and addressing their demands in local level planning process. 1.1.6 CAC Graduation Status:
The major objective of CACs assessment is to promote self-awareness, participation and empowerment, to visualized outcomes, even illiterate people can identify the real gap between what they have expected before and the real situation in the ground now. Programme aims to categorize the CAC which were formed in the programme. All VDCs and Municipaliites were analyzed based on 14 criteria's of SM Guideline 2071. The key
Status of CAC Maturity Medium 9%
Weak 3%
Exercise in spider web -CAC graduation
Moderat e 88%
dimensions of analyzing CACs were CAC functional status, level of awareness, transformation, linkage and resource mobilization and empowerment. The assessment was conducted with CAC members in
10
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
participatory way by using the spider web tools facilitated by social mobilizers. The situation analysis result shows that out of total 438 CAC 88% (385) falls in satisfactory, 9% (40) falls medium and rest 3% (13) falls in weak category.
1.7 District/Municipal Social Mobilization Coordination Committee
During the year all 9 DDCs and 21 Municipalities has formed D/MSMC and functioning well. The main purpose of this
Status of D/SMSCC and LSPs No. of D/MSSC
36
committee is to support the successful implementation
of
social
mobilization
activities by coordinating the SM agencies
21 22
9
DDC
No. of LSPs
Municipality
working in the district. By the end of this fiscal year the total number of members involved in D\MCMSC are 288 out of which 30% are female. D\MCMSC has conducted 107 meetings and made 300 decisions. The major decisions comprised contract extension of SMs, recruitment of new SMs, LSP selection and their contract extension. Moreover, D/MSMCC members were involved monitor the WCF/CAC activities and LBs activities as a whole in the local level. The RCU team is frequently backstopping and about the role and responsibilities of D/MSMCC in local level. 1.1.8 Local Service Provider (LSP)
The hiring process of LSP in far-west region was successfully completed. The total of 58 LSP were hired and contracted (36 LSP for 9 in DDC and 22 LSPs for 21 in Municipalities) The role of LSPs found more effective in regular monitoring of overall social mobilization activities and providing backstop to their Social Mobilizers, WCF/CAC for smooth operation by organizing the cluster level meeting and sharing of best practices. The LSPs has been contributing effectively to undertaking of UCPA database, selection of SMs, cluster wise monitoring and CAC graduation, Similarly, the support and role of LSP found very crucial in formation of new WCF and reformation of WCF in to creating conducive environment of social mobilization process by
11
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
coordinating political parties, civil society organizations (CSOs) and other stakeholders at local level. 1.1.9 Social Mobilizers
Out of total 462 SM post only 444 SMs are working and remaining 18 post are vacant and in hiring process. The ratio of male and female 50%. In the new Municipalities 138 ward has no provision of SMs. However, the available SMs
Existing Social Mobilizers
Fema le 50%
are is
Male 50%
concerns Municipality are working for all wards.
The role of SM is increasing day by day. In addition to his/her regular assignment they are working as key focal person for VDC. All the government and non-government agencies are closely coordinating SMs before implementing the program in VDC and ward level. 1.1.10 Conduction of Underlying Causes of Poverty Analysis (UCPA) in wards or VDCs
Programme has made mandatory to analyzed UCPA for all VDCs and Municipalities to identify the socio-economic condition of community/settlement. The process of UCPA is basically applied three steps with the participation of local people. a) Preparation of Access Resource Map of VDC/ wards, b) Preparation of Social Resource Map and c) Preparation of Wellbeing Ranking of Poor Settlement. 171 wards of Municipalities and 220 VDC are completed so far. The remaining Municipalities ward and VDCs are in process of completion. Harmonization and Linkage of CACs: RCU Dhangadhi has initiated to gear-up better coordination and linkage with different stakeholders to linkage CACs for better institutional development and increase income generating activities. Similarly D/MSMCs have been also made policy to make coordination with SM agencies through the integrated approach. So far total 1910 members of 110 CACs has been aligned with cooperatives and able to raise their demands and pull resources from other stakeholders. Similarly CACs members have taken technical and financial support from LBs, Local level Cooperatives, NNSWA, Community Forestry, PAF, Agriculture service, Livestock service, MEDEF, USAID-PACT for the making of CAC building, toilet construction, temple construction, drinking water, irrigation, goat raising, poultry farming, small credit grant, improved vegetable seed, alignment with cooperative membership, skill development in planning process and so on.
12
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
1.2 Livelihood Improvement Programme Since FY 069/70 onward LIP program has been implementing for poor of poorest members of CACs in order to address the needs and bringing changes in their economic and livelihood status. The program has initiated to provide LIP grant support of Rs.100, 000 to each CACs. Till the date total (069/70 to 071/72) Total of 424 VDCs and Municipality CACs have received LIP grants. Only 176 CACs are remaining to receive LIP grants. The total benefited members of those 424 CACs is 2004 so far. During the last of this fiscal year 134 CACs received LIP grant, among them only 29 CACs are able to mobilize among 144 members due to last hour of the fiscal year and work load of completion the CIG projects in CACs. LIP training also could not organize timely and there was being delayed on releasing budget to CACs. CACs are now in the condition to process of mobilizing the fund with preparing Livelihood Improvement Plan and individual business plan. Total 407 Social Mobilisers, 32 local bodies staff i.e. VDC secretaries/POs and 58 LSP coordinators have received training on Livelihood Improvement Program (LIP) and its mobilization procedure. During the FY 071/72, total 140 members of different WCFs and CACs received different skill related to income generation trainings from different stakeholders. Table 1: Details of LIP in Districts and Municipality
Local Bodies
Districts (9) Municipalities (21) Total
Total Number of LIP 315
Total
Total
Benefited CAC members
Amount Male
Expended 32000000
269
Female 1441
1141
10900000 109
593 43 550
424
42900000
312
2004
1691
Table 1 Source: Data collected from SMs LBs wise data is attached in Annex
13
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Among total members 2004, female are 1691(84%) and male are 312 (16%). The Benefited CAC member's by Sex figure shows that female members received Male more LIP funds. This is due to the 16% Municipalities, where more than 97% members are female. During the reporting period Sum of Rs. 42900000 has been disbursed to the CAC members. Out of the Female 84% total is Rs 32000000 (75%) amount is allocated for VDCs and remaining amount Rs.10900000 (25%) is allocated for Municipalities.
During the reporting period different income generation implemented
activities by
the
were CAC
identified members
and in
consultation with SMs. Among the implemented LIP activities more than 19 major core income generating activities i.e. goat raising, pig raising, poultry, other livestock (buffalo/Cow/Rabbit etc), vegetables, Mushroom, cash crop (ginger), other
14
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Retail/Tea/Cosmetic/Meat Shops, Furniture, Hair dressing and Beauty Parlor, Catering, Tailoring,
Metal
workshop/Aran/,
Candle,
Carpet,
Lather
Shoe
making.
Number of LIP Shemes Lather Shoe making
6 3 1 4 1
Candle Furniture
62 37 26 3 6
Tent House/Catering Bamboo products Retail/Tea/Meat/Cosmetic Shops
191
Mushroom farming
8 3
Rabbit farming
7
68 53 Poultry farming
119 144
Goat farming
1262 0
200
400
600
800
1000
1200
1400
Analyzing the data, most of the members i.e. 1262 schemes more than 62% members invested the grants in goat raising. The second priority businesses are pig 144, Poultry 119, Vegetables 119, Small scale shops of retail/Tea/Meat/Cosmetic etc, Tailoring and Metal/Iran works. With those other businesses examples are also started by CACs members i.e. Hair dressing, Beauty parlor, Bamboo products, Catering, Carpets, Candle and Auto Riksa. The LIP grants are revolved among members of CACs. The short term revolving schemes found as daily income generating types of businesses like different types of shops (grocery, sewing cutting) then after vegetables poultry, mushroom. In activities like raising goats, pigs and growing cash crops, which are taking as business taking longer period to have income but still members are able to manage refund in instalments and most of members are ready to invest in those business. Raising animals are taking as easy business where women from CACs can run together with households and farms works.
15
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Analysis the total 290 LIP grants provided during F/Y 069/70 to 070/71 and its utilization, the total grants of Rs. 29000000 is mobilized among members of CACs and currently the total capital of this grants is reached to Rs. 37800000 and revolving within the members of CAC. The interest rate is 6% to 10%. However RCU have suggesting CACs the interest rate should not more than 6 percent. CACs are making their own decisions hence there is no much cases about loan overdue and bad debt but there is very necessary to provide skills on loan mobilization to those CACs. During the year due to the Goat diseases at far-west region more than 15 CACs has completely lost their Goats and getting problems for repayment. INDICATORS, BASELINES AND TARGETS
Output
OUTPUT 1: Citizens and community organizations are empowered to actively participate and assert their rights in local governance
INDICATOR (for outputs only) or ACTIVITY
TARGET (for 15 July 2015)
VDCs and Municipalities conducted ward level planning workshop to prepare annual plan as per guideline.
85% of VDCs and Municipalities conduct ward level annual planning workshops in 2014/15
100% LBs (328 VDCs and 21 Municipality) has conducted ward level planning.
Ward level planning workshop with documented participation of women, children and DAG.
80% ward level planning workshops documented participation of women, children and DAG in 2014/15
83% LBs (272 VDCs and 17 Municipality) has made document of women, child and Dag participants.
CAC members engaged in Livelihood Improvement Programme (LIP).
-1830 CACs will receive LIP support in 2014/15CAC graduation institutionalized
424 CACs Out of total 468 existing CAC
WCF are empowered to actively participate and assert their rights in local governance
60% of WCFs under Category A or B by the end of 2014/15
WCFs category practic has not started yet.
0.1.Strengthen the social mobilisation institutions
- At least 50% of D/MSMCs hold regular trimester meeting - LSPs hired in all districts by 2nd trimester
ALL 30 D/MSMCs has made 107 meeting and 300 decisions. However in 2nd trimester 50 LSPs has hired and rest in 3rd trimester. In total 58 LSPs are working
ACTUAL ACHIEVEMENT (as at 15 July 2015)
16
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
0.2.Ensure consistent methodology and quality assurance of Social Mobilisation implementation
NSP role fully resourced and operating satisfactory in line with the signed MoU
LDTA is rolled out to implement the capacity development activities.
0.3.Clarifying WCF mandate
Âź of WCF members are replaced focused on inactive members
36% (26870 )WCF members are replaced.
0.4.Mainstreaming accountability and monitoring at the local level
More than 50% of WCFs are engaged in monitoring and oversight functions by the end of 2014/15
36% WCFs are engaged in monitoring and oversigh funcions
0.5.Establish CAC graduation and expansion modality
- 2,000 CACs graduate to self-sustained cooperatives- 2,000 replacement CACs established- 2,000 additional CACs with new/aligned funding
88% (385) CACs are graduated. 1910 members of 110 CACs aligned with cooperatives and are able to capture the resource from other stakeholders.
0.6.Implement LIP activities for graduated CACs
1,932 CACs receive LIP support, helping at least 15,000 households to start income generating projects
424 CACs implemented LIP out of 468 CAC. 2004 HH benefited
0.7.Harmonisation of Social mobilisation programmes
- All DDCs hold trimester consultative meeting with SM agencies- At least one new national MoU signed with MoFALD
LBs of Baitadi and Darchula has conducted meeting with SM agiences and NGOs desk
0.8.Improve effectiveness of targeted (35%) grants to women, Children and DAGs
At least 80% of local bodies meet or exceed the minimum provisions
100% LBs the meet the 35% targeted grants
17
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
OUTPUT 2 Accountability Mechanism for Local Governance are in place 2.1 Local Governance & Accountability Facility (LGAF) Local Governance and Accountability Facility (LGAF) is a semi-autonomous body to improve governance at local level by coordinating local bodies and citizens through greater participation of the citizens on the planning, implementation, monitoring process. Its main objective is to support and institutionalized the downward accountability system in local level. Then CSOs has been assigned to implement the programme from February 2015. Out of 9 DDCs 8 DDCs and 14 Municipalities have been supported by 8 CSOs in the region. Out of 328 VDCs 62 VDCs and 169 Municipalities ward have been covered so far. LGAF provides assistant to the CSOs for the promotion of local governance & good governance system. The CSOs facilitating on the three intervention areas; Coordination with local bodies, Facilitation and Monitoring of the service delivery system. After agreement with CSOs, LGAF provided 4 days capacity development training to project coordinators, focal persons, accountability officers & sub-engineers about the importance of LGAF on the local bodies, Local self-governance act/regulations-1999, local bodies resource mobilization & management guideline-2069, public hearing, public auditing, social auditing guideline-2067, code of conduct on the CSOs for the successful implementation of programme. Similarly, CSOs organized orientation programme to LBs officials, political parties' leaders, WCF/CAC members, Social mobilizers, VDC secretary and other stakeholders of respective DDCs, VDCs & municipalities. LGAF programme has supported to enhance the capacity of LBs to make accountable towards citizen and maintaining transparency and promoting downward accountability in LBs. The LBs have already started/committed to conduct planning, monitoring & evaluation processes by following participatory methods with inclusive participation & in compliance with the Grant Guidelines. The local communities/citizens have started field verifications of the progress as shown in the documents by the local bodies and have become more vocal in expressing their opinions and demands. Public participation on CSO activities detail below:
18
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Total SN
Project Activities
Male
1
District Level Orientation
2
Municipality Level Orientation
3
VDC Level Orientation
4
District Level Public Dialogue on the state of compliance of LBs
5
Municipality Level Learning ,Sharing & Review Meeting
6
VDC Level Learning, Sharing & Review Meeting VDC Level One Day Capacity Development Training for the members (WCF,CAC & SM on public Audits) Municipality Level One Day Capacity Development Training for the members (WCF,CAC & SM on public Audits)
7 8
9 10 11
12
One day awareness on citizen entitlements & civic responsibility at community level Other activities Sharing meeting Sharing of findings on compliance of infrastructure projects being implemented ( at least 2 Projects') V/MSMC/CAC, VDC staffs and political representatives, WCF (VDC=9 and Municipalities
Total
In
addition,
DDC-VDCs
Female
225 269 1169 251 1079 2265
23 129 392 42 279 926
1322
575
381
316
1095 214 348
864 247 139
2064 10682
706 4638
and
Municipalities are more aware of
250
conducting the Social audit, Public
200
hearing and Public audit at local level
230 190
150 100
which
directly
support
the
establishment of governance system. Figure below illustrates that DDCVDCs and Municipalities conduction
50
19 6 12
-
4
9
9
Social Audit VDCs
Public Audit Municipalities
Public Hearing DDCs
of Public audit, Social audit and public hearing status of LBs.
19
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
SN 1 2 3 4 5 6
7
8 9
Description
VDCs
Social Audit
Municipalities
-
Public Audit
190
Public Hearing
230
Number of public audit completed projects Number of LB's where civil society led compliance monitoring introduced Number of WCFs in which at least one member received orientation on monitoring and oversight function Number of WCFs that engaged in monitoring & oversight function in the current fiscal year Number of WCF's that perform oversight function (public audit) Number of LSPs involved in social mobilization oriented on accountability tools in the current fiscal year
1750 62 560
1358 736 36
DDCs
6
4
12
9
19
9
989
780
14
9
168
-
287
-
168 2200
Table 2 Information of
INDICATORS, BASELINES AND TARGETS Output
OUTPUT 2: Accounta bility mechanis ms for local governan ce are in place
INDICATOR (for outputs only) or ACTIVITY WCFs start practicing social accountability tools in monitoring of local governance actors’ activities Civil society led compliance monitoring in 75 districts National accountability initiatives are closely aligned
Local Bodies grievance system established 2.1. Establish new LGAF modality
2.2. Civil society led compliance monitoring in 75 districts
TARGET (for 15 July 2015)
ACTUAL ACHIEVEMENT (as at 15 July 2015)
85% of LBs compliant with public hearings and social audits guidelines
9DDC,62VDCs&14 municipality are completed
CSOs operating in 75 districts and report progress regularly (LGAF 66; SALG 9; alignment with PRAN) - Develop training and IEC materials, and experience sharing with PRAN/SALG - Introduce alignment activities with (USAID) Sajhedari programme Establish tracking system of grievance cases in LBs - LGAF NC meet at least once every trimester - LGAF institutionalised in Good Governance Section CSOs operating in 75 districts and report progress regularly (LGAF 66; SALG 9; alignment with PRAN)
9 DDC ,14 Mun & 62 VDCs
LGAF/CSOs (LGAF,8 District & SALG 1 )
Focal person assignment on the 9 DDCs
9 CSOs are working in the 9 districts
20
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Output
INDICATOR (for outputs only) or ACTIVITY
TARGET (for 15 July 2015)
2.3. Consolidate Social Mobilisation process of LGCDP II by integrating accountability tools
30,000 (85%) WCFs oriented on social accountability tools
2.4. Align national accountability programmes with LGAF
- Develop training and IEC materials, and experience sharing with PRAN/SALG - Introduce alignment activities with (USAID) Sajhedari programme Public hearing compliance: - VDCs: 3000 (83%) - Municipalities: 100 (85%) - DDCs: 75 (100%) Social Audit compliance: - DDCs: 60 (80%)
2.5. Improve grievance mechanism
ACTUAL ACHIEVEMENT (as at 15 July 2015) 14 municipality and 62 VDCs WCF & CAC are oriented on public audit & oversight monitoring
62 VDC,9 DDC and 14 Mun
Downward Accountability
OUTPUT 3 Local Bodies Access to Resource Increased LBs are supposed to increased resources either from receiving more funds form central level agencies or increased their own internal resources by tax and harmonizing local tax system with national level tax system. The programme has made efforts to increase the internal revenue of LBs. An internal review management training at DDC level and integrated property tax system training at municipality level was held during the reporting period. However no countable progress has been made to increase the resources in the region. Only 3 (Kailali, Kanchanpur and Doti DDCs), 14 municipalities and 42 VDCs has increased their inter review by 10%. MoFALD has taken initiation to major the performance of LDOs, Eos which also helps to improvement the LBs resources.
3.1 MCPM of District development committee (DDC) In this fiscal year the performance of MCPM went down in compression last year. The table below shows that only Dadeldhura and Kanchanpur DDCs has increase additional grant by 15% and 10% respectively. The remaining 7 DDCs are in position of deduction additional grant by 15% to 20% respectively. SN District 1 2 3 4 5 6 7 8 9
Fiscal Year Remarks 2067/68 2068/69 2069/70 2070/71 Bajhang 57 58 73 47 20% Deduction Kanchanpur 65 57 69 68 10% Additional Grant Dadeldhura 49 52 68 71 15% Additional Grant Doti 58 61 63 35 20% Deduction Achham 41 61 59 41 All Deduction Baitadi 55 57 58 36 20% Deduction Kailali 59 58 54 56 15% Deduction Bajura 51 61 54 31 20% Deduction Darchula 46 56 48 28 All Deduction Table 3 DDC MCPM Status
21
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
3.2 MCPM of municipalities The performance of MCPM during the reporting period is not satisfactory in compression of last years. The table below shows that Dhangdhi, Bheemdatta, Dipayal-Silgadhi, Amargadhi and Dashrathchnd municipalities has loosed their performance and grant deducted by 10% to 20%. However, Tikapur municipality has increased by 10% additional grant during the year. SN MUNS 1 2 3 4 5 6
Fiscal Year Remarks 2067/68 2068/69 2069/70 2070/71 Tikapur 76 78 72 74 10% Additional Grant Dhangadhi 73 75 72 66 10% Deduction Bheemdatta 52 64 68 61 15% Deduction Dipayal Silgadhi 53 57 68 50 20% Deduction Amargadhi 45 69 60 51 15% Deduction Dashrathchand 42 65 51 45 20% Deduction Table 4 Municipality MCPM Status 3.3 MCPM of Village Development Committee (VDC)
Table below shows comparison of the MC of VDCs of the far west region. In the FY 2071/72, there were 117 VDCs failed in MC. Table below show details: SN District
1 2 3 4 5 6 7 8 9
Bajhang Kanchanpur Dadeldhura Doti Achham Baitadi Kailali Bajura Darchula Total
Total no of VDC 42 13 20 50 62 62 42 27 41 328
Fiscal Year
Remarks
VDC failed in MC
VDC failed in MC
VDC failed in MC
VDC failed in MCPM
2067/68 1 1 1 0 2 5 1 1 2 14
2068/69 3 2 3 6 21 7 4 2 5 53
2069/70 4 2 2 3 9 17 3 8 12 60
2070/71 15 0 11 11 3 39 4 11 23 117
Table 5 VDC MC & MCPM Status
22
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
OUTPUT 4 Public Finance Management System Improved The output 4 basically aims to improve efficiencies and effectiveness of MoFALD, local bodies and other governance in the field of financial management system to reduce the fiduciary risk at centre and local level. The programme has focussed to support process of planning monitoring, implementing, budgeting and reporting system. The programme have supported to conduct VDC accounting software training and strengthen internal audit section in all nine districts. In this training 283 VDC staffs have been trained. As per the LBs report, 57 VDCs have adopted VDC accounting software and made functional, 45 VDCs have introduced simplified expenditure system from this fiscal year. Similarly, four municipalities and nine DDCs have been practicing of e-bidding system and 14 Municipalities and nine DDCs have prepared annual procurement plan in this year. These system started by LBs have been supporting to reduce fiduciary risk to some extent. Indicator VDCs adopted VDC accounting software and made functional
Target 1000 National wide(8 last year)
Achievement Remarks 57 Dadeldhura, Baitadi, Doti, Kailai Kanchanpur 0
Municipalities that adopted accrual accounting system and made functional Number of DDC/Municipalities initiated/practiced e-bidding for procurement
6 National wide NA
9 DDC and 4 municipality
Number of LBs (DDC & municipality ) that prepared procurement plan in the current fiscal year Number of VDCs in which trained staff on accounting maintain VDC account
75 DDC and 130 Mun
9 DDC and 6 Mun
NA
283
Dashrathchan, Sanfebagar, Amargadhi and Dhangadhi Mun. 6 Mun. comprised out of 58 283 VDCs out of total 328
4.2 GESI responsive Budgeting and Auditing Practices at LBs 4.2.1 GESI and GRB adoption: All the nine DDCs have formed Gender Responsive Budget committee (GRBC) and Gender Equality and Social Inclusion Implementation Committee (GESIIC) based on GESI policy and MoFALD letter. The GRBC and GESIIC committees are not yet formed at VDC and Municipality level due to the draft form of strategy. Despites, approved GRB and Social Inclusion budget formulation and auditing guideline 2068, its implementation in the LBs seems very poor. Even DDCs have not applied its tools and indicators so far. Only the 35 percentage amount allocated to the target group (women, Children and DAG) by LBs. However, in this year seven DDCs and three municipalities have endorsed GESI agendas in the District Periodic Plan and annual plan for mainstreaming the issues.
23
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
4.2.2 GESI auditing progress:
This year MoFALD/LGCDP II supported NRs. 120,000 for the five districts namely Achham, Bajura, Baitadi, Dadeldhura and Darchula and two municipalities Dipayal-Silgadhi and Dashrachchand in this region. Except Darchula all the targeted LBs have conducted GESI audit. In addition, Kanchanpur and Bajhang DDCs have conducted GESI audit from their own internal fund. In the case of FWDR six DDCs out of nine and two old Municipalities have conducted GESI audit. This is one of the major achievement of LBs are gradually internalized the GESI policy and guideline. The spider diagram shows overall progress Progress of Gender audit in DDCs status of the GESI and GRB indicators at DDC and Municipalities and Municipality. As per the auditing report, Local Bodies Policy/guideli all the LBs seemed strengthened in the good ne/manual National Capacity governance indicators in an average. Among 15.0 Policy/commit Development the DDCs Kanchanpur and Bajura have 10.0 ment plan of Local received highest (10/10.7) score and implementa… Bodies 5.0 Human Dashrathchand Municipality has got less Resource Target 0.0 Development Program score (6.5) only among them. Similarly, target /Coordinatio… programme indicator in all the DDCs and Program Good Planning/Impl Municipalities seems moderate of which Governance ementation/ Kanchanpur DDC and Bajhang DDC have got Monitoring/… Internal quite good marks (8/7.9) and Baitadi DDC, structure Achham DDC and Dasharathchand MUN have received marks Full marks got less marks (6/6/6.5) in the same indicator. Furthermore, all the LBs seemed poor in remaining indicators whereas the status of human resource development/coordination/collaboration indicator appeared very poor in terms of GESI and GRB. Therefore all the LBs needs more exercises for further improvement.
24
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
OUTPUT 5 Institutional and Human resource Capacities of LBs and Central Level Agency Involved in Local Governance 5.1 Capacity development Capacity development is a major cross-cutting area of the programme. CD activities are mandated to LBs for making more accountable and effective service delivery through institutional and human resource development. Therefore, programme have supported on demand based and non-demand (Contextual) based CD activities to the LBs. Local Level Planning training in two districts was directly supported by MoFALD, in this training 1685 WCF member were participated of which 46% were women. And 427 Social Mobilizers have received SM training from all districts. The training was organized by National Service Provider/LDTA. The following table shows the detail of capacity development related training during the reporting period. SN
Training/workshop/orientation
Level (RL/DL/VL)
# of events
Participates
1 2
Social Mobilization TOT Social mobilization training
RL DL
1 18
24 517
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Review workshop of CSO/LGAF Social Security training Municipal Website training GESI training CFLG Orientation GESI training Orientation on building code CFLG orientation GESI training VDC Accounting Software RTI training to VDC secretary CAC graduation training to SM MCPM orientation Revenu management orientation Community Mediation
RL RL RL RL Muns Muns Mun. level DDC level DDC level DDC level
1 1 1 1 7 2 1
26 25 21 19 237 102 12 179 296 257 508 39 49 33 228 12 56
20 21 22
Web based Community Mediation Training Local Level Planning Process Training Orientation on Public Private Partnership LSGA Guied line Training
5 7
DL DL DL DL DL Mun Mun Mun
10 3 1 2 2 2
Total Female Male 6 18 213 304
61 36 41
25
2 2 2 4 92 78 0 38 195
24 23 19 15 145 24 12 141 101
41 343 15 11 7 64 1 21 28
216 165 24 38 26 164 11 35 33
6
30
4
37
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
ICT related training to municipality satffs Vital Event Registrationand Social Security Training
23 24 25 26 27 28 29 30 31 32 33 34 TOTAL of All Training
Mun Mun
Solid waste management Training CAC graduation Measurement Training Positive attitude Orientation to municipal level monitoring and supervision committee Vital Event Registrationand Social Security Training
Mun
IPT training , Surkhet MODA training Orientation of MCPM Orientation on building code Local Bodies Accountant training
Mun Mun Mun Mun Mun
Mun Mun
2 1
1
1 1
37
1 1
0
Mun Mun
45
11
11
34
0
1
14 7
23 4
0 0
0 0
0
1
0 0 0 0 2
2 4 0 0 18
0 1 1 1 1 1 1
1 2 4 0 0 20 2899
1207
1692
5.2 Information & Communication Technology (ICT) and Capacity Development of LBs LGCDP Phase -II provides the system, procedures, structures, tools and capacities to facilitating the transformation of the local bodes into local government entities. MoFALD and UNV have set up new polite initiative, 'University Youth ICT Volunteers' for LGCDP-II. This component aims to digitize the working procedure of government of Nepal as well as strengthen and maintain the IT infrastructure of LBs (DDCs/Municipalities). Under this initiation, total 136 volunteers are as 'ICT Volunteers' in each 75 and 58 Municipalities, 3 in the ministry (MoFALD) initially 2 years. For the more UNV Nepal has placed National UN Volunteers as 'ICT Expert' in each regional Cluster Unit (RCU) and 2 in Program coordination Unit. MoFALD/RCU coordinating ICT volunteers and their activities at local level. UNV is supporting on capacity enhancement of ICT volunteers working at different level. In the far-west region 13 ICTVs are working in 7 DDC and 6 old Municipality. During fiscal year 2071/72 (2014), MOFALD/LGCDP provided budget Rs.11700000 to all DDCs and 6 Municipalities to procure desktop sever, hybrid solar along with required networking devices and utilized received budget. The basic IT infrastructure setup are being utilized with optimize resources with the best possible. MOFALD/ LGCDP has also set up new server at National Information Technology Canter
26
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
(NITC), Singhadurbar, with support from UNV ICT Experts. The server is planned to host website of all 191 Municipalities, 75 DDCs and other future applications. This was initiated with objective to have uniformity and standard in websites and system LBs use, and to provide more flexibility in every aspect of system. Design, setup, configuration and support.
Key Achievements Activities
Progress Status
Remarks
Biometric Digital Attendance system
Biometric Digital Attendance system installed in Dhangadhi municipality office, ICTV of Dhangadhi municipality has taken full initiation of implementation of system.
ICT Survey
ICT survey of all LBs conducted with the support of ICTVs regarding the availability of IT resources and capability of handling these resources by LBs staff. ICT survey is one of the major tool which supports E-governance.
Audio of Notice Board
Audio of notice board has been implemented in all DDC and 5 Municipalities (MUN:Dhangadhi, Bhemdatta, Amargadhi,Dipayal Silgadhi)
Uniformity of LBs Websites
Uniformity in website of 6 MUN (Dhangadhi, Tikapur , Bheemdatta, Amargadhi, Dipayal Silgadhi and Dasthrathchand) successfully completed. Also proved website training to ICTVs and Information officer of each municipality. 14 new MUNs websites is ongoing on uniformity manner. 9 DDC new website template is ready and plan to implement in new FY 2072. All LBs websites are hosted at GIDC/NITC and complete ownership of LBs.
Official Social Media
All ICTVs created official Facebook page for respected LBs where they work.
WBRS
MIS
All LBs timely submitted WBRS reporting due to fully supporting of ICTVs. Weakness & feedback is provided by ICTVs on WBRS which is very helpful for VDC module of WBRS. ICTVs had collected basic internet connectivity ides of VDC level. WBRS BHAG-2 Entry technical supported by all ICTVs of their working LBs. DDC kailai and its VDCs started online MIS this FY. Dhangadhi MUN implemented MIS this FY. DDC kanchanpur, Achham, Bajhang and Bheemdatta in final stage of MIS implication.
27
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
Group SMS
DDC Doti stared Group and web SMS for mass communications.
Wi-Fi free Zone
DDC Doti had Wi-Fi free areas for public access.
Office CCTV System
DDC Bajhang implanted CCTV for office security as well performance of LBs officials.
ICT support on Regular office work
Regular IT support by ICTV their duty station LBs.
GIS MAPs
Hybrid Soar Installation
GIS of all LBs has been design and updated. Political boundary map. Maps of all new municipality. Other resource maps. LSP cluster Map. Update social and resource map. Resource and social map of all VDC of Doti District updated by ICTVs of Doti DDC. 9 DDC and 6 MUNs successfully installed solar system with technical support of ICTVs.
District Fact Sheet
Updated district fact sheet designed by ICTV DDC kailali.
ITVS of DDC Doti, Bajhang & Bajura are fully support on data collection of Bottleneck analysis system of MoFALD.
Capacity building training:
Organized 3 days capacity building training on Internet and application to DDC staffs at kailali in two events. Organized 20 days capacity building training on Internet and application to Dhangadhi MUNs staffs at kailali. One month basic computer & internet training for LBs staffs is ongoing at Dhangadhi municipality. 7 days basic Computer and application training completed by DDC Doti for LBs staffs. 4 days basic computer and internet training for DDC staff at Bajura DDC. Upgraded Operating System and anti-virus upgraded operating system and antivirus. Installed LAN intra network at DDC kailali and Dhangadhi MUN office. File and Printer Sharing. In this FY DDC Kailali, Doti and Bajura and MUN Dhangadhi and Tikapur conduced IT for LBs officials for improved for IT knowledge and skills. Graphs below show basic IT status of LBs officials.
28
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
IT Skill of Municiaplity staffs
DDC Staff IT Status
20 17 12
10
12 12 78
77 33
Number of employees that can use internet, email
17 15
4
44
3 1
21
11
Number of employees that can use office package Number of employees that can un/install software/drivers
21 18 10 7
18 16
18 14
8 5
7 4 3
11 10 11 9 8 8 9 910 7 7 6 55 44 4
8 5 22
Number of employees that can troubleshoot hardware/ problem problems
5.3 Demand Based Capacity Development Capacity development (CD) is a major cross-cutting area of the LGCDP II. All the LGCDP II activities needs CD inputs and also many of its activities have a significant element of CD. Most of the social mobilization programme have a CD activities. Similarly, CD activities more need in to the Local bodies for making LBs accountable towards people, effective service delivery and responds to local demands. Therefore MoFALD supported on many CD activities to the LBs. Basically, MoFALD have supported on the institutional capacity development activities and human development activities. The MoFALD/LGCDP II supported directly to the LBs, through LDTA and RCU as well. This year the programme supported on demands based CD activities along with the regular activities. In the context of Far Western Region the programme supported to two DDCs namely Darchula and Kanchanpur out of 9 DDCs and five Municipalities (Api, Belauri, Attriya, Dashrathchand and Dodhara-Chandani) out of 21 Municipalities. All these LBs have received some budget for the CD activities and also LBs should held result based effective programme through this budget. Achievement of the demand based CD activities: All LBs have conducted CD activities according to the approved activities from MoFALD. MoFALD have allocated all about NRs. 1,840,000 for two DDCs and five Municipalities. Generally LBs conducted training and workshop about MCPM, local self-governance act and regulation, revenue or tax, web based, accounting training and cross-cutting. The targeted group of these activities were political parties, new/old Secretaries, LBs staff, SM, WCF and committee member. According to the available data respected LBs 570 people have benefited from demand base CD activities of
29
11
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
which only the 23% women have participated. Moreover, NRs.1806565 expended from allocated budget of 7 LBs. Similarly, from these activities LBs achieved following things: LBs staff and targeted participants have aware on the MCPM. Internalized web-based reporting system New Secretaries have aware on the accounting management system, Local-self act, regulation, guideline and modules. Indicator
Target
Number of VDC Secretaries taking responsibility of more than one VDC.
- More than 90% of VDCs are supported by a dedicated VDC Secretary - More than 90% VDC Secretaries in office for at least 6 months in 2016/17
Number of VDCs where VDC's secretary are in office for at least 6 months
LDO/EO transfer rate Update and digitise local bodies information systems
- 75% of Municipalities and DDCs adhere to two year tenure of EO/LDO in 2016/17 Unified web-sites for 9 DDCs and 21 Municipalities linked for web reporting
Achievement 45 Person (87%)
Remarks
233 (71%)
6 ldo/12 eo DDC = 0 and Mun 21 completed
OUTPUT 6 Access to and quality of local infrastructure and other socio economic administered by LBs are improved This output address and ensure their effectiveness and efficiency while delivering of services related to infrastructure development, vital events registration, social security payments and community mediation. In FY 2071/72, there are 10981 different projects completed in LBs (DDC 1435, Municipality 2544 and VDCs 7002) of this region, which have benefitted 2392853 population (DDC45105, Municipality 618154 and VDC 1323694) respectively the region. Similarly the total cost of the implemented project is Rs.1219395000 (DDC 252130, Municipality 372361, VDC 594904) Out of total benefitted population In DDC 54% from Disadvantaged groups. So far target group wise budget allocation and implementation is concerned; DDC by and large followed the blended guideline meeting the target as mentioned. Similarly 2544 different project completed in 21 municipalities which have 618154 population of the region. Likewise 7002 different project completed at 238 VDC of Far –west region the total population beneficed at DVCs projects 1323694. Details of infrastructure projects are shown in table and figure below. The government of Nepal has provision to distribution of social security allowances to senior citizen, single women, widow, disabled, endangered and Dalit children.
30
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
6.1 Status of Project Funding Matrix 6.1.1 District level
In FY 2071/72, there are 1435 different projects completed in nine districts of this region, which have benefitted 451005 population of the region. Out of total benefitted population 54% are from Disadvantaged groups. So far target group wise budget allocation and implementation is concerned; DDC by and large followed the blended guideline meeting the target as mentioned. Regional Scenario of Sectoral projects: DDCs
SN
Sector
1
Road, Bridge, Culvert
2
Irrigation
3
WASH
4
Education
5
Environment
6
8
Health Economic infrastructure Social Infrastructure
9
Agriculture
10
Promotional
7
Total
Projects
Total Cost ('000)
Municipalities Benefitted Populatio n
Projec t
Total Cost ('000)
VDCs
Benefitt ed Populati on
Projec t
Total Cost ('000)
Benefitte d Populatio n
441 123 63 140 35 138
114553 19377 8875 17086 8092 25584
151636 42728 37211 21476 14445 42926
534 228 144 160 123 306
134234 34238 8124 17518 26753 32941
214507 55233 22245 30676 25581 52303
918 708 646 719 516 642
136164 62266 54235 52685 46749 43738
248653 132137 109222 134518 99675 133108
115
18512
42345
258
30246
50846
591
34648
125127
101 71 208 1435
7306 4831 27913 252130
32281 18200 47756 451005
134 53 604 2544
14005 4599 69704 372361
38981 16722 111060 618154
705 622 935 7002
57451 60979 45990 594904
97219 128365 115670 1323694
31
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Sector wise Project Numbers 1000 900 800 700 600 500 400 300 200 100 0 Road,Bri dge,Culv Irrigation ert
WASH
Educatio Environ n ment
Economo Social c Agricultu Promotio Health Infrastru infrastru re nal cture cture
DDCs
441
123
63
140
35
138
115
101
71
208
MUNs
534
228
144
160
123
306
258
134
53
604
VDCs
918
708
646
719
516
642
591
705
622
935
Table 4: District-wise project, cost and benefitted population
SN 1 2 3 4 5 6 7 8 9
District Bajura Bajhang Achham Doti Kailali Darchula Baitadi Dadeldhura Kanchanpur Total
Number of Projects completed 46 158 133 72 182 68 139 64 573 1435
Cost NRs ('000)
Approx. Benefitted Population
57445 56550 25981 9556 75331 26666 12718 28250 34906 327402
20634 36130 47728 3344 49932 10437 15595 3178 50241 327402
DAG
NON DAG 20529 29170 45949 3053 48933 5477 15595 2863 43268 214837
Total 41163 65300 93677 6397 98864 15914 31190 4992 93509 451005
District-wise benefitted Population (DAG and NON DAG)
32
Rema rks
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Sectoral Investments in DDCs Projects Aggriculture 2%
Promotional 11%
Social Infrastructure 3% Economoc infrastructure 7%
Road,Bridge,Culvert 45%
Health 10% Environment 3% Education 7%
WASH 4%
Irrigation 8%
Regional Scenario of Sectoral projects under DDCs
60000 50000 40000 30000 20000 10000 0
Bajura Bajhan Achha g m 20634 36130 47728
3344
Darch Baitadi Dadel Kanch ula dhura anpur 49932 10437 15595 3178 50241
NON DAG 20529 29170 45949
3053
48933
DAG
Doti
Kailali
5477
15595
2863
43268
District-wise benefitted Population (DAG and NON DAG) comparison chart 6.1.2 Municipality Level
Altogether, 2544 projects were implemented through 21 municipalities of the region during the FY: 071/72. These includes community infrastructure, promotional and matching fund
33
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
projects. In twenty one municipalities’ total of 618154 populations were benefited through community infrastructure projects (54 % DAG). Similarly, there are 534 infrastructure projects completed in 21 municipalities, which benefitted the 618154 population of the region. The details shown in table and figure below. Table 5: Municipality wise project, cost and benefitted population
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
125 95 270 64 173
11844 17679 39630 8077 40105
88 150 95 183 82
10275 97804 2617 59495 8779
25138 44389 4224 47599 9985
No. of Projects
SN 1 2 3 4 5
Approx. Benefitted Population NON DAG Total DAG 6406 6035 12441 9322 12918 22240 19197 14925 34122 6916 6426 13342 23542 22951 46493
Municipalities Amargadhi Api Attariya Badimalika Belauri Bhajani Trishakti Bhemdatta Dashrathchand Dhangadhi Dipyal silgadhi Dodhara Chadani Ghodaghodi Jayaprithvi Jhalari Pipladi LamkiChuwa Mangalsen Parasuram Patan Punarbas Safebagar Tikapur Total
101 94 116 85 179 68 105 153 105 81 132 2544
Cost NRs ('000)
3324 44389 3880 44729 9679
28462 88777 8106 92328 19664
10390 14952 12426 9149 15803 13812 15193 8383 8232 9411 9314 7376 27033 28695 18326 35921 11945 11615 9933 8932 6816 15083 8592 9403 1649 12818 12132 30957 4516 3440 42063 15532 14556 503088 336199 287390
27378 29615 13292 16690 47021 23560 13634 17995 24950 7956 30088 618154
34
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Sectoral Investments in Municipalites Projects Promotional Activities 19% Agriculture 1%
Roads, Bridges & Culverts 36%
Health 4%
Social Infrastructures 8%
Education 9% Environment 7%
Economic Infrastructures 5%
Irrigation 2%
WASH 9%
Regional Scenario of Sectoral projects under Municipalities
Benefitted Population
NON DAG 46%
DAG 54%
Municipality benefitted Population (DAG and NON DAG)
35
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
6.1.3 VDC Level
At VDC level, there are 7002 small projects run by different community and users groups. It has served big population of the region i.e. 1323694 (60% are DAG). Details of the projects have been shown in table as below. Table 6: VDC wise project, cost and benefitted population
SN
District
No. of Projects
Cost NRs ('000)
Approx. Benefitted Population NON DAG Total DAG 97271 96274 193545
1
Achham
554
105088
2
Bajhang
706
92820
58841
24284
83124
3
Bajura
552
60240
56380
29170
85550
4
Doti
949
74787
98970
54223
153192
5
Kailali
836
125341
134849
129102
263951
6
Biatadi
1712
105081
85319
38979
124297
7
Darchula
840
59780
75533
74979
150512
8
Dadeldhura
457
36519
45625
37240
82866
8
Kanchanpur
396
50175
94335
92322
186657
7002
709830
747122
576572
1323694
Total
Sectoral investments in VDCs Agriculture 10%
Promotional Activities 8%
Roads, Bridges & Culverts 23%
Social 10%
WASH 10%
Economic 6% Health 7%
Irrigation 9% Environment 8%
Education 9%
Regional Scenario of Sectoral projects under VDCs
36
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
140000 120000 100000 80000 60000
40000 20000 0
Achha m 97271
Bajhan g 58841
Bajura
Doti
56380
98970
Biatadi Darchul Dadeld Kancha a hura npur 134849 85319 75533 45625 94335
NON DAG 96274
24284
29170
54223
129102
DAG
Kailali
38979
74979
37240
92322
6.2 Budget Expenditure vs Benefitted Population Cost Benefit i.e. Budget Expenditure vs Benefitted Population is a systematic approach to estimating the strengths and weaknesses of alternatives that satisfy transactions activities or functional requirements for any projects. In this scenario, Expenditure in local bodies i.e. DDC, Municipality and VDC are doing their expenditure as per guided by LBFAR. It consists of recurrent and capital fund from central government and local bodies too. The budgets are central grants, local revenue collection as well as donations from international partners. Total expenditure is the sum of all expenditure respective local bodies. It covers infrastructure development programs i.e. WASH, road bridges, culverts, irrigation etc and capacity development and other promotional activities i.e. child focuses, women focused DAG focused programs. Table: Expenditure and Benefitted population at local bodies
SN Local body
Expenditure
Expenditure
Benefitted
NRs ('000)
(%)
Population
Benefitted Population (%)
1 DDC
252130
21
359609
19
2 Municipality
372361
31
204306
26
3 VDC
594904
49
1288047
55
1219395
100
1851962
100
Total
37
Remarks
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
The table above shows the expenditure and benefitted population at DDC, Municipality and VDCs. Out of total expenditure DDCs,
Expenditure vs Benefitted Population
Municipalities and VDCs 21%, 31% and 49%. Similarly, out of total benefitted population
60
DDCs, Municipalities and VDCs have 19%,
40
26% and 55% respectively. The trend shows
20
55 49 31 26
21 19
0
in all local bodies amount spent is higher in
DDC
comparison to their benefitted population.
Municipality
Expenditure (%)
VDC
Benefitted Population (%)
Similarly, the figure above shows the expenditure vs population benefited i.e. cost benefit analysis. It is normally done after the completion of project, as taken DDC, Municipality and VDC a project, the above graph shows the project cost and its relationships. The outcome of the analysis will determine whether the project was financially feasible, or not.
Project vs Benefitted population The figure no. 8 below shows the numbers of projects, total cost and benefitted population of the fiscal year 20171/72 (2013/14). There were total of 10981 projects completed in three different local bodies i.e. DDC, Municipalities and VDCs. Number of projects exceeded while there are very small projects under VDC and municipalities for the targeted populations’ i.e. child – 10 %, women – 10 %, DAG – 15 %, matching fund. The volume of expenditure they are doing sometimes quite low. Apart from there are also small projects under local bodies for promotional and capacity development activities. It is mandatory to split the remaining 65% to 60 % infrastructure and 40 % promotional activities . Project, Cost and Benefitted Population
Project, Cost and Benefitted Population 1400000
1200000 1000000 800000 600000 400000 200000 0
No. of Projects 1435
Total Cost 252130
Municipalites
2544
372361
618154
VDCs
7002
594904
1323694
DDCs
Benifited Populatin 451005
38
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
6.3 Community Infrastructure Development Grants: This program has been implemented in CACs in name of SPMP since FY 070/71 and during FY 071/72, the program operational guideline is slightly changed and implemented as Community Infrastructure Development Schemes in CACs, where those schemes are more focused in directly income generation and livelihood development of CAC members. Till the date (069/70 to 071/72) total of 362 CACs received grant sum of Rs. 124341812 to implement 3595 income generating schemes at VDCs and Municipality level. Out of total 251 CAC of VDCs received grant Rs. 88576302 for 2277 community and individual schemes, where has 111 CACs of Municipalities received grant of Rs. 35765510 for 1318 community and individual schemes. The total benefited member of those 362 CACs is 55546 (male 26640 and female 28906) so far. Out of total 36761(male 17448 and female 19313) members from VDC and 18785 (male 9192 and female 9593) members from Municipality benefited.
Among them total schemes almost all are already completed and few of them are supposed to complete before the month in the month. Different Community Infrastructure Schemes are identified by CACs and concerned LBs and RCU have assessed and recommended for the implementation.
Local Bodies
Districts (9) Municipalities (21) Total
No. of Received Grant
CAC Total CIDS Number CIDS
251
2277
111
1318
362
3595
of
Total Amount Expended
Benefited CAC members Male
88576302 35765510 124341812
17448 9192 26640
Total
Female 36761 19313 18785 9593 28906
55546
Table 6: Details of CIG in Districts and Municipality
The LBs have released grants to the CACs, through VDC to implement the projects demanded by CACs. The orientation was given to LBs and SMs about the guidelines. The RCU/DGE/UGEs has provided support to SMs on assessing the feasibility of proposed schemes for the poverty reduction of CACs members. Different infrastructure schemes e.i. Sheds of Goat, Pig, Poultry, Buffalo/Cow, Milk Dairy, Irrigation (Sallow/Cannel), Vegetable tunnel house, Mushroom farming, Vegetable collection center, Fruit farming, Banana farming, Bee keeping, Fish pond, Herbal plant collection center, Bamboo
39
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
products, Drinking water, Community building, Water/Cellar Mill, Others, Metal Workshop/Iran, Tent House/Catering, Handicraft, Solar/Micro-Hydro, Aggregate/Bolder Collection center, Toilet, Tailoring, Lather Shoe making, Improving Stop, Foot Trial and PrePrimary School. The details of types and number of schemes are presented in following diagram.
Number of schemes CIG Projects Pre-Primary School
4
Foot Trile
2
Improving Stop Lather Shoe making Tailoring
30 1 42
Toilet
90
Aggregate/Boalder Collection center
2
Solar/Micro-Hydro
7
Handicraft
2
Tent House/Catering
1
Metal Workshop/Iran
7
Water/Celler Mill
14
Community building
24
Drinking water
54
Bamboo products
3
Hurbel plant collection center
1
Fish pound
3
Bee keeping
86
Banana farming
5
Fruit farming
1
Vegetable collction center
7
Mushroom farming
25
Vegetable tunnel house
184
Irrigation (Sallow/Cannel)
195
Milk Dairy
4
Buffalo/Cow shed Improvement
178
Poultry Shed
195
Pig Shed
305
Goat Shed
2123
40
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
The above diagram shows that there are higher number of schemes on sheds of goats, pigs and other livestock. In FY 070/71, the guideline also allowed to approve schemes related to community building, drinking water schemes, public toilet and rural electrification so more numbers of such types of schemes are constructed. But in FY 2071/72, only schemes related to direct income generation are identified and approved. CACs are running public audit after the completion of CIG schemes. The details of Small infrastructure schemes supported in CAC till date is as per attached sheet (annex-2). Program coordination and harmonization The possible list of livelihoods activities and livelihood related infrastructures activities for CACs were discussed and shared in meetings of line agencies i.e. DADO, DLSO, Small cottage and industry office, women and children development office, skill development office and other stakeholders working in livelihood sectors is continued at district level for prioritizing their activities at target groups level and also coordination in technical support from local level planning process. Program harmonization meetings were done with MEDEP Area program Support Office (APSOs), Dhangadhi to identifying possible supplements and complements areas in collaboration and promoting small and microenterprise schemes at CACs level. SMs and members of CACs of some Local bodies were trained on micro enterprises schemes i.e. Start and Improve Your Business (SIYB). Resource sharing in LIP and Community Infrastructure Development Grants with district level stakeholders likes MEDEP, PAF, Kishan project and UPAP at district level. Success/failure cases Success  Line agencies along with other stakeholders have realized the objective of formation of CACs and started to harmonize their activities in CACs e.g. providing technical training to CACs members as per their selected livelihood schemes but still require to mainstream from ministries and department level of concerned Line agencies.  The MEDEP program has provided technical support on capacitating SMs on promoting small and microenterprises at local level planning and further implementation (collaboration and partnering in CACs livelihood program and technical support in at Baitadi, Parsuram and Sanfebagar Municipality.
41
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
6.4 Social Security & Vital Registration The Government of Nepal has provisioned to distribute social security allowances to senior citizens, single woman, widow woman, disable person, endangered people, and nutrition allowance for dalit children & medicine amount for senior citizen. During the year, it was observed that all DDCs and Municipalities has formed social security coordination committee and assigned focal person to conduct regular meeting and other supports. The all VDCs have been delivering the allowance timely. Similarly, all VDCs are updating data as per the guideline. Regarding the MIS of social security Dadeldhura, Kanchanpur, Bajahang & Achham DDCs has completed and using the software. Including cash payment 10 municipality has started banking payment system through opening personal account in different financial institutions. Dododhar VDC of Kailali district started MIS entry system on vital registration. MoFALD/DOCR with the support of RCU implemented on social security & vital registration training at 8 DDC and 14 municipalities of the region. In addition, vital event registration questionnaire survey has also been completed at Kailali, Doti & Bjaura district and Tikapur/Dipaya-Silgadhi municipality. The table below shows that the details of allowances distributed by the LBs; Status of Social Security Allowance Distribution SN 1 2 3 4 5 6 7 8 9
Types of Beneficiaries Senior citizen (Other) Senior citizen (Dalit) Single Woman Widow woman Fully Disabled Partial Disabled Endangered (Raute,Raji) Children Dalit Medicine above 70 Total
Numbers Payment Amount RS. Remarks 55403 332418000 33702 202212000 20215 121290000 47182 283092000 1961 23532000 2024 7286400 2807 33684000 72624 174297600 73452 146904000 305363 1341192000
Summary of Vital Event Registration SN Types Number Remarks 1 Birth 118220 2 Mirages 22123 3 Death 10726 4 Migration 25360 4.1 Entire 54235 4.2 Exit 37410 5 Divorce 28 Total 242742
42
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
6.5 Community Mediation LGCDP is coordinating other agencies to bring them in one umbrella within the districts. The program has supported Kailali, Kanchapurt, Doti and Dadeldhura DDCs and Bhimdatt and Depayal Silgadi Municipality to conduct the orientation programme at district and community level. Altogether 11 events with 595 participants (42% female) from SMs, LBs stakeholders, Local facilitators have participated in the orientation programme. There are other agencies who are also working in the field of community mediation i.e. REWDUC and CeLRRD (Doti, Dadeldhura, Kailali and Kanchanpur DDCs and Dhangadi, Amargadi, Bhimdatt and Depayal-Silgadi Municipalities) As of date 38 VDCs and 50 wards have been covered. Total 933 local facilitators have been involved in this programme. During the year sum of 4241 community disputes were registered and 78% (3338) community disputes were settled at community level.
OUTPUT 7 Strengthen integrated planning, budgeting, monitoring, evaluation and coordination amongst local governance actors 7.1 Planning and Monitoring and Evaluation
The 14 steps of planning process has been internalized in LBs. Most of the DDCs/VDCs/Municipalities have been following the Local Bodies Resource Mobilization and Management Guidelines 2069 during the planning process of local bodies. Integrated Planning Formulation and supervision and monitoring committee has been formed in all LBs. The program follows the performance and Result Based Monitoring (RBM) system from implementation to execution level. There is a monitoring mechanism from grass root level to central level. As per provision, project wise Monitoring & Supervision Committee were formed and carried out monitoring accordingly in field level. The concerning LBs technicians, though not much frequently, carried out monitoring of projects being implemented by their respective LBs. Besides, many LBs made involved political party leaders in carrying out monitoring of projects implemented in field level. There were occasional visits to local bodies from central level personnel for monitoring purposes. Besides, but regular monitoring, supervision and quality control is from regional coordination unit as well as district/ municipality Office bearers. In the same way, Baitadi, Kanchanpur, Kailali, Bajura, Achham, Bajhang and Doti district has completed the District Periodic Plan with the support of MoFALD and other development partner. Darchula district is in the line of completing of DPP where has Dadeldhura could not started due to the conflict with development partners.
43
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
7.2 Financial Delivery For the FY: 2071/072, LGCDP has provided budget as pool fund to LBs under the 30 activities of 8 budget heads. Almost
Status of LGCDP Budget Delivery
demand side budget has expenditure by LBs. The budget heads were SMs operating
fund,
capital
grant fund, LIP/CIG fund, WCF/CAC operating fund, ICTs, and Engineers salary and
other
development
capacity program
300000000 250000000 200000000 150000000 100000000 50000000 0 DDCs
Received Budget 181404550
Expenditur e Budget 173292627
Budget Freez 8111923
Municipality
99188750
81900514
17288236
Total
280593300
255193141
25400159
heads. The total received budget of DDC and Municipality was Rs. 28059330/- and expenditure budget was Rs. 25519341/-. Moreover 91% overall budget was expenditure of both LBs. So far individually LBs wise, 96% budget expenditure of DDC and 83% budget expenditure of Municipality respectively. In an average the major budget was freeze in lab establishment, natural digester management, making of transportation plan, and salary of municipality engineers and so on. The maximum budget was utilized under the SMs operating, CAC/WCFs operating, LIP/CIG operating, Capacity building of LBs and capital grant budge heads.
7.3 Gender and Social Inclusion (GESI) GESI focused to implement GESI policy 2066 and Gender Responsive and Social inclusion budget implementation and auditing guideline 2068, adopting Gender Responsive Budget and mainstreaming the GESI in all the level of planning, implementation and monitoring, the Gender Based violence (GBV) strategic and action plan in all the LBs. LGCDP II included GESI in the output no 1 and 7. However output no. 4 explained about the GRB and GRBA internalized by local bodies. Furthermore, LGCDP II supports to internalized GESI through technical backstopping and facilitation for mainstreaming the women, children, Dalits and Disadvantage people in all the process of planning, budgeting, implementation and monitoring. The programme aims to bring these people in the front line of development.
44
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
In this region, all DDC, VDC and Municipality have adopted 35% target budget effectively. GESI policy implemented by all LBs regarding participation of women and DAG in various committees and planning, monitoring, implementing process. However, it is realised to orient and clear GESI guideline and police for VDCs and Municipalities level. The report is prepared based on the LBs progress on GESI in this fiscal year 2071/72. Indicator based progress achievement: A. Gender Equality and Social inclusion All nine DDCs, 328 VDCs and 21 Municipalities have allocated more than 10 percentage target budget for women from DDC council and also expended 90% budget on directed benefited activities i.e. Income Generation Activities (IGA), skill development activities(SDA), awareness raising activities (health, sanitation, right and social issues) and infrastructure such as drinking water. Similarly, LBs allocated more than 15% budget for the Disadvantage groups. LBs reported that allocated budget expended in the same activities Women receiving tailoring training from the support of Dipayal demands by the DAG. Mainly, the silgadhi Muns. budget has expended in livelihood improvement activities, skill development activities, small infrastructure i.e. drinking water, irrigation, street, sanitation. Furthermore, awareness raising activities and promotional activities. Demand of WCF V/S addressed by LBs
As per the RBM report 2071/72 of LBs
Demand v/s address by LBS
regarding the demand forwarded by WCF and
2,850
addressed by LB in their annual programme for target group, the result shows LBs have
1,750
addressed less than 45% percentage demands of the target group. Out of total 1750 demands of women, 1560 for Children and 2850 for DAG’s demands forwarded by WCF to the VDC of which 42%,40% and 36%
590
1,560 728
570
840
625 226
224
1,015 345
deman of address by demand of address by demand of addressed women LBs women Children LBs DAG by LB for children DAG
VDC
Municipality
addressed respectively by VDCs. Similarly, in
45
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
the case of municipalities 590 demands of women, 570 of Children and 840 for DAG demands forwarded by WCF to the Municipalities, of which 38% of women, 38% of Children and 41% of DAG demands have addressed by Municipalities. The percentages show that less projects approved by LBs in comparison of demanded projects. However, the total project included by LBs in their annual plans calculated more than 85% as the number of projects addressed from the same projects forwarded by WCF. Representation of the women in the CAC, WCF, ward level planning and LBs council
Disadvantage Group (DAG)
DDC
VDC
Others
Municipalities
46
53715
212705
43801
87518 237159 112475
747122
120469
92171
40456
69774
285137
327072
126673
99191
139655
105107
709830
Number of project v/s benefited population: Here, LBs progress analysed from GESI perspective. The progress analyzed based on the RBM which shows that all about 10,981 projects in ten sector 1) roads, bridge Benefited population from the LB's and culvert 2) WASH 3) Irrigation 4) Economic infrastructure 5) projects Environment 6) Education 7) Social infrastructure 8) Health 9) agriculture and 10) Promotional activities accomplished by LBs in f/y 2071-72. Out of total projects 11.35 percentage project for women, 10.83 percentage for Children and 17.54 percentage projects were target groups. Similarly, 3,610,030 population have benefited Male Female Children Male Female Children from the total projects of which 27%
1323 408
15104
26382
3181 952
9010
15471
7320 3822
1423 101
2948
3684
31049
36873
52345
71896
All about 74554 community people have Sex wise representation in WCF,CAC, represented in the WCF of which 46% women ward level planning and LBs councile have participated. The representation of the women seems quite good than the provision of the social mobilization guideline 2071. Similarly, 12666 DAG community have participated in the CACs of which 88% involvement of women. Moreover, 41% women have participated in the ward level planning process out of 148,722 participants. Similarly 36% women have joint the LBs council out of 47350 people. The data shows women involvement in planning process and Men Women Men Women Men Women Men Women decision making level has been gradually WCF CAC Ward level PP LBs council increasing. However, LBs need to make VDC Municipality DDC effective participation of the women in decision making, monitoring and supervision committee as well.
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
women, 20% Children and 53% men have been benefited.
AMEP progress on GESI: OUTPUT
INDICATORS, BASELINES AND TARGETS INDICATOR (for outputs only) or ACTIVITY
TARGET (for 15 July 2015)
Achievement (as at 15 July 2015)
OUTPUT 1: Citizens and community organizations are empowered to actively participate and assert their rights in local governance OUTPUT 5: Institutional and human resource capacities of LBs and central level agencies involved in local governance strengthened.
0.8.Improve effectiveness of targeted (35%) grants to women, Children and DAGs
At least 80% of local bodies meet or exceed the minimum provisions
More than 90% LBs 35% budget for women, children and DAGs).
4.7.Capacity building for mainstreaming crosscutting themes
Incorporate cross -cutting themes in all training courses in line with principles outlined in LBRMMOG
All DDCs and old municipalities have incorporated cross cutting themes in all the training courses.
OUTPUT 7:Proportion of capital funds that are allocated and spent to target groups by LBs Proportion of capital funds that are allocated and spent to target groups by LBs Proportion of capital funds that are allocated and spent to target groups by LB
# of local bodies (DDC, municipalities, VDCs) that have adopted CFLG processes, population issues integrated genderresponsive budgeting, gender auditing and EFLG
60% of VDC plans in line with article 19 of LB RMG - CFLG adoption initiated by 75 DDCs and 58 municipal councils- 10 VDCs declared child friendly - GRB implemented in 30 DDCs , 15 Municipalities - 60% districts and 50% Municipalities adopt EMP F7
6.3.Mainstream GESI, CFLG and EFLG, disaster management and programme monitoring plans in local periodic and annual plans
All new/updated District/Municipality periodic and annual plans incorporates cross cutting issues
9 DDCs have formed GRB committee and adopted. Six DDC and two Mun. has conducted GESI audit
Seven DDCs out of nine have mainstreamed GESI in District Periodic Plan
7.4 Child Friendly Local Governance Child Friendly Local Governance is an important area of the programme. Mainly, CFLG focused three areas one plan for children, voice of the children and budget for children. Therefore, MoFALD have developed CFLG national strategic and Implementation manual 2068. All the LBs should mandatory for implementation of these document during the planning, budgeting, implementation and monitoring process. LGCDP II have been supporting budget to the LBs for internalizing and capacity building. Likewise, UNICEF, Nepal
47
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
also supported in six districts namely Achham, Bajhang, Bajura, Baitadi, Dadeldhura and Doti for CFLG programme. The UNICEF supporting Child club, Child network, CFLG declaration and school for the strengthening and adopting CFLG by LBs and other government officials. Key achievement a) Proportion of capital funds that are allocated and spent to target groups by LBs: As per the
LBs report regarding the 10% allocation budget and 80% expenditure, it has found that almost all LBs have allocated 10% to 15% budget for Children and expended at least 80% budget on direct benefited activities for them. This year 100% LBs have allocated budget and expended to children whereas five DDCs, Four Municipalities and 148 VDCs have only the allocated budget and expended as per the indicator in last year. Mainly, the allocated budget expended on playground maintenance, library and ECDC established, institutional (Child club, child network) development, capacity/empowerment development, educational materials manage, scholarship, school building maintenance and boundary construction and declaration of complete immunization programme. The data shows that maximum percentages of amount expended on to the child capacity building related activities and institutional development activities. However 44% DDCs and 47% Municipalities have not provided the actual expended project data. b) Approved plan of activities by LBs:
As per the 328 VDCs RBM data 2071/72 all about 3,231 demands forwarded by
Children's demand V/S addressed by LBs 3,231
WCFs to the VDC council, of which 44% demands in same topics addressed by
1,696
the VCDs and included in annual plan. Similarly,
752
Municipalities
demands WCF
have
from
752
21
forwarded
Children’s plan to the Municipalities of
VDC
projects forwarded by WCFs
435 Muns
included in annual plan
which 47% demands have included in annual plan by the municipalities. The addressed percentage shows quite good according to the CFLG indicator. The indicator mended 40% demands should include by the VDCs and Municipalities out of total forwarded demands by LBs.
48
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
c) CFLG adoption:
According to the CFLG strategic and implementation module 2068 all LBs should adopt the CFLG but lack of budget, capacity building and proper guidance regarding the importance of the CFLG, LBs have given less priority to this matter. However, UNICEF supported six districts on CFLG through DDCs and this year MoFALD support to other remaining DDCs and Municipalities for orientation and Balvela. The support of UNICEF and MoFALD helped to internalize the CFLG by LBs. As the result shows in the context of FWDR, Eight DDCs out of nine, 257 VDCs out of 328 and 13 Municipalities out of 21 have adopted CFLG, whereas remaining one DDC Darchula have also decided for CFLG adoption from DDC council. The ratio of the CFLG adoption this year by LBs is increased than last year, As per the last year annual report, 6 DDCs, 4 municipalities and 153 VDCs had adopted CFLG. Moreover, 8 DDCs have assigned focal person of CFLG and three DDCs, 314 VDCs and seven Municipalities internalized CFLG indicators so far. Regarding the CFLG committee meeting it was reported that only the 5 DDCs, 2 Municipalities held the quarterly meeting as per the guideline. Similarly, Baitadi DDC, Dashrathchand Municipality and Bhajani-trisakti Municipalities have conducted half yearly joint monitoring this year. d) Promotion of Child club and network:
According to the LBs report 120 child network of DDC, 771 Child club of VDC and 77 of Municipalities have registered in District Child welfare Committee through the recommendation of each respected. Similarly, 1187 child groups in VDC and 280 child group in Municipalities have formed. Generally, the child club, network and child group have been formed in the UNICEF supported districts so far. However, Kailali, Kanchanpur DDC and Dhangadhi,
Tikapur
municipality have formed child club from their own internal fund. e) Child gathering (BALBHELA):
To organize Child gathering during the planning process is very important task of LBs. All the demands of WCF for children should come from the
49
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Child gathering (Balbhela). As per the available data from LBs all about seven DDCs, 272 VDCs and nine Municipalities have conducted child gathering in this year which is more than 42% in compression of last year. During the last year only 4 DDCs, 2 municipalities and 145 VDCs have conducted child gathering. 1. CFLG progress according to the AMEP
OUTPUT 1: Citizens and community organizations are empowered to actively participate and assert their rights in local governance
INDICATORS, BASELINES AND TARGETS TARGET (for 15 July 2015) - BalBhela to be implemented in a total of 25 DDCs and 20 MunicipalitiesManual developed for Social Mobilisers A total of 25 DDCs (including their VDCs) and 20 Municipalities incorporate children’s needs in annual plan through BalBhela
OUTPUT 5: Institutional and human resource capacities of LBs and central level agencies involved in local governance strengthened. OUTPUT 7:Proportion of capital funds that are allocated and spent to target groups by LBs Proportion of capital funds that are allocated and spent to target groups by LBs Proportion of capital funds that are allocated and spent to target groups by LBs
Incorporate cross -cutting themes in all training courses in line with principles outlined in LBRMMOG
Achievement (as at 15 July 2015) Balvela conducted in 272 VDC, seven DDCs and nine municipalities Only 92 VDCs out of 328 and two municipalities out of 21 incorporated children's need from balbhela. Remaining LBs have addressed their needs through WCF.
- 60% of VDC plans in line with article 19 of LB RMG - CFLG adoption initiated by 75 DDCs and 58 municipal councils10 VDCs declared child friendly - GRB implemented in 30 DDCs , 15 Municipalities - 60% districts and 50% Municipalities adopt EMP
CFLG adoption in nine DDCs, 13 Municipalities and 257 VDCs. Out of 328 VDCs 32 VDCs has planned to CFLG declaration next year.
All new/updated District/Municipality periodic and annual plans incorporates cross cutting issues
Seven DDCs out of nine have mainstreamed CFLG in District periodic plan and
4. Overall scenario of the CFLG progress in FWDR this year. Indicator Is the invested plan prepared on the base of 15% or 10% allocated budget for children or not?
9 DDC 8
50
328 VDC 160
21 Muns 7
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
out of 10% Total Capital Grant (Internal and External) of DDC for target group, at least minimum 80 % budget allocation and expenditures in Children benefited projects (Yes/No)
9
328
13
Focal Desk person is assigned for CFLG in DDC or not?
8
8
DDC council decided for adaptation of the CFLG or not
9
257
13
Two days orientation programme held about CFLG or not?
9
238
10
DDC have CFLG promotional action plan or not?
3
CFLG indicators are internalized in DDC or not
6
314
5
Is the out of total demands of children, 40% annual plan of the Children related topics addressed by the Municipal
8
105
10
Is the child Gathering held or not
7
272
9
2270
454
7
Total number of the children participation ( WCF, CAC, Integrated plan, CFLG committee and Municipal council) Is the CFLG committee meeting held in the at least quarterly or not
5
2
Is the CFLG committee conducted half-yearly joint monitoring
2
Number of child networking and Child club
1 (Baitadi) 120
771
77
Number of Child group
0
1187
280
have the capacity building of the child club in the child related agendas.
48
98
7.3 Environment Friendly Local Governance (EFLG) The MoFALD has endorsed the Environment Friendly Local Governance Framework 2013 with an aim to make the entire nation environment friendly and achieve its indicators from individual level, household, settlement, village, Municipality and District. It come up with an integrated policy to make local bodies and people protect the environment and sanitation. The framework includes waste management, environment protection, climate change, disaster risk management through local governance. So, LGCDP-II will roll out the EFLG Framework in all the LBs and supported grants for EFLG activities as well. MoFALD has supported to three Municipalities namely Bhajani-trisakti, Belaury and Punarwas on demand base EFLG activities. Highlights:
As of now three DDC namely Achham, Bajura and Dadeldhura have declared ODF. Rauteli VDC of Kanchanpur district have declared smokeless VDC Installed 12000 Improve Cook Stove in 51 VDCs of Achham district LAPA action plan preparation in Lamki-Chuwa Municipalities. 9981 Metallic ICS installation in Dadeldhura
51
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
1. Key achievements 1.1 ELFG adoption: As per the report of LBs 6 DDCs namely Dadeldhura, Kailali, Baitadi, Achham, Kanchanpur and Bajura and four Municipalities Api, Lamki-Chuwa, Bheemdutta and Dashrathchand have formed EFLG coordination committees. Similarly, 4 DDCs and 7 Municipalities have Environment Management Plan. However, only 1 DDC and 2 municipalities have used EMP in Infrastructure Projects In < 25% Projects and three municipalities will be in process of using EMP.
1.2 Gender wise representation: As per SEX WISE REPRESENTION IN available data of DDCs and Municipalities EFLGCC regarding the gender wise composition in EFLGCC only the 10% women representative Women seems in the committee. Representation of 10% the women become very nominal due to the member structure of the District/Municipal EFLGCC. As we know very few women government officers have been exciting in Men the government office. According to the 90% EFLG framework 2013 only the officer can be member of this committee in DDC and Officer or representative can be member in Municipality EFLGCC. Therefore MoFALD/Environment unit should think about the committee member and ensure at least 33% women representation in entire committee. 1.3 Indicator wise progress of LBs: the table shows the indicator wise progress of Far western region. Indicator EFLGCC * EFLGCC Composition Male Female No of EFLGCC meeting conducted No of Training Conducted
DDC (Nine)
Municipalities (21) 6
4
53 7 8 3
64 6 5 4
52
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Training Subject
EFLG frame work 2070 framework 2070, Indicators and renewable energy in VDC LAPA
Committee formation and waste management training Orientation on EFLG Framework 2070 and wate management Orientation on EFLG
EFLG Total Training participants
285
142
Male Female EMP** Guidelines Available
202 83 4
115 27 7
Use of EMP in Infrastructure Projects In < 25% Projects
1
2
Use of EMP in Infrastructure Projects In process Does District/Municipality Environment Energy and Climate Change Section/Unit Functional?
0
3
7
6
1.4 Demand driven project/activities progress: MOFALD/LCGDP II provided support on EFLG demand base activities in three new Municipalities. The MoFALD provided NRs. 500,000 each to the programme implementation.
LB Name
Activities implemented by Municipalities
Implementatio n Site
Uni t
Total Total Approve Expenses d (Rs.) Budget
Bhajanitrisakti
Conservation of the municipality 4 Bigha land by
ward no. 12
4 Big ha
500000
Gangalataal maintenance and fishery by the women farmer group in contract
ward no. 14
no
500000
Nainitaal conservation
ward no. 14
no
Shovataal conservation with greenary park construction
ward no. 7
no
Punarwash
Belauri
500000
500000
600000
500000
53
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
Visitors
54
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Issues, Challenges-way forward and Recommendation The major issues and challenges observed during programme implementation have been pointed out as; Issues/Challenges and Recommendation for way forward Issue and challenges Social Mobilization 1. Lack of knowledge to the WCF and CAC
way forward 1. It is required to empower WCF and CAC members
on accountability and responsibility
on local level planning and oversight functioning
towards citizen
process at VDC and ward level.
2. VDC staffs have lack of knowledge on 2. MoFALD/LGCDP II should train to VDC staffs on social development sector. 3. D/SMSCC are not actively functioning with their role and responsibility.
social
development,
planning
and
oversight
package at District level. 3. It would be better to organized training on role and
4. No uniformity on the SM data base
responsibility,
5. Community Mediation activities are not
mobilization tool and technique to the D/MSMCC
effectively implemented in community.
effective
implementation
social
member. 4. LGCDP
should
develop
computerized
Social
Mobilization database package for the uniformity database. 5. LGCDP need to organize refresher training to existing local facilitators, need to provide CM matching fund to LBs, CM guidelines, in order to effective implementation of Community Mediation activity
55
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
Issue and challenges
way forward
Capacity Development 1. Unavailability of any CD grant to 1. CD grant should be provide as per requirements implement annual activities as targeted
and its proper utilisation to be ensured from
in CD plan
concerning
2. Institutionalisation of LBs i.e. VDCs for 2. LGCDP II/DDCs need to focus on capacity governance system
development of VDCs for institutionalisation and establishment of governance system. 3. LB officials and local political parties to be well oriented/trained in various aspects 4. Fulfilment of all vacant positions in LBs; especially VDC positions 5. LBs to be focused for promoting transparency and accountability through Information, Technology and Communication (ICT).
LIP/LLED 1. All SMs are not able to internalize and 1. Require to build a mechanism for monitoring of mobilize LIP grant at same procedure
proper utilization of LIP for ensuring the quality of
level.
program as per expected one.
2. Due to lack of monitoring system in local 2. There is urged to have a separate section in DDCs bodies on ongoing LIP activities in CACs
and Municipalities for the promotion of economic
there is a risk on continuation of LIP
development sectors. ď&#x201A;ˇ LSP should be accountable on regular follow up
schemes adopted by members. 3. Development grant for CAC, stepwise grants implementation guideline was
facilitating enterprises, technical backstopping to
not able to follow by CACs because of
the CACs and reporting.
delayed
to
budget
release
from 3. MoFALD should release budget on time for
MoFALD. 4.
and make necessary liaison on promoting and
effective implementation of grant.
Community building along with drinking 4. RCU and LBs should collaborate the livelihood water schemes are still remaining
program with other organizations like MEDEP and
incomplete because of high budgeting
other line agencies as per their expertise area.
on design and estimation compared to 5. National along with district level coordination is the CACs actually received from this
needed for having support from concerned
grant
agencies such as DADO, DLSO, WCDO, and DPHO,
56
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
5. Livelihood issues is not the priority issue NGO/INGO etc. of LBs so their efforts are not seemed 6. DDC must reviews the technical aspects of all CAC effective for ensuring the livelihood of the poor in their territory. proposals/ business plan before approving it and transfer the fund of all LIP and Community
6. Due to wide coverage of LIP throughout the districts and municipalities the monitoring mechanism on proper utilization of LIP fund could not be established yet.
Infrastructure Development Scheme activities. This helps to ensure the quality review of proposed enterprises making good tracking system of success
and failure. 7. Lack of the clear guideline and backstopping support can promote loan 7. The programme reporting system through RBM overdue situation in CAC and create should have consistent in their indicators which conflict among the members. avoid confusion to the DGEs/UGEs and RCU time 8. CACs are engaging more on the interest and again it should be internalized with LBs in their calculation and monthly installments rather than their regular meeting online reporting system for making the data more session regarding their other issues and authentic and reliable. awareness activities. 9. Harmonization program at local level is not being effective as expected because of not having direction from concerned ministries and district agencies. Fiduciary Risk/M & E
LBs need to be made more accountable through empowering local communities
Strictly
following
government
policies
and
guidelines/manuals/circulars 1. Fiduciary risk at LBs, especially at VDCs
Frequent
monitoring
from
higher
authorities/Applying monitoring findings for timely correction
Provision of reward, recognition and punishment
Orientation to entire LBs officials, LSPs/CSOs, WCF/CAC and other community groups about Public
Financial
Management/Fiduciary
Risk
Reduction Action Plan (FRRAP). 2. Monitoring of programme activities/LB activities not enough
LB should develop
monitoring mechanism and
should focus on Result Based Monitoring and regular monitoring is required from various
57
| 2071/72(2014/15)
Annual Progress Report: LGCDP -II, RCU Dhangadhi
concerning ď&#x201A;ˇ
Encouraging third party monitoring/LGAF
Gender Equality and Social Inclusion (GESI) 1. LBs gives low priority to the crosscutting and seek the donor for budget to active the committees and other activities. 2. Joiner staff of the LBs are not aware about the cross-cutting issues especially GESI, GRB and GBV. Therefor it effect the planning/ budgeting and implementing time. 3. Less sensitization at local level on Gender and social inclusion issues specially on target group like women, socially and economically backward and DAG group. 4. Gender Based violence Action plan is not implementing properly by the LBs. 5. Not the clear GESI policy and strategic for municipalities and VDCs for implementation. 6. Lack of coordination between District Women and Children office and LBs regarding the GESI and CFLG issues. 7. Still none of the activities conducted on Gender based violence to the CAC and WCF by LBs. 8. GRB and GESI committees are inactive. 9. Municipalities are less aware on the GESI policy, GRB and GRBA. Child Friendly Local Governance (CFLG)
1. MoFALD should monitor for proper implementation of policy, guideline and procedure have done by LBs or not? 2. It would be better to conduct training/orientation Programme on GESI/GRB to junior staff of LBs as well for sensitizing about the GESI and GBV 3. MoFALD/LGCDP should organize orientation/training Programme about GESI, GRB and GBV to the WCF, IPC member and CAC. 4. MoFALD/LGCDP should support to implement the GBV action plan and GBV desk effective. 5. MoFALD finalize the GESI localization strategic and deliver to the Municipalities and VDCs as soon as possible. 6. LBs, especially DDC should to build-up the coordination regarding the GESI and GBV activities. 7. GBV is main issues of the CAC and WCF. Therefore MoFALD/LGCDP should give attention to make some activities for addressing this issue. 8. It would be better to allocate some budget for making the committees strengthening and effective at least once a time. Similarly, MoFALD should think about the number of the committee regarding same issue. 9. Need to conduct orientation Programme about the GESI to all municipalities GESI focal person and UGE.
1. Lack of coordination among LBs and other likeminded agencies/UNICEF such as District Child welfare committee regarding the Child issues, activities and implementation of the strategic and guideline. 2. No capacity building activities have conducted till date for RCU responsible
1. It would be better to build coordination and collaboration among all the related agencies from top to bottom level. 2. MoFALD should develop CFLG activities and allocate budget for the effectiveness of the Programme 3. Conduct capacity building related activities to the Experts team as well
58
Annual Progress Report: LGCDP -II, RCU Dhangadhi
| 2071/72(2014/15)
Expert, UGE/DGE and LBs especially to the new municipalities in the context of FWDR. 3. Nominal budget for non-UNICEF supported districts for CFLG activities. Environment Friendly Local Governance (EFLG) 1. EFLG committee is not so effective due to the no budgetary provision. 2. Lack of awareness among people and less consciousness of municipal towards this issues. 3. Lack of awareness on people about the waste management. 4. Not separate unit of Environment and waste management in case of Municipalities. 5. Less coordination, coaching and followup from the PUC level
1. MoFALD should think about the budget at least for EFLG coordination committee. 2. Need to conduct awareness activities, make EFLG plan and endorse in the council. 3. EFLG indicators not properly implementing due to the lack of budget and capacity. 4. Municipality need to established separate unite for Environment and waste management 5. MoFALD/LGCDP should conduct capacity building activities for related Experts and LBs focal person at least. 6. It would be better to do frequent coordination, follow-up regarding the EFLG activities from PCU.
Social Security and Vital Registration 1. DDC, Municipality and VDC have not enough equipment (computer, printer) for establishing MIS system etc) in social security section. 2. Untrained Human Resource in the section 3. District Disable Coordination committees is inactive. 4. Weak monitoring from LBs and stakeholders ICT
1. Need to special orientation for the focal person on payment system. 2. Need training for social mobilizers on importance of social security and vital registration. 3. Need training for social security coordination committee in DDC, municipality and VDCs. 4. MIS system to be made compulsory
59
Annual Progress Report: LGCDP -II, RCU Dhangadhi
1. There is no specific budget for IT related work and capacity development. 2. E-governance services has not been used in LBs. 3. Software being not linked with each other, hence uniformity in achieving in EGov. 4. Assigned ICTVs as electronic background still there is need of IT training for them. 5. Some of the LBs have still slow internet connectivity. 6. Central E-governance portal.
| 2071/72(2014/15)
1. Need of better coordination and harmonization with DGE/UGEs, ICTVs and LBs official for effective implementation of IT services & public service delivery. 2. Capacity development of ICTV as well as LBs official based on their need. 3. Proper utilization of IT resource at LBs make policy and Plan for IT infrastructure for LBs. 4. There is a need of uniformity in LBs in using of software as well hardware tool for technology. 5. MoFALD need to maintain central server for each LBs Information management. 6. Make e-governance policy for good governance.
Recommendations for further actions
Introduction of results-based management for DDCs and municipalities. Strengthening local accounting systems, including use of IT tools to automate transactions.
Enhancing local resource mobilization and fiscal sustainability, including the development and pilot implementation of Administration and Revenue System (ARS) and support for drafting a Fiscal Responsibility Bill.
Strengthening WCF and promotion of public auditing by Ward Citizen Forums and Citizen Awareness Centres.
Strengthening external and internal audits of local bodies, including application of risk-based internal audits of village development committees (VDCs) by DDCs.
Capacity-development of various stakeholders: LBs officials especially VDCs, Social Mobilisers, WCF/CAC members, D/MSMC committee; GESI/GRB/CFLG/EFLG committees and programme staff (both District and Region).
Various economic development activities should be initiated through LIP/SPMP programmes for livelihood improvement of rural people
Strengthening of monitoring mechanism being focused to Result Based Monitoring in district/regional/central level
Mainstreaming of cross cutting issues in planning, implementation and monitoring including policy intervention: GESI/CFLG/EFLG; LIP/LLED, Social Security System/Vital Registration and ICT.
60
Government of Nepal Ministry of Federal Affairs and Local Development Local Governance and Community Development Programme-II Result Based Progress Reporting Reporting period: Annual FY: 2071/72 Reporting office: LGCDP,RCU Dhangadhi No. of VDCs/ward in reported in this reporting period: 328/21
Annex 1
All Cost and budget amount in thousand NRs. Accomplishments S.N.
Indicators
Total of Region VDC
I
Citizens & Communities Empowerment: Social Mobilization (Output 1)
1
Number of Ward Citizen Forums (WCF) established (cumulative)
2,944
266 6,632
Men
36,873
3,684
Women
31,049
2,948
26,185
685
328
140
3
Number of WCFs that replace executive members as per guidelines during the reporting period
4
Number of Citizen Awareness Centre established (Cumulative) Total members in CAC
5
DDC
67,922
Total members in WCFs 2
Municipality
8,743
3,923
Men
1,423
101
Women
7,320
3,822
6
Number of CAC graduated during the reporting period
292
93
7
Number of VDCs and municipalities that conducted ward level planning workshop in the current fiscal year
328
21
2,538
239
8
Number of total wards in which planning meetings were organized by LBs Number of participants in ward level planning meetings
9
124,241
24,481
Men
71,896
15,471
Women
52,345
9,010
Remarks
Number of citizens who participated in LB's Council (total) 10
11 12
41,486
4,504
1,360
Men
26,382
3,181
952
Women
15,104
1,323
408
272
17
22,616
8,242
2,555,021,044
3,418,936,142
9,855
2,423
562,671,124
475,102,069
3,631
1,035
3,231
911
4,172
1,198
1,375
393
1,696
411
1,805
495
65,938,805
43,012,689
27,734,300
73,088,881
42,935,819
26,473,650
81,247,280
71,624,473
42,862,100
102,704,107
8,896,000
8,092,215
306
121
-
-
Total
Total
1,411
593
115
24
Number of VDCs and municipalities that maintained the list of participants by women, children, youths and DAG in ward level planning workshop in the current fiscal year Number of projects forwarded by WCFs to LBs
13
Total cost of the projects forwarded by WCF to LBs
14
Number of projects forwarded by WCFs to LBs (VDC & municipality) that included in annual plan
15
Total cost of projects forwarded by WCFs that included in annual plan of LBs ( VDC & Municipality )
16
Number of projects forwarded by WCFs addressing the need of women
17 18
Number of projects forwarded by WCFs addressing the need of children Number of projects forwarded by WCFs addressing the need of DAG
20
Number of projects forwarded by WCFs addressing the need of women that included in annual of LBs forwarded by WCFs addressing the need of children that included in Numberplan of projects
21
annual of LBs forwarded by WCFs addressing the need of DAG that included in annual Numberplan of projects plan of LBs
19
22
Total budget allocated by LBs in annual plan addressing the needs of women Total budget allocated by LBs in annual plan addressing the needs of children
23 Total budget allocated by LBs in annual plan addressing the needs of DAG 24 25
Total budget allocated by LBs in annual plan addressing the needs of environment, climate change and disaster
26
Number of SM received LIP training
27
No. of LIP exposure visits
28
Number of LIP projects initiated/completed in reporting period (categorized)
29 30
Number of CACs that have received LIP support in current FY
Total Onfarm 1,623
Total Offfarm 361
Total others 20
31 32 33
No. of current and graduated CAC members involved in Micro Finance Institution/cooperatives No. of CAC members received enterprenuership (LIP) training in current FY (categorized by gender and social group -Dalit)
3,278
1,919
Total
Total
140
40
Dalit 90
34
No. of LBs allocated budget for LIP in current FY
-
-
35
Number of DDCs that signed at least one MoU with NGO engaged in social mobilization in the current fiscal year
-
22
36
36
Number of District/Municipality Social Mobilization Committees that organize meeting regularly
-
21
9
II
Downward Accountability ( Output 2) Social Audit
-
6
4
Public Audit
190
12
9
Public Hearing
230
19
9
1,750
989
780
62
14
9
560
168
-
1,358
287
-
736
168
36.00
22.00
42
14
1
2
Number of LBs that conducted social audit, public audit and public hearing as per LBRMM guidelines in the current FY
Number of public audit completed projects Number of LB's where civil society led compliance monitoring introduced
3
4
Number of WCFs in which at least one member received orientation on monitoring and oversight function Number of WCFs that engaged in monitoring & oversight function in the current fiscal year
5 6
Number of WCF's that perform oversight function (public audit)
7
Number of LSPs involved in social mobilization oriented on accountability tools in the current fiscal year
III
LB's Access to Resources ( Output 3)
1
Number of LB's whose own source revenue (OSR) increased by 10 percent in the current fiscal year No. Of municipalities that have introduced Integrated Property tax Number of LB's(DDC & municipality ) whose revenue coverage ratio increased by 10 percent in the current FY
2 3
3
14 10
5
14
9
Number of DDCs/Municipalities prepared Revenue Enhancement and Projection Plan 4 IV
Public Financial Management (Output 4)
VDC
Municipality
Women
DDC
Men 165
15
1 2
Number of VDCs that adopted VDC accounting software and made functional Number of municipalities that adopted accrual accounting system and made functional
57 -
-
Number of VDCs that have introduced simplified expenditure system in the current fiscal year 3
4 5 6
45 Number of DDC/Municipalitties initiated/practiced e-bidding for procurement Number of LBs (DDC & municipality ) that prepared procurement plan in the current fiscal year Number of VDCs in which trained staff on accounting maintain VDC account
V
Capacity Development (Output 5)
1
Number of VDC Secretaries taking responsibility of more than one VDC.
3
Number of VDCs where VDC's secretary are in office for at least 6 months Number of WCF members who received training on social mobilization,
4
5
4
9
14.00
9
283
45 233 -
-
Male
-
-
Female
-
-
1,510
175
810
95
700
80
Number of WCF members who received training on local level planning, monitoring, civic oversight Male Female Number of WCF members who received training on CFLG
6
1,232
81
male
699
56
female
533
25
Number of WCF members who received training on EFLG 7
285
169
male
185
142
female
100
27
-
-
-
-
Number of WCF members who received training on GESI male
8
female
-
-
7,400
3,616
Male
1,184
110
Female
6,216
3,506
Number of CAC members who received training on REFLECT (Total) 9
-
Number of VDC's Secretaries and or Office Assistants who participated in training programme (Total):planning/Monitoring By categry i) LBRMMG/Annual 10 ii) Cross-cutting issues/themes: CFLG, GESI, EFLG, DRR by sex
11
Number of LB's staff (DDC & municipality) who participated in training on periodic/annual planning, monitoring (Total)
GESI 12
EFLG
Other, if any
408
428
208
251
Male
39
56
Female
10
24
Male
25
35
Female
10
10
Male
25
20
7
7
Male
27
36
Female
10
9
Male
35
45
Female
20
9
-
480
Number of stakeholders (LAs, NGOs) other than LB's staff who participated in training/orientation programme on periodic/annual planning, monitoring(Total) 13
Male
Total
95
Female DRR
482
21
Number of LB's staff (DDC & municipality) who participated in training programme on cross cutting issues such as CFLG, GESI, EFLG, DRR . CFLG
Total
Number of LBs and Line agencies staff trained in DPMAS (Total) -
-
Female
-
-
12
21
Number of LBs staff trained in MIS
7
20
15
Number of LBs (DDC and Municipalities) prepared /updated CD plan as per National CD strategy
-
-
16
No. of Social Mobilizers received SM training
121
306
17
Total no. of WCF and CAC members received IG training in current FY
20
60
18
Number of LIP project initiated/completed in reporting period
363
302
VI
Access to Basic Services Including Community Infrastructure ( Output 6)
14
20
-
Male
Number of LBs staff trained in web-based reporting
Female
18
1
Number of new quality labs established in DDCs in current FY
1
2
Number of non-functional quality labs made functional in current FY
1
3
Number of Municipalities implemented Building code
4
No. of masons trained in earth quake resistant building
-
238
25
5
No. of Engineers/Junior Engineers trained in national building codes
-
98
7
-
58
2
2
6
1
Number of Persons provided ToT/MToT/Training on Community mediation
7
Number of Community Mediation Centers established in LBs in the current fiscal year
6
8
No. of community disputes registered in CM Centres
-
-
-
1,436
Birth under 5 yrs.
93,044
24,737
Death
12,811
7,634
Vital event Registration
9
No. of Vital event registration carried in reporting FY
Divorce Migration
15
13
21,593
13,960
Marriage
17,131
8,437
Number of districts where vital registration and social protection MIS established 10
Text Benifitted
4
11
Number of LB'S staff trained on Vital event registration
12
Number of districts covered by vital registration campaign
13
No of Social security beneficiaries and amout in reporting FY
-
17
8 9
1341192000
1,215,104,400
126,087,600
282,993
22,370
Senior citizen 56,110
Dalit Children 72,013
Single women 20,215.00
305363 14
Number of DDCs where grievance mechanism are functional(Focal point appointed, grievance handled).
9
Number of grievances reported to DDCs which could not resolved by VDCs/Municipality 15
1,547
16
Number of places selected for Local economic development projects(sub-urban areas)
17
Number of LED Projects initiated
18
Number of DDCs who prepared Project Funding Matrix (PFM) for the current fiscal year
19
Number of VDCs who prepared Project Funding Matrix (PFM) for the current fiscal year
20
Number of Municipalities who prepared Project Funding Matrix (PFM) for the current fiscal year Project types
Number of projects by type ( road, irrigation, drinking
15
9 280 21 Number of projects
Beneficiaries by sex Men
Women
Beneficiaries by ethinicity DAG NDAG
Remarks
20.1
Number of projects by type ( road, irrigation, drinking water etc,) and number of beneficiaries ( by sex and ethnicity) included in PFM prepared by DDCs
Roads, Bridges & Culverts
441
66,457
63,214
80,396
71,438
WASH
123
18,431
17,197
21,290
21,523
63
16,643
15,623
21,976
15,298
140
9,768
9,875
10,987
10,610
35
6,215
6,248
7,760
6,685
Education
138
18,602
17,479
21,131
21,990
Social Infrastructures
115
18,511
17,413
22,087
20,562
Health
101
13,060
12,813
17,143
15,144
Irrigation Economic Infrastructures Environment
Agriculture
71
8,223
7,746
10,206
7,994
208
21,369
19,101
24,243
23,594
1,435
197,279 Communities contribution in total budget
186,709
237,218
214,837
Promotional Activities Total
Total Budget (Rs.000)
Project Type Roads, Bridges & Culverts
20.2
159,423
17,219
114,553
WASH
23,237
3,700
19,377
Irrigation
11,586
1,911
8,875
23,237
6,151
17,086
9,196
983
8,092
29,456
5,059
25,584
Distribution of budget by Economic Infrastructures type of project ( road, irrigation, drinking water etc. Environment ) in PFM prepared by DDCs Education Social Infrastructures
27,417
3,255
18,512
Health
8,262
956
7,306
Agriculture
5,574
744
4,831
Promotional Activities Total Project types
20.3
Number of projects by type (road, irrigation, drinking water etc. ) and number of beneficiaries ( by sex and ethnicity ) included in PFM prepared by VDCs
LBs Contribution
30,014
3,748
27,913
327,402
43,724
252,130
Number of projects
Beneficiaries by sex Men
Women
Remarks
Beneficiaries by ethinicity DAG NDAG
Roads, Bridges & Culverts
918
105,021
94,481
133,924
114,729
WASH
708
55,739
50,001
80,268
51,869
Irrigation
646
47,047
41,912
68,888
40,335
Economic Infrastructures
719
56,908
50,721
66,258
68,260
Environment
516
42,537
34,920
57,273
42,402
Education
642
55,188
51,570
71,653
61,455
Social Infrastructures
591
53,958
47,035
83,986
41,140
Remarks
20.3
(road, irrigation, drinking water etc. ) and number of beneficiaries ( by sex and ethnicity ) included in PFM prepared by VDCs Health
705
43,536
34,726
55,849
41,369
Agriculture
622
54,470
48,773
66,929
61,436
Promotional Activities
935
49,827
43,704
62,094
53,576
7,002
564,231 Communities contribution in total budget
497,842
747,122
576,572
Total
Total Budget (Rs.000)
Project Type Roads, Bridges & Culverts WASH
20.4
Irrigation Distribution of budget by Economic Infrastructures type of project ( road, irrigation, drinking water etc. Environment ) in PFM prepared by VDCs Education
25,900
136,164
74,513
11,632
62,266
67,756
10,118
54,235
66,694
9,963
52,685
49,972
8,960
46,749
58,802
8,357
43,738
41,050
6,499
34,648
Health
51,395
11,025
57,451
Agriculture
82,796
11,321
60,979
Promotional Activities
48,129
8,643
45,990
709,830
112,418
594,904
Project types
20.5
168,722
Social Infrastructures
Total
Number of projects by type ( road, irrigation, drinking water etc,) and number of beneficiaries ( by sex and ethnicity) included in PFM prepared by Municipalities
Number of projects
Men
Women
Beneficiaries by ethinicity DAG NDAG
Remarks
534
90,686
82,580
115,623
99,904
WASH
228
23,182
21,965
27,320
28,403
Irrigation
144
9,672
9,287
10,899
12,098
Economic Infrastructures
160
13,574
12,821
16,066
15,352
Environment
123
10,225
10,219
14,482
11,578
Education
306
18,943
17,800
28,593
24,239
Social Infrastructures
258
22,169
19,851
30,790
20,365
Health
134
17,664
13,888
20,837
18,352
53
6,860
6,804
8,909
7,845
604
46,094
43,201
62,678
49,254
2,544
259,069 Communities contribution in total budget
238,416
336,199
287,390
Promotional Activities Total Project Type
20.6
Beneficiaries by sex
Remarks
Roads, Bridges & Culverts
Agriculture
Distribution of budget by type of project ( road, irrigation, drinking water etc.
LBs Contribution
Total Budget (Rs.000)
LBs Contribution
Remarks
Roads, Bridges & Culverts WASH
20.6
Irrigation Distribution of budget by Economic Infrastructures type of project ( road, irrigation, drinking water etc. Environment ) in PFM prepared by Education Municipalities. Social Infrastructures Health Agriculture
134,234
5,615
34,238
8,247
1,387
8,124
19,136
2,326
17,518
26,043
4,019
26,753
40,419
3,927
32,941
52,396
3,708
30,246
14,423
1,614
14,005
5,504
681
4,599
124,712
9,428
69,704
Total
503,088
50,000
372,361
Number of Userâ&#x20AC;&#x2122;s Committees formed by LBs to implement projects
22
Amount of budget released to Userâ&#x20AC;&#x2122;s Committee to implement projects
23
Number of LBs that conducted gender budget audit
7,002
2,544
1,435
709,830
503,088
327,402
2
6.00
Planning & Monitoring ( Output 7)
1
Number of LBs that prepared periodic plan in Current FY
2
Number of LBs that prepared annual monitoring plan
3
17,294
38,461
Promotional Activities 21
VII
173,747
Number of LBs where supervision & Monitoring Committees are functional ( regular meeting/monitoring visits took place)
5
-
7
50
6
9
328
19
9
4
Number of DDCs where DPMAS functional
6
Number of LBs where CFLG adopted
253
Number of LBs where Balbhela organized in planning process 7
8 9 10 11 12
Number of LBs where EFLG adopted Number of projects in which Environmental Management Plan (EMP) prepared as per guidelines. Number of physical development projects conducted IEE/EIA as per rules
13
9
272
9
7
28
10
9
-
6
4
516
123
35
-
7
2
9
2
6
Number of LBs having DRR plan prepared/integrated in periodic plan Number of LBs where gender responsive budget adopted Number of LBs that conducted gender audit
-
-
13 14
Number of LBs those prepared Resource maps /GIS Maps Number of LBs those have implicit provision of youth participation in planning process
68
21
9
240
19
9
No. Of DDCs/ Municipalities those prepared Transport master plan (DTMP/MTMP) 15 16
17
14 No. of VDCs organized IPFC meeting
Number of LBs that follow membership in local committee as per LB's Resource Mobilization Guidelines
9
328
Integrated Plan Formulation Committee
305
18
9
Supervision & Monitoring Committee
210
21
9
User's Committee
328
21
9
VDC Level LIP Status (Fiscal Year 69/70 to 71/72)
Annex 3
Livestock/Dairy
Others
Beneficiaries
0
0
5
0
0
0
0
9
70
4
66
70
3600000
0
0
0
0
0
0
0
0
1
39
2
37
39
4400000
3 Achham
62
62
7
41
14
16
4
0
20
211
15
12
0
12
0
250
38
0
0
0
3
3
0
3
1
47
316
85
232
316
6200000
4 Bajura
24
24
19
5
0
3
0
0
3
114
4
12
0
0
1
131
16
0
0
0
3
0
0
0
0
18
152
48
103
152
2400000
5 Bajhang
42
42
15
24
0
4
0
0
4
161
3
8
0
0
1
173
25
0
0
0
5
5
0
0
0
35
212
29
183
212
3900000
6 Darchula
36
36
1
21
11
3
0
0
3
121
0
7
0
3
3
133
6
0
0
0
4
3
1
0
0
14
150
30
120
150
3300000
7 Baitadi
56
56
8
31
17
5
1
0
7
185
3
35
1
4
1
231
20
0
1
0
9
9
1
0
0
41
278
54
224
278
5600000
8 Dadeldhura
18
18
5
12
0
1
0
0
1
96
0
5
0
0
0
101
5
1
0
0
5
3
0
0
1
16
118
13
105
118
1700000
9 Kanchnapur
9
9
1
3
5
9
0
0
9
15
6
0
0
0
0
21
5
0
1
37
1
0
0
0
0
44
4
71
328
328
35
22
56
149
110
48
7
3
57
969
47
81
1
22
7
1128
120
1
3
37
3
3
3
226
Total Femal
Male
Total
Total
Rabbit
Pig
Goat
S.N Total
75 1411
269
1141
Municipality Level LIP Status (Fiscal Year 69/70 to 71/72)
1
1
3
0
0
0
1
14
48
0
48
48
700000
8
1
0
3
0
3
8
57
0
0
1
66
1
0
0
0
0
0
0
0
0
1
70
0
70
70
900000
3 Atariya 4 Lamkichuha
13
4
0
1
3
0
0
0
1
4
0
0
0
5
6
0
0
0
0
0
0
0
0
6
11
0
11
11
400000
15
2
1
0
1
2
0
2
1
1
0
0
0
2
4
0
1
0
0
0
0
0
1
7
11
0
11
11
200000
5 Ghodaghodi 6 Bhajani Trisakti
9
2
0
0
2
1
0
1
0
2
0
0
0
2
0
0
0
0
0
0
0
0
0
0
3
0
3
3
200000
12
3
0
0
3
0
0
0
0
0
0
0
0
0
6
0
0
0
0
0
0
0
0
6
6
0
6
6
300000
7 Dipayal Silgadhi 8 Mangalsen
14
10
0
10
0
3
0
3
34
0
0
3
3
39 13
0
0
0
9
1
0
0
0
23
65
0
65
65
1000000
11
5
0
3
2
0
0
0
14
0
0
0
0
14 10
0
0
0
0
0
0
0
0
10
24
3
22
24
500000
9 Sanfebagar 10 Badimalika
12
8
0
3
4
1
0
1
18
1
3
0
0
23
0
0
0
0
0
0
0
0
0
0
24
0
24
24
700000
12
3
3
0
0
0
0
0
12
0
8
0
0
20
0
0
0
0
0
0
0
0
0
0
20
3
17
20
300000
11 Jayaprithibi 12 Api
15
5
1
4
0
0
0
0
22
1
3
0
0
26
3
0
0
0
1
0
0
0
0
4
30
4
26
30
500000
17
5
2
2
1
0
0
0
20
1
5
0
0
26
3
0
0
0
1
0
0
1
0
5
31
13
18
31
500000
13 Dashrathchand 14 Patan
13
12
0
12
0
1
0
1
60
0
0
4
0
64
5
0
0
0
1
0
0
0
0
7
72
0
72
72
1200000
13
6
0
4
2
0
0
0
14
0
7
0
3
23
1
0
0
0
0
1
1
0
0
4
27
8
18
26
600000
15 Amargadhi 16 Parsuram
11
8
0
8
0
3
0
3
30
1
3
0
9
43
3
1
0
0
4
0
0
0
0
8
53
7
47
53
800000
12
2
2
0
0
0
1
1
1
7
0
0
0
8
0
0
0
0
0
0
0
0
0
0
9
0
9
9
200000
17 Bheemdatt 18 Punarbash
19
9
0
9
0
1
0
1
30
5
4
1
1
42
8
0
0
0
7
1
0
0
0
16
59
7
53
60
900000
15
3
1
0
2
0
0
0
3
0
0
0
0
3
0
0
0
0
0
0
0
0
0
0
3
0
3
3
300000
19 Belauri 20 Dodhara Chandani
14
3
0
1
2
0
0
0
4
0
0
0
3
7
0
0
0
0
0
0
0
0
0
0
7
0
7
7
300000
10
2
0
1
1
2
0
2
5
1
1
0
0
7
1
0
0
1
1
0
0
0
0
4
13
0
13
13
200000
21 Jhalari
11
2
0
1
1
2
0
2
0
2
5
0
0
7
0
0
0
0
0
0
0
0
0
0
9
0
9
9
271
110
Total
18
67
24
20
1
21
97
38
8
22
457
71
1
3
3
27
4
1
1
3
114
593
43
Total
Femal
Male
Tailoring
Furniture
Total
Pig
293
550
Total Amount
0
Total Projects
8
Total
Leather shoe
33
Metal Workshop
3
Auto Rikshwa
0
Hair Dreesing/Beauty
0
Retail/Tea/Cosmeti
13
Buffalo
17
Cow
1
Poultry
0
Goat
1
Total
0
Ginger
7
Vegetable
0
9
2071/72
7
9
2070/71
14
2069/70
1 Dhangadhi 2 Tikapur
S.N
Carpet
Beneficiaries
Candle
Others
Total no of CACs
Livestock/Dairy
Total VDCs/Wards
Agriculture/Irrig
Name of district
LIP Rece.CAC
Total Amount
0
1
Total Projects
4
31
Leather shoe
57
0
Bamboo
0
3
Tailoring Metal Workshop Carpet
1
0
Tent House
0
3
Hair Dreesing/Beaut
0
0
Furniture
16
26
Retail/Tea/Cos metick/Meat
39
7
Buffalo
4
0
Cow
3
1
Poultry
0
5
Total
1
37
Ginger
26
7
Mushroom
5
0
Vegetable
0
50
2071/72
31
50
2070/71
31
2 Doti
2069/70
1 Kailali
Name of district
Total no of CACs
Agriculture/Irrigat
Total VDCs/Wards
LIP Rece.CAC
593
200000 10900000
75 1411
900000 32000000
GoN/MoFALD Local Governance and Community Development Programme (LGCDP-II) Regional Coordination Unit, Dhangadhi Annual ICT RBM Report FY 71/72 SN
1
Indicators
5
Dadeldhura Doti
Achham
Bajura
Bajhang
Darchula Remarks
Baitadi
16
25
8
10
9
7
Number of employees that can use office package
21
18
26
11
9
10
5
10
8
15
4
6
5
3
7
5
8
4
4
5
2
ICT Efficiency of Local Body staffs Number of employees that can un/install
Basic Training (email, internet, Office Pacakge)
4
kanchanpur
18
Number of employees that can troubleshoot hardware/ problem problems
3
Kailali
Number of employees that can use internet, email
software/drivers
2
District 4 4 2 1 22
15
20
Google (Groups, Drive, Hangout and other features of google) training
22
15
20
Server/Desktop
12
21
10
9
9
9
Solar Power(1/0)
1
1
1
1
1
1
free wifi zone (1/0)
1
0
1
0
0
0
Digital display board (1/0)
0
0
0
0
0
Group SMS (1/0)
0
0
1
1
1
1
Audio Notice Board (yes=1/No=0)
1
1
0
1
1
1
Network Matarial (Router, Switch,Hub)
5
8
8
4
4
4
File server ( 1/ 0 )
1
1
1
1
1
1
1
0
1
1
0
1
CAC WCF
0 0
ODF LSP Cluster New MUN Political boundary Landuse
1 1 1 1 1
0 0 0 1 1 1 1
1 1 1 1
0 0 0 1 1 1 1
0 0 0 0 1 1 1
1 1 0 0 1 1 1
Capacity building training Hardware/ Software tourbleshoot provided to LBs Staffs trianing
ICT infrastructure of Local Body
Computer networking & file sharing system Printer server
GIS Map updated
1 1
8
7
Regular update social media (facebook , twitter)
6
MIS
7
Document Management System
8
Online Reporting Systems update
9
1
1
1
1
0
1
website crashed
1
0
1
0
1
Annual Reprot update
1
1
1
1
1
1
Digital archives
1
0
1
1
1
1
WBRS
1
DPMAS SMDB
0 1
1 1
0 0 0 0 0
1 1 1 process 0 0 0 1
1 0
Darta Chalani Accest management Personal Information System Filed Visit Report success story/video/photo collection
1 0 0 0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
1 0 1 0 0 0 0 0
1
1
1
1
1
1
0
0
0
0
0
1 1 0
1 1 0
1 1 0
1 1 0
1 1 0
Website update
Automation/Digitization of Official Procedures Queue Managment System NGO record management Biometric Attendance
Grievance Handling system
Sectoral Offices information system Monthly Reports/Annual Reporting
10
11
Digital Citizion Charter
Government services delivered electronically
IPT Vital Registration MIS Accural accounting
0
1 1 0
GoN/MoFALD Local Governance and Community Development Programme (LGCDP-II) Regional Coordination Unit, Dhangadhi Annual ICT RBM Report FY 71/72 SN
Indicators
1
2
ICT Efficiency of Local Body staffs
Capacity building training provided to LBs Staffs
Municipality Dhangadhi Bheemdatta Tikapur Amargadhi Dipyal Singadhi Dashrathchan Remarks
Number of employees that can use internet, email
10
12
15
7
12
7
Number of employees that can use office package
20
17
17
7
12
8
4
3
2
1
4
1
1
1
30
3
30
3
16
30 15
0 6
6
9
1
1
1
1
0
0
0
0
0
0
0 1
0 0 1
0 0 1
0 0 1
0 0 0
1 1 1
1 1 0
1 1 1
0 0
0 0
Number of employees that can un/install software/drivers
3
Number of employees that can troubleshoot hardware/ problem problems Basic Training (email, internet, Office Pacakge)
3 10
Hardware/ Software tourbleshoot trianing
10
4
Google (Groups, Drive, Hangout and other features of google) training
3
4
Server/Desktop
20
Solar Power(1/0)
0
free wifi zone (1/0)
0
ICT infrastructure of Local Digital display board (1/0) Body
0
Group SMS (1/0) Audio Notice Board (yes=1/No=0)
0 1
Network Matarial (Router, Switch,Hub)
1
Computer networking & File server ( 1/ 0 ) file sharing system Printer server
1 0
1 1 0
1 1
0 0
0 0
0 0
1
CAC
5
GIS Map updated
WCF ODF
6
MIS
7
Document Management System
8
9
LSP Cluster New MUN Political boundary Landuse भूमि प्रयोग (Landuse)
0 0 1 1 1
Regular update social media (facebook , twitter)
1
Website update Annual Reprot update
1 1
Digital archives
0
WBRS Online Reporting Systems DPMAS update SMDB Darta Chalani Accest management Personal Information System Filed Visit Report success story/video/photo collection
Automation/Digitization of Queue Managment System Official Procedures
1 1 1
0 0 0 1 1
0 0 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
0 1 0 0 0 0 0 0 0
0 1 0 0 0 0 0 0 0
0 0 0 1
0 0 0
0 0 1 0 0
0 1 1 1 0 0 0 0 0
0n process
0 0 0 0
0 0 0 0 0
1 0
0 0
0 0
0 0
0 0
0 0
1 1
1 1 1
1 1 0
0 0 0
1 0 1
1 1 0
1 1
0 0 1 1 1
0 0 0 1 0
1
1 1 1
NGO record management Biometric Attendance Grievance Handling system
Sectoral Offices information system Monthly Reports/Annual Reporting
10
Digital Citizion Charter IPT
11
Government services delivered electronically
Vital Registration MIS Accural accounting
1
Government of Nepal Ministry of Federal Affairs and Local Development
Local Governance and Community Development Program (LGCDP) II Regional Coordination Unit - Dhangadhi ICT Progress Report, LGCDP, RCU Dhangadhi SN
1
2
District
Achham
Audio Notice Board status
1618097620144
Socail Media
Websites/Facebook update status
Printer Sharing ,Working on upgrading internet speed from Being Updated Regularly 384 kbps to 512 kbps from Nepal www.facebook.com/ddc. Telecom(No other local ISP achham available)
Baitadi
updated regularly https://www.facebook.co m/ddcbaitadi
3
Bajhang
1618092421144 www.facebook.com/ddcb ajhang
DMAS
-
-
-
GIS Map Update
WBRS Reporting
Regular IT support to LBs
Training Conducted for LBS
Feedback
No,But Supporting Individually
Need ICT training Programme activity in LGCDP
updated
Regularly Being WBRS BHAG-2 Entry Suported,Upgrding Windows XP ongoing to Window7 in all DDCS laptop/desktop Computer
updated
WBRS Bhag-2 Entry ongoing
Regular support on various It related issues such as Upgrating OS, installing OS and other essential softwares
No
Need of ICT related training
updated
WBRS Bhag-2 Entry ongoing
Regular Support- creating fb id, skype id, gmail id, installing printer driver,installing antiviruses, upgrading Windows in various laptops/desktops Computer
No
Need of ICT related training activity
updated
bhag2 entry in progress
regular support as per requirements of staffs
not started yet
need detail guidelines about working on local
Completed 3 days training on Internet and application to LB No Training, Providing support individually
Need of website and website Need of ICT related training
Completed 7 days training on Basic Compter and application to LB staffs
Need of website and website training
www.facebook.com/ddcb ajura
Bajura
1618097541024
5
Dadeldhura
1618096410051
6
Darchula
1618093410033
7
Kailali
1618091524747
www.facebook.com/ddck ailali
8
Kanchanpur
1618099521147
www.facebook.com/ddck website updated regularly anchanpur
Doti
Printer sharing, Internet Speed upgrade
Updated Regularly DDC SMS System, File and Printer www.ddcbajhang.gov.np Sharing , Working on Toll-free https://www.facebook.co number, CCTV and upgrading m/DDCBajhang internet speed for ddc
4
9
Innovation/ Creativity activates performed
https://www.facebook.co m/pages/जिविस-डडेल्धरु ा
updated regularly
trying to upgrade internet from 256kbps to 1mbps dedicated
Facebook page updated regularly
Preparing District Fact Sheet, Printer and file sharing
Not in use
Up to date
WBRS ongoing
Providing regular IT support
Internet network Extended in every department, Installing optical fiber network(in
Not in use
up to date
WBRS ongoing
Providing regular IT support
https://www.facebook.co m/DDCdarchula
Facebook page and
Facebook page updated regularly
1618094420156 https://www.facebook.co m/Doti.DDC
Printer sharing, Internet Speed upgrade and co-ordination with LSPs
Not in use
Up to date
WBRS ongoing
Providing regular IT support
Government of Nepal Ministry of Federal Affairs and Local Development
Local Governance and Community Development Program (LGCDP) II Regional Coordination Unit - Dhangadhi ICT Progress Report SN Municipality
Audio Notice Board status
1 Dashrathchand
2
Amargadhi
3
Tikapur
Social Media
www.facebook.com/da shrathchandmun 1618096410022
www.facebook.com/a margadhimun
Websites/Facebook update status
Innovation/ Creativity activates performed
updated regularly (https://www.facebook.com
Printer, File Sharing,Regular Maintenance of computer,printer,photocopy Internet Speed upgrade
DPMAS
updated
updated regularly and new website is Internet speed upgraded up to 1mbps but due fault in progress. of ISP not working propely.
updated regularly and new website is in progress.
printer sharing,maintenance of computer,memory management of computer system
"Facebook page updated regularly and website in progress" "Facebook page updated regularly but we don't have website "
Lan Networking, File Sharing, Upgrading Net Speed, E-attendance System
GIS Map Update
WBRS Reporting Ongoing
Updated
Ongoing
not yet plan for ashar
ongoing
https://www.facebook. com/tikapurmp 4
Dhangadi
1618091520733
https://www.facebook. com/dhangadhimun
5
Bhimdutta
1618099525333
https://www.facebook. com/bheemdattamun https://www.facebook.
6
Silgadi
1618094420297
com/pages/DipayalSilgadhi-municipality
Lan Networking, File Sharing, Upgrading Net Speed,
-
Updated Updated
WBRS ongoing WBRS ongoing
Regular IT support to LBs
Training Conducted for LBS
Providing regular IT support NO to LBs staffs by creating social media ID,regular Regular support to the the application has submitted to EO but staffs and maintainance of the EO got transfeered.It being 2 computer and Installation months new EO has not arrived but regular support to the staffs and maintainance of completed 2days training on Basic computer and Installation Computer Course for staffs,ward of Windows-7 to the seceratary,social mobiliser computer those who completed 2days training on Basic support. Computer Course for staffs,ward Providing regular IT support seceratary,social mobiliser Providing regular IT support
Not yet
Feedback
Remarks
Need of Website and IT related training
Fascinating staffs from ICT
Need of Website and IT related training
when i asked to IO for ICT training ,IO said who will give the
need ICT training Programme activity in LGCDP Programme
Need ICT training Programme activity in LGCDP Programme Need ICT training Programme activity in LGCDP Programme
Annex 5
Progress Status of Demand Based Activities at DDC and Municipality Level (071/072) DDCs
Darchula
Kanchanpur
Training Name MCPM orientation Orientation training on Local self governance act, regulation and Manual to the new VDC Secretaries Revenu management orientation
Venue DDC hall, Darchula DDC hall, Darchula
Bhawana training hall
CFLG orientation
DDC hall
Right to information
DDC, Kanchanpur
GRB
DDC, Kanchanpur
Web based Minicipality Level
Orientation on building code of conduct
Api
Orientation to the municipal staff and ward secretaries on different policy, guideline and act
F
M
Other No of Participants F
M
F
M Approved budget Expended budget
2
49
5
1
0
1
6
36
11
38
2
11
0
1
0
3
1
6
1
10
1
33
1
3
1
1
5
22
7
26
New Secretaries
Tax committee, DAO, NCC, Businessman, taxpayer Line Agenciess, Political partie,NGO federation, Media and DDC staff VDCs secretaries and DDC staff DDC staff, political parity and sectroal agencies
Municipality staff, Bhawana Hall, Darchla
Janjati
Political parties, NCC, Contractor, Traidars, NGO and civil society
Bhawana Hall, Darchla
1
27
4
23
1
24
3
21
1
26
5
21
1
12
1
11
9
42
2
17
1
2
51
2
19
2
12
2
36
5
1
0
0
1
29
6
11 30
1
21
0
1
0
0
2
18
2
19
Bhawana Hall, Darchla
Ward Secrateries, SM and Municipal staff
1
40
0
3
0
1
3
33
3
37
NIIT training center
Ward Secrateries, SM and Municipal staff
90
14
0
0
0
0
3
11
3
11
Positive attitude building training
DDC hall
Municipality staffs,sm,wcf members and other stakeholders members of supervision and monitoring committee
2
107
33
74
1
29
10
19
3
25
0
25
Orientation on LSGA, guidelint line
290000
256685
245000
244880
155000
155000
235000
235000
460000
460000
230000
230000
225000
225000
Muns staff, ward secretaries
Interaction with Municipal tax counsile committee and NCC Computer training for Municipal staff
Orientation to municipal level monitoring and supervision committee Dashrathchan Orientation on revenue enhancement to d municipal staffs study to promote and conservation of the public land and support to construct infrastructure Attriya Local Bodies Account training
Dodharachandani Mun
DDC staffs and political parties
Municipality staff, Political parties, WCF, CAC coordinator Municipality staff,
Orientation on public procurement
Orientation on Public Private Partnership
Duration Particip Dalit ants F M
DDC,Kanchanpur
Orientation on MCPM Belauri
Target group
Municiplity hall Municiplity hall
staffs of municipality
Municiplity hall
Local body staffs,line agency representatives,different committees
Municipality Hall
Accountant and ward secretary
1
2
20
1
3
1
15
2
Municipality Hall
all Staff, ward secretary
1
2
20
1
3
1
15
2
Orientation on MCPM Orientation on Web based reporting Inventory Management software developed
NA
Annex 6 A
Project Funding Matrix of DDCs Annual Progress Report (Fiscal Year 2071/72) SN
1
2
Districts
Bajura
Bajhang
Sector
Other Stakehol ders
UC
LBs
Benifited Population Disadvantage Group (DAG)
Total
Male
Female
Others
Children Total
Male
Total
Children Total
Female
Male
Total
Children
Female
5
39995
5599
0
45595
1293
1150
431
2874
1014
917
483
2414
2307
2067
914
5288
WASH
5
2379
333
0
2712
1821
1619
607
4047
1530
1384
728
3642
3351
3003
1335
7689
Irrigation
1
174
24
0
199
632
562
211
1404
569
515
271
1355
1201
1077
482
2759
Economic Infrastructures
7
1701
238
0
1940
224
199
75
497
247
224
118
589
471
423
192
1086
Environment
0
1519
213
0
1731
158
141
53
352
206
187
98
491
365
327
151
843
Education
10
1975
277
0
2252
1405
1249
468
3122
1241
1123
591
2954
2646
2371
1059
6076
Social Infrastructures
0
0
0
0
0
1801
1601
600
4003
1514
1370
721
3604
3315
2971
1321
7607
Health
2
244
34
0
278
1049
933
350
2332
788
713
375
1876
1837
1646
725
4208
Agriculture
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Promotional Activities
16
Total
46
Roads, Bridges & Culverts
46
17600
300
0
17900
1688
1500
WASH
36
10700
2040
0
12740
1623
Irrigation
14
3500
700
0
4200
3645
Economic Infrastructures
7
4251
4250
0
8501
Environment
3
1000
200
0
1200
Education
9
780
150
0
Social Infrastructures
6
2500
500
Health
3
500
100
Promotional Activities Total
Achham
Actual cost sharing (NRs in '000)
Roads, Bridges & Culverts
Agriculture
3
Number of Projects completed
2402 50390
336 7055
0 0
2738 57445
901 9285
801 8254
300 3095
2003 20634
1514 8622
1370 7801
721 4106
3604 20529
2415 17907
2171 16055
1021 7201
5607 41163
563
3750
1470
1330
700
3500
3158
2830
1263
7250
1443
541
3607
1974
1786
940
4700
3597
3229
1481
8307
3240
1215
8100
1365
1235
650
3250
5010
4475
1865
11350
968
860
323
2150
357
323
170
850
1325
1183
493
3000
756
672
252
1680
281
255
134
670
1037
927
386
2350
930
1752
1557
584
3893
2352
2128
1120
5600
4104
3685
1704
9493
0
3000
360
320
120
800
378
342
180
900
738
662
300
1700
0
600
338
300
113
750
588
532
280
1400
926
832
393
2150
5
1300
260
0
1560
2970
2640
990
6600
2100
1900
1000
5000
5070
4540
1990
11600
29
4919
1000
0
5919
2160
1920
720
4800
1386
1254
660
3300
3546
3174
1380
8100
158
47050
9500
0
56550
16259
14452
5420
36130
12251
11085
5834
29170
28510
25537
11254
65300
Roads, Bridges & Culverts
46
10617
1805
0
12422
13914
12368
4638
30920
12475
11287
5941
29703
26389
23655
10579
60623
WASH
21
550
94
0
644
2730
2426
910
6066
2630
2380
1253
6263
5360
4806
2162
12329
Irrigation
8
1400
238
0
1638
1700
1511
567
3778
1178
1066
561
2805
2878
2577
1128
6583
Economic Infrastructures
9
530
90
0
620
450
400
150
1000
1095
991
522
2608
1545
1391
672
3608
Environment
3
886
151
0
1037
117
104
39
260
265
239
126
630
382
343
165
890
Education
4
350
60
0
410
261
232
87
580
70
64
34
168
331
296
121
748
3
Achham Social Infrastructures
10
2025
344
0
2369
738
656
246
1640
525
475
250
1250
1263
1131
496
2890
Health
3
303
52
0
355
554
493
185
1232
152
138
73
363
707
631
257
1595
Agriculture
2
908
154
0
1062
203
180
68
450
193
175
92
460
396
355
160
910
Promotional Activities Total 4
Doti
27 133
4637 22206
788 3775
0 0
5425 25981
811 21478
721 19091
270 7159
1802 47728
714 19298
646 17460
340 9190
1701 45949
1525 40776
1367 36552
611 16349
3503 93677
Roads, Bridges & Culverts
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
WASH
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Irrigation
1
500
50
0
550
10
10
10
30
5
5
5
15
15
15
15
45
Economic Infrastructures
1
500
50
0
550
0
50
0
50
0
35
0
35
0
85
0
85
Environment
3
1500
150
0
1650
150
330
150
630
100
150
250
500
250
480
400
1130
Education
1
395
40
0
435
0
0
0
0
300
150
0
450
300
150
0
450
Social Infrastructures
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
49
3215
322
0
3537
94
557
1133
1784
241
448
714
1403
335
1005
1847
3187
17
2577
258
0
2835
400
200
250
850
300
200
150
650
700
400
400
1500
Health Agriculture Promotional Activities Total 5
Roads, Bridges & Culverts
Kailali
Darchula
8687
869
0
9556
654
1147
1543
3344
946
988
1119
3053
1600
2135
2662
6397
92
10332
6974
27651
44957
7654
6925
3645
18224
7501
6786
3572
17859
15155
13711
7217
36083
WASH
3
0
0
166
166
0
0
0
0
0
0
0
0
0
0
0
0
Irrigation
4
400
250
800
1450
964
872
459
2296
945
855
450
2250
1909
1728
909
4546
Economic Infrastructures
1
100
0
0
100
4
4
2
10
4
4
2
10
8
8
4
20
Environment
3
1435
34
0
1469
751
680
358
1789
736
666
351
1753
1488
1346
708
3542
Education
26
3735
2525
5798
12058
2318
2098
1104
5520
2272
2056
1082
5410
4590
4153
2186
10930
Social Infrastructures
43
5883
1173
5650
12706
3570
3230
1700
8500
3499
3165
1666
8330
7069
6395
3366
16830
Health
1
400
47
0
447
3303
2988
1573
7864
3237
2929
1541
7707
6540
5917
3114
15571
Agriculture
4
428
0
0
428
86
78
41
204
84
76
40
200
170
153
81
404
Promotional Activities
5
1523
24
0
1548
2321
2100
1105
5525
2274
2058
1083
5415
4595
4157
2188
10940
182
24237
11028
40065
75331
20971
18974
9986
49932
20552
18594
9787
48933
41523
37568
19773
98864
Roads, Bridges & Culverts
15
20700
70
0
20770
1806
2576
906
5288
340
486
270
1096
2146
3062
1176
6384
WASH
13
1115
112
0
1227
335
542
565
1442
410
439
337
1186
745
981
902
2628
Total
6
72
Irrigation
3
150
15
0
165
56
57
65
178
10
13
8
31
66
70
73
209
Economic Infrastructures
4
1150
115
0
1265
250
302
192
744
307
315
281
903
557
617
473
1647
Environment Education
10
525
53
0
578
166
67
565
798
41
45
177
263
207
112
742
1061
Social Infrastructures
14
1945
195
0
2140
397
471
264
1132
586
602
193
1381
983
1073
457
2513
1
50
5
0
55
25
34
45
104
15
21
28
64
40
55
73
168
Health
6
Darchula
Agriculture Promotional Activities
8
425
43
0
468
212
240
299
751
202
225
126
553
414
465
425
1304
68
26060
606
0
26666
3247
4289
2901
10437
1911
2146
1420
5477
5158
6435
4321
15914
Roads, Bridges & Culverts
22
1,419
338
-
1757
1052
935
351
2337
982
888
467
2337
2033
1823
818
4674
WASH
25
2,324
747
-
3064
1567
1393
522
3482
1462
1323
696
3482
3029
2716
1219
6964
Irrigation
11
1,415
425
-
1840
610
542
203
1355
569
515
271
1355
1179
1057
474
2710
-
-
0
0
0
0
0
0
0
0
0
0
0
0
0
Total
Economic Infrastructures 7
Baitadi
Environment
4
672
73
20
8554
438
61
Social Infrastructures
10
740
148
-
Health
0
0
-
-
Agriculture
0
0
-
-
Promotional Activities
221
196
74
491
206
187
98
491
427
383
172
982
1329
1182
443
2954
1241
1123
591
2954
2570
2304
1034
5908
888
617
549
206
1372
576
521
274
1372
1194
1070
480
2744
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
-
3878
64
2295
1622
1442
541
3604
1514
1370
721
3604
3135
2811
1261
7208
19001
2234
61
12718
7018
6238
2339
15595
6550
5926
3119
15595
13568
12164
5458
31190
Roads, Bridges & Culverts
6
2428
413
0
2841
244
217
81
542
237
225
115
577
480
442
197
922
WASH
5
1444
245
0
1689
115
102
38
255
94
90
46
230
209
192
84
401
Irrigation
3
395
67
0
462
79
70
26
176
75
71
37
183
154
142
63
296
-
23
3960
673
0
4633
206
183
69
458
108
103
53
263
314
286
121
600
Environment
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Education
5
6313
1073
0
7386
199
177
66
443
263
250
128
642
463
428
195
890
Social Infrastructures
8
4129
702
0
4831
448
398
149
996
318
302
155
775
766
701
304
1467
Health
1
370
63
0
433
7
6
2
15
5
5
2
12
12
11
5
22
Promotional Activities Total
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
13
5106
868
0
5974
132
117
44
293
74
71
36
181
206
188
80
394
64
24145
4105
0
28250
1430
1271
477
3178
1174
1117
573
2863
2604
2388
1049
4992
209
11462
1719
0
13181
8091
8370
2469
16461
6698
7254
2790
13952
14789
15624
5260
30413
WASH
15
866
130
0
996
1160
1231
359
2391
980
1040
404
2020
2140
2271
763
4411
Irrigation
18
941
141
0
1082
2310
2349
699
4659
1920
2134
811
4054
4230
4483
1510
8713
Economic Infrastructures
88
4894
734
0
5628
2980
3098
912
6078
2568
2785
1071
5353
5548
5883
1982
11431
Environment
19
1080
162
0
1242
1234
1324
384
2558
1032
1118
430
2150
2266
2442
814
4708
Education
53
2957
444
0
3401
1687
2134
573
3821
1704
1846
710
3550
3391
3980
1283
7371
Social Infrastructures
24
1290
193
0
1483
1768
1876
547
3644
1416
1534
590
2950
3184
3410
1137
6594
Health
41
2224
334
0
2558
1541
1521
459
3062
1123
1196
464
2319
2664
2717
923
5381
Agriculture
60
2194
329
0
2524
1432
1520
443
2952
1156
1178
467
2334
2588
2698
910
5286
Promotional Activities
46
2445
367
0
2812
2563
2052
692
4615
2270
2316
917
4586
4833
4368
1609
9201
Roads, Bridges & Culverts
Kanchanpur
866 2007
47
Agriculture
9
-
139
Economic Infrastructures Dadeldhura
0
Education
Total
8
0
Total
573
30353
4553
0
34906
24766
25475
7536
50241
20867
22401
8654
43268
45633
47876
16190
93509
1435
252130
43724
40126
327402
105107
99191
40456
237218
92171
87518
43801
214837
197279
186709
84256
451005
Road,Bridge,Culvert
441
114553
17219
27651
159423
35741
34040
13083
80396
30716
29174
14338
71438
66457
63214
27422
151636
Irrigation
123
19377
3700
166
23237
9351
8756
3542
21290
9081
8442
4404
21523
18431
17197
7947
42728
Far-West DDC PFM Compiled Summary
Grand Total Region
WASH
63
8875
1911
800
11586
10006
9214
3455
21976
6636
6409
3063
15298
16643
15623
6518
37211
140
17086
6151
0
23237
5081
5096
1721
10987
4686
4779
2215
10610
9768
9875
3937
21476
35
8092
983
0
9196
3388
3447
1309
7760
2827
2801
1487
6685
6215
6248
2796
14445
Health
138
25584
5059
5859
29456
9118
8695
3891
21131
9484
8784
4432
21990
18602
17479
8323
42926
Economoc infrastructure
115
18512
3255
5650
27417
9700
9101
3832
22087
8811
8312
4029
20562
18511
17413
7861
42345
Social Infrastructure
Education Environment
101
7306
956
0
8262
6911
6832
3859
17143
6149
5981
3478
15144
13060
12813
7337
32281
Agriculture
71
4831
744
0
5574
4690
4418
1541
10206
3533
3329
1599
7994
8223
7746
3140
18200
Promotional
208
27913
3748
0
30014
11121
9592
4222
24243
10248
9509
4754
23594
21369
19101
8976
47756
1435
252130
43724
40126
327402
105107
99191
40456
237218
92171
87518
43801
214837
197279
186709
84256
451005
Annex 6b Project Funding Matrix of Minicipality Annual Progress Report (Fiscal year 2071/72)
ga dh i
1
Dh an
SN
M un ici pa lit y
Actual cost sharing (NRs in '000) Sector
Number of Projects completed
Other Stakehold ers
UC
LBs
Benifited Population
Disadvantage Group (DAG)
Total Male
Children
Female
Others
Total
Male
Total
Children Total
Female
Male
Total Children
Female
Roads, Bridges & Culverts
67
32891
5591
38482
8201
7801
4001
20003
7558
7190
3687
18435
15760
14991
7688
38438
WASH
12
777
132
910
1721
1637
839
4197
1991
1893
971
4855
3711
3530
1810
9052
Irrigation
2
60
10
70
961
914
469
2343
1863
1772
909
4543
2823
2686
1377
6886
Economic Infrastructures
2
249
42
291
465
443
227
1135
686
653
335
1674
1152
1096
562
2809
Environment
2
51
9
59
638
606
311
1555
446
424
217
1087
1083
1030
528
2642
Education
20
5038
856
5894
1096
1042
535
2673
595
566
290
1450
1690
1608
825
4123
Social Infrastructures
12
2200
374
2574
2750
2616
1342
6708
2102
1999
1025
5126
4852
4615
2367
11834
Health
2
1100
187
1287
578
550
282
1410
614
584
299
1497
1192
1134
581
2907
Agriculture
3
87
15
102
1904
1812
929
4645
1786
1699
871
4356
3690
3510
1800
9001
61
8398
1428
9826
1201
1143
586
2930
699
665
341
1706
1901
1808
927
4636
183
50851
8645
59495
19516
18564
9520
47599
18339
17444
8946
44729
37854
36008
18466
92328
33
9856
2062
11918
2148
2200
230
4578
2900
2923
75
5898
5048
5123
305
10476
6
3673
321
3994
967
990
104
2060
1305
1315
34
2654
2272
2305
137
4714
22
2577
0
2577
560
630
0
1190
170
171
0
341
730
801
0
1531
Promotional Activities Total Roads, Bridges & Culverts WASH
0
Irrigation
Ti ka
2
pu r
Economic Infrastructures
4
2413
98
2511
102
271
0
373
100
99
0
199
202
370
0
572
Education
11
2857
210
3067
500
430
1000
1930
874
880
150
1904
1374
1310
1150
3834
Social Infrastructures
27
7868
636
8504
1680
1169
45
2894
1000
900
0
1900
2680
2069
45
4794
2
2186
0
2186
97
111
300
508
138
69
123
330
235
180
423
838
Environment
Health Agriculture Promotional Activities Total Roads, Bridges & Culverts
m Bh ee
3
da tta
WASH
27
6726
579
7305
930
921
148
1999
650
680
0
1330
1580
1601
148
3329
132
38156
3906
42063
6984
6722
1827
15532
7137
7037
382
14556
14121
13759
2208
30088
38
38700
0
12100
59414
11008
9959
5242
26209
11794
10483
3931
26209
22802
20443
9173
52417
3
500
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
da tta Bh ee
m
3
Irrigation
1
400
100
0
500
22
20
11
53
24
21
8
53
46
41
18
Economic Infrastructures
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Environment
0
4500
237
0
1185
1100
995
524
2619
1178
1047
393
2619
2278
2043
917
5237
Education
21
1285
0
0
4500
174
158
83
415
187
166
62
415
361
323
145
829
Social Infrastructures
0
0
160
28
25
13
67
30
27
10
67
58
52
23
133
0
0
0
0
0
0
0
0
0
0
0
0
18
160
Health
3
400
Agriculture
3
320
80
0
400
115
104
55
274
123
110
41
274
238
214
96
548
63
16260
567
9700
31645
6196
5606
2951
14753
6639
5901
2213
14753
12835
11508
5164
29507
Promotional Activities
ad hi
Total
Am
ar g
4
105
150
62525
984
21800
97804
18643
16868
8878
44389
19975
17755
6658
44389
38618
34623
15536
88777
Roads, Bridges & Culverts
19
1190
238
0
1428
278
369
29
676
322
398
0
720
600
767
29
1396
WASH
26
1925
385
0
2310
273
375
45
693
507
504
52
1063
780
879
97
1756
Irrigation
15
935
187
0
1122
288
436
46
770
412
502
42
956
700
938
88
1726
Economic Infrastructures
31
2385
477
0
2862
529
442
83
1054
525
412
112
1049
1054
854
195
2103
Environment
8
1645
329
0
1974
409
413
121
943
213
251
90
554
622
664
211
1497
Education
7
780
156
0
936
60
120
400
580
36
70
300
406
96
190
700
986
Social Infrastructures Health Agriculture Promotional Activities Total
nd ch a at h
0
444
193
412
144
749
202
182
89
473
395
594
233
1222
128
0
768
407
413
121
941
293
461
60
814
700
874
181
1755
9870
1974
0
11844
2437
2980
989
6406
2510
2780
745
6035
4947
5760
1734
12441
23
590
118
0
708
399
439
449
1287
253
309
357
919
652
748
806
2206
WASH
13
316
63
0
379
212
218
163
593
120
128
158
406
332
346
321
999
Environment Education
sh r
74
640
125
Economic Infrastructures
Da
370
Roads, Bridges & Culverts
Irrigation
5
6 13
Social Infrastructures
4
117
23
0
140
51
101
62
214
55
61
74
190
106
162
136
404
10
153
30
0
183
34
183
66
283
36
171
60
267
72
354
126
552
4
76
15
0
91
27
18
103
148
10
18
161
189
37
36
264
337
17
409
82
0
491
124
108
338
570
35
45
483
563
159
153
821
1133
1
20
4
0
24
15
12
14
41
18
20
22
60
33
32
36
101
23
601
0
0
601
360
407
321
1088
444
466
376
1286
804
873
697
2374
Health Agriculture Promotional Activities
95
2281
336
0
2617
1222
1486
1516
4224
971
1218
1691
3880
2195
2704
3207
8106
Roads, Bridges & Culverts
18
1750
396
0
2146
679
785
976
2441
1065
946
355
2366
1744
1731
1331
4806
WASH
14
1840
542
0
2382
754
871
1084
2709
1182
1050
394
2626
1936
1922
1478
5335
Irrigation
3
480
113
0
593
188
217
270
674
294
261
98
653
482
478
368
1327
Economic Infrastructures
4
230
50
0
280
89
102
127
319
139
124
46
309
228
226
174
627
Environment
6
890
170
0
1060
336
388
482
1205
526
467
175
1168
861
855
657
2374
21
260
43
0
303
96
111
138
345
150
134
50
334
246
244
188
678
sil al Di pa y
6
ga d
hi
Total
Education
dh i ilg a pa ya ls Di
6
Social Infrastructures
118
105
39
261
193
191
147
531
Health
0
0
0
0
0
0
0
0
Agriculture
0
0
0
0
0
0
0
0
Promotional Activities
i hv pr it ya Ja
2023
883
785
294
1962
1446
1435
1104
3985
82
6929
1850
0
8779
2780
3211
3995
9985
4356
3872
1452
9679
7135
7082
5446
19664
15
2900
580
0
3480
567
513
270
1350
1260
1140
600
3000
1827
1653
870
3480
5
650
130
0
780
483
437
230
1150
126
114
60
300
609
551
290
1160
Irrigation
16
190
38
0
228
630
570
300
1500
441
399
210
1050
1071
969
510
2040
Economic Infrastructures
12
450
90
0
540
420
380
200
1000
651
589
310
1550
1071
969
510
2040
2
4265
853
0
5118
119
108
57
283
54
49
26
129
173
157
82
330
Education
16
100
20
0
120
399
361
190
950
23
21
11
55
422
382
201
804
Social Infrastructures
13
600
120
0
720
46
42
22
110
290
263
138
691
336
304
160
641
Health
15
500
100
0
600
308
279
147
734
128
116
61
305
436
395
208
831
3
1571
314
0
1885
24
21
11
56
43
39
20
102
66
60
32
126
19
200
1523
0
1723
525
475
250
1250
441
399
210
1050
966
874
460
1840
116
11425
3768
0
15193
3521
3186
1677
8383
3457
3128
1646
8232
6978
6314
3323
13292
3
682
136
0
818
286
255
95
637
247
230
88
565
442
466
143
1051
WASH
18
1850
370
0
2220
380
338
127
845
280
260
30
570
545
590
80
1215
Irrigation
24
1459
290
0
1749
460
409
153
1023
345
340
50
735
701
685
130
1516
Environment
6
760
150
0
910
446
396
149
990
261
258
45
564
617
588
115
1320
22
1176
235
0
1411
755
671
252
1677
340
361
349
1050
800
761
769
2330
Education
4
600
120
0
720
625
555
208
1389
420
358
70
848
950
808
150
1908
Social Infrastructures
9
340
68
0
408
283
252
94
629
240
250
157
647
480
400
247
1127
0
0
0
0
Environment
Health Agriculture
0
0
0
0
19
1417
280
0
1697
784
697
261
1742
823
734
280
1837
1383
1334
450
3167
105
8284
1649
0
9933
4019
3573
1340
8932
2956
2791
1069
6816
5918
5632
2084
13634
3
682
136
0
136
546
485
182
1213
426
386
152
1015
972
871
334
2227
WASH
18
1850
370
0
370
411
365
137
914
422
382
151
1006
834
748
288
1919
Irrigation
24
1459
290
0
290
661
587
220
1468
549
497
196
1308
1210
1084
416
2777
Promotional Activities Total Roads, Bridges & Culverts
Economic Infrastructures
ba s
270
809
Economic Infrastructures
na r
108
651
Roads, Bridges & Culverts
Pu
87
563
Total
9
75
1779
Promotional Activities
m
236
0
Agriculture
ra su ra
0
500
WASH
Pa
36
1279
Roads, Bridges & Culverts
8
200
14
Total
7
2
Environment Education Social Infrastructures
6
760
150
0
150
640
569
213
1421
422
381
151
1004
1061
950
364
2425
22
1176
235
0
235
1083
963
361
2406
785
710
280
1869
1868
1673
641
4275
4
600
120
0
120
897
797
299
1993
634
574
226
1509
1531
1371
525
3502
9
340
68
0
68
406
361
135
902
484
438
173
1152
890
799
308
2054
19
1417
280
0
280
1125
1000
375
2500
1373
1243
490
3270
2499
2243
866
5770
Agriculture
0
0
0
0
0
0
0
0
0
0
0
0
Promotional Activities
0
0
0
0
0
0
0
0
0
0
0
0
Health
Total
105
8284
1649
0
1649
5768
5127
1923
12818
5096
4610
1820
12132
10864
9737
3743
24950
13
2321
0
0
2321
877
813
428
2140
2692
2436
1282
6410
3570
3249
1710
8550
WASH
6
624
0
0
624
228
211
111
555
212
192
101
505
440
403
212
1060
Irrigation
7
595
0
0
595
49
46
24
120
75
68
36
178
124
113
60
298
Economic Infrastructures
3
690
0
0
690
144
133
70
350
698
632
332
1662
842
765
402
2012
Environment
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
11
890
0
0
890
264
245
129
645
512
464
244
1220
777
709
373
1865
Social Infrastructures
7
720
0
0
720
1026
912
342
2280
168
152
80
400
1194
1064
422
2680
Health
2
190
0
0
190
246
228
120
600
0
0
0
0
246
228
120
600
Agriculture
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
19
921
0
0
29891
2155
1997
1051
5255
521
471
248
1240
2675
2468
1299
6495
M an
10
ga ls
en
Roads, Bridges & Culverts
Education
Promotional Activities
Sa fe
11
ba ga r
Total
68
6951
0
0
35921
4989
4585
2275
11945
4878
4414
2323
11615
9867
8998
4598
23560
Roads, Bridges & Culverts
1
110
0
0
1020
307
278
146
732
99
88
33
220
406
366
179
952
WASH
6
289
0
0
289
66
60
32
158
0
0
0
0
66
60
32
158
Irrigation
5
502
0
0
502
50
46
24
120
0
0
0
0
50
46
24
120
Economic Infrastructures
3
230
0
0
230
46
42
22
110
19
17
6
42
65
59
28
152
Environment
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
22
5170
0
0
5170
819
741
390
1950
939
834
313
2086
1758
1575
703
4036
Social Infrastructures
7
163
0
0
17283
214
194
102
510
99
88
33
220
313
282
135
730
Health
1
5
0
0
5
0
0
0
0
0
0
0
0
0
0
0
0
Agriculture
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
36
6582
0
0
6460
393
356
187
936
392
349
131
872
786
704
318
1808
81
13049
0
0
30957
1897
1716
903
4516
1548
1376
516
3440
3445
3092
1419
7956
27
3059
306
0
3365
1330
1183
443
2956
955
864
455
2274
2286
2047
898
5231
WASH
1
343
34
0
377
59
52
20
131
35
32
17
84
94
84
36
215
Irrigation
1
164
16
0
180
46
41
15
103
38
35
18
91
84
76
34
194
12
1313
131
0
1444
593
527
198
1317
422
382
201
1005
1015
909
399
2322
3
378
37
0
415
147
131
49
327
112
101
53
266
259
232
102
593
10
999
100
0
1099
502
446
167
1115
349
316
166
830
851
762
333
1946
Social Infrastructures
5
472
47
0
519
250
222
83
555
176
159
84
418
425
381
167
973
Health
9
677
67
0
744
451
401
150
1001
347
314
165
827
798
715
315
1828
Agriculture
9
400
43
0
443
419
372
140
931
338
305
161
804
757
678
300
1735
Promotional Activities
8
750
75
0
825
395
351
132
878
326
295
155
777
721
646
287
1655
0
Education
Promotional Activities Total Roads, Bridges & Culverts
Pi ri Jh ala
12
pl a
di
Economic Infrastructures Environment Education
Total
85
8555
856
9411
4191
3726
1397
9314
3098
2803
1475
7376
7289
6528
2872
16690
Roads, Bridges & Culverts
25
6290
944
7234
1064
1870
3260
6194
2418
2188
1151
5757
3482
4058
4411
11951
WASH
17
1820
415
2235
195
345
535
1075
1467
1327
699
3493
1662
1672
1234
4568
7
355
53
408
0
0
0
0
198
179
94
472
198
179
94
472
Irrigation
Ap i
13
Economic Infrastructures
Ap i
13
3
1400
210
1610
70
140
350
560
187
169
89
446
257
309
439
Environment
13
1894
284
2178
0
0
192
192
270
244
128
642
270
244
320
834
Education
17
2767
415
3182
50
210
135
395
396
358
189
943
446
568
324
1338
Social Infrastructures
6
378
57
435
190
258
458
906
357
323
170
850
547
581
628
1756
Health
7
345
52
397
0
0
0
0
132
120
63
315
132
120
63
315
Agriculture
0
0
0
0
0
0
0
0
Promotional Activities
0
0
0
0
0
0
0
0
Total
95
15249
2430
0
17679
1569
2823
4930
9322
5426
4909
2584
12918
6995
7732
7514
22240
Roads, Bridges & Culverts
25
4018
1369
0
5387
3500
2054
1500
7054
800
530
1600
2930
4300
2584
3100
9984
WASH
14
2805
236
0
3041
562
456
600
1618
329
298
100
727
891
754
700
2345
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Irrigation
La m
kiC
hu w a
Economic Infrastructures 14
5
860
258
0
1118
198
145
0
343
151
150
0
301
349
295
0
644
Environment
12
740
111
0
851
300
654
0
954
95
123
51
269
395
777
51
1223
Education
16
1897
379
0
2276
234
340
1500
2074
230
241
800
1271
464
581
2300
3345
Social Infrastructures
17
5113
230
0
5343
567
244
350
1161
109
179
200
488
676
423
550
1649
Health
14
1115
121
0
1236
500
288
176
964
350
310
200
860
850
598
376
1824
Agriculture
15
1450
105
0
1555
323
358
70
751
100
226
48
374
423
584
118
1125
Promotional Activities
61
5443
783
0
6226
5460
4255
4061
13776
3614
4785
2707
11106
9074
9040
6768
24882
179
23441
3592
0
27033
11644
8794
8257
28695
5778
6842
5706
18326
17422
15636
13963
47021
Total
Gh od
ag ho di
Roads, Bridges & Culverts
15
16
1385
208
0
1593
1410
1500
3100
6010
1876
1756
1200
4832
3286
3256
4300
10842
WASH
2
150
23
0
173
230
213
351
794
245
265
0
510
475
478
351
1304
Irrigation
1
150
23
0
173
234
212
0
446
300
181
0
481
534
393
0
927
Economic Infrastructures
7
1622
243
0
1866
878
650
0
1528
780
778
0
1558
1658
1428
0
3086
Environment
1
100
15
0
115
133
190
71
394
123
118
28
269
256
308
99
663
Education
13
550
83
0
633
656
790
1205
2651
816
782
2000
3598
1472
1572
3205
6249
Social Infrastructures
20
1465
157
0
1622
1345
1286
750
3381
500
455
0
955
1845
1741
750
4336
Health
7
815
0
0
815
168
144
127
439
304
56
779
1139
472
200
906
1578
Agriculture
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
27
2161
0
0
2161
78
56
26
160
115
145
210
470
193
201
236
630
94
8398
751
0
9149
5132
5041
5630
15803
5059
4536
4217
13812
10191
9577
9847
29615
Promotional Activities Total Roads, Bridges & Culverts
Be
lau
ri
16
1006
34
7999
1360
0
9359
1764
1568
588
3921
1614
1460
768
3842
3378
3028
1357
7763
WASH
8
11455
1947
0
13402
3005
2671
1002
6678
2698
2441
1285
6424
5703
5112
2287
13102
Irrigation
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Economic Infrastructures
4
273
46
0
319
11
9
4
24
10
9
5
23
20
18
8
47
Environment
4
5100
867
0
5967
67
59
22
149
61
55
29
146
128
115
51
294
Education Social Infrastructures
14
352
60
0
412
1687
1500
562
3749
1543
1396
735
3674
3230
2896
1297
7424
9
3221
548
0
3769
852
758
284
1894
780
705
371
1856
1632
1463
655
3750
Be
lau
ri
16
Health Agriculture Promotional Activities Total
Bh aj an
17
iT ris ha kt
i
Roads, Bridges & Culverts
ali ka m
788
5253
2162
1956
1030
5148
4526
4057
1818
0
0
0
0
0
0
0
0
0
0
10401 0
89
4603
783
0
5386
844
750
281
1875
772
698
367
1837
1615
1448
649
3712
173
34278
5827
0
40105
10594
9417
3531
23542
9639
8721
4590
22951
20233
18138
8121
46493
244
4558
7521
6039
565
14125
787
538
138
1463
8308
6577
703
15588
9
0
259
156
150
37
343
17
13
9
39
173
163
46
382
Irrigation
3
130
20
0
150
387
386
49
822
70
80
22
172
457
466
71
994
13
1472
272
52
1797
341
405
171
917
196
228
86
510
537
633
257
1427
Environment
1
500
100
0
600
120
111
78
309
45
100
22
167
165
211
100
476
Education
5
231
25
0
256
245
168
1321
1734
0
0
0
0
245
168
1321
1734
12
639
56
0
695
1301
1181
443
2925
100
145
94
339
1401
1326
537
3264
Health
4
362
10
0
372
1790
0
12
1802
23
0
0
23
1813
0
12
1825
Agriculture
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
16
1417
172
0
1589
1120
938
103
2161
267
239
105
611
1387
1177
208
2772
88
8806
1172
296
10275
12981
9378
2779
25138
1505
1343
476
3324
14486
10721
3255
28462
Economic Infrastructures
5
354
46
0
400
1076
956
359
2391
922
834
439
2196
1998
1791
798
4587
13
492
64
0
557
163
145
54
363
142
129
68
339
306
274
122
702
Irrigation
2
127
17
0
143
21
19
7
47
18
17
9
44
40
36
16
91
Economic Infrastructures
1
343
-
0
343
527
468
176
1171
458
415
218
1092
985
883
394
2262
-
0
-
0
0
0
0
0
0
0
0
0
0
0
0
32
4822
629
0
5,450
256
228
85
569
223
202
106
530
479
429
191
1099
Social Infrastructures
4
315
-
0
315
280
249
93
622
258
234
123
615
538
482
216
1237
Health
1
123
-
0
123
326
290
109
725
274
248
130
652
600
538
239
1377
Agriculture
0
-
-
0
-
0
0
0
0
0
0
0
0
0
0
0
0
Promotional Activities
6
746
-
0
746
463
411
154
1029
403
364
192
959
866
776
346
1988
64
7321
756
0
8077
3112
2766
1037
6916
2699
2442
1285
6426
5811
5208
2323
13342 8286
Education
Total Roads, Bridges & Culverts
i
2101
0
508
Environment
Ch ad an
2364
0
250
WASH
Ba di
1492
0
3805
Roads, Bridges & Culverts
Do dh ar a
0
0
4
Social Infrastructures
0
-
31
3513
351
0
3864
2051
1823
684
4557
1529
1417
746
3729
3580
3240
1429
WASH
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Irrigation
1
164
16
0
180
77
68
26
171
62
57
30
150
138
125
56
321
16
1751
175
0
1926
1060
942
353
2355
802
743
391
1956
1862
1685
744
4311
Economic Infrastructures Environment Education Social Infrastructures Health
Total
217
30
Total
19
1275
0
WASH
Promotional Activities
18
11
2
252
25
0
277
135
120
45
300
98
91
48
240
233
211
93
540
11
832
85
0
917
713
634
238
1584
554
513
270
1350
1266
1147
508
2934
4
377
37
0
414
281
250
94
624
205
190
100
501
486
440
194
1125
20
1599
160
0
1759
1351
1201
450
3003
996
923
486
2430
2348
2125
936
5433
Agriculture
8
207
21
0
228
528
469
176
1173
451
418
220
1101
979
888
396
2274
Promotional Activities
8
750
75
0
825
533
474
178
1185
397
368
194
969
931
842
372
2154
101
9445
945
0
10390
6728
5981
2243
14952
5095
4722
2485
12426
11823
10703
4728
27378
Roads, Bridges & Culverts
95
11240
2810
0
14050
2486
2249
1184
5920
2600
2311
867
5778
5086
4561
2051
11698
WASH
11
1796
449
0
2245
104
94
50
248
180
160
60
399
284
254
109
647
Irrigation
21
668
167
0
835
193
175
92
459
181
161
60
402
374
335
152
861
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Environment
17
1597
399
0
1996
272
247
130
649
322
286
107
716
594
533
237
1364
Education
17
1688
422
0
2110
205
186
98
489
172
153
57
383
378
339
155
872
Social Infrastructures
31
4211
1053
0
5264
975
882
464
2322
738
656
246
1641
1714
1539
711
3963
6
1358
339
0
1697
522
472
248
1242
378
336
126
840
900
808
374
2082
At ta r
20
iya
Economic Infrastructures
Health Agriculture
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
72
9146
2287
0
11433
3304
2990
1573
7867
2145
1907
715
4766
5449
4896
2288
12634
270
31704
7926
0
39630
8063
7295
3839
19197
6716
5970
2239
14925
14779
13265
6078
34122
Roads, Bridges & Culverts
13
898
135
1033
2066
554
492
185
1231
606
539
202
1347
1160
1031
387
2578
WASH
31
833
125
958
1916
988
878
329
2196
1081
961
360
2403
2070
1840
690
4599
Irrigation
7
169
25
195
389
255
226
85
566
279
248
93
619
533
474
178
1185
Economic Infrastructures
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Promotional Activities
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Education
17
814
122
936
1872
357
318
119
794
391
348
130
869
748
665
249
1663
Social Infrastructures
45
1445
217
1662
3323
896
796
299
1990
980
871
327
2178
1876
1667
625
4168
Health
11
540
81
621
1241
295
262
98
655
323
287
108
717
617
549
206
1372
Pa
ta
Environment
Agriculture Promotional Activities Total
Far-west Mun. Compliedsummary
21
n
Total
6
195
29
224
448
149
132
50
330
163
144
54
361
311
276
104
691
23
1664
250
1914
3828
374
332
125
830
409
363
136
908
782
695
261
1738
153
6558
984
7541
15083
3866
3437
1289
8592
4231
3761
1410
9403
8098
7198
2699
17995
2544
372361
50000
29638
503088
139655
126673
69774
336199
120469
112475
53715
287390
259069
238416
123164
618154
Roads, Bridges & Culverts
534
134,234
17,294
13,377
173,747
48,054
43,632
23,916
115,623
42,723
38,966
18,127
99,904
90,686
82,580
42,002
214,507
WASH
228
34,238
5,615
958
38,461
10,958
10,508
5,849
27,320
12,339
11,465
4,548
28,403
23,182
21,965
10,320
55,233
Irrigation
144
8,124
1,387
195
8,247
4,573
4,473
1,852
10,899
5,204
4,878
1,949
12,098
9,672
9,287
3,728
22,245
Economic Infrastructures
160
17,518
2,326
52
19,136
7,049
6,606
2,408
16,066
6,613
6,281
2,388
15,352
13,574
12,821
4,717
30,676
Environment
123
26,753
4,019
-
26,043
5,742
5,944
2,797
14,482
4,778
4,546
2,159
11,578
10,225
10,219
5,124
25,581
Education
306
32,941
3,927
936
40,419
9,960
9,487
9,140
28,593
9,078
8,419
6,653
24,239
18,943
17,800
15,665
52,303
Social Infrastructures
258
30,246
3,708
1,662
52,396
13,460
11,794
5,536
30,790
8,751
8,158
3,392
20,365
22,169
19,851
8,923
50,846
Health
134
14,005
1,614
621
14,423
10,121
7,327
3,383
20,837
7,542
6,561
4,061
18,352
17,664
13,888
7,444
38,981
53
4,599
681
224
5,504
3,654
3,681
1,574
8,909
3,206
3,123
1,505
7,845
6,860
6,804
3,079
16,722
Agriculture Promotional Activities Total
604
69,704
9,428
11,614
124,712
26,085
23,222
13,318
62,678
20,233
20,076
8,935
49,254
46,094
43,201
22,162
111,060
2,544
372,361
50,000
29,638
503,088
139,655
126,673
69,774
336,199
120,469
112,475
53,715
287,390
259,069
238,416
123,164
618,154
Annex 6 C
Project Funding Matrix of VDCs Annual Progress Report (Fiscal Year 71/72) SN
1
Districts
Bajura
Sector
Disadvantage Group (DAG)
Others
Total
Total
Total Male
Female
Children
Total
Male
Female
Children
Total
Male
Female
Children
6526
1305
7831
4410
3990
2100
10500
1470
1330
700
3500
5880
5320
2800
14000
WASH
51
3037
3037
607
3644
4242
3838
2020
10100
1974
1786
940
4700
6216
5624
2960
14800
Irrigation
18
8534
8534
1707
10241
3402
3078
1620
8100
1365
1235
650
3250
4767
4313
2270
11350
Education
98
4016
4016
803
4819
903
817
430
2150
357
323
170
850
1260
1140
600
3000
Environment
45
3514
3514
703
4217
706
638
336
1680
281
255
134
670
987
893
470
2350
Health
68
2485
2485
497
2982
4578
4142
2180
10900
2352
2128
1120
5600
6930
6270
3300
16500
Economic
31
3545
3545
709
4254
336
304
160
800
378
342
180
900
714
646
340
1700
Social
46
6043
6043
1209
7251
315
285
150
750
588
532
280
1400
903
817
430
2150
Agriculture
70
7480
7480
1496
8976
2772
2508
1320
6600
2100
1900
1000
5000
4872
4408
2320
11600
Promotional Activities
78
5020
5020
1004
6024
2016
1824
960
4800
1386
1254
660
3300
3402
3078
1620
8100
552
50200
50200
10040
60240
23680
21424
11276
56380
12251
11085
5834
29170
35931
32509
17110
85550
105
20558
20558
4112
24669
3866
3437
1718
8592
1009
913
480
2402
4875
4349
2199
10994
95
14632
14632
2926
17558
2867
2548
1274
6371
1621
1467
772
3860
4488
4015
2046
10231
Irrigation
100
4824
4824
965
5788
1693
1505
752
3762
783
708
373
1864
2476
2213
1125
5625
Education
100
9763
9763
1953
11716
1896
1685
843
4214
565
511
269
1346
2461
2197
1112
5559
Environment
20
13782
13782
2756
16538
4433
3940
1970
9850
1130
1022
538
2691
5563
4963
2508
12541
Health
50
1068
1068
214
1282
2858
2540
1270
6351
1715
1551
817
4083
4573
4092
2087
10434
Economic
60
3445
3445
689
4135
4647
4131
2065
10327
826
747
393
1966
5473
4878
2459
12293
Social
65
689
689
138
827
1076
956
478
2390
340
307
162
809
1415
1264
640
3199
Agriculture
55
1792
1792
358
2150
1025
911
456
2278
1156
1046
550
2752
2181
1957
1006
5030
Promotional Activities
56
6798
6798
1360
8157
2117
1882
941
4705
1055
955
502
2512
3172
2837
1443
7217
706
77350
77350
15470
92820
26478
23536
11768
58841
10199
9228
4857
24284
36677
32764
16625
83124
Roads, Bridges & Culverts
66
21596
21596
4319
25915
7139
6459
3400
16998
6305
5997
3075
15377
13444
12456
6475
32375
WASH
33
5212
5212
1042
6254
6166
5578
2936
14680
5539
5269
2702
13509
11704
10847
5638
28189
Irrigation
38
11625
11625
2325
13950
4119
3727
1961
9807
5366
5104
2618
13088
9485
8831
4579
22895
Education
20
797
797
159
957
1452
1313
691
3456
691
657
337
1685
2142
1970
1028
5141
Total
Achham
Other Stakehol ders
UC
LBs
6526
WASH
3
VDC
Approx. Benifited Population
47
Roads, Bridges & Culverts
Bajhang
Actual cost sharing (NRs in '000)
Roads, Bridges & Culverts
Total
2
Number of Projects complete d
3
Achham
Environment
30
3249
3249
650
3899
3419
3093
1628
8140
3809
3623
1858
9289
7227
6716
3486
17429
Health
90
12690
12690
2538
15228
4242
3838
2020
10099
4993
4750
2436
12178
9235
8587
4455
22277
104
1852
1852
370
2223
2354
2130
1121
5604
1917
1823
935
4675
4270
3953
2056
10279
Social
74
12179
12179
2436
14615
7416
6709
3531
17656
6014
5720
2933
14667
13429
12430
6465
32323
Agriculture
88
14582
14582
2916
17499
3560
3221
1695
8475
3914
3723
1909
9546
7474
6944
3604
18021
Promotional Activities
11
3790
3790
758
4548
990
895
471
2356
926
881
452
2259
1916
1776
923
4615
554
87574
87574
17515
105088
40854
36963
19454
97271
39472
37547
19255
96274
80326
74510
38709
193545
87
17330
17330
3119
20449
1461
1299
487
3248
5734
4934
2667
13335
7195
6233
3154
16582
WASH
116
8197
8197
1475
9673
6859
6097
2286
15242
1035
890
481
2406
7894
6987
2768
17649
Irrigation
119
7610
7610
1370
8979
8145
7240
2715
18100
1181
1017
550
2748
9326
8257
3265
20848
Education
15
687
687
124
810
2148
1909
716
4772
4432
3813
2061
10307
6579
5722
2777
15079
151
6454
6454
1162
7616
2148
1910
716
4774
1035
890
481
2406
3183
2800
1197
7180
92
6461
6461
1163
7624
3001
2667
1000
6668
2364
2034
1100
5498
5365
4702
2100
12167
Economic
Total Roads, Bridges & Culverts
4
Doti
Environment Health Economic
97
3707
3707
667
4374
11575
10288
3858
25721
1108
953
515
2576
12682
11242
4373
28297
Social
121
5081
5081
915
5995
3736
3321
1245
8302
1035
890
481
2406
4771
4211
1727
10708
Agriculture
101
6852
6852
1233
8086
3736
3321
1245
8302
3176
2733
1477
7386
6912
6054
2723
15688
50
1000
1000
180
1180
1728
1536
576
3839
2216
1907
1031
5154
3944
3443
1607
8993
949
63378
63378
11408
74787
44536
39588
14845
98970
23316
20062
10845
54223
67852
59650
25690
153192
199
33637
33637
6896
47191
15682
14917
7650
38249
13335
12065
6350
31749
29017
26982
14000
69998
WASH
28
2994
2994
614
4223
2186
2080
1067
5333
2406
2177
1146
5729
4593
4257
2212
11062
Irrigation
11
1175
1175
241
4819
2965
2820
1446
7231
2748
2486
1308
6542
5712
5306
2755
13773
Education
101
14107
14107
2892
21046
7020
6678
3425
17123
10307
9325
4908
24540
17327
16003
8333
41663
Environment
44
8262
8262
1694
4218
2596
2470
1267
6333
2406
2177
1146
5729
5003
4647
2412
12062
Health
81
7416
7416
1520
15643
5932
5643
2894
14469
5498
4975
2618
13091
11431
10618
5512
27560
Economic
57
6343
6343
1300
7547
2780
2644
1356
6780
2576
2331
1227
6134
5356
4975
2583
12914
231
17683
17683
3625
4228
2596
2470
1267
6333
2406
2177
1146
5729
5003
4647
2412
12062
Agriculture
18
2015
2015
413
12924
7969
7581
3887
19437
7386
6683
3517
17586
15356
14263
7405
37024
Promotional Activities
66
8304
8304
1702
3503
5561
5290
2713
13563
5154
4663
2454
12271
10715
9953
5167
25835
836
101936
101936
20897
125341
55288
52591
26970
134849
54223
49059
25820
129102
109511
101650
52790
263951
71
4723
4723
888
5611
2727
2424
909
6059
1772
2259
1905
5936
4499
4683
2814
11995
8073
19404
Promotional Activities Total Roads, Bridges & Culverts
5
Kailali
Social
Total Road,Bridge,Culvert Irrigation
6
Darchula
114
8073
1518
9591
4235
3764
1412
9411
2915
3148
3930
9993
7150
6912
5342
WASH
48
2374
2374
446
2820
1147
1020
382
2549
899
628
563
2090
2046
1648
945
4639
Education
89
6510
6510
1224
7734
3827
3402
1276
8504
2434
2801
2781
8016
6261
6203
4057
16520
Environment
35
3045
3045
572
3617
3131
2783
1044
6958
1632
1999
5857
9488
4763
4782
6901
16446
161
7202
7202
1354
8555
4911
4366
1637
10914
2960
4291
2970
10221
7871
8657
4607
21135
Economoc infrastructure
80
4773
4773
897
5670
7835
6964
2612
17410
3589
4965
4949
13503
11424
11929
7561
30913
Social Infrastructure
23
1449
1449
272
1721
3360
2987
1120
7467
5323
334
2345
8002
8683
3321
3465
15469
Health
6
Darchula
Aggriculture
119
7349
7349
1382
8730
394
350
131
876
634
242
421
1297
1028
592
552
2173
Promotional
100
4823
4823
907
5730
2423
2154
808
5385
1742
2723
1968
6433
4165
4877
2776
11818
Total
7
Baitadi
840
50320
50320
9460
59780
33990
30213
11330
75533
23900
23390
27689
74979
57890
53603
39019
150512
Road,Bridge,Culvert
177
11676
11676
1985
13661
4321
3245
1513
9079
1234
1240
495
2969
5555
4485
2008
12048
Irrigation
214
9879
9879
1680
11559
4530
3240
1554
9324
1400
1100
500
3000
5930
4340
2054
12324
WASH
278
15268
15268
2596
17864
5432
4317
1950
11699
1500
1400
580
3480
6932
5717
2530
15179
Education
124
7185
7185
1221
8406
3215
2145
1072
6432
1456
1130
517
3103
4671
3275
1589
9535
Environment
166
6287
6287
1069
7356
7007
3451
2092
12550
3003
1479
896
5378
10010
4930
2988
17928
Health
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Economoc infrastructure
118
6343
6343
1078
7421
5479
2699
1635
9813
2348
1157
701
4206
7827
3855
2336
14018
Social Infrastructure
104
10811
10811
1838
12649
3215
2566
1156
6938
1200
1100
460
2760
4415
3666
1616
9698
Aggriculture
59
13382
13382
2275
15657
1120
970
418
2508
850
545
279
1673
1970
1515
697
4181
Promotional
472
8981
8981
1527
10508
8657
5490
2829
16976
5467
4874
2068
12409
14124
10364
4898
29386
Total
8
Dadeldhura
1712
15268
105081
42976
28123
14220
85319
18458
14024
6496
38979
61434
42147
20716
124297
3828
3828
670
4498
1880
1788
917
4586
1525
1380
726
3632
3405
3168
1643
8217
WASH
43
8725
8725
1527
10252
2628
2500
1282
6409
2246
2032
1070
5348
4874
4532
2351
11757
Irrigation
18
1096
1096
192
1288
1543
1467
753
3763
1460
1321
695
3476
3003
2788
1448
7238
Economic
112
3147
3147
551
3697
2073
1972
1011
5057
1753
1586
835
4175
3827
3558
1846
9231
Environment
11
643
643
112
755
1472
1401
718
3591
1439
1302
685
3426
2911
2702
1403
7017
Education
68
2964
2964
519
3483
1840
1751
898
4489
1339
1212
638
3189
3180
2962
1536
7678
Social
29
3012
3012
527
3539
1597
1519
779
3896
1520
1375
724
3619
3117
2895
1503
7515
Health
27
1998
1998
350
2347
1073
1020
523
2616
954
863
454
2271
2027
1883
977
4887
Agriculture
69
2888
2888
505
3393
3290
3130
1605
8025
2516
2276
1198
5990
5806
5406
2803
14016
Promotional
65
2780
2780
486
3266
1309
1245
639
3193
888
804
423
2115
2198
2049
1062
5309
457
31080
31080
5439
36519
18706
17794
9125
45625
15641
14151
7448
37240
34347
31945
16573
82866
151
16290
16290
2606
18897
15744
13547
7323
36614
15407
13257
7166
35829
31151
26804
14489
72443
WASH
14
1516
1516
243
1759
1461
1257
680
3398
1429
1230
665
3324
2890
2487
1344
6722
Irrigation
16
1730
1730
277
2007
1667
1435
776
3878
1633
1405
760
3798
3300
2840
1535
7675
Education
60
6473
6473
1036
7509
6257
5384
2910
14550
6123
5269
2848
14239
12380
10652
5758
28790
Environment
14
1514
1514
242
1756
1461
1257
680
3398
1429
1230
665
3324
2890
2487
1344
6722
Health
32
3452
3452
552
4005
3338
2872
1553
7763
3266
2810
1519
7595
6604
5682
3072
15358
Economic
15
1628
1628
260
1888
1563
1345
727
3636
1531
1318
712
3561
3095
2663
1439
7197
Social
14
1518
1518
243
1761
1461
1257
680
3398
1429
1230
665
3324
2890
2487
1344
6722
Agriculture
43
4639
4639
742
5381
4484
3858
2085
10427
4388
3776
2041
10205
8872
7634
4126
20632
Promotional Activities
37
4494
4494
719
5213
3128
2692
1455
7275
3062
2635
1424
7122
6191
5327
2879
14397
396
43254
43254
6921
50175
40564
34904
18867
94335
39698
34159
18464
92322
80262
69063
37331
186657
7002
594904
594904
112418
709830
327072
285137
137855
747122
237159
212705
126708
576572
564231
497842
264564
1323694
Roads, Bridges & Culverts
Kanchanpur
89813
15
Total
9
89813
Road, Bridge & Culverts
Total Grand Total Region
Far-west VDC Complied summary
Roads, Bridges & Culverts
918
136164
136164
25900
168722
57231
51106
26017
133924
47790
43374
23565
114729
105021
94481
49581
248653
WASH
708
62266
62266
11632
74513
35174
30903
14510
80268
20565
19099
12205
51869
55739
50001
26715
132137
Irrigation
646
54235
54235
10118
67756
30112
26608
12355
68888
16935
15304
8096
40335
47047
41912
20451
109222
Education
719
52685
52685
9963
66694
28790
25305
12373
66258
28118
25416
14726
68260
56908
50721
27100
134518
Environment
516
46749
46749
8960
49972
26373
20943
10450
57273
16164
13977
12260
42402
42537
34920
22710
99675
Health
642
43738
43738
8357
58802
30700
27819
13452
71653
24487
23751
13217
61455
55188
51570
26668
133108
Economic
591
34648
34648
6499
41050
38165
32024
14314
83986
15793
15011
10336
41140
53958
47035
24650
125127
Social
705
57451
57451
11025
51395
24247
21572
10150
55849
19289
13154
8926
41369
43536
34726
19077
97219
Agriculture
622
60979
60979
11321
82796
28350
25849
12843
66929
26120
22923
12393
61436
54470
48773
25236
128365
Promotional Activities
935
45990
45990
8643
48129
27929
23008
11392
62094
21897
20696
10983
53576
49827
43704
22375
115670
7002
594904
594904
112418
709830
327072
285137
137855
747122
237159
212705
126708
576572
564231
497842
264564
1323694
Total
VDC Level Status of Community Infrastructure Grant (Fiscal Year 2070/71 to 2071/72)
Annex 7 Beneficiaries
360
0
0
1 90
91
1
0
0
0
2
482
1847
1867
10545000
0
2
32
0
458
0
2
2
5
5
3
4
1
0
34
0
0
42
508
1772
1726
13605000
3 Achham
62
62
19
28
47
0
23
0
0
0
0
0
0
23
94
24
70
12
0
12
0
0
106
0
1
1
5
5
8
1
0
0
0
0
0
10
145
3605
3685
17011981
4 Bajura
24
24
5
12
17
0
4
0
0
0
0
0
0
4
229
0
229
0
0
0
0
0
229
0
0
2
2
1
0
0
0
0
0
1
2
237
698
862
5911113
5 Bajhang
42
42
12
19
31
0
65
50
0
0
0
0
0
115
154
0
154
1
0
1
26
0
181
2
2
17
17
4
0
0
0
0
2
3
39
354
3179
4006
11118642
6 Darchula
36
36
9
16
25
0
7
0
2
25
1
0
0
35
0
0
0
0
0
0
0
0
0
0
0
4
4
2
0
4
0
8
1
2
1
0
19
58
2089
2181
8593000
7 Baitadi
56
56
15
25
40
0
9
27
1
0
30
0
0
67
245
0
245
0
0
0
85
0
330
0
0
6
6
4
1
1
0
0
1
1
0
0
8
411
2101
2800
14247038
8 Dadeldhura
18
18
4
9
13
0
1
1
5
0
0
0
0
0
7
50
0
50
1
0
1
2
0
53
2
2
5
5
0
0
0
0
0
0
0
0
0
67
1518
1417
4709528
9 Kanchnapur
9
9
0
9
9
3
0
0
0
3
0
0
0
0
6
0
0
0
6
6
0
3
0
9
0
0
0
0
0
0
0
0
0
0
0
0
0
15
639
769
328
328
2277
17448
74
177
251
4
111
1
82
6
25
56
1
1
287
1364
39
1325 213
11
202
148
1
1726
4
3
7
45
90 135
23
6
6
1
42
4
1
30
3
Bee- keeping
Fish farming
Banana Farming
Total
Collective
Individual
Individual
Project no.
Individual
Poultry farming
Milk Dairy
Total
Drinking water
Total Community Building
Water mill
Metal Workshop Aggrigate Collection
Hand Crafts
Total
Male
Femal
Total
7
0
7
7
0
0
13
0
0
1
0
14
0
0
0
4
0
0
0
0
9
1
14
0
0
0
0
0
0
0
0
28
698
638
1336
2205000
9
9
0
9
9
5
0
0
0
0
1
0
6
10
10
0
40
26
14
0
0
0
1
51
0
0
0
0
0
0
0
0
57
375
411
786
2835000
3 Attariya
13
4
0
4
4
2
0
1
0
0
0
0
3
50
0
50
16
0
16
0
0
0
0
66
0
0
0
0
0
0
0
0
69
526
453
979
1260000
4 Lamki Chuha
15
2
0
2
2
0
0
0
0
0
0
0
0
25
0
25
25
0
25
0
0
0
0
50
0
0
0
0
0
0
0
0
50
120
139
259
630000
5 Godaghodi
9
2
0
2
2
0
0
0
0
0
0
0
0
0
0
0
2
2
0
0
0
0
0
2
0
0
0
0
0
0
0
0
2
87
99
186
630000
12
3
2
2
4
0
0
0
0
0
0
2
2
40
0
40
0
0
0
0
0
0
0
40
0
0
1
0
0
0
0
1
43
124
150
274
1407510
7 Dipayal-Sil
14
10
0
10
10
0
0
0
0
0
0
0
0
226
0
226
0
0
0
0
0
20
0
246
0
0
0
0
0
0
0
0
246
392
441
833
3150000
8 Mangalsen
11
5
0
5
5
0
2
0
0
0
0
0
2
0
0
0
0
0
0
0
0
0
0
0
3
3
0
0
0
0
0
0
5
504
505
1009
1575000
9 Saffe
12
8
0
8
8
0
2
0
0
0
0
0
2
113
0
113
0
0
0
30
30
0
0
143
0
0
0
0
0
0
0
0
145
654
673
1327
2520000
10 Badimalika
12
3
2
1
3
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
3
3
0
0
0
0
0
0
3
444
499
943
1133000
11 Jai Prithibi
15
5
0
5
5
0
0
14
0
0
0
0
14
37
0
37
2
0
2
47
47
0
0
86
0
0
0
0
0
0
0
0
100
791
774
1565
1575000
12 Api
17
5
2
3
5
0
1
1
0
0
0
0
2
0
0
0
0
0
0
0
0
17
0
17
2
2
0
0
0
0
0
0
21
311
348
659
1820000
13 Dashrathcha
13
12
0
12
12
0
4
0
0
30
0
0
34
166
0
166
0
0
0
24
24
0
0
190
0
0
0
0
0
2
0
2
226
431
670
1101
3780000
14 Patan
13
6
1
5
6
0
30
0
0
0
0
0
30
0
0
0
0
0
0
52
52
0
0
52
1
1
0
2
0
0
0
2
85
880
910
1790
1975000
15 Amargadi
11
8
0
8
8
0
4
25
0
0
0
0
29
50
0
50
0
0
0
25
25
0
0
75
0
0
0
0
0
0
0
0
104
1043
1013
2056
2520000
16 Parsuram
12
2
1
1
2
0
15
0
0
0
0
0
15
25
0
25
0
0
0
0
0
0
0
25
0
0
0
0
0
0
0
0
40
171
164
335
765000
17 BhimDatt
19
9
0
9
9
4
0
41
1
0
0
1
47
0
0
0
0
0
0
0
0
1
1
2
0
0
0
0
3
0
2
5
54
1092
1215
2307
2835000
18 Punarbas
15
3
0
3
3
0
0
3
0
0
0
0
3
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
3
0
0
0
945000
19 Belauri
14
3
0
3
3
7
0
1
0
0
0
0
8
12
0
12
2
2
0
0
0
0
0
14
0
0
0
0
0
0
0
0
22
501
385
886
945000
20 Dodhara
10
2
0
2
2
0
0
2
0
0
0
2
4
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
4
34
74
108
630000
21 Jhalari
11
2
0
2
2
4
0
1
0
0
0
0
5
5
0
5
1
1
0
0
0
0
0
6
0
0
0
0
0
0
0
0
11
14
32
46
103
111
22
58
102
220
759
749
92
57
178 178
10
1318
9192 9593
6 Bhjani Trishakti
Total
271
110
8
1
30
2
5
10
Collective
Project no.
Project no.
Pig shed
31
47
3
1079
9
9
1
2
3
2
2
18785
Total Amount
Vegetable
Vegetable colct. centre
14
2 Tikapur
Goat Shed
Total Projects
Cannel Irrigation
1 Dhangadhi
S.N
Shallo Irrigation
Beneficiaries
CIG recived CAC
Others
2071/72
WASH
2070/71
Livestock/Dairy Cow/Buffal o shed
Total no of CACs
Agriculture/Irrigation
Total VDCs/Wards
Name of Municipality
Municipality Status of Livelihood Infrastructure Grant ( FY 70/071 to 2071/72) CIG
630000 35765510
1
1
30
2
4
Total
Bamboo
Tailoring
Water mill
Cellar mill
Toilet
Total
Milk Dairy
Individual
Collective
Project no.
Individual
Collective
Project no.
Total
Harba col. centre
Fish farming
Fruit Farming
Shallo Irrigation
2071/72
S.N Total
0
1
122
19313
Total Amount
1
2
Total Projects
0
424
Foot Trile
5 186
0
Monteswari School
153 191
424
Leather shoe
15
1
Improved Cooking
168
0
Metal Workshop
29
0
Tent House
1
0
Community Building
1
0
Total
25
0
Drinking water
0
0
MHP
0
1
Total
1
0
Pig shed
Alt energy (solar)
1
38
Goat Shed
Poultry farming
31
35
Mushroom
24
3
Bee- keeping
7
50
Cannel Irrigation
31
50
CIG recived CAC
31
2 Doti
2070/71
1 Kailali
Name of district
Femal
Others
Male
WASH
Vegetable
Solar/MHP
Vegetable col. centre
Livestock/Dairy
Total no of CACs
Agriculture/Irrigation
Total VDCs/Wards
CIG
2835000 88576302
Annex 8 District Wise Social Security Status of Fiscal Year 2071/72 Target groups SN
Name of District
Senior citizen (Other) Total
Received Amount
Senior citizen (Dalit) Total Received Amount
Single Woman Total
Widow woman
Received Amount
Total
Fully Disabled
Received Amount
Total
Received Amount
Partial Disablled Total
Endangered (Raute,Raji)
Received Amount
Received Amount
Total
Received Amount
medicine For 70 above Total Received Amount
Total
Total Amount
1 Achham
6815
40890000
6558
39348000
7743
46458000
0
0
0
15100
36240000
10884
21768000
47174
22014000
2403
14418000
3044
18264000
0
0
2028000
58 79
0
3669
16 169
208800
2 Bajura
284400
0
0
6111
14666400
7000
14000000
22475
85674800
3 Bajhang
39816000
3134
18804000
7
42000
4580 27480000
55
660000
75
270000
0
0
8827
21184800
8000
16000000
31314
124256800
4 Baitadi
6636 7826
46956000
3653
21918000
3889
23334000
3653 21918000
438
5256000
58
208800
0
0
8218
19723200
11455
22910000
39190
162224000
5 Dadeldhura
3420
20520000
2114
12684000
2418
14508000
1634
9804000
194
2328000
119
428400
467
5604000
4908
11779200
4802
9604000
20076
87259600
6 Doti
3277
19662000
3187
19122000
27
162000
9111 54666000
108
1296000
215
774000
0
0
9038
21691200
6063
12126000
31026
129499200
7 Darchula
2908
17448000
813
4878000
691
4146000
2456 14736000
189
2268000
112
403200
45
540000
2554
6129600
5055
10110000
14823
60658800
8 Kanchanpur
5575
33450000
3236
19416000
780
4680000
7344 44064000
346
4152000
240
864000
120
1440000
4597
11032800
2243
4486000
24481
123584800
13600 81600000
9 Kailali
192000
Total
Children Dalit
185104800
10110
60660000
5930
35580000
2
12000
256
3072000
957
3445200
2025
24300000
9521
22850400
15645
31290000
58046
262809600
10 Dhangadhi Mun
1496
8976000
525
3150000
949
5694000
1106
6636000
38
456000
37
133200
61
732000
616
1478400
1605
3210000
6433
30465600
11 Tikapur Mun
1100
6600000
748
4488000
665
3990000
939
5634000
15
180000
46
165600
72
864000
776
1862400
700
1400000
5061
30366000
12 Bheemdatt Mun
2571
15426000
1401
8406000
0
0
2759 16554000
137
1644000
28
100800
17
204000
2358
5659200
1605
9630000
10876
65256000
20215 121290000
47182 283092000
1961
23532000
2024
7286400
2807
33684000
Total
55403 332418000 33702 202212000
District Wise Vital registration Status of Fiscal Year 2071/72 Annual Birth Registration S.N.
Districts
Death Registration
Migration Registration
Marriage
Migratio Registrat Registratio Emigrat Immigration n n Number ion ion Number
Divorce
Total
Female
Male
Total
Female
Male
Total
1 Achham
11043
8505
19548
525
762
1287
1956
300
1712
25
1737
0
2 Bajura
3805
3706
7511
174
320
494
505
363
791
0
791
0
8873
3 Bajhang
4468
4929
9397
313
622
935
1105
1027
1558
134
1692
1
12465
4 Baitadi
3317
3124
6441
253
351
604
841
752
1397
62
1459
2
8640
5 Dadeldhura
3380
3638
7018
212
336
548
1012
1473
1150
324
1474
0
10051
6 Doti
5107
5934
11041
171
493
664
1002
2158
6350
355
6705
2309
2564
4873
153
264
417
550
562
819
137
956
1 0
14866
7 Darchula 8 Kanchanpur
7803
9860
17663
791
1354
2145
5726
6315
6581
12926
19507
9
31858
16533
19095
35628
1200
2432
3632
9641
12144
11389
33009
44398
15
61060
57765
61355
119120
3792
6934
10726
22338
25094
31747
46972
78719
28 177306
9 Kailali Total
23091
6402
Remarks
72624 174297600
75057 150114000
310975 1347160000
cg';"lr !@ bkmf !* sf] pkbkmf -!_ ;+u ;DjlGwt
bkmf !* sf] pkbkmf -!_ ;+u ;DjlGwt
lhNnf ljsf; ;ldltx?n] ;+l3o dfldnf tyf :yflgo ljsf; dGqfnodf k7fpg]
lhNnf ljsf; ;ldltn] ;+l3o dfldnf tyf :yflgo ljsf; dGqfnodf k7fpg]
;fdflhs ;"/Iff cg'bfg ljt/0fsf] jflif{s k|ult ljj/0f s|;
cf=a= @)&!/ @)&@ ;+Vof
ljj/0f
dlxnf
k"?if
;fdflhs ;"/Iff cg'bfg ljt/0fsf] jflif{s k|ult ljj/0f cf=a= @)&!/@)&@ ljt/0f ul/Psf] hDdf /sd
b/
s}lkmot
s|;
ljj/0f
hDdf
;+Vof
b/
dlxnf
1 h]i7 gful/s -blnt_
k"?if
ljt/0f ul/Psf] hDdf /sd
s}lkmot
hDdf
1 h]i7 gful/s -blnt_ 2941
2 Bajura
3617 1289
6558
500
39348
Dhangadhi
525
500
3150000
2403
500
14418
Tikapur
3 Bajhang
1317
1791
748
3108
18648
Bheemdatt
1644
3653
500
21918
1401 2674
500 500
4488000
500
4 Baitadi 5 Dadeldhura
2009 960
1500
16,044,000
994
1954
500
11724
6 Doti
1573
1614
3187
500
19122
1496
500
8976000
533
639
1172
500
7032
1100
500
6600000
1704
1532
3236
500
19416
500
35580
500 1500
15426000
16162
2770 5930 15039 31201
2571 5167
4500
1684854
949
500
5694000
1 Achham
3792
3023
6815
665
500
3990000
2 Bajura
2078
1591
3669
500 500
40890
0
500
0
3 Bajhang
3710
2926
6636
500
39816
1500
9684000
4 Baitadi
4480
3346
7826
500
46956
5 Dadeldhura
1697 1602
1723 1675
3420
500
20520
3277
500
19662
1 Achham
7 Darchula 8 Kanchanpur
3160
9 Kailali Total 2 h]i7 gful/s
1114
-cGo_
6 Doti
1736
1775
3511
500
21066
8 Kanchanpur
2643 4788
2932 5575 5322 10110
500
33450
26526
24313 50839
500 4500
60660 305034
3 Psn dlxnf
0
Dhangadhi Tikapur Bheemdatt Total
0
3 Psn dlxnf Bheemdatt Dhangadhi Tikapur Total 4 ljwjf
0
1614
Dhangadhi Tikapur Bheemdatt
5
Total 0 k"0f{ c;Qm ck+utf ePsf] JolQm
0
Dhangadhi Tikapur
1 Achham
7743
7743
500
46458
2 Bajura
3044
3044
500
18264
3 Bajhang
42
7
7
500
4 Baitadi
3889
3889
500
23334
5 Dadeldhura
2418
2418
500
14508
27
27
500
162
7 Darchula
691
691
500
4146
8 Kanchanpur
780
780
500
4680
4
500
6 Doti
9 Kailali
4 Total
0
18603
24 111618
18603
4 ljwjf 1 Achham
0
2 h]i7 gful/s -अन्य_
22014
7 Darchula
9 Kailali Total
Total
Bheemdatt Total
0
0
0
0
500
0
93006000
1106
500
6636000
939
4000
45072000
2759
500
16554000
4804
5000
288240000
38
1000
456000
15 137
1000 1000
1644000
190
3000
2280000
37
300
133200
46
300 300
165600
900
399600
732000
72
1000 1000
17
1000
150
3000
204000 1800000
180000
6 cfl;+s c;Qm ck+utf ePsf] JolQm Bheemdatt Dhangadhi Tikapur Total
0
0
7 nf]kpGd"v cflbjf;L hghftL Dhangadhi
Total
0
28 111
61
Tikapur Bheemdatt
0
8406000
0
100800
864000
2 Bajura
0
0
500
0
3 Bajhang
4580
4580
500
27480
4 Baitadi
3653
3653
500
21918
5 Dadeldhura
1634
1634
500
9804
6 Doti
9111
9111
500
54666
7 Darchula
2456
2456
500
14736
8 Kanchanpur
7344
7344
500
44064
9 Kailali
13600
Total 42378 5 k"0f{ c;Qm ck+utf ePsf] JolQm
13600
500
0 42378
81600 254268
192 1 Achham
8 afnjflnsf Dhangadhi Tikapur Bheemdatt Total
Dhangadhi Tikapur Bheemdatt Total s'n hDdf ;+Vof
1000 1000
55
1000
660
438
1000
5256
194
1000
2328
3 Bajhang
108
1000
1296
4 Baitadi
7 Darchula
189
1000
2268
5 Dadeldhura
8 Kanchanpur
346
1000
4152
6 Doti
9 Kailali Total
256
1000
3072
7 Darchula
1771
9000
21252
3 Bajhang 4 Baitadi 5 Dadeldhura 6 Doti
0
0
300
209
2 Bajura
58 79
300
284
3 Bajhang
75
300
270
4 Baitadi
58
300
209
119
300
428
215
300
774
7 Darchula
112
300
403
8 Kanchanpur
240
300
864
957 1913
300
3445
2700
6886.8
45
1000
540
467
1000
5,604
2025
1000
24,300
120
1000
1,440
2657
4000
31,884
15100
5 Dadeldhura 6 Doti
0
0
7 nf]kpGd"v cflbjf;L hghftL 1 Darchula 2 Dadeldhura 3 Kailali 4 Kanchanpur Total
0
0
8 afnjflnsf
6111
200 200
36240
2 Bajura 3 Bajhang
8827
200
21185
4 Baitadi
8218
200
19723
1 Achham
0
0
2080900 5659200
600
9218500
1605
2000
3210000
700
2000
1400000
1605 3910
2000
3210000
6000
7820000
2358 3750
10 Ho]i7 gful/s :jf:Yof]krf/ vr{ 1 Achham 2 Bajura
8 Kanchanpur 9 Kailali
1 Achham
1478400
200 200
428,492,100 2028
6 cfl;+s c;Qm ck+utf ePsf] JolQm
9 Kailali Total
0
200
776
9 जेष्ठ gful/s :jf:Yof]krf/ vr{
16 169
2 Bajura
0
616
14666
0
0
10884 2000 5355 2000
21768
8000 2000 11455 2000
16000
4802 2000 6063 2000
9604
10710
22910
12126
5055 2000 2243 2000
10110
15645 2000 29006 8000
31290
4486
58012 2,639,106
5 Dadeldhura
4908
200
11779
6 Doti
9038
21691
7 Darchula
2554
200 200
8 Kanchanpur
4597
200
11033
9521 0 68874
200
22850
1800
165298
9 Kailali Total
0
6130
Annex 9
9 j^} lhNnf ljsf; ;dltsf] sfof{no ;j}
cf=j= 071รท72 sf nflu :yfgLo zf;g tyf ;fd'bfoLs ljsf; sfo{qmdaf^ pknJw jh]^ tyf vr{ l;=g=
sfo{qmdsf] gfd
s'n hDdf
s'n hDdf
k|fKt ah]^
jfsL lkm|h
vr{ jh]^
ah]^
1 k'hLut tkm{ 1=1
Nofk^k vl/b cg'bfg
1800000
1786409
13591
1=2
sfo{qmd cg'udgsf] nflu df]^/;fO{sn v/Lb
1440000
1439800
200
1=3
cg'bfg -df+udf cfwf/Lt_ *]:s^k, ;e{/,lk|G^/, g]^js{;fdu|L / OG^/g]^ vl/b cg'bfg
2700000
2572005
127995
1=4
xfO{j|L* ;f]nf/ :yfkgf cg'bfg
2700000
2760129
-60129
s'n jh]^
8640000
8558343
81657
2 ;fdflhs kl/rfn tkm{
0
0
0
44857500
920737
2=1
;fdflhs kl/rfnssf] hLjg lgjf{x eQF
45778237
2=2
;fdflhs kl/rfnssf] Ifdtf ljsf; (Operating Cost)
3480000
2979526
500474
2=3
;fdflhs kl/rfnssf] b}=e=eQF
3480000
3313688
166312
s'n jh]^
52738237
51150714
1587523
4182500
3059449.8
1123050.2
4182500
3059449.8
1123050.2
0
0
0
3 ;"rgf k|ljlw :jo;]js hLjg lgjfx{ eQf s'n jh]^ 4 j*F gful/s dGr tyf gful/s ;r]tgf s]Gb|sf] Joj:yfkg vr{ 4=1
j*f gful/s dGrsf] ;+rfng cg'bfg -jflif{s_
4=2
gful/s ;r]tgf s]Gb|sf] ;+rfng cg'bfg -jflif{s_
4=3
u/Lljsf cGt/lgxLt sf/)fsf tYof+s ;+sng (UCPA) s'n jh]^ 5 :yfgLo ;]jf k|bfos %gf}^ tyf k/fdz{
11399750
11153750
246000
10440000
10440000
0
492000
492000
0
22331750
22085750
246000
0
0
0
497695
42305
5=1
:yfgLo ;]jf k|bfos %gf}^ nfut vr{
540000
5=2
:yfgLo ;]jf k|bfossf] ;]jf k/fdz{ vr{
6711263
4600899.3
2110363.8
s'n jh]^
7251263
5098594.3
2152668.8
6 lhljsf]kfh{g tyf ;\;fgf ef}lts k"jf{wf/ sfo{qmd
0
0
0
11500000
400000
6=1=
gful/s ;r]tgf s]Gb|sf nflu lhljsf]kfh{g /
11900000
6=1=
cGo cfo cfh{g sfo{qmd gful/s ;r]tgf s]Gb|af^ df+u eO{cfPsf ;\;fgf
15390000
14858000
532000
6=1=
k"jf{wf/ lgdf{)f cg'bfg -ut jif{sf] lkm|h_ gful/s ;r]tgf s]Gb|af^ df+u eO{cfPsf ;\;fgf
43155000
43155000
0
70445000
69513000
932000
0
0
0
1200000
1104637
95363
774770
13630
k"jf{wf/ lgdf{)f cg'bfg -rfn' cf=j=_ s'n jh]^ 7 sfo{qmd vr{ 7=1
;fd'bfoLs d]nldnfk sfo{qmd, hf]*f cg'bfg
7=2
df+udf cfwf/Lt afnd}qL :yfgLo zf;g
788400
7=3
;DjGwL cled'vLs/)f afne]nf / jfnjfnLsfsf] JolQmut #^gf btf{
505000
150000
355000
7=4
n}+lus pQ/bfO{Tj tyf ;fdflhs ;dfj]zLs/)f
600000
541000
59000
7=5
lhlj;sf] cf=n]=kf zfvfsf] ;'b[(Ls/)f
1700000
1700000
0
7=6
lhlj;sf] /fhZj zfvfsf] ;'b[l(s/)f
200000
200000
0
1153039
646961
7=7
k"jf{wf/ ljsf; sfo{qmd
1800000
7=8
cWofjwLs lhlj;sf] of]hgf
2100000
1831340
268660
7=9
df+udf cfwf/Lt Ifdtf ljsf; sfo{qmd
535000
501565
33435
7=10
uflj; ;lrjx?nfO{ ;"rgfsf] xs ;DjGwL cled'vLs/)F
900000
840562
59438
7=11
uflj; ;xfos sd{rf/Lx?nfO{ ljQ Joj:yfkg tflnd
2200000
2098645
101355
Pd cfO P; O{G^L
1625000
1352070
272930
14115800
12456989
1658811
0
0
0
7=12
s'n jh]^ 8 sfo{qmd cg'udg tkm{ 8=1 8=2
lhNnf ;fdflhs kl/rfng cg'udg cg'bfg
900000
772162
127838
:yfgLo ljsf; sf]ifaf^ ul/g] cg'udg sfo{qmd
800000
797635.5
2364.5
1700000
1369797.5
330202.5
181404550
173292638
8111912.5
s'n jh]^ s'n hDdf jh]^
Annex 9
21 j^} gu/dflnsfx?sf] cf=j= 071รท072 sf nflu :yfgLo zf;g tyf ;fd'bfoLs ljsf; sfo{qmdaf^ pknJw jh]^ tyf vr{
l;=g=
sfo{qmdsf] gfd
s'n hDdf k|fKt ah]^
1=1 1=2 1=3
1 k'hLut tkm{ Nofk^k vl/b cg'bfg sfo{qmd cg'udgsf] nflu df]^/;fO{sn v/Lb cg'bfg -df+udf cfwf/Lt_ *]:s^k, ;e{/,lk|G^/, g]^js{;fdu|L / OG^/g]^ vl/b cg'bfg
1=4
xfO{j|L* ;f]nf/ :yfkgf cg'bfg s'n jh]^ 2 ;fdflhs kl/rfn tkm{ 2=1 ;fdflhs kl/rfnssf] hLjg lgjf{x eQF ;fdflhs kl/rfnssf] Ifdtf ljsf; (Operating Cost) 2=2 hDdf jh]^ 3 ;"rgf k|ljlw :jo;]js hLjg lgjfx{ eQf s'n jh]^ 4 j*F gful/s dGr tyf gful/s ;r]tgf s]Gb|sf] Joj:yfkg vr{ j*f gful/s dGrsf] ;+rfng cg'bfg -jflif{s_ gful/s ;r]tgf s]Gb|sf] ;+rfng cg'bfg -jflif{s_ u/Lljsf cGt/lgxLt sf/)fsf tYof+s ;+sng (UCPA) s'n jh]^ 5 :yfgLo ;]jf k|bfos %gf}^ tyf k/fdz{ 5=1 :yfgLo ;]jf k|bfos %gf}^ nfut vr{ 5=2 :yfgLo ;]jf k|bfossf] ;]jf k/fdz{ vr{ s'n jh]^ 6 lhljsf]kfh{g tyf ;\;fgf k"jf{wf/ sfo{qmd gful/s ;r]tgf s]Gb|sf nflu lhljsf]kfh{g / 6=1 4=1 4=2 4=3
s'n hDdf
jfsL lkm|h ah]^
vr{ jh]^
1200000
1200000
0
900000
900000
0
4200000
4193400
6600
3500000
3499615
385
9800000
9793015
6985
18391500
12214268
6177232
960000
806745
153255
19351500
13021013
6330487
2409400
2209800
199600
2409400
2209800
199600
847500
824370
23130
5940000
3405915
2534085
250000
237000
13000
7037500
4467285
2570215
460000
459900
100
2872500
2360779
511721
3332500
2820679
511821
2530000
2300000
230000
6=2
cGo cfo cfh{g sfo{qmd gful/s ;r]tgf s]Gb|af^ df+u eO{cfPsf ;\;fgf
17010000
17010000
0
6=3
k"jf{wf/ lgdf{)f cg'bfg -k'/fgf] 58 g=kf=_ gful/s ;r]tgf s]Gb|af^ df+u eO{cfPsf ;\;fgf
15435000
15120000
315000
34975000
34430000
545000
200000
200000
0
440600
435300
5300 0
k"jf{wf/ lgdf{)f cg'bfg gof 72 / 61 -rfn' cf=j=_ s'n jh]^ 7 sfo{qmd vr{ 7=1 ;fd'bfoLs d]nldnfk sfo{qmd, hf]*f cg'bfg df+udf cfwf/Lt afnd}qL :yfgLo zf;g cled'vLs/)f 7=2 7=3 afne]nf / jfnjfnLsfsf] JolQmut #^gf btf{ ;xof]u 7=4 n}+lus pQ/bfO{Tj tyf ;fdflhs ;dfj]zLs/)f 7=5 gkfsf] cf=n]=kf zfvfsf] ;'b[(Ls/)f 7=6 gkfsf] /fhZj zfvfsf] ;'b[l(s/)f 7=7 jftfj/)f d}qL sfo{qmd 7=8 Plss[t ;DktLs/)f 7=9 gu/ oftfoft u'? of]hgf 7=10 df+udf cfwf/Lt Ifdtf ljsf; sfo{qmd 7=11 cfGt/Ls cfosf] nut ;Sng ug]{ 7=12 ljkt Joj:yfkg sfo{qmd 7=13 gkfsf sd{rf/L / j*f ;lrjx?nfO{ ;"rgfsf] xs ;DjGwL cled'vLs/)F 7=14 /fhZj ;DefAotf cWoog tyf k|If]k)f s'n jh]^ 8 sfo{qmd cg'udg tkm{ gu/ ;fdflhs kl/rfng cg'udg cg'bfg 8=1 9 O{lGhlgol/+u hLjg lgjfx{ eQf s'n jh]^ s'n hDdf jh]^
315000
315000
240000
240000
0
600000
510000
90000 0
300000
300000
1500000
1500000
0
2000000
1999967
33
3890000
2682345
1207655
1305000
1155000
150000
1420000
1330000
90000
5310000
1710000
3600000
1420000
1419410
590
900000
599450
300550
19840600
14396472
5444128
762250
762250
0
1680000
0
1680000
2442250
762250
1680000
99188750
81900514
17288236
Annex 10
Gender Equality and Social Inclusion F/Y 2071/72
Indicator
Achham
Bajura
Bajhang
Baitadi
Dadeldhura
Darchula
Doti
Kailali
Kanchanpur
1) District Development Committee Indicator Based Annual Progress Report S.n
A.
Gender Equity
1
is the 90% budget invested in direct benefited activities of 10% allocated budget from DDC internal and external total fund for target groups? Out of 10% allocated fund from the District Development centeral Fund direct benefited activities forwomen Women is 90% invested in Typesfor of project 90% invested for the
yes
yes
yes
yes
yes
yes
yes
yes
yes
9
yes
yes
yes
yes
yes
yes
yes
yes
yes
9
4
Is the gender responsive and social inclusion budget planning process guideline followed in all the stepes of local level planning process and decide by DDC planning councile.
yes
yes
yes
yes
yes
yes
yes
yes
yes
9
5
Is the DDC annual gender responsive and social inclusion budget audit? Preparation and implementation of action plan or not?
yes
yes
yes
yes
yes
no
no
no
yes
6
6
Have the GESI agenda and issues mainstreaming in the district periodic planning process or not Women representative (CAC, WCF, IPC, GRBC and district councile)
yes
yes
no
yes
no
yes
yes
yes
yes
6
0
18
86
34
20
23
35
0
138 354
8
Is the 40% or above WCF plan endorsed in district development plan or not?
yes
yes
yes
yes
yes
yes
yes
yes
yes
9
9
Is the local level gender equility and social inclusion policy prepare and implement in the base of national level GESI policy?
none no
no
no
no
no
no
no
no
0
C.
Social Inclusion
10
Out of 15% Total Capital Grant (Internal and External) of DDC , at least minimum 90 % budget allocation and expenditures in DAGs benefited projects(yes/no) Types of project 90% invested for the disadvantage group
yes
yes
yes
yes
yes
yes
yes
yes
yes
9
Total number of social and economic disadvantae group (CAC, WCF, Comperhensive planning committee, GRSI budget planning committee, district councile) Is the DDC have conducted GESI training, number of women and men participant
50
180
741
1530 1435
1237
0
0
185 5128
32
205
51
34
43
0
0
0
2 3 B.
7
11 D. 12
13
Progress status of DDCs
Total
Skill development and awareness activities on HIV/AIDS ,domestic voilence against in same sectors women,Awareness activities,IGA acivities,Capacity building, old people's home GESI responsive Budgeting and Auditing Practices at Local Governance Only the case of target budget
but working based on the national level policy
Reward to Dalit and Janjati students who have received excellent in SLC, Counseling to the Disabled, Sanitation campaign start in the Dalit community,Capacity building activities, Representation of the women and Disadvantage group in the CAC, WCF, Comperhensive planning committee, GRSI budget planning committee and councile.
38
2) Municipality Indicator based annual progress report (Old) S.n
Remarks
Indicator
Status of Municipalities
Total
Amargad hi
Bheemdu tt
Dipayalsi lgadhi
Dashrath chand
Dhangad hi
Tikapur
Old (Out of 58)
A.
Gender Equity
1
is the 90% budget invested in direct benefited activities of 10% allocated budget from Municipality capital fund for target groups?
yes
yes
yes
yes
yes
yes
6
2
Types of project 90% invested for the women in same sectors Is the gender responsive and social inclusion budget planning process guideline followed in all the stepes of local level planning process and decide by Municipal development planning councile.
skill development,public service preparation yes yes ofyes yes class, yesCapacity yes building
6
3
4
Total number of women participte ( CAC, WCF, Comperhensive planning process committee, gender responsive budget processing committee and muncipality councile.
97
387
1565
B.
GESI responsive Budgeting and Auditing Practices at Local Governance
5
Is the Municipal annual gender responsive and social inclusion budget audit? Preparation and implementation of action plan or not?
no
2
no
481
o
600
no
yes
yes
no
6
371
6
Is the 70% WCF plan endorsed in Muncipal development plan or not? yes
yes
yes
yes
yes
yes
6
7
no Is the muncipal prepare and implemented local level gender equality and social inclusion policy in the base of national level GESI policy? Have the GESI agenda and issues mainstreaming in the Muncipality yes periodic planning process or not Social Inclusion
no
no
no
no
no
0
yes
yes
no
no
no
3
8
C. 9
10
D. 11
yes yes yes yes yes Is the 90% budget of the 15% total allocated budget from Yes 6 muncipality fund for the disadvantage group have invested in entire area or not? Types of project 90% invested for the disadvantage group S support on old people's home, skill 6 development training to the Dalit community, promotion to the local arts and Representation of the women and Disadvantage group in the CAC, WCF, Comperhensive planning committee, GRSI budget planning committee and councile. 494 2105 Total number of social and economic disadvantae group 108 761 850 0
Jaypriti vi
Attriya
Belaury
Lamkichuwa
Sanfeeb agar
Mangle sen
Punarw as
Api
(CAC, WCF,Indicator Comperhensive planning committee, budget 3) Municipality based annual progress reportGRSI (New) Total
A.
Gender Equity
1
is the 90% budget invested in direct benefited activities of 10% allocated budget from Municipality capital fund for target groups?
yes
yes
yes
yes
yes
yes
na
yes
7
2
Types of project 90% invested for the women in same sectors
3
Is the gender responsive and social inclusion budget planning process guideline followed in all the stepes of local level planning process and decide by Municipal development planning councile.
Infrastructure, institutional development,Swing cutting training, treatment HIV infected yes yes women na and yes yes yes support no toyes
5
4
Total number of women participte ( CAC, WCF, Comperhensive planning process committee, gender responsive budget processing committee and muncipality councile.
653
283
1749
B.
GESI responsive Budgeting and Auditing Practices at Local Governance
5
Indicators
6 7
8 C. 9
10 D.
295
143
375
0
0
0
no Is the Municipal annual gender responsive and social inclusion budget audit? Preparation and implementation of action plan or not? Is the 70% WCF plan endorsed in Muncipal development plan or not? yes
no
no
no
no
no
no
0
yes
yes
yes
yes
yes
yes
6
no Is the muncipal prepare and implemented local level gender equality and social inclusion policy in the base of national level GESI policy? Have the GESI agenda and issues mainstreaming in the muncipality no periodic planning process or not Social Inclusion
no
no
no
yes
yes
yes
2
no
yes
no
no
yes
no
2
na
yes yes yes 6 Is the 90% budget of the 15% total allocated budget from yes Yes yes yes muncipality fund for the disadvantage group have invested in entire area or not? Types of project 90% invested for the disadvantage group Infrastructure, social activities,Capacity building and IGA,skill devlopment, promotional activities Representation of the women and Disadvantage group in the CAC, WCF, Comperhensive planning committee, GRSISanitation budget planning
Total number of social and economic disadvantae group (CAC, WCF, Comperhensive planning committee, GRSI budget planning committee and Muncipality councile. 4) Municipality Indicator based annual progress report
45
S.n
Indicators
Progress status of GESI
JhalariPapladi
Jaypritivi
DodharaChandani
Parsuram
Badimalik a
Patan
Bhajanitrisakti
Godaghod i
committee and councile. 11
305
A.
Gender Equity
1
is the 90% budget invested in direct benefited activities of 10% allocated budget from Municipality capital fund for target groups?
yes
yes
yes
na
na
na
na
na
2
Types of project 90% invested for the women in same sectors
IGA,skill development,safe-motherhood, women cooperative,Infrastructure, institutional development
97
382
35
146
35
1045
Total
3
3
Is the gender responsive and social inclusion budget planning process guideline followed in all the stepes of local level planning process and decide by Municipal development planning councile.
yes
yes
4
Total number of women participte ( CAC, WCF, Comperhensive planning process committee, gender responsive budget processing committee and muncipality councile.
0
653
B.
GESI responsive Budgeting and Auditing Practices at Local Governance
5
Is the Municipal annual gender responsive and social inclusion no budget audit? Preparation and implementation of action plan or not? Is the 70% WCF plan endorsed in Muncipal development plan or not? no
no
no Is the muncipal prepare and implemented local level gender equality and social inclusion policy in the base of national level GESI policy? Have the GESI agenda and issues mainstreaming in the Muncipality yes periodic planning process or not Social Inclusion
6 7
8 C. 9
10 D. 11
yes
na
na
na
na
na
3
0
0
0
0
0
653
no
na
na
na
na
na
0
yes
no
na
na
na
na
na
1
no
no
na
na
na
na
na
0
no
no
na
na
na
na
na
1
yes yes na na na na na 2 Is the 90% budget of the 15% total allocated budget from yes municipality fund for the disadvantage group have invested in entire area or not? Types of project 90% invested for the disadvantage group S skill development,Infrastructure, social activities and IGA 9 Representation of the women and Disadvantage group in the CAC, WCF, Comperhensive planning committee, GRSI budget planning committee and 45 na na na na na 45 Total number ofcouncile. social and economic disadvantae group (CAC, WCF, Comperhensive planning committee, GRSI budget planning committee and Muncipality councile.
5) Village Development Committee Indicator based annual progress report
Bajura
Baitadi
Dadeldh ura
Darchula
Doti
Kailali
Kanchan pur
Total
Bajhang
Status
Achham
S.N. Indicator
1
Total number of VDCs, 90% budget invested in direct benefited activities of 10% allocated budget from VDC total capital fund for target groups?
62
42
24
56
18
36
50
31
9
328
2
Types of project 90% invested for the women in same sectors Total number of VDCs who have followed the guideline of gender responsive and social inclusion budget planning process in all the stepes of local level planning process and decide by VDC planning councile. Total number of women participate ( CAC, WCF, Comperhensive planning process committee,VDC councile.)
Skill development training, awareness activities on HIV/AIDS and violence against18 women,Infrastructure, skill 9 62 domestic 42 24 56 36 50 31
328
3
4
5 6
7
8
Total number of VDC who have endorsed 80% WCF plan in village development plan Is the 90% budget of the 15% total allocated budget from VDC capital fund for disadvantage group have invested in entire area or not? Total number of social and economic disadvantage group representation (CAC, WCF, Comperhensive planning committee, GRSI budget planning committee and VDC councile. Total participants in local level planning process
328
3774
6155
3534 7687 2099
1081
1633 4047 1098 31108
62
42
24
56
18
36
50
31
9
328
62
42
24
56
18
36
50
31
9
328
415
944
878
1333 1435
1237
0
3139 545 9926
19245 10992 7560 16964 7539
10624 13553 1464 5922 93863
Remarks
Just follow the target group budget
©
Local Governance and Community Development Program (LGCDP-II)
Regional Coordination Unit (RCU), Dhangadhi
Tel.:+977-91 523240/525301
Fax No.:+977-91 523039