Air dome installation process Helsinki, Finland
Location: Helsinki, Finland Air dome dimensions: 115,2m x 70,85m x 20,0m Air dome purpose: Football, Multisport Year of installation: 2014
Terrain preparation works.
Building the concrete foundation around perimeter of the dome.
Construction of the wall continues. Auxiliary object (with cafe, wardrobes‌) will be built at one side.
At the side of auxiliary object, wall will reach 7m in height.
Building of the concrete foundation around the perimeter.
Field is already flat. One edge of the wall is still in progress.
Industrial tunnel entrance gap.
Preparatory works for the installation of artificial turf – special soft base which helps prevent the injuries during the practice and games.
Preparatory works for the installation of artificial turf are finished.
Artificial turf installing.
The rubber track is at the side.
Artificial turf with infill material.
The artificial turf is ready to be played on it.
Works inside of auxiliary object.
Windows from inside cafe bar to the up-coming air dome.
Installing revolving door entrance to the air dome.
Industrial tunnel assembling.
Preparing of anchoring system for the dome.
Membrane delivering to the field.
Stretching the membrane.
Large separate membrane sections are fixed together by means of aluminum plates.
Membrane stretching is almost done.
Anchoring works around the perimeter.
Membrane is being fixed to the wall of auxiliary object.
Ventilation system has been placed inside of the building and ready to start inflating the air dome.
Inflating the air dome.
Air dome - outside view.
Air dome - inside view.
Air ventilation tubes inside the air dome.
Lightning system with seats have been installed.
Air dome is ready to be played indoor.