Climbing wall complex

Page 1

Climbing Wall

The climbing wall is designed to be attached to a platform and is great for children to try and climb up. You will need 2.5� 3mm mild steel pipe, chequer plate and metal paint. You will also need to cement in the foundations of the climbing wall. Make sure you have at least 1.5 metres of space around the climbing wall.

Per climbing wall 2.5� 3mm mild steel pipe 2mm chequer plate

Amount 30ft 2ft by 8ft

How to build 1. Weld the frames to the measurements in the diagrams. 2. Cut the climbing pods and fill the ends to make sure they are very smooth. 3. Make sure that there are no sharp edges on the climbing pods/handles.

4. Before cementing in the frame sand and paint with undercoat the section of metal that will be going in the foundation. 5. Cement in the foundation and weld the climbing wall to the platform. 6. Paint.

Colour Scheme See the complex guide for the colour scheme of the climbing wall

1


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.