Platform - 3 door with roof
The 3 door Platform with roof is great for all of our complexes. You will need 2.5” 3mm mild steel pipe, 2” mild steel pipe, chequer plate, iron sheet and metal paint. You will also need to cement in the foundations of the platforms. Make sure you have at least 2 metres of space around the platform.
Per 3 door platform roof 2.5” 3mm, mild steel pipe 2” 3mm, mild steel pipe Iron sheet 1.5 x 1.5” 2mm hollow sec 2mm chequer plate
Amount 60ft 66ft 2 30ft 4ft x4ft
How to build 1. Weld the frames to the measurements in the diagrams 2. Make sure that there are no sharp edges. 3. Dig the foundations as shown in the diagram. 1
4. Before cementing in the frame, sand and paint with undercoat the section of metal that will be going in the foundation. 5. Place the frame in the foundations and make sure it is level on all axes. 6. Cement in the frame. 7. Paint. 8. Drill and rivet on the frame.
Colour Scheme See complex guide for colour scheme Foundations
X marks the centre of the foundation and where the leg should go. 30” deep
18” 18”
4ft
4ft
2