Steps - complex

1


The Steps are designed to be attached to one of our platforms in a complex. You will need 2.5� 3mm mild steel pipe, chequer plate, chain and metal paint. You will also need to cement in the foundations. Make sure you have at least 1.5 metres of space around the Steps.

Per Steps 2.5� 3mm mild steel pipe Medium chain 2mm chequer plate

Amount 30ft 4m 1 8x4ft sheet

How to build 1. Weld the frame to the measurements in the diagrams. 2. Make sure that there are no sharp edges. 3. Before cementing in the frame, sand and paint with undercoat the section of metal

that will be going in the foundation. 4. Weld the steps to the platform and then cement in the foundation. 5. Attach the chain using hooks or small bits of pipe. 6. Paint.

Colour Scheme For colour scheme see the complex guides