Watersituationandmitigation 2016 07 22 en

Page 1

Summary of the water volume, and progress of water shortage prevention and mitigation measures in Rayong and Chonburi Provinces for 2016 22 July 2016 Water War Room

0


OVERVIEW OF WATER Chachoengsao Reserve Pond P2

P4 P3

P5

17

P6

Private Pond

Samnakbok Reserve Pond P7

Bang Phra res. P9

19.21

76

P-BPN P8

3.31

Nong Kho res.

P10

P1

SITUATION IN

RAYONG-CHONBURI AREA 22 JUL 2016

Chonburi

Rayong

Bangphra

Nongkho

Dokkrai

Nongplalai

Klong Yai

Prasae

117.00

21.40

79.41

163.75

40.10

248.00

19.21

3.31

15.76

55.43

30.64

133.32

16%

15%

20%

34%

76%

54%

7.16

2.31

12.76

41.93

27.64

113.32

-

-

0.557

-

-

+3.25

+0.43

Reservoir capacity (MCM) Current storage volume (MCM) Percentage of reservoir capacity Useable storage volume (excluding Dead Storage) (MCM) Inflow into reservoir (MCM) Water volume compared to previous week (-decrease, +increase) (MCM) Total water volume in each area

-

0.557 +2.27

+3.12

+3.68

+5.92

22.53 MCM (16.3%)

101.83 MCM (35.9%)

+0.54 +4.76

Note: * When storage volume falls below 15.2 MCM, it is not possible to transfer water from Klongyai Reservoir to Nongplalai Reservoir

29

133.32 Prasae res.

30.64

Khlong Yai res. 55.43 Nong P11Pla Lai res. P12 P-NP3 15.76 P13 Dok Krai res. P14

P

29

120 P7

P15

184

P16

Raw Water Pipe Line (EW)

Source of data: Royal Irrigation Department

Demand 2558 (MCM.) Supply (MCM.) Pump Station Raw Water Pipe Line (RID)

Existing Pipe Network

Existing Pipe Network

Constructing Pipe Network

1 Constructing Pipe Network


SUMMARY OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES IN RAYONG AND CHONBURI PROVINCES Planned water volume

Measure

Total

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Total

8

8

0

9

9.3

9

9.3

9.3

9

15

15

15

115.9

22 JUL 2016

8.6

8.2

1.32

8.92

9.02

8.15

50.49

6.28

1.0

Plan Actual

1.2 Pump water from Rayong River back to Nongplalai Reservoir using RID’s Wat Lahanyai pump station. 1.3 Pump water from Rayong River 1.4 Water transfer from Bangpakong River + Private Pond

Actual

*Water Volume from Oct –Dec 2015 Total 10.64 MCM

Planned

1. Primary measures 1.1 Water diversion via pumping from Prasae Reservoir

2016 Jan

Plan

8

8

0

9

9.3

9

9.3

1.0

2.0 0.5

0.5

1.0

4.0

5.0

7.0

7.0

4.0

27.0

13.3

15

23

22.5

19.5

145.9

Remarks 1. Mar 2016 had dregging sediment in front of Mor Mui weir which place inside Klong Nam Dang canal. So it needed to stop divert water from Prasae reservoir for a whole month and adjust the water diversion plan from 8 MCM to 9 or 9.3 MCM per month started from Apr – Sep 2016 2 2. On Oct – Dec 2016 Plan to divert water can be change depend on water situation


Simulation of water volume in main Rayong Reservoirs

Assume by used rainfall as 1997 in first half year and no inflow between JUN - AUG

22 JUL 2016 Water Volume : 101.83 MCM.

3


WATER SITUATION

OF

BANGPHRA, NONGKHO RESERVOIR

4


WATER SITUATION

OF

NONGPLALAI, DOKKRAI

Source of data: Royal Irrigation Department

AND

KLONGYAI RESERVOIRS


WATER SITUATION

OF

PRASAE RESERVOIR

Source of data: Royal Irrigation Department

6


WATER SITUATION

OF

DOKKRAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

NONGPLALAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

KLONGYAI RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

BANGPHRA RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


WATER SITUATION

OF

NONGKHO RESERVOIR (BY YEAR)

Source of data: Royal Irrigation Department


PROGRESS OF WATER SHORTAGE PREVENTION AND MITIGATION MEASURES

IN

RAYONG AND CHONBURI PROVINCES On 15 July 2016

12


Prasae – Nongpalai project (1) Prasae-Nongplalai Pump Station: Completed pouring concrete, lean concrete base for support pump and motor, intake channel, roof work. Now a days work are 1.1 Build control room Switch Gear 1.2 Installtion tools for supporting pipe 1.3 Paint work both inside and outside 1.4 Construction SCADA building process for 30% Actual: 93.52 % (2) Pipe laying for 30 km section: Completed pipe jacking across Route 344 and joined the main pipe only. Work Process 0.225 km. pipe laying left. (On process contractors order pipe) (3) Head Tank: Installing Slip Form which already 100% of work process. Completed anchorage head for posttension system 100%. The process to install stair out side tank about 100%, install Metal Bellow tools and steel pipe inside Head tank . Actual 98.62% (4) Sub_115 kv: Actual 99.71% 4.1 Repair road inside the site 4.2 Wiring work

*Remarks: between negotiation with supplier


Summary of the water volume, and progress of water shortage prevention and mitigation measures in Rayong and Chonburi Provinces for 2015-16 (cont.)


Summary progress of Tabma reservoir

On 15 Jul 2016

Objective For increase water supply in Rayong area not less than 47 MCM/year Project Construct pumping station nearby Rayon River and Tabma canal. For divert and keep water inside Tabma reservoir then send the water into EW pipe line system. Budget: Water Volume: Construction period: Due date:

2,202.7 million baht 47 MCM/year 60 months (extended contact) 15 JUL 2016

Work progress (Plan) : Actual:

100 % (15 Jul 16) 76.98 %

Remarks: The project don’t have work of process because of heavy rainfall.

15


NONGPALAI – NONGKHO ROUTE NO.2 PIPE LAYING PROJECT Objective : Increase capacity to supply water for Borwin Pluak Daeng area about 60 MCM/ year.

Component:

1. Temporary pumping station construction and install pump 2. Pipe lying size 1,200 mm. length 10.1 km. and 700 mm. length 11.2 km. 3. SCADA

Work Process: on 15 Jul 2016 - Plan - Delay from plan

95.02 % 3.50 %

PIPE: on 15 Jul 2016

- Pipe size 1,200 mm. finished - Pipe size 700 mm. finished

PUMP STATION:

- Finished install pump and motor - Finished electric system - During system test

16


End of Presentation

17


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.