RESA Discussion Points

Interruptible Load Program (ILP)

ILP Preparatory Activities

ILP Feedback from Contestable Customers Contracted

ILP Implementation Activities


INTERRUPTIBLE LOAD PROGRAM


ILP Implementation

Process being finalized is to utilize stand-by generation of contracted Contestable Customers to relieve system demand duringYellow and Red Alert Situations

4

October 3, 2014


ILP Implementation

5

October 3, 2014


ILP Implementation

Customer participation is voluntary and done via coordination by the DU direct to the customers for confirmation

6

October 3, 2014


ILP Implementation

7

October 3, 2014


ILP Implementation

Contracted volumes by the RES customer will be re-declared to MERALCO/DU and settled at the ERC approved ILP rate

8

October 3, 2014


ILP Implementation

9

October 3, 2014


ILP Implementation SAMPLE COMPUTATION: De-Loaded kWh De-loaded kWh=Hourly Baseline kWh-Metered kWh during ILP

Date with ILP April 1, 2014

10

Deloading Hour 2:00pm3:00pm

Baseline kW (A) 2,305

Metered kW during ILP (B) 474

De-loaded kW (A – B) 1,831

October 3, 2014


ILP Implementation De-loading Compensation De-loading Compensation=Incremental De-loading Rate × De-loaded kWh + Maintenance Cost ₱18,365 De-loading Compensation

=

(₱9.71/kWh x 1,831 kWh) Incremental De-loading Rate x De-loaded kWh

+

₱585.92 Maintenance Cost

Where: (₱43.26/L x 0.34 L/kWh) Generation Cost of Fuel x Fuel Consumption Rate Generation Cost of Fuel ₱9.71/kWh Incremental De-loading Rate

11

1,831 kWh De-loaded kWh ₱585.92 Maintenance Cost

=

= =

Generation Cost of Fuel is the average price of diesel from Caltex, Petron & Shell the city or municipality where the ILP CC is located as of the end of the previous calendar month Fuel Consumption Rate is 0.34 L/kWh (2,305 kW – 474 kW) x 1 hour Baseline kW – Metered kW 1,831 kWh x ₱0.32/kWh or ₱23,548 per month, whichever is lower

-

₱5/kWh Average Generation Charge of ILP CC

October 3, 2014


ILP Implementation Meralco Payment to ILP RES (ILP Amount) ILP Amount = [Redeclared BCQ x ILP Rate] + Maintenance Cost ₱27,517 ILP Amount

=

1,831 kWh x ₱14.71/kWh Redeclared BCQ x ILP Rate

x

₱585.92 Maintenance Cost

Where: ₱43.26/L x 0.34 L/kWh Generation Cost of Fuel x Fuel Consumption Rate ₱14.71/kWh ILP Rate

=

Generation Cost of Fuel is the average price of diesel from Caltex, Petron & Shell the city or municipality where the ILP CC is located as of the end of the previous calendar month Fuel Consumption Rate is 0.34 L/kWh

12

1,831 kWh Redeclared BCQs ₱585.92 Maintenance Cost

=

Generator Redeclared BCQs to Meralco

=

1,831 kWh x ₱0.32/kWh or ₱23,548 per month, whichever is lower

October 3, 2014


Sample ILP Participation Complete Deloading from 10am to 1pm (Tuesday load profile)

kWh Utilized per Interval

2,500 2,000 1,500 1,000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Interval

Normal Operations

13

Deloaded interval: 10am-1pm

Note: Customer X has ample provision for diesel generator that could address energy needs during deloading.

October 3, 2014


Sample ILP Participation

kWh utilized from the grid of Customer X (Feb 26-Mar 25, 2014) Status Quo: No ILP participation Scenarios: 1- ILP @ Tuesdays, 10am-1pm 2- ILP @ Tuesdays, 12nn-3pm 3- ILP @ Tuesdays, 10am-3pm 4- ILP @ Tues and Thurs, 10am-3pm 5- ILP @ Tues, Thurs, and Sats, 10am-3pm

1,322,809 1,293,658

1,293,216 1,273,802 1,228,646 1,185,538

Status Quo

Scenario 1

Scenario 2

Scenario 3

Scenario 4

Scenario 5

October 3, 2014


ACTIVITIES TO BE UNDERTAKEN


ILP Preparatory Activities

Confirm compensation rate approved by the ERC against embedded generation costs Identify preferred operating hours and sustainable operating period Identify personnel to be contact point upon enrolment to ILP

16

October 3, 2014


Why Participate?

Shortage in 2015 will result to Automatic Load Drop (ALD) / Manual Load Drop (MLD) Scenarios for all those connected to the grid Enrolment to ILP will ensure prior notification for any ALD/MLD scenario during Yellow and Red Alert grid situations Operation of stand-by generation capacity will be compensated via ILP approved rate

17

October 3, 2014


FEEDBACK ON ILP


Contestable Segment Feedback

Number of Contracted Number of Committed RES Customers

12

75

Committed Contracted Load for ILP, MW

245


IMPLEMENTATION ACTIVITIES


Implementation Activities

RESA, MERALCO and ERC discussions on-going for the implementation of ILP on the retail supply segment via re-declaration process of RES volume to MERALCO DOE support being provided to allow for re-declaration of RES volume in the WESM Review of tax applications on-going to determine possible assistance to be requested involving impact of ILP transactions to both the RES and participating ILP