129 HESTON ROAD DELIVERY PLAN DECEMBER 2020
1
OVERVIEW The Heston Road project is presently going through a management and delivery restructure to ensure the delivery of the 9 properties and the retail unit Moninstone have made the following appointments to ensure the overall project and facilitate the sale of the properties in 2021 Appointment of Contract Administrator Andrew Breathwick Engaged the following professional team members CIBER Limited – Project Management Harrabin – Independent PQS MJ Architects – Design and Procurement
2
IMMEDIATE ACTIONS TAKEN W/E 27TH NOV Moninstone have initiated the following Reprogrammed the project for a 2021 finish Commenced a procurement process to accept an incoming contractor Taken steps to secure the site, and checked the status of building control inspections so far ( favourable reports with no defects as at 27/11) Engaged with the outgoing contractor for transitions Retained the incumbent designer Ed Deacon to finish design under warranty Retained the PQS for valuation Initiated information exchanges with and Independent PQS Practice 3
DELIVERY TEAM
4
OUTLINE PROGRAMME EARLY JUNE 2021 FINISH
5
THANK YOU HESTON@CIBER.GROUP HTTP://WWW.CIBER.GROUP