Endpoint London Concept Proposals May 2014
02 - Concept Direction // Other Spaces & Places Creative, social & industrial
03 - General View // Entrance & Meeting Rooms Space Entrance & Meeting Rooms
04 - Entrance // Lobby Entrance & Meeting Rooms
05 - Entrance // Reception Entrance & Meeting Rooms
06 - Main Meeting Room // View 1 Entrance & Meeting Rooms
07 - Main Meeting Room // View 2 Entrance & Meeting Rooms
08 - Meeting & Work Rooms Entrance & Meeting Rooms
09 - Entrance & Work Space // Option 1 Entrance & Meeting Rooms
10 - Entrance & Work Space // Option 2 Entrance & Meeting Rooms
11 - Concept Direction // Other Spaces & Places Office Floor
12 - General View // Office Space Option 1 // View 1 Office Floor
13 - General View // Office Space Option 1 // View 2 Office Floor
14 - General View // Office Space Option 2 Office Floor
15 - General View // Ceiling Option 1 Office Floor
16 - General View // Ceiling Option 2 Office Floor
17 - General View // Ceiling Option 3 Office Floor
18 - Office Space // Option 1 // View 1 Office Floor
19 - Office Space // Option 2 // View 1 Office Floor
20 - Office Space // Option 1 // View 2 Office Space
21 - Office Space // Option 1 // View 3 Office Floor
22 - Concept Direction // Other Spaces & Places Workshop & Kitchen Floor
23 - General View // Studio & Kitchen Space Workshop & Kitchen Floor
24 - Library Workshop & Kitchen Floor
25 - General View // Studio & Kitchen Space // Option 1 Workshop & Kitchen Floor
26 - General View // Studio & Kitchen Space // Option 3 Workshop & Kitchen Floor
27 - Studio // View 1 // Option 1 Workshop & Kitchen Floor
28 - Studio // View 1 // Option 3 Workshop & Kitchen Floor
29 - Workshop // View 2 // Option 1 Workshop & Kitchen Floor
30 - Workshop // View 2 // Option 2 Workshop & Kitchen Floor
31 - Workshop // View 2 // Option 3 Workshop & Kitchen Floor
32 - Kitchen Workshop & Kitchen Floor
Build Cost Summaries
Endpoint London
Assumptions
COLLECTION
For the purposes of this proposal, we have made some assumptions to enable us to quote. They are intended only to indicate our recommended budget for a project of this type and if appointed we would redefine these as part of the project definition phase.
Gross Total (£)
Rate (£/m2)
1
ENABLING
5,586.00
29.00
2
BUILDING WORKS
65,477.00
366.00
3
FIXED FURNITURE
54,826.00
281.00
4
LOOSE FURNITURE
39,050.00
200.00
5
FF&E
2,444.00
13.00
6
ELECTRICAL
7,606.00
39.00
TOTAL ESTIMATED WORKS
174,989.00
897.00
5
DESIGN FEES
4,350.00
6
DESIGN DEVELOPMENT
9,873.00
7
PROCUREMENT
4,557.00
8
PROJECT MANAGEMENT Part A
7,595.00
9
PROJECT MANAGEMENT Part B
7,595.00
ESTIMATED PROJECT TOTAL
208,959.00
Thank you