Regent Square West Dallas Apartments - SD Estimate Houston, TX May 18, 2011 May 31, 2011
Estimate Recap Building Area
Cost/GSF
Offsite Work
$1,660,939
0.98 acres
$1,694,835 / acre
Sitework
$864,346
1.78 acres
$485,587 / acre
Parking
$7,701,543
170,762 sf
$45.10 / sf
$30.07 / sf
Residential
$51,171,697
357,494 sf
$143.14 / sf
$199.80 / sf
$61,398,524
528,256 sf
$116.23 / sf
GRAND TOTAL
Sellable Area
Cost/Rentable SF
Gross Building Cost
$6.48 / sf
256,121 sf
256,121 sf
$3.37 / sf
$239.72 / sf
GID WEST DALLAS APARTMENTS, Houston, Texas LIST OF QUALIFICATIONS AND CLARIFICATIONS May 19, 2011 General Project Information
o o o o o o o o o
The Budget Cost is based on the following: 100% Schematic Drawings dated May 5, 2011 (see list of drawings attached.) Exterior skin consists of brick, stucco, cast stone (Arriscraft), metal panels The Structure is included as post-tensioned cast-in-place concrete on auger cast piles. Our price is based on working hours between 7 a.m. to 10 p.m., Monday through Saturday. No other restrictions are considered. Budget pricing includes costs for pursuing LEED Building certifications. We include the cost associated with providing a Contractor Controlled Insurance Program (CCIP). J.E. Dunn will be furnished all CAD drawing (architectural and structural background) and Revit model files for our use in preparing shop drawings. General Building Permits are included. Price includes a payment & performance bond.
The Budget Cost excludes the following: o We have assumed that all residential units are rental units and have excluded insurance premiums for condominiums. o It is assumed that air rights for tower cranes and the building are obtained and provided by the owner. o Cost for crane easements. o Cost for utility easements. o We have not included the cost of a detailed LEED or 3rd Party building commissioning in our budget. o LEED certification of any buildings. o Impact fees. o Expediting of any permits or fees. o Builders risk insurance. o Document reproduction. o Environmental survey. o Soils report. o Materials testing and inspections. o Project survey. o Tap and meter fees. o Mold-free certification for each apartment. o Retail space is included as cold dark shells.
Regent Square List of Clarifications May 19th, 2011 Page 2
1.
GENERAL REQUIREMENTS
1.1
1.3 1.4 1.5
All supervision, engineering, temporary protection, temporary utilities, safety, cleanup, preconstruction, hoisting, and equipment necessary to perform the work is included. Substantial completion for of the project is 610 calendar days from start of construction. This assumes that building permits are issued when required to allow work to start as shown in our construction schedule. General conditions are included Budget is based upon a sales tax rate of 8.25% for Houston, Texas. Previously agreed upon preconstruction costs are not included in this estimate.
2.
DEMOLITION
2.1
The Budget Cost is based on the following: Demolishing all existing offsite streets for new paving & utilities.
2.2 2.3 2.4 2.5
The Budget Cost excludes the following: Temporary rental of parking meters or relocation of such. Demolition, removal or abatement of the existing Allen House Apartments and buildings. Cost associated with any City required street or sidewalk usage rental. Demolition or relocation of any dry type utilities.
3.
MASS EXCAVATION & SITE PREPARATION
3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8
The Budget Cost is based on the following: Temporary dewatering system as needed. Clearing. Mass excavation and grading of the site. Estimate assumes a balanced site. Temporary roads. Erosion Control and SWPP plan. Building Pads. (24� select fill material max). Cuts & fills as required for offsite road work. A $30,000 tree relocation allowance.
1.2
3.9 3.10 3.11 3.12
The Budget Cost excludes the following: Excavation shoring. Shoring is included for site utilities trenches. Removal or replacement of hazardous materials, unsuitable soils or rock, and any other unforeseen structures or utilities. Permanent dewatering system. NPDES monitoring systems.
Regent Square List of Clarifications May 19th, 2011 Page 3
4.
FOUNDATION EXCAVATION
4.1
The Budget Cost is based on the following: Included with foundation allowance – reference line item #9.
4.2
5.
The Budget Cost excludes the following: Removal or replacement of hazardous materials, unsuitable soils or rock, and any other unforeseen structures or utilities. SITE UTILITIES
5.5 5.6 5.7
The Budget Cost is based on the following: New domestic water, fire water, water meters, taps, backflow preventers, sewer, and storm drainage as shown. Cost includes utility piping, street cutting/demo, street patching, and traffic control. Off-site utilities as shown. A $3,500 allowance for a water and drain line for the dog park fountain (not shown on the pricing documents). Unknown underground utility relocation/demolition allowance of $100,000. Centerpoint relocation allowance cost of $805,000 for overhead power lines. Relocation allowance of $100,000 for phone and cable lines.
5.8 5.9 5.10 5.11 5.12
The Budget Cost excludes the following: Water tap or sewer impact fees. Detention basin/pond. Filtration or treatment of storm water. Gas services and meters to the building are assumed to be by local utility company. Fiber-optic cable/telecom/data/security work other than the allowance included above.
6.
SITE IMPROVEMENTS AND HARDSCAPE
5.1 5.2 5.3 5.4
6.1 6.2 6.3 6.4 6.5 6.6 6.7
The Budget Cost is based on the following: Pedestrian sidewalks on the South side of West Dallas and along the East side of Rochow to the end of Phase I limits. An allowance of $10,000 is being carried for site furniture. An allowance $55,000 is being carried for street lighting along W. Dallas. Parking striping within the parking deck. 6” crushed concrete base material with SS-1 primer coat @ 0.15 to 0.25 gallon per sq. yd, with 2” type D HMAC on the base material at all site streets. An Allowance of $15,000 is being carried for the fountain located in the entry plaza dog park. An Allowance of $10,000 is included for garage signage.
Regent Square List of Clarifications May 19th, 2011 Page 4
6.8 6.9 6.10 6.11
The Budget Cost excludes the following: Sandblasted curbs. Wheel stops. Permanent fencing. Bus stops.
7.
LANDSCAPING
7.1
The Budget Cost is based on the following: Street level landscaping and irrigation is included as an allowance for $50,000.
8.
SOIL POISONING
8.1
The Budget Cost is based on the following: Termite treatment beneath the slab on grade at occupied buildings.
9.
CONCRETE FOUNDATIONS
9.1
The Budget Cost is based on the following: An allowance of $528,256 is included for footings, grade beams, pile caps, auger cast piles, building pad, any and all other below grade foundation work.
9.2 9.3 9.4
The Budget Cost excludes the following: Foundation drainage. Excavation and removal of hazardous materials. Foundation testing.
10.
CONCRETE FRAME
10.1
The Budget Cost is based on the following: Concrete frame as shown on structural drawings.
10.2 10.3 10.4 10.5
The Budget Cost excludes the following: Puddling is excluded. Slab concrete strength is increased by 1,000 psi to remove the need. Architectural concrete finishes. Powder blasting/sand blasting for architectural finishes. Epoxy coated post tension cables.
Regent Square List of Clarifications May 19th, 2011 Page 5
11.
CONCRETE FORMWORK
11.1 11.2 11.3
The Budget Cost is based on the following: All formwork necessary to complete the concrete structure. MDO plywood forms at all exposed exterior walls and columns. BB plywood horizontal / MDO vertical for interior wall and column in the residential floors.
11.4
The Budget Cost excludes the following: Architectural concrete.
12.
CONCRETE REINFORCING STEEL/POST TENSIONING
12.1 12.2
The Budget Cost is based on the following: Reinforcing included as per structural drawings. Foundation reinforcement is included in line 9 Foundations.
12.3 12.4
The Budget Cost excludes the following: Encapsulated Cables (except at the pool deck area). Galvanized or epoxy coated rebar.
13.
EXTERIOR CAST STONE/LIMESTONE
The Budget Cost is based on the following: 13.1 Stonework in areas indicated on the drawings. The Budget Cost excludes the following: 13.2 Flamed granite. 13.3 Limestone veneer.
Regent Square List of Clarifications May 19th, 2011 Page 6
14.
14.1 14.2 14.3 14.4 14.5 14.6 14.7
15.
15.1
15.2
MASONRY The Budget Cost is based on the following: 12" CMU at walls greater than 13' tall. 8" CMU at walls less than 13' and trash chutes. All partitions within the parking deck area are CMU unless noted otherwise on the drawings. Modular face brick is assumed included as shown in the Basis of Design. Compressible fire safing insulation at the top of interior CMU walls with a continuous dovetail slot and dovetail anchors per seismic requirements. Gray "type S" mortar at all CMU areas. An allowance of $34,000 is being carried for the masonry screen wall south of the electrical poles in the entry plaza. STRUCTURAL & MISCELLANEOUS STEEL The Budget Cost is based on the following: Miscellaneous steel pricing is based on the following: stairs and rails, masonry and framing clips, window washing roof tie downs only (no davits) at 8 story buildings and office building, We have included Rheinzink metal panels.
The Budget Cost excludes the following: 15.3 Concrete column embed corner guards in the parking deck. 15.4 Angles at top of each side of masonry walls. 15.5 Stainless steel cable railing at parking garage ramps as shown and at the South face of the parking garage in lieu of the wall assembly shown on the pricing documents. 16.
ROUGH CARPENTRY
16.1 16.2 16.3
The Budget Cost is based on the following: Fair Housing Act in-wall blocking within the units at toilet & tub/shower walls. Roof blocking. Door bucks in stud partitions and window blocking.
17.
FINISH CARPENTRY
17.1 17.2 17.3 17.4
The Budget Cost is based on the following: Nominal 1�x 6� MDF base in corridors and elevator lobbies. Standard casing at all pre-hung doors within the units. 1" x 6" painted one-piece MDF base in the units. Crown molding included in the units at kitchen and living room.
Regent Square List of Clarifications May 19th, 2011 Page 7
17.5 17.6 17.7
Casing at unit entry doors frames. Ventilated wire shelving for closets. Common area casework is included as an allowance of $30,000. This will include mailrooms, maintenance rooms, and coffee bars.
17.8 17.9
The Budget Cost excludes the following: Chair rail and crown molding at corridors. Wood closet shelving and rods.
18.
MAIN LOBBY FINISHES
18.1
18.2
The Budget Cost is based on the following: Main Lobby Finishes are an allowance of $203,120. This allowance includes the main concierge desk, the lobby flooring, lobby wall treatments, any wood trim, articulated drywall ceilings (or other ceilings), interior partitions/storefronts, and millwork. Exterior partitions, exterior doors, HVAC, plumbing, fire protection, and electrical system costs are included elsewhere in the Budget.
18.3
The Budget Cost excludes the following: Audio-visual equipment, plasma screen televisions, and furniture.
19.
WATERPROOFING & SEALANTS
19.8 19.9 19.10 19.11 19.12 19.13 19.14 19.15 19.16 19.17 19.18 19.19 19.20 19.21
The Budget Cost is based on the following: Bentonite waterproofing with HPDE protection layer at elevator pit slabs and site retaining walls. Joint sealants at exterior concrete paving. Joint sealants at garage expansion joints, pour strip joints and control joints. Joint sealants at top of wall and control joints in CMU. Joint sealants at hollow metal door frames. Pedestrian traffic coating at apartment balconies. Fluid applied membrane air barrier with a wet film thickness of 70 mils to exterior sheathing behind masonry, plaster and metal panels. Joint sealants in exterior sheathing 40 mil self adhering rubberized asphalt wall flashing at framed window, door and louver openings. 40 mil self adhering rubberized asphalt transition strips over window flanges. 24 ga. Stainless steel sheet metal flashing at heads of windows and doors. 24 ga. Stainless steel sheet metal flashing at base of walls. 40 mil self adhering rubberized asphalt thru-wall flashing. 215 mil hot fluid-applied rubberized asphalt waterproofing, composite drainage board and 2� rigid insulation at areas to receive concrete paving or pavers at amenity deck.
Regent Square List of Clarifications May 19th, 2011 Page 8
19.22 215 mil hot fluid-applied rubberized asphalt waterproofing, water retention composite drainage board, root barrier and 2” rigid insulation at areas to receive landscaping at amenity deck. 19.23 215 mil hot fluid-applied rubberized asphalt waterproofing and composite drainage board at planter slabs and walls on amenity deck. 19.24 215 mil hot fluid-applied rubberized asphalt waterproofing at pool tub slab and walls on amenity deck. 19.25 Precast concrete pavers on pedestal system at amenity terrace. 19.26 Joint sealants at vertical masonry joints, masonry/metal panel transitions and masonry/plaster transitions. 19.27 Expansion joint cover assemblies between apartments and garage
19.28 19.29 19.30 19.31
The Budget Cost excludes the following: Damp proofing behind stucco at CMU/Concrete walls. Traffic topping in parking decks above non-enclosed spaces. Caulking the slab on grade joints. Mold-free certification. Can be added at $325 per unit for 511 total units.
20.
BUILDING INSULATION
20.1 20.2 20.3
The Budget Cost is based on the following: R-19 unfaced fiberglass insulation is included at exterior walls. R11 and R19 unfaced insulation is included at interior walls. Exposed rigid thermal insulation on the parking garage where heated areas are above.
20.4
The Budget Cost excludes the following: Sprayed insulation to deck.
21.
ROOFING & SHEET METAL
21.3
The Budget Cost is based on the following: Roofing system is assumed to consist of a Firestone modified roofing system consisting of an SBS Ultra White cap with three plies of Ply VI felts in hot asphalt. ¼” per foot tapered insulation and ½” cover board (R-25). 24 ga. pre-finished metal flashing for roofing systems, including parapet coping, counter flashings, scuppers, and downspouts. 20 year manufacturer's warranty.
22.
ENTRANCE CANOPIES
22.1
The Budget Cost is based on the following: Composite metal cladding of structure carried in other areas.
21.1
21.2
Regent Square List of Clarifications May 19th, 2011 Page 9
23.
HOLLOW METAL DOORS AND FRAMES
23.1 23.2
The Budget Cost is based on the following: Hollow metal door frames with wood doors at all unit entries. Hollow metal doors and frames at the elevator penthouse, the parking deck, and exterior doors.
24.
WOOD DOORS AND FRAMES
24.6 24.7
The Budget Cost is based on the following: Common area doors to be 8’-0” high, prefinished solid core wood doors in hollow metal frames. 8’-0” high, 20-minute rated solid core field painted select plain sliced maple doors at the apartment entries and common areas. 8’-0” high x 1 3/8” thick two-panel hollow core pre-hung masonite doors at the apartment interiors. Doors at HVAC closet and laundry rooms with stacking washer/dryers are louvered. Laundry rooms with side by sides are two-panel doors. All pre-hung doors are field painted and have 4 -9/16” jambs. Service and back-of house doors assumed to be 8’-0” high, hollow metal doors in hollow metal frames. All pre-hung doors are framed with #473 finger jointed wood casing. 45-minute rated wood doors at the trash rooms on the typical floors.
24.8
The Budget Cost excludes the following: Smoke hardware at 45-minute rated wood doors at the trash rooms on the typical floors.
25.
FINISH HARDWARE
25.1 25.2
The Budget Cost is based on the following: We have included hinges within the apartments to match the hardware sets. All fire rated doors will have intumescent seals built into the door.
25.3
The Budget Cost excludes the following: Magnetic doors strikes or other security hardware.
24.1 24.2 24.3
24.4 24.5
Regent Square List of Clarifications May 19th, 2011 Page 10
26.
SPECIAL DOORS & DOCK EQUIPMENT
26.1
The Budget Cost is based on the following: Two steel coiling doors.
26.2
The Budget Cost excludes the following: Dock Levelers, bumpers and any other dock equipment.
27.
BALCONY RAILINGS
27.1
The Budget Cost is based on the following: Kynar XL finished metal framed glass railing at balconies.
27.2
The Budget Cost excludes the following: Bituminous coating around the posts at balcony railings.
28.
GLASS, GLAZING & STOREFRONT
28.3
The Budget Cost is based on the following: Storefront cost is based on aluminum storefront with Kynar XL finish. Residential windows to be non-operable Kawneer punch windows, storefront and curtain wall in lieu of MI Windows. All miscellaneous aluminum brake metal.
29.
ROOF TOP ELEMENTS
29.1
The Budget Cost is based on the following: See allowances
29.2
The Budget Cost excludes the following: Architectural roof screens.
30.
DRYWALL
28.1 28.2
30.1 30.2
30.3 30.4
The Budget Cost is based on the following: Drywall partitions and ceilings as shown. Exterior wall framing with Dens-glass sheathing and R-19 batt insulation has been included in the wall cavity with a 2" leg deflection track at the top exterior wall frame (not slotted head track) at all retail areas. 5/8� DensShield at restroom walls. 5/8� XP mold resistant wall board at laundry rooms.
Regent Square List of Clarifications May 19th, 2011 Page 11
30.5
30.6
Common area ceilings are included as soffitted. Apartment unit ceilings in concreteframed buildings will be 60% skim coated exposed structure, and 40% flat drywall ceilings. Drywall walls and ceilings at spaces along exterior walls to have a level 5 finish. All other drywall to be a Level 4 finish.
31.
ACOUSTICAL
31.1
The Budget Cost is based on the following: Acoustical ceiling for the theater is included in the $90/sf finish allowance for the theater finishes and the finish system.
31.2 31.3
The Budget Cost excludes the following: Acoustical ceilings or grids in the retail spaces. Special roof or under roof treatment to abate cooling tower or condenser noise.
32.
STUCCO
32.1
The Budget Cost is based on the following: Stucco/EIFS is included as shown on the drawings.
33.
CLUB/FITNESS FINISHES
33.1
34.
34.1 34.2
The Budget Cost includes the following: Allowances are carried for the areas as follows: a. Leasing Office: $65/sf b. Gym/Fitness: $75/sf c. Theater: $90/sf d. Laundry: $40/sf e. Internet CafĂŠ: $75/sf f. Kitchen: $905/sf g. Dining Room: $80/sf h. Bar: $100/sf FLOOR AND WALL TILE The Budget Cost is based on the following: Ceramic tile at unit bathroom floors, tubs, showers, public restrooms, kitchen backsplash and vanity backsplash. Noble Seal crack isolation and waterproofing membrane in included at the bathroom and shower floors.
Regent Square List of Clarifications May 19th, 2011 Page 12
34.3 34.4
The Budget Cost excludes the following: Mud set tile. Epoxy grout at shower floors or walls.
35.
INTERIOR STONE WORK
35.1
The Budget Cost is based on the following: There is no interior stone work included in the units. Any common area stone work is included in the finish allowances as described elsewhere in this document.
36.
KITCHEN & BATH COUNTERTOPS
36.2 36.3
The Budget Cost is based on the following: Granite countertops are included at $24/sf at the kitchens and unit desk top. This should cover 3 cm granite. Residential bathroom vanities are solid surface. Granite countertops are on ¾” plywood substrates.
36.4
The Budget Cost excludes the following: Granite backsplashes at the kitchens.
37.
RESILIENT TILE & CARPET
37.1 37.2 37.3 37.1 37.2 37.3
The Budget Cost is based on the following: Carpet is included at common area corridors and offices at $40/SY. Carpet is included at unit bedrooms at $16/SY. VCT is included at back-of-house areas. 4” rubber base at all areas to receive VCT flooring. Engineered wood plank flooring for unit living room and kitchen floors. Acoustimat included at engineered wood flooring areas.
37.4
The Budget Cost excludes the following: Flooring within the retail and office areas.
38.
PAINTING
38.1 38.2 38.3 38.4 38.5
The Budget Cost is based on the following: All drywall ceilings and walls within the residential units. All painted surfaces in the residential units include a prime coat plus two finish coats. Drywall ceilings at the typical corridors and other public areas. All doors and frames except pre-finished doors. All wood base as indicated.
36.1
Regent Square List of Clarifications May 19th, 2011 Page 13
38.6
All “fast track� metal stairs and handrails.
38.7 38.8 38.9 38.10 38.11 38.12 38.13 38.14
The Budget Cost excludes the following: Painting the balcony bottoms and edges. Painting any millwork or cabinets. Painting within the retail spaces, restaurant space. Painting in the garage. CMU walls are not painted. Wall covering. Faux painting. Painting of exposed, concealed or Mechanical Room MEP pipes, duct, conduits, vents or other materials
39.
MISCELLANEOUS SPECIALTIES
39.1 39.2 39.3 39.4 39.5 39.6 39.7 39.8
The Budget Cost is based on the following: One 5 lb extinguisher is included at each apartment. Mailboxes for each apartment are included. Trash chutes are included. Trash sorters are included as an allowance of $20,000. Three dog wash sinks are included as an allowance of $3500/ea. Lockers at the fitness room are included in an allowance of $2000. iPod Docks are included as an allowance of $300/unit for a total of $83,400, and includes the dock and speaker wire. Speakers are not included. Bike racks are included in an allowance of $5,000.
The Budget Cost excludes the following: 39.9 Window washing equipment 39.10 Exercise equipment 39.11 Trash compactors 39.12 Wall bumpers at service corridor. There does appear to be a service corridor. 40.
TOILET PARTITIONS
40.1 40.2
The Budget Cost is based on the following: Plastic laminate ceiling hung toilet partitions at the amenities level bathrooms. Plastic laminate wall mounted urinal screens to match toilet partitions at the amenities level bathrooms.
Regent Square List of Clarifications May 19th, 2011 Page 14
41.
TOILET ACCESSORIES
41.3
The Budget Cost is based on the following: Units allow for toilet paper holder, towel bar, shower curtain rod, towel ring. An allowance for common area restrooms toilet accessories of $700/bathroom for a total of $9,350. Medicine cabinets for the unit bathrooms.
42.
PARKING EQUIPMENT
42.1
The Budget Cost is based on the following: Parking equipment is included as an allowance of $30,000.
43.
RESIDENTIAL CABINETS
43.1
The Budget Cost is based on the following: Cabinets are included as and allowance of $2800/unit for a total of $778,400.
43.1 43.2 43.3
The Budget Cost excludes the following: Light valances. Crown molding at the kitchen cabinets. Casework furr downs between top of cabinet and ceiling.
44.
FURNISHINGS
41.1 41.2
44.1
The Budget Cost is based on the following: An allowance of $280/unit with a total of $77,840 for 6-gauge, Bali Customiser 1" horizontal mini-blinds on all exterior glass (other than at sliding door and fixed door panel) in the residential units and fitness center.
44.2 44.3 44.4
The Budget Cost excludes the following: Walk-off mats. Televisions and all audio video equipment. Blinds at unit sliding balcony door or fixed door leaf.
45.
RESIDENTIAL APPLIANCES
45.1 45.2 45.3
The Budget Cost is based on the following: Residential appliances are assumed at $2700/unit Wine coolers are allowed separately at $450/unit. All appliances, assumed to have stainless steel finish.
Regent Square List of Clarifications May 19th, 2011 Page 15
45.5
The Budget Cost excludes the following: Dryer exhaust booster fans that may be required. Venting is assumed to be through the side of the building. Canopy hoods.
46.
ELEVATORS
46.1 46.2 46.3
The Budget Cost is based on the following: Two Otis Gen 2 room less passenger elevators with 2500 lb capacity and 450 fpm. One Otis Gen 2 room less freight elevator with 4000 lb capacity and 450 fpm. Elevator cab finishes allowed at $10,000/cab for a total of $30,000.
46.4 46.5 46.6
The Budget Cost excludes the following: Card readers. Televisions. Monthly maintenance agreement beyond first three months
47.
PLUMBING
45.4
47.1 47.2 47.3 47.4 47.5 47.6
47.7 47.8
The Budget Cost is based on the following: An allowance for the TEAL System structure on the roof of $20,000 is included. Domestic water piping will be CPVC. In the residential area, PVC risers will be employed and connected to plastic Sovent laterals. Drainage is included for the parking deck, amenity area, and roofs. Grease and lint traps. Plumbing fixtures as follows: 47.6.1 San Hose h/cap water closets. 47.6.2 San Hose elongated bowl water closets 47.6.3 Danze Parma lavatory faucets. 47.6.4 EZ-flow under counter mount lavatories. 47.6.5 Pacific 2 compartment under counter mount kitchen sinks 47.6.6 Danze Anu k/sink faucets. 47.6.7 Sterling Ensembles #71101110 42� x 60� oval bath tubs. 47.6.8 Job built showers. 47.6.9 Danze Parma tub valves. 47.6.10 Danze Parma shower valves. 47.6.11 Badger 1/3 garbage disposals. 47.6.12 Washing machine boxes. 47.6.13 Icemaker box Installation only of owner supplied water meters, excluding wiring or receiving stations. Quantum flow booster pump.
Regent Square List of Clarifications May 19th, 2011 Page 16
47.9 47.10 47.11 47.12 47.13 47.14 47.15 47.16 47.17 47.18
The Budget Cost excludes the following: Water heaters. Sewer impact fees. Domestic water meters. Painting of plumbing materials. Water softeners. Floor drains at balconies. Thermostatic valves. Water hammer arresters. Water softeners. Sovent system.
48.
HVAC
48.5 48.6 48.7
The Budget Cost is based on the following: VRV HVAC system is included with all condensers being located on roof areas. Combination fiberglass & flex duct systems for all residential units, with return air through louvered doors. Thermostats with locking covers will be provided for common corridors. Test & Balance of common area HVAC systems only. Total airflow will be measured and recorded for the residential units. Mechanical louvers, where required for mechanical ventilation or outside air intakes. Start up of all mechanical equipment. Stair pressurization.
48.8
The Budget Cost excludes the following: Condenser water circulating system beyond valved risers at non-residential cores.
49.
FIRE PROTECTION
48.1 48.2 48.3 48.4
49.1 49.2 49.3 49.4 49.5 49.6
The Budget Cost is based on the following: A complete and operable fire protections system which meets NFPA 13, NFPA 14 & NFPA 20 as interpreted by the City of Houston. The wet systems for the tower will be designed for light hazard occupancy and hydraulically calculated per NFPA 13. A wet pipe sprinkler system for the residential/common area space per the approval of the local authority having jurisdiction. A dry pipe sprinkler system for the garage per the approval of the local authority having jurisdiction. Standpipes will be provided in stairs. Design, fabrication, installation & testing to meet the applicable codes.
Regent Square List of Clarifications May 19th, 2011 Page 17
49.7
Semi-recessed sprinkler heads will be provided in common areas. Concealed sprinkler heads will be provided in the units and lobby areas. Brass upright sprinkler heads will be provided in exposed areas. 49.8 Wet type, insulated (no heat trace) standpipe system for the parking levels. 49.9 1250 gpm @ 220 psi diesel fire pump with tank and jockey pump. 49.10 Surge tanks as required by Code criteria (currently priced as 4 X 4,000-gallon tanks). 49.11 Piping materials will be CPVC for all residential levels and steel in all other areas.
The Budget Cost excludes the following: 49.12 Balconies, terraces, courtyards, and pool areas. 49.13 Requirements to meet Factory Mutual requirements. 49.14 Diesel fuel for fire pump. 50.
ELECTRICAL
The Budget Cost is based on the following: 50.1 All local and state amendments to the National Electrical Code. 50.2 Any local fees and/or permits required for installation. 50.3 Meter sockets for each residential unit, and key public areas are included. Owner or Utility Company supplies meters. 50.4 Fire alarm system as per code. 50.5 MC cable will be used at all remaining areas where allowable by code. 50.6 Aluminum feeders will be used where allowed by code. 50.7 Residential tower light fixture allowance of $300,000 is included. 50.8 Concrete duct bank at high-voltage primaries. Not required by code at secondaries. 50.9 Rough-in for the parking control system. 50.10 An Allowance of $200,000 is included for car charging stations in the parking garage. The Budget Cost excludes the following: 50.11 Impact fees associated with bringing permanent utility services onto the site. 50.12 Traffic signal work. 50.13 Electrical capacity for future work, including future tower on Block D. Those costs will be included with that specific pricing.
Regent Square List of Clarifications May 19th, 2011 Page 18
51.
IN UNIT LOW VOLTAGE CABLING
51.1 51.2 51.3 51.4
The Budget Cost includes the following: Security system backbone. Security equipment is not included. Fire alarm system. Telecom system backbone. Phone equipment is not included. Cable TV conduit and home runs. One outlet in each bedroom and one in the living room only.
51.5 51.6
The Budget Cost excludes the following: Audio visual equipment and cabling. Sleeving for satellite TV systems.
52.
SWIMMING POOL
52.2 52.3 52.4
The Budget Cost is based on the following: Swimming pool is included as an allowance of $135/SF, including pool, perimeter edging, pumps and equipment, skimmers, etc. Raised pool fountains are included as allowances of $30,000/ea (total of 2). Heated pool spa is included as an allowance of $125/sf. Pool fencing and gates are included as shown on the amenity deck landscape plans.
53.
TERRACE LEVEL IMPROVEMENTS
52.1
53.1
54.
54.1
54.2 54.3
The Budget Cost is based on the following: The amenity deck improvements are included as shown the May 5, 2011 SD Drawings and in the detailed estimate package. Some specific allowances are below: a. Outdoor Fireplace (SF-2): $40,000 b. Rainwater harvesting system (ST-3): $10,000 c. Small outdoor Living Cabanas (ST-2): $10,000 d. Cast Stone Hearth (SF-1): $20,000 e. Landscape Allowance : $350,000 INSURANCE, PERMITS, & FEES The Budget Cost is based on the following: For this pricing exercise, general liability insurance is included in the subcontract numbers and JE Dunn GL Insurance is included at 0.77%. In final pricing, a contractor controlled insurance program will be priced at 1.5% at no additional cost to the Owner. Excess Liability Insurance - $25,000,000 limit – included in CCIP program rate. Insurance on equipment.
Regent Square List of Clarifications May 19th, 2011 Page 19
54.4 54.5 54.6 54.7 54.8
Subguard/SDI program is included in lieu of subcontractor bonds at 1.5% of subcontractor cost. Lump Sum Fee equal to 2.5% of the GMP price. Lump Sum Contractor's Contingency equal to 2.0% of the GMP price. Building permit. Performance & payment bonds.
The Budget Cost excludes the following: Condominium Insurance premium equal to $4,280 per unit at apartment units. If any units currently designated as apartments are changed to condos, this premium will be added. 54.10 Builder's Risk Insurance & difference in conditions policies. 54.11 Permit expeditor. 54.12 All third party materials testing, soils testing, moisture control testing & lab testing is by others. 54.9
Regent Square - Block D Apartments 19-May-11
Document List Number G1 G2 G4 G5 C1S C2S L1.01 L1.02 L1.03 L1.04 L1.05 A1.1.0 A2.1.1 A2.2.1 A2.3.1 A2.7.1 A2.8.1 A2.9.1 A2.21.1 A3.1.1 A3.1.2 A3.1.3 A3.1.4 A3.2.1 A3.2.2 S0.00 S1.00 S2.00 S2.01 S2.02 S2.03 S2.04 S2.05 S2.06 S5.10 S5.20 M6.01 E1.01 E6.01 P6.01
Title Cover Sheet Drawings Index and General Notes Code Information Accessibility Standards Accessibility Room Layouts Schematic Grading & Drainage Plan Schematic Underground Utilities Plan Site Plan Entry Plaza Enlarged Plan Terrace Plan Terrace Sections Roof Terrace Options Site Plan Floor Plan - Level 1 Floor Plan - level 2 Floor Plan - Levels 3 to 6 Floor Plan - Level 7 Floor Plan - Level 8 Floor Plan - Level 9 to 20 Floor Plan - Roof South Elevation North Elevation East Elevation West Elevation Building Section Building Section Cover Sheet Foundation Plan - Level 1 Forming Plan - Level 2 Forming Plan - Level 3-6 Forming Plan - Level 7 Forming Plan - Level 8 Forming Plan - Level 9 Forming Plan - Level 10-20 Forming Plan - Level Roof Concrete Column Schedule Concrete Shearwall Schedule Mechanical VRV Diagram Electrical Site Plaan Electrical Riser Diagram Plumbing Gas & Water Riser
Revision Num 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Revision Date 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011 05-05-2011
Regent Square - Block D Apartments 19-May-11
Narrative List Company ZCA Cobb Fendley SWA WSP Flack+Kurtz
Title Schematic Design Outline Specifications Basis of Design - SD Phase Landscape Site Development Design Description MEP Systems Schematic Design Narrative
Revision Date 05-05-2011
Act ID
Description
Dur. (Wds)
Early Start
Early Finish
-1 1
2 3
4
5
6
7
8
9
MONTH 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
GENERAL GN-100
Construction NTP
GN-120
Overall Duration - CAL. DAYS
GN-130
Substantial Completion / Occupation
0
Construction NTP
09JAN12
624d * 09JAN12 0
23SEP13
Overall Duration - CAL. DAYS
Substantial Completion / O
23SEP13
PROCUREMENT / MOCKUPS PR01-100
Critical / Long Lead Items Procurement
120d
16JAN12
02JUL12
PR01-110
Building Skin Mockup / Approval
30d
05JUN12
17JUL12
Critical / Long Lead Items Procurement Building Skin Mockup / Approval
CONSTRUCTION Foundations / Below Grade Work CN-100
Mobilize / SWPPP
5d
09JAN12
13JAN12
Mobilize / SWPPP
CN-105
Demo / Clear Site
20d
16JAN12
10FEB12
Demo / Clear Site
CN-110
Foundations / Below Grade Structure
60d
13FEB12
04MAY12
Foundations / Below Grade Structure
Above Grade Structure CN-122
Above Ground Structure - F1-F7 + Pool Deck
120d
23APR12
10OCT12
CN-120
Above Ground Structure - F8-Roof
86d
11OCT12
14FEB13
Above Ground Structure - F1-F7 + Pool Deck Above Ground Structure - F8-Roof
MEP Rough-in / Interior Framing CN-135
MEP Risers / Primary Rough-in
170d
26JUL12
28MAR13
CN-142
Interior Framing / MEP Rough-in - F1-F7 Units
100d
09AUG12
03JAN13
CN-140
Interior Framing / MEP Rough-in - F8 - F21 Units
120d
16NOV12
09MAY13
CN-200
Permanent Power
0
15MAR13
110d
18JUL12
MEP Risers / Primary Rough-in Interior Framing / MEP Rough-in - F1-F7 Units Interior Framing / MEP Rough-in - F8 - F21 Units Permanent Power
Building Skin / Roof / Dry-in CN-132
Building Skin - F1-F7
Start date 03JAN12 Finish date 23SEP13 Data date 09JAN12 Run date 31MAY11 Page number 1A Š Primavera Systems, Inc.
PR05-Regent Sch...
21DEC12
JE Dunn Construction Regent Square - Scheme 7A 21 Story Tower + Parking Garage Preliminary Schedule
Building Skin - F1-F7
Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point
Act ID
Description
Dur. (Wds)
Early Start
Early Finish
-1 1
2 3
4
5
6
7
8
9
MONTH 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
CN-130
Building Skin - F8 - F21
135d
08NOV12
22MAY13
Building Skin - F8 - F21
CN-133
Temp. Roofing for Units Below F7
15d
08NOV12
30NOV12
Temp. Roofing for Units Below F7
CN-136
Temp Dry-in for Units Below F7 to Start Finishes
0
03DEC12
CN-123
Roofing - F6 / F7
40d
11JAN13
07MAR13
CN-125
Roofing / Roof Top Work - High Roof @ F21
60d
15FEB13
09MAY13
CN-126
Permanent Dry-in - Units below F7
0
Temp Dry-in for Units Below F7 to Start Finishes Roofing - F6 / F7 Roofing / Roof Top Work - High Roof @ F21 Permanent Dry-in - Units below F7
07MAR13
Interior Finishes / Elevators CN-152
Interior Finishes - F1-F7 Units
110d
03DEC12
08MAY13
CN-160
Install Elevators
135d
27DEC12
08JUL13
CN-150
Interior Finishes - F8 - F21 Units
120d
07FEB13
26JUL13
CN-162
Amenity Deck Area Finishes
80d
11APR13
02AUG13
CN-205
JED Pre-Punch Units - F1-F7
20d
09MAY13
06JUN13
CN-165
2 Elevators Ready for Temp. Use
0
10JUN13
CN-170
Remove Man / Material Hoist
5d
10JUN13
14JUN13
CN-180
Finish Skin @ Hoist
35d
17JUN13
05AUG13
CN-190
Finish Units at Hoist Location
45d
08JUL13
09SEP13
CN-210
JED Pre-Punch Units - F8-F21
25d
12AUG13
16SEP13
Interior Finishes - F1-F7 Units Install Elevators Interior Finishes - F8 - F21 Units Amenity Deck Area Finishes JED Pre-Punch Units - F1-F7 2 Elevators Ready for Temp. Use Remove Man / Material Hoist Finish Skin @ Hoist Finish Units at Hoist Location
JED Pre-Punch Units - F8-F21
Closeout / Occupancy Certification CN-218
Owner / Arch. Punchlist - F1-F7
10d
07JUN13
20JUN13
CN-225
Inspections / TCO - F1-F7
10d
07JUN13
20JUN13
CN-235
Early Completion of Units - F1-F7 Level
CN-230
Inspections / Occupancy Cert. - Full Bldg.
Start date 03JAN12 Finish date 23SEP13 Data date 09JAN12 Run date 31MAY11 Page number 2A Š Primavera Systems, Inc.
PR05-Regent Sch...
0 20d
26AUG13
Early Occupancy of the Units will be subject to removal of Owner / Arch. Punchlist - F1-F7 hoist, completion of the street level work, Life Safety Systems and to City Requirements. Amenity Deck area work might not Inspections / TCO - F1-F7 be complete 100% at the time of early occupancy of units.
20JUN13
Early Completion of Units - F1-F7 Level
23SEP13
Inspections / Occupancy Cer
JE Dunn Construction Regent Square - Scheme 7A 21 Story Tower + Parking Garage Preliminary Schedule
Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point
Act ID
Description
CN-220
Owner / Arch. Punchlist - F8-F21
CN-240
Substantial Completion
Start date 03JAN12 Finish date 23SEP13 Data date 09JAN12 Run date 31MAY11 Page number 3A Š Primavera Systems, Inc.
PR05-Regent Sch...
Dur. (Wds) 10d 0
Early Start
Early Finish
10SEP13
23SEP13
Owner / Arch. Punchlist - F
23SEP13
Substantial Completion
-1 1
2 3
JE Dunn Construction Regent Square - Scheme 7A 21 Story Tower + Parking Garage Preliminary Schedule
4
5
6
7
8
9
MONTH 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point
AREA SUMMARY PROJECT NAME PROJECT # DATE
FLOOR
GID West Dallas Apartments SD Estimate - 21 Floors 31-May-11
RETAIL
Office
Common & Service
Leasable
Residential
Common & Service
Leasable
Level 1 Level 2 Level 3 Level 4 Level 5 Level 6 Level 7 Level 8 Level 9 Level 10 Level 11 Level 12 Level 13 Level 14 Level 15 Level 16 Level 17 Level 18 Level 19 Level 20 Level 21 TOTAL
0
0
0
0
11,941 11,941 11,941 11,941 11,941 11,941 11,941 11,941 11,941 11,941 11,941 11,941 11,941
Common Area 7,383 5,984 5,952 5,952 5,952 5,952 4,701 2,056 1,710 1,710 1,710 1,710 1,710 1,710 1,710 1,710 1,710 1,710 1,710 1,710 1,710
268,062
66,162
Sellable 7,712 18,445 18,453 18,453 18,453 18,453 12,860
Lobbies Amenities 1,601
938
2,539
7,108
7,108
Fitness
Storage 3,414 197 199 199 199 199 3,395
2,721
2,721
7,802
Back of House 4,012 509 503 503 503 503 1,015 486 459 459 459 459 459 459 459 459 459 459 459 459 459 14,001
Avg Unit Size 924 Notes: 1. Elevator cores and stairs in Tower and Parking Deck are included in residential common area calculations. 2. Terraces are not included in gross area calculations. 3. Amenity deck and pool areas are not included in gross area calculation. 4. Vertical shafts and circulation are included in residential common area. 5. Unit areas - area calculated from center line of demising walls between units,to exterior face of glass, to exterior face of stucco and to corridor side of wall separating unit and corridor. 6. Retail - area calculated from outside face of window system where glass is predominant to the outside face of retail corridor and to center line of demising walls.
GROSS AREA SUMMARY - FOR ESTIMATE COMPARISON PURPOSES TOWER PARKING RETAIL
371,604 (Tower Heated + Loading Dock) 170,762 0
Gross Building
542,366
LOADING DOCK
PARKING
Total Heated 24,122 25,135 25,107 25,107 25,107 25,107 21,971 13,309 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 0 368,395
Pools
Unit Number of Balcony Units 669 10 1591 22 1565 22 1565 22 1565 22 1565 22 977 14
Area # of Spaces 22,590 88 25,289 65 25,329 75 25,329 75 25,329 75 25,329 75 21,567 59
Area 3,209
2,149
2,149
AMENITY DECK
12 12 12 12 12 12 12 12 12 12 12 12 12
21,236
290
170,762
512
3,209
STRUCTURE GROSS(Including balcony, amenity)
Area
25,130 903 903 903 903 903 903 903 903 903 903 903 903 903
GROSS AREA (ENCLOSED)
25,130
49,921 50,424 50,436 50,436 50,436 50,436 43,538 13,309 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 14,110 0 542,366
50,590 52,015 52,001 52,001 52,001 52,001 44,515 40,588 15,013 15,013 15,013 15,013 15,013 15,013 15,013 15,013 15,013 15,013 15,013 15,013 15,013 0 590,881
GID West Dallas Apartments SD Estimate - 21 Floors
A1 A2 A3 A4 A6 A7 A8 A9
1BD/1BA 1BD/1BA 1BD/1BA 1BD/1BA 1BD/1BA 1BD/1BA 1BD/1BA 1BD/1BA
TOTAL 1 Beds B1 B2 B3 B4 B5 B6 B7 B8 TOTAL 2 Beds
TOTAL
2BD/2BA 2BD/1BA 2BD/2BA 2BD/2BA 2BD/2BA 2BD/2BA 2BD/2BA 2BD/1BA
UNIT HEATED SQUARE FOOTAGE
12
0
12
709 SF
8,507 SF
12
0
12
709 SF
8,507 SF
39 38 26 13 27 28 5 6
39 38 26 13 27 28 5 6
39 38 26 13 27 28 5 6
182
182
182
13 19 19 13 13 7 6 6
26 38 38 26 26 14 12 12
26 19 38 26 26 14 12 6
96
192
167
1,215 SF
116,645 SF
290
374
361
1,052 SF
305,076 SF
873 964 935 985 947 748 3,645 1,233
SF SF SF SF SF SF SF SF
989 SF 1,360 906 1,433 1,195 1,298 1,262 1,137 1,079
SF SF SF SF SF SF SF SF
TOTAL HEATED SQUARE FOOTAGE
BATHROOMS
TOTAL Efficiency
BEDROOMS
0BD/1BA
QUANTITY
S1
DESCRIPTION
UNIT NAME
May 31, 2011
34,034 36,632 24,297 12,805 25,578 20,955 18,225 7,398
SF SF SF SF SF SF SF SF
179,924 SF 17,680 17,208 27,223 15,535 16,874 8,831 6,820 6,474
SF SF SF SF SF SF SF SF
Estimate Number:
Estimate General Summary Sheet Offsite Work Project: Owner: Architect:
Regent Square- Block D - Offsite Work GID Urban Development ZeiglerCooper
Location: Area: Cost / Acre
ITEMS
MATERIAL
LABOR
Date: Estimator: Type of Building: Duration: No. of Units: ENR Cost Index:
Houston, TX
0.98 acres $1,694,835.32 SUB
TOTAL
2011 SD Pricing 5/18/2011 MH Multi Use
87 Weeks 278
COST/Acre
1. GENERAL REQUIREMENTS
$0
$0
$0
$0
1a. CRANES & HOISTS
$0
$0
$0
$0
2. DEMOLITION
$0
$0
$17,160
$17,160
$17,510.20
3. SITE EXCAVATION & PREPARATION
$0
$0
$32,000
$32,000
$32,653.06
4. FOUNDATION EXCAVATION
$0
$0
$0
$0
5. SITE UTILITIES
$0
$0
$1,266,415
$1,266,415
6. SITE IMPROVEMENTS
$0
$0
$202,824
$202,824
7. LANDSCAPING
$0
$0
$0
$0
$0.00
8. SOIL POISONING
$0
$0
$0
$0
$0.00
9. CONCRETE FOUNDATIONS
$0
$0
$0
$0
$0.00
10. BUILDING CONCRETE
$0
$0
$0
$0
$0.00
11. FORMWORK
$0
$0
$0
$0
$0.00
12. RESTEEL/POST TENSIONING
$0
$0
$0
$0
$0.00
13. EXTERIOR CONCRETE/STONE
$0
$0
$0
$0
$0.00
14. MASONRY
$0
$0
$0
$0
$0.00
15. STRUCTURAL & MISC. STEEL
$0
$0
$0
$0
$0.00
16. ROUGH CARPENTRY
$0
$0
$0
$0
$0.00
17. FINISH CARPENTRY
$0
$0
$0
$0
$0.00
18. MAIN LOBBY FINISHES
$0
$0
$0
$0
$0.00
19. WATERPROOFING & SEALANTS
$0
$0
$0
$0
$0.00
20. BUILDING INSULATION
$0
$0
$0
$0
$0.00
21. ROOFING & SHEET METAL
$0
$0
$0
$0
$0.00
22. ENTRY CANOPIES
$0
$0
$0
$0
$0.00
23. HOLLOW METAL
$0
$0
$0
$0
$0.00
24. WOOD DOORS
$0
$0
$0
$0
$0.00
25. FINISH HARDWARE
$0
$0
$0
$0
$0.00
26. SPECIAL DOORS & DOCK EQUIPMENT
$0
$0
$0
$0
$0.00
27. BALCONY RAILINGS
$0
$0
$0
$0
$0.00
28. GLASS, GLAZING & STOREFRONT
$0
$0
$0
$0
$0.00
29. ROOF TOP ELEMENT
$0
$0
$0
$0
$0.00
30. DRYWALL
$0
$0
$0
$0
$0.00
31. ACOUSTICAL
$0
$0
$0
$0
$0.00
32. STUCCO/EIFS
$0
$0
$0
$0
$0.00
33. AMENITY, FITNESS, CLUB ROOMS
$0
$0
$0
$0
$0.00
34. CERAMIC TILE
$0
$0
$0
$0
$0.00
35. INTERIOR STONE WORK
$0
$0
$0
$0
$0.00
36. KITCHEN & BATH COUNTERTOPS
$0
$0
$0
$0
$0.00
37. FLOORING (CARPET/RESILIENT/WOOD)
$0
$0
$0
$0
$0.00
38. PAINT & WALLCOVERING
$0
$0
$0
$0
$0.00
39. MISC. SPECIALTIES
$0
$0
$0
$0
$0.00
40. TOILET PARTITIONS
$0
$0
$0
$0
$0.00
41. TOILET ACCESSORIES
$0
$0
$0
$0
$0.00
42. PARKING EQUIPMENT
$0
$0
$0
$0
$0.00
43. RESIDENTIAL CABINETS
$0
$0
$0
$0
$0.00
44. BLINDS & SHADES
$0
$0
$0
$0
$0.00
45. RESIDENTIAL APPLIANCES
$0
$0
$0
$0
$0.00
46. ELEVATORS
$0
$0
$0
$0
$0.00
47. PLUMBING
$0
$0
$0
$0
$0.00
48. H.V.A.C.
$0
$0
$0
$0
$0.00
49. FIRE PROTECTION
$0
$0
$0
$0
$0.00
50. ELECTRICAL
$0
$0
$0
$0
$0.00
51. IN-UNIT LOW VOLTAGE CABLING
$0
$0
$0
$0
$0.00
52. SWIMMING POOL
$0
$0
$0
$0
$0.00
53. TERRACE LEVEL IMPROVEMENTS
$0
$0
$0
$0
$0.00
54 EXTRA
$0
$0
$0
$0
$0.00
55 EXTRA 56 EXTRA 3
$0 $0
$0 $0
$0 $0
$0 $0
$0.00 $0.00
$1,518,399
$1,518,399
$1,549,386.62
$0 $0 $1,518,399 $0 $0 $12,789 $22,776 $2,658 $1,556,622 $16,609 $1,573,231 $47,197
$0.00 $0.00 $1,549,386.62 $0.00 $0.00 $13,050.23 $23,240.80 $2,711.74 $1,588,389.39 $16,948.35 $1,605,337.74 $48,160.13
$1,620,428 $0 $0 $40,511
$1,653,497.87 $0.00 $0.00 $41,337.45
SUB TOTAL
$0
$0 Labor Burden Sales Tax
26.50% 8.25%
SUB TOTAL Contractor's Contingency Builder's Risk Insurance GL Insurance & Fees SDI/Subguard Program Building Permits
0.00% by owner 1.50%
SUB TOTAL Payment & Performance Bond
1.0000%
SUB TOTAL General Conditions
3.00%
Condo Insurance Premium Storn/Time Inflation
0 0 2.50%
TOTAL
Fee
GRAND TOTAL
$1,660,939
$0.00 $0.00
$0.00 $1,292,260.20 $206,963.15
$1,694,835.32
Line Item Summary UNIT/ DESCRIPTION
QTY.
0
LS
11,700 455
sf cy
Site Demolition (Texas Environmental) Remove existing parking Remove parking canopy Remove existing fencing & assoc. electric Remove Paving at Rochow Haul Off Pavement
UNIT
MATERIAL
SUB TOTAL
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
Building Pad Select Fill - assume 2' fill Haul Off Spoils Remove Trees Transplant Trees - Allowance
0 CY 0 cy 4 ea 3 ea
SUB TOTAL
2011-Conc 1 of 1
$15,000.00
$1.00 $12.00
SUB
TOTAL
$0 $0 $0 $0 $0 $0 $11,700 $5,460 $0 $0
$0 $0 $0 $0 $0 $0 $11,700 $5,460 $0 $0
$17,160
$17,160
Line Item:
3. SITE EXCAVATION & PREPARATION
Estimate #:
2011-Conc
Offsite Work
UNIT/ UNIT
Estimate #:
UNIT/
LABOR
Line Item Summary QTY.
2. DEMOLITION
Sheet #:
UNIT/
MATERIAL
Project:
DESCRIPTION
Line Item:
Offsite Work
Project:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$15.00 $12.00 $500.00 $10,000.00
SUB
TOTAL
$0 $0 $0 $2,000 $30,000 $0 $0 $0
$0 $0 $0 $2,000 $30,000 $0 $0 $0
$32,000
$32,000
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
MATERIAL
241 34
LF LF
10" Storm 12" Storm 15" Storm Storm MH Storm Inlet Curb Inlet
92 366 365 5 5 4
LF LF LF EA EA EA
Water and Drain Line to Doggie Fountain (no details shown)
0
ls
Tejas Utility - Onsite Tejas Utility - Public Storm and Water Tejas Utility - Public Sanitary Allowance - Relocate Unknown underground utilities
0 1 1 0
ls LS LS LS
Centerpoint Allowance - Relocate Overhead Power
1
LS
Relocate ATT/Comcast Allowance
1
LS
SUB TOTAL
5. SITE UTILITIES
Estimate #:
2011-Conc
Sheet #:
UNIT/
MATERIAL
LABOR
$0 08" Water Line 08" Water Line (Road Bore)
Line Item:
Offsite Work
Project:
UNIT/
LABOR
SUB
$0
TOTAL
SUB
$0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $98,615 $262,800 $0 $0
$0 $0 $0 $98,615 $262,800 $0 $0
Included in Tejas Utility numbers Below
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
1 of 1
$0
$3,500 $88,348 $98,615 $262,800 $100,000
$805,000 $100,000
$805,000
$805,000
$0 $100,000 $0 $0
$0 $100,000 $0 $0
$1,266,415
$1,266,415
Line Item Summary UNIT/ QTY.
UNIT
MATERIAL
UNIT/
MATERIAL
LABOR
SUB
sy lf sf sf sy sf cy sf sf sf sf
$0 $0 $0
0 1,050 0
sf sf ea
Footings for Planters No Details
0
sf
Trash Bin, Dog Waste
0
ea
0 0 0 0 0 0
lf ea ls ea lf ea
Fountain - Allowance
0
LS
Pavers Entry Area Pavers at Unit Entries
0 0
sf sf
Site Furnishings Allowance Decorative Light Poles along Dallas
0 11
LS EA
4' Ornamental Fence Ornamental Gates walk Sliding Gate motor operator Perimeter Chain link Fencing Decorative Bollards
0 0 0
SUB TOTAL
2011-Conc 1 of 1
UNIT/
LABOR
$0 $0 $0 $0 $0 $0 $0 $0 $0
2,311 1,300 0 20,800.00 2,311.11 4,117.00 0.00 0
Estimate #: Sheet #:
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Asphalt @ Rochow Curb @ Rochow Demo Rochow (included above) Fine Grade/Recompact Rochow Lime Treat Rochow Sidewalk @ W Dallas and Rochow Import fill @ Rochow PV 4 Pavers on support Grid PV 6 - 7" concrete at Plaza, integral color, sandblast finish, sawcut joints at 48" o.c. 7" Paving under pavers 7" Paving at Service yard Concrete Edge Banding (surrounds gravel, crushed granite etc. Pavers at parallel parking on Rochow Driveway entrance Premium
6. SITE IMPROVEMENTS
Offsite Work
Project:
DESCRIPTION
Line Item:
TOTAL
SUB
$26.00 $14.00 $1.50 $1.50 $4.50 $5.00 $15.00 $20.00
$0 $0 $60,089 $18,200 $0 $31,200 $10,400 $20,585 $0 $0
$0 $0 $60,089 $18,200 $0 $31,200 $10,400 $20,585 $0 $0
$0 $0 $0
$10.00 $4.00 $4.00
$0 $0 $0
$0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$4.50 $7.00 $2,500.00
$0
$0
$15.00
$1,500.00 $55.00 $750.00 $22,250.00 $3,500.00 $25.00 $950.00 $15,000.00 $15.00 $15.00 $10,000.00 $5,000.00
$0
$0
$7,350 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $55,000 $0
$7,350 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $55,000 $0
$202,824
$202,824
Estimate General Summary Sheet Sitework Project: Owner: Architect:
Regent Square- Block D - Sitework GID Urban Development ZeiglerCooper
Location: Area: Cost / Acre
ITEMS
MATERIAL
LABOR
Houston, TX
1.78 acres $485,587.44 SUB
Estimate Number:
2011 SD Pricing
Date: Estimator: Type of Building: Duration: No. of Units: ENR Cost Index:
5/18/2011 MH
TOTAL
Multi Use
87 Weeks 278
COST/SF
1. GENERAL REQUIREMENTS
$0
$0
$0
$0
1a. CRANES & HOISTS
$0
$0
$0
$0
$0.00
2. DEMOLITION 3. SITE EXCAVATION & PREPARATION
$0 $0
$0 $0
$15,000 $161,532
$15,000 $161,532
$8,426.97 $90,748.31
4. FOUNDATION EXCAVATION 5. SITE UTILITIES 6. SITE IMPROVEMENTS
$0 $0 $0
$0 $0 $0
$0 $191,848 $241,047
$0 $191,848 $241,047
$0.00 $107,779.78 $135,419.38
7. LANDSCAPING 8. SOIL POISONING
$0 $0
$0 $0
$50,000 $0
$50,000 $0
$28,089.89 $0.00
$0.00
9. CONCRETE FOUNDATIONS
$0
$0
$0
$0
$0.00
10. BUILDING CONCRETE 11. FORMWORK
$0 $0
$0 $0
$0 $0
$0 $0
$0.00 $0.00
12. RESTEEL/POST TENSIONING 13. EXTERIOR CONCRETE/STONE
$0 $0
$0 $0
$0 $0
$0 $0
$0.00 $0.00
14. MASONRY
$0
$0
$40,918
$40,918
$22,987.67
15. STRUCTURAL & MISC. STEEL 16. ROUGH CARPENTRY 17. FINISH CARPENTRY 18. MAIN LOBBY FINISHES 19. WATERPROOFING & SEALANTS 20. BUILDING INSULATION 21. ROOFING & SHEET METAL 22. ENTRY CANOPIES 23. HOLLOW METAL 24. WOOD DOORS 25. FINISH HARDWARE 26. SPECIAL DOORS & DOCK EQUIPMENT 27. BALCONY RAILINGS 28. GLASS, GLAZING & STOREFRONT 29. ROOF TOP ELEMENT 30. DRYWALL 31. ACOUSTICAL 32. STUCCO/EIFS 33. AMENITY, FITNESS, CLUB ROOMS 34. CERAMIC TILE 35. INTERIOR STONE WORK 36. KITCHEN & BATH COUNTERTOPS 37. FLOORING (CARPET/RESILIENT/WOOD) 38. PAINT & WALLCOVERING 39. MISC. SPECIALTIES 40. TOILET PARTITIONS 41. TOILET ACCESSORIES 42. PARKING EQUIPMENT 43. RESIDENTIAL CABINETS 44. BLINDS & SHADES 45. RESIDENTIAL APPLIANCES 46. ELEVATORS 47. PLUMBING 48. H.V.A.C. 49. FIRE PROTECTION
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $14,824 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $14,824 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0.00 $0.00 $0.00 $0.00 $8,328.09 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
50. ELECTRICAL 51. IN-UNIT LOW VOLTAGE CABLING 52. SWIMMING POOL 53. TERRACE LEVEL IMPROVEMENTS 54 EXTRA 55 EXTRA 56 EXTRA 3
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
$75,000 $0 $0 $0 $0 $0 $0
$75,000 $0 $0 $0 $0 $0 $0
$42,134.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$790,169
$790,169
$443,914.92
$0 $0 $790,169 $0 $0 $6,655 $11,853 $1,383 $810,059 $8,643 $818,703 $24,561 $843,264 $0 $0 $21,082
$0.00 $0.00 $443,914.92 $0.00 $0.00 $3,739.02 $6,658.72 $776.94 $455,089.61 $4,855.87 $459,945.48 $13,798.36 $473,743.84 $0.00 $0.00 $11,843.60
SUB TOTAL
$0
$0 Labor Burden Sales Tax
26.50% 8.25%
SUB TOTAL Contractor's Contingency Builder's Risk Insurance GL Insurance & Fees SDI/Subguard Program Building Permits
0.00% by owner 1.50%
SUB TOTAL Payment & Performance Bond
1.0000%
SUB TOTAL General Conditions
3.00%
Condo Insurance Premium
0 0 2.50%
TOTAL Storn/Time Inflation Fee
GRAND TOTAL
$864,346
$485,587.44
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/ QTY.
UNIT
Site Demolition (Texas Environmental) Remove existing parking Remove parking canopy Remove existing fencing & assoc. electric
1
LS
Remove Paving at Rochow Haul Off Pavement
0 0
sf cy
MATERIAL
SUB TOTAL
Project:
UNIT/
MATERIAL
LABOR
Building Pad Select Fill - assume 2' fill Haul Off Spoils Remove Trees Transplant Trees - Allowance
UNIT
5,983 CY 5,983 cy 0 ea 0 ea
SUB TOTAL
2011-Conc 1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$15,000.00
$1.00 $12.00
SUB
TOTAL
$0 $15,000 $0 $0 $0 $0 $0 $0 $0 $0
$0 $15,000 $0 $0 $0 $0 $0 $0 $0 $0
$15,000
$15,000
Line Item:
3. SITE EXCAVATION & PREPARATION
Estimate #:
2011-Conc
Sitework
UNIT/ QTY.
Estimate #: Sheet #:
Line Item Summary DESCRIPTION
2. DEMOLITION
Sitework
Line Item Summary DESCRIPTION
Line Item:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
$0
$0
$15.00 $12.00 $500.00 $10,000.00
SUB
TOTAL
$0 $89,740 $71,792 $0 $0 $0 $0
$0 $89,740 $71,792 $0 $0 $0 $0
$161,532
$161,532
2011_05_31 Added Floor Estimate REVISED.xls, Site Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/ QTY.
UNIT
MATERIAL
241 34
LF LF
10" Storm 12" Storm 15" Storm Storm MH Storm Inlet Curb Inlet
92 366 365 5 5 4
LF LF LF EA EA EA
Water and Drain Line to Doggie Fountain (no details shown)
1
ls
Tejas Utility - Onsite Tejas Utility - Offsite Storm & Water Tejas Utility - Offsite Sanitary
1 0 0
ls ls ls
Allowance - Relocate Unknown underground utilities
1
LS
Centerpoint Allowance - Relocate Overhead Power
0
LS
Relocate ATT/Comcast Allowance
0
LS
SUB TOTAL
Estimate #:
2011-Conc
Sheet #:
UNIT/
MATERIAL
LABOR
$0 08" Water Line 08" Water Line (Road Bore)
5. SITE UTILITIES
Sitework
Line Item Summary DESCRIPTION
Line Item:
UNIT/
LABOR
SUB
$0
TOTAL
SUB
$0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$3,500 $0 $88,348 $0 $0 $0 $100,000 $0
$3,500 $0 $88,348 $0 $0 $0 $100,000 $0
Included in Tejas Utility Numbers Below
$0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
1 of 1
$0
$3,500 $88,348 $98,615 $262,800 $100,000
$805,000 $100,000
$0
$0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$191,848
$191,848
2011_05_31 Added Floor Estimate REVISED.xls, Site Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/ QTY.
UNIT
MATERIAL
UNIT/
MATERIAL
LABOR
SUB
0 0 0 0.00 0.00 0.00
sy lf sf sf sy sf
PV 4 Pavers on support Grid PV 6 - 7" concrete at Plaza, integral color, sandblast finish, sawcut joints at 48" o.c. 7" Paving under pavers 7" Paving at Service yard Concrete Edge Banding (surrounds gravel, crushed granite etc. Pavers at parallel parking on Rochow Driveway entrance Premium
407
sf
8,463 1,272 2,243
sf sf sf
$0 $0 $0
$0 $0 $0
$10.00 $4.00 $4.00
287 0 2
sf sf ea sf
2
ea
118 2 1 1 335 12
lf ea ls ea lf ea
Fountain - Allowance
1
LS
Pavers Entry Area Pavers at Unit Entries
1,272 1,529
sf sf
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$4.50 $7.00 $2,500.00
293
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
4' Ornamental Fence Ornamental Gates walk Sliding Gate motor operator Perimeter Chain link Fencing Decorative Bollards
Site Furnishings Allowance Decorative Light Poles along Dallas
1 0
LS EA
SUB TOTAL
2011-Conc 1 of 1
UNIT/
LABOR
Asphalt @ Rochow Curb @ Rochow Demo Rochow (included above) Fine Grade/Recompact Rochow Lime Treat Rochow Sidewalk @ W Dallas and Rochow
Trash Bin, Dog Waste
Estimate #: Sheet #:
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Footings for Planters No Details
6. SITE IMPROVEMENTS
Sitework
Line Item Summary DESCRIPTION
Line Item:
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
SUB
TOTAL
$20.00
$0 $0 $0 $0 $0 $0 $0 $0 $0 $8,140
$0 $0 $0 $0 $0 $0 $0 $0 $0 $8,140
$84,630 $5,088 $8,972
$84,630 $5,088 $8,972
$1,292
$1,292
$0 $5,000 $0 $4,395 $0 $0 $3,000 $0 $6,490 $1,500 $22,250 $3,500 $8,375 $11,400 $0 $15,000 $0 $19,080 $22,935 $0 $10,000 $0 $0
$0 $5,000 $0 $4,395 $0 $0 $3,000 $0 $6,490 $1,500 $22,250 $3,500 $8,375 $11,400 $0 $15,000 $0 $19,080 $22,935 $0 $10,000 $0 $0
$241,047
$241,047
$26.00 $14.00 $1.50 $1.50 $4.50 $5.00
$15.00
$1,500.00 $55.00 $750.00 $22,250.00 $3,500.00 $25.00 $950.00 $15,000.00 $15.00 $15.00 $10,000.00 $5,000.00
2011_05_31 Added Floor Estimate REVISED.xls, Site Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/
PL 03 ground cover 1 gallon PL 04 seasonal plantings PL 05 ornamental shrubs, 5 gallon PL 06 evergreen trees, 14' savannah holly PL 07 perennial plantings, 1 gallon PL 08 sodded lawn Irrigation Allowance
QTY.
MATERIAL
LABOR
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0
$5.00 $10.00 $5.00 $650.00 $5.00 $4.00 $10,000.00
$0 $20,545 $1,680 $375 $3,250 $1,530 $1,216 $10,000 $0
$6,139 $0
$0 $0
$7.00 $0.00
$6,139 $0
1,378
sf ls
$0 $0 $0 $0 $0
$5.00
-1
$0 $0 $0 $0 $0
$6,890 $0 ($1,625) $0 $0
$0
$0
$1,625.00
$50,000
UNIT/
SF-01 Seat Wall-Cast Stone Veneer
UNIT
384 2,790
sf sf
83
sf
SUB TOTAL
$6,890 $0 ($1,625) $0 $0
$50,000
Line Item:
14. MASONRY
Estimate #:
2011-Conc
Sitework
Line Item Summary QTY.
TOTAL
$0 $20,545 $1,680 $375 $3,250 $1,530 $1,216 $10,000 $0
$0 $0
Project:
1 of 1
UNIT/
LABOR
sf
Carry Fwd.
WL-02 Brick Veneer at Garden Wall WL-04 12" x 8' h screen wall - Allowance
2011-Conc
877
Adjust for $50,000 Landscape Allowance
DESCRIPTION
Estimate #: Sheet #:
UNIT/
MATERIAL
4,109 SF 168 SF 75 SF 5 EA 306 SF 304 SF 1 LS
PV 12 - Crushed stone paving 3/4' black star gravel, 3" depth, filter fabric, stabilized subgrade, 877 sf PV 9 - decomposed granite paving 3" depth, filter fabric, stabilized subgrade 1,378 sf
UNIT
7. LANDSCAPING
Sitework
Line Item Summary DESCRIPTION
Line Item:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0
$0
$0
$12.00 $12.19 $28.00
SUB
TOTAL
$0 $4,608 $34,000 $0 $2,310 $0 $0
$0 $4,608 $34,000 $0 $2,310 $0 $0
$40,918
$40,918
2011_05_31 Added Floor Estimate REVISED.xls, Site Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Sitework
Project:
Line Item: Estimate #:
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
1 1
Bentonite Waterproofing Joint Sealants
MATERIAL
UNIT/
MATERIAL
Project:
LABOR
SUB
$0 $0 $0 $0 $0
$0
$0
$12,046.00 $2,778.00
UNIT/
Electrical
QTY.
UNIT
1
LS
SUB TOTAL
1 of 1
SUB
TOTAL
$0 $12,046 $2,778 $0 $0
$0 $12,046 $2,778 $0 $0
$14,824
$14,824
Line Item:
50. ELECTRICAL
Estimate #:
2011-Conc
Sitework
Line Item Summary DESCRIPTION
2011-Conc
UNIT/
LABOR
$0 $0 $0 $0 $0
ls ls
SUB TOTAL
Sheet #:
19. WATERPROOFING & SEALANTS
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0
$0 $0 $0
$0
$0
$75,000
SUB
TOTAL
$0 $75,000 $0
$0 $75,000 $0
$75,000
$75,000
2011_05_31 Added Floor Estimate REVISED.xls, Site Detail
Estimate General Summary Sheet Garage/Parking Project: Regent Square- Block D Garage Owner: GID Urban Development Architect: ZeiglerCooper
Location: Area: Cost / Car:
ITEMS
MATERIAL
2011-Conc
Date:
5/18/2011
Estimator: Type of Building: Duration: No. of Cars ENR Cost Index:
Houston, TX
170,762 sf $15,042
LABOR
Estimate Number:
SUB
TOTAL
MH Multi Use
87 Weeks 512
COST/SF
1. GENERAL REQUIREMENTS
$0
$0
$0
$0
$0.00
1a. CRANES & HOISTS
$0
$0
$198,000
$198,000
$1.16
2. DEMOLITION
$0
$0
$0
$0
$0.00
3. SITE EXCAVATION & PREPARATION
$0
$0
$0
$0
$0.00
4. FOUNDATION EXCAVATION
$0
$0
$0
$0
$0.00
5. SITE UTILITIES
$0
$0
$0
$0
$0.00
6. SITE IMPROVEMENTS
$0
$0
$42,436
$42,436
$0.25
7. LANDSCAPING
$0
$0
$0
$0
$0.00
8. SOIL POISONING
$0
$0
$2,033
$2,033
$0.01
9. CONCRETE FOUNDATIONS
$0
$0
$170,762
$170,762
$1.00
10. BUILDING CONCRETE
$0
$0
$2,804,472
$2,804,472
$16.42
11. FORMWORK
$0
$0
$0
$0
$0.00
12. RESTEEL/POST TENSIONING
$0
$0
$0
$0
$0.00
13. EXTERIOR CONCRETE/STONE
$0
$0
$0
$0
$0.00
14. MASONRY
$0
$0
$2,014,003
$2,014,003
$11.79
15. STRUCTURAL & MISC. STEEL
$0
$0
$550,695
$550,695
$3.22
16. ROUGH CARPENTRY
$0
$0
$0
$0
$0.00
17. FINISH CARPENTRY
$0
$0
$0
$0
$0.00
18. MAIN LOBBY FINISHES
$0
$0
$0
$0
$0.00
19. WATERPROOFING & SEALANTS
$0
$0
$76,400
$76,400
$0.45
20. BUILDING INSULATION
$0
$0
$13,475
$13,475
$0.08
21. ROOFING & SHEET METAL
$0
$0
$0
$0
$0.00
22. ENTRY CANOPIES
$0
$0
$0
$0
$0.00
23. HOLLOW METAL
$0
$0
$11,000
$11,000
$0.06
24. WOOD DOORS
$0
$0
$0
$0
$0.00
25. FINISH HARDWARE
$0
$0
$0
$0
$0.00
26. SPECIAL DOORS & DOCK EQUIPMENT
$0
$0
$0
$0
$0.00
27. BALCONY RAILINGS
$0
$0
$0
$0
$0.00
28. GLASS, GLAZING & STOREFRONT
$0
$0
$0
$0
$0.00
29. ROOF TOP ELEMENT
$0
$0
$0
$0
$0.00
30. DRYWALL
$0
$0
$0
$0
$0.00
31. ACOUSTICAL
$0
$0
$0
$0
$0.00
32. STUCCO/EIFS
$0
$0
$61,500
$61,500
$0.36
33. AMENITY, FITNESS, CLUB ROOMS
$0
$0
$0
$0
$0.00
34. CERAMIC TILE
$0
$0
$0
$0
$0.00
35. INTERIOR STONE WORK
$0
$0
$0
$0
$0.00
36. KITCHEN & BATH COUNTERTOPS
$0
$0
$0
$0
$0.00
37. FLOORING (CARPET/RESILIENT/WOOD)
$0
$0
$0
$0
$0.00
38. PAINT & WALLCOVERING
$0
$0
$207,468
$207,468
$1.21
$1,700
$255
$0
$1,955
$0.01
40. TOILET PARTITIONS
$0
$0
$0
$0
$0.00
41. TOILET ACCESSORIES
$0
$0
$0
$0
$0.00
42. PARKING EQUIPMENT
$0
$0
$30,000
$30,000
$0.18
43. RESIDENTIAL CABINETS
$0
$0
$0
$0
$0.00
44. BLINDS & SHADES
$0
$0
$0
$0
$0.00
45. RESIDENTIAL APPLIANCES
$0
$0
$0
$0
$0.00
46. ELEVATORS
$0
$0
$0
$0
$0.00
47. PLUMBING
$0
$0
$50,000
$50,000
$0.29
48. H.V.A.C.
$0
$0
$110,995
$110,995
$0.65
49. FIRE PROTECTION
$0
$0
$170,762
$170,762
$1.00
50. ELECTRICAL
$0
$0
$524,448
$524,448
$3.07
51. IN-UNIT LOW VOLTAGE CABLING
$0
$0
$0
$0
$0.00
52. SWIMMING POOL
$0
$0
$0
$0
$0.00
53. TERRACE LEVEL IMPROVEMENTS
$0
$0
$0
$0
$0.00
54 EXTRA 1
$0
$0
$0
$0
$0.00
55 EXTRA 2 56 EXTRA 3
$0 $0
$0 $0
$0 $0
$0 $0
$0.00 $0.00
$7,038,450
$7,040,405
39. MISC. SPECIALTIES
SUB TOTAL
$1,700
$255
26.50% 8.25%
Labor Burden Sales Tax
SUB TOTAL Contractor's Contingency Builder's Risk Insurance GL Insurance & Fees SDI/Subguard Program Building Permits
0.00% by owner 1.50%
SUB TOTAL Payment & Performance Bond
1.0000%
SUB TOTAL General Conditions
3.00%
Condo Insurance Premium
0 0 2.50%
TOTAL Inflation/Escalation Fee
GRAND TOTAL
$41.23
$68 $140
$0.00 $0.00
$7,040,612 $0 $0 $59,302 $105,602 $12,322
$41.23 $0.00 $0.00 $0.35 $0.62 $0.07
$7,217,839 $77,015
$42.27 $0.45
$7,294,854 $218,846
$42.72 $1.28
$7,513,700
$44.00
$0 $0 $187,843
$0.00 $0.00 $1.10
$7,701,543
$45.10
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/ QTY.
Man/Material Hoist Allotment Tower Crane
UNIT
1
MATERIAL
SUB TOTAL
LABOR
SUB
SUB
$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0
$0
$0
Striping Signage Clean & Pressure Wash
UNIT
512 1 170,762
MATERIAL
$198,000.00
SUB TOTAL
$198,000
LABOR
Termite Treatment
22,590
UNIT
SF
SUB TOTAL
$0 $0 $198,000 $0 $0 $0
$198,000
Line Item:
6. SITE IMPROVEMENTS
Estimate #:
2011-Conc
SUB
SUB
$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0
$0
$0
1 of 1
$30.00 $10,000.00 $0.10
TOTAL
$0 $15,360 $10,000 $17,076 $0 $0
$0 $15,360 $10,000 $17,076 $0 $0
$42,436
$42,436
Line Item:
8. SOIL POISONING
Estimate #:
2011-Conc
Garage/Parking
UNIT/ QTY.
TOTAL
UNIT/
LABOR
Line Item Summary DESCRIPTION
$0 $0 $198,000 $0 $0 $0
Sheet #:
UNIT/
MATERIAL
EA LS SF
Project:
1 of 1
Garage/Parking
UNIT/ QTY.
2011-Conc
UNIT/
LABOR
Line Item Summary DESCRIPTION
Estimate #: Sheet #:
UNIT/
MATERIAL
LS
Project:
1a. CRANES & HOISTS
Garage/Parking
Line Item Summary DESCRIPTION
Line Item:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0
$0 $0 $0 $0
$0
$0
$0.09
TOTAL
$0 $2,033 $0 $0
$0 $2,033 $0 $0
$2,033
$2,033
2011_05_31 Added Floor Estimate REVISED.xls, Garage Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/
Foundation Allowance
QTY.
UNIT
170,762
MATERIAL
SUB TOTAL
LABOR
SUB
SUB
$0 $0 $0 $0
$0 $0 $0 $0
$0
$0
Parking Structure Area DCI Additive (Per Specs)
UNIT
170,762 1
MATERIAL
$1.00
SUB TOTAL
LABOR
SUB
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0
CMU walls (interior) CMU walls Brick Veneer
812 197,431 2,255
UNIT
sf sf sf
SUB TOTAL
$170,762
$170,762
Line Item:
10. BUILDING CONCRETE
Estimate #:
2011-Conc 1 of 1
$15.58 $144,000.00
SUB
TOTAL
$0 $2,660,472 $144,000 $0 $0
$0 $2,660,472 $144,000 $0 $0
$2,804,472
$2,804,472
Line Item:
14. MASONRY
Estimate #:
2011-Conc
Garage/Parking
UNIT/ QTY.
$0 $170,762 $0 $0
UNIT/
LABOR
Line Item Summary DESCRIPTION
TOTAL
$0 $170,762 $0 $0
Sheet #:
UNIT/
MATERIAL
SF LS
Project:
1 of 1
Garage/Parking
UNIT/ QTY.
2011-Conc
UNIT/
LABOR
Line Item Summary DESCRIPTION
Estimate #: Sheet #:
UNIT/
MATERIAL
SF
Project:
9. CONCRETE FOUNDATIONS
Garage/Parking
Line Item Summary DESCRIPTION
Line Item:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0
$0
$0
$10.00 $10.00 $14.00
SUB
$0 $8,120 $1,974,310 $31,573 $0 $0
$2,014,003
TOTAL $0 $8,120 $1,974,310 $31,573 $0 $0
$2,014,003
2011_05_31 Added Floor Estimate REVISED.xls, Garage Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/ QTY.
UNIT
Stair 3 Stair 4 Stair 5 Beam at Stair 3 chase Stair #3 roof deck support Stair #4 roof deck support Stair #5 roof deck support Galvanized steel pipe bollards (70 ea)
1 1 1 1 1 1 1 1
LS LS LS LS LS LS LS LS
Painted Metal Security Fencing Stainless Steel Cable Railing System at South Elevation Adjust to SS across South Garage Wall (Remove Wall)
1 1
LS LS
1
LS
1,316
LF
Barrier Strands @ Ramps
MATERIAL
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$96,545.00 $97,123.00 $97,123.00 $5,443.00 $9,117.00 $18,466.00 $12,834.00 $25,128.00 $26,517.00 $64,965.00 $51,374.00 $35.00
Garage/Parking
Joint Sealants
UNIT
1
MATERIAL
SUB
LABOR
TOTAL $0 $96,545 $97,123 $97,123 $5,443 $9,117 $18,466 $12,834 $25,128 $0 $26,517 $64,965
$51,374 $0 $46,060 $0 $0 $0 $0 $0 $0
$51,374 $0 $46,060 $0 $0 $0 $0 $0 $0
$550,695
$550,695
Sheet #:
UNIT/
MATERIAL
1 of 1
$0 $96,545 $97,123 $97,123 $5,443 $9,117 $18,466 $12,834 $25,128 $0 $26,517 $64,965
Line Item: Estimate #:
UNIT/ QTY.
2011-Conc
UNIT/
LABOR
Line Item Summary DESCRIPTION
Estimate #: Sheet #:
UNIT/
MATERIAL
SUB TOTAL Project:
15. STRUCTURAL & MISC. STEEL
Garage/Parking
Line Item Summary DESCRIPTION
Line Item:
19. WATERPROOFING & SEALANTS
2011-Conc 1 of 1
UNIT/
LABOR
SUB
ls
$0 $0 $0 $0
$0 $0 $0 $0
SUB TOTAL
$0
$0
$76,400.00
$76,400 $0 $0 $0
TOTAL $76,400 $0 $0 $0
$76,400
$76,400
SUB
2011_05_31 Added Floor Estimate REVISED.xls, Garage Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/
Insulation underside A/C areas in garage
QTY.
UNIT
3,500
MATERIAL
SUB TOTAL
LABOR
SUB
SUB
$0 $0 $0 $0
$0 $0 $0 $0
$0
$0
UNIT
11
HM Doors, Frames, Hardware
1 of 1
$3.85
TOTAL
$0 $13,475 $0 $0
$0 $13,475 $0 $0
$13,475
$13,475
Line Item:
23. HOLLOW METAL
Estimate #:
2011-Conc
Garage/Parking
UNIT/ QTY.
2011-Conc
UNIT/
LABOR
Line Item Summary DESCRIPTION
Estimate #: Sheet #:
UNIT/
MATERIAL
SF
Project:
20. BUILDING INSULATION
Garage/Parking
Line Item Summary DESCRIPTION
Line Item:
MATERIAL
Sheet #:
UNIT/
MATERIAL
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0
$0 $0 $0 $0
$0
$0
ea
SUB TOTAL
LABOR
1 of 1
$1,000.00
TOTAL
$0 $11,000 $0 $0
$0 $11,000 $0 $0
$11,000
$11,000
Line Item:
32. STUCCO/EIFS
Estimate #:
2011-Conc
Project: Garage/Parking
Line Item Summary UNIT/ DESCRIPTION
Stucco/EFIS (Removed in Stainless adjustment above)
QTY.
7,235
UNIT
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
$0 $0 $0 $0
$0 $0 $0 $0
SUB TOTAL
$0
$0
$61,500 $0 $0 $0
TOTAL $61,500 $0 $0 $0
$61,500
$61,500
SUB
SUB
sf
$8.50
2011_05_31 Added Floor Estimate REVISED.xls, Garage Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/
Paint (R&M) CMU Elastomeric Paint
QTY.
UNIT
1 197,468
MATERIAL
SUB TOTAL
LABOR
SUB
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0
UNIT
17
Fire Extinguishers (1 per 10,000 SF)
EA
MATERIAL
$10,000.00 $1.00
LABOR
$0 $1,700 $0 $0 $0
$100.00
Traffic Control Gates - Allowance
UNIT
2
EA
SUB TOTAL
$0 $10,000 $197,468 $0 $0
$207,468
$207,468
Line Item:
39. MISC. SPECIALTIES
Estimate #:
2011-Conc 1 of 1
SUB
TOTAL
SUB
$0 $255 $0 $0 $0
$0 $0 $0 $0 $0
$0 $1,955 $0 $0 $0
$255
$0
$1,955
$15.00
$1,700
Line Item:
42. PARKING EQUIPMENT
Estimate #:
2011-Conc
Garage/Parking
UNIT/ QTY.
$0 $10,000 $197,468 $0 $0
UNIT/
LABOR
Line Item Summary DESCRIPTION
TOTAL
SUB
Sheet #:
UNIT/
MATERIAL
SUB TOTAL
Project:
1 of 1
Garage/Parking
UNIT/ QTY.
2011-Conc
UNIT/
LABOR
Line Item Summary DESCRIPTION
Estimate #: Sheet #:
UNIT/
MATERIAL
ls SF
Project:
38. PAINT & WALLCOVERING
Garage/Parking
Line Item Summary DESCRIPTION
Line Item:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0
$0
$0
$15,000.00
SUB
TOTAL
$0 $30,000 $0 $0 $0 $0
$0 $30,000 $0 $0 $0 $0
$30,000
$30,000
2011_05_31 Added Floor Estimate REVISED.xls, Garage Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/ QTY.
UNIT
1
Plumbing
MATERIAL
SUB TOTAL
LABOR
SUB
SUB
$0 $0 $0 $0
$0 $0 $0 $0
$0
$0
UNIT
MATERIAL
$50,000
SUB TOTAL
Project:
LABOR
Sprinklers
170,762
UNIT
sf
SUB TOTAL
$50,000
$50,000
Line Item:
48. H.V.A.C.
Estimate #:
2011-Conc
SUB
SUB
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0
1 of 1
$0.65
TOTAL
$0 $110,995 $0 $0 $0
$0 $110,995 $0 $0 $0
$110,995
$110,995
Line Item:
49. FIRE PROTECTION
Estimate #:
2011-Conc
Garage/Parking
UNIT/ QTY.
$0 $50,000 $0 $0
UNIT/
LABOR
Line Item Summary DESCRIPTION
TOTAL
$0 $50,000 $0 $0
Sheet #:
UNIT/
MATERIAL
170,762
Garage Ventilation
1 of 1
Garage/Parking
UNIT/ QTY.
2011-Conc
UNIT/
LABOR
Line Item Summary DESCRIPTION
Estimate #: Sheet #:
UNIT/
MATERIAL
LS
Project:
47. PLUMBING
Garage/Parking
Line Item Summary DESCRIPTION
Line Item:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0
$1.00
TOTAL
$0 $170,762 $0 $0 $0
$0 $170,762 $0 $0 $0
$170,762
$170,762
2011_05_31 Added Floor Estimate REVISED.xls, Garage Detail
Print Date: 5/31/2011
Print Time: 3:39 PM
Project:
UNIT/
Electrical
Car Charging Stations Allowance
QTY.
UNIT
170,762
sf
1
LS
SUB TOTAL
50. ELECTRICAL
Estimate #:
2011-Conc
Garage/Parking
Line Item Summary DESCRIPTION
Line Item:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$1.90
$200,000
TOTAL
$0 $324,448 $0 $0 $200,000 $0 $0 $0
$0 $324,448 $0 $0 $200,000 $0 $0 $0
$524,448
$524,448
2011_05_31 Added Floor Estimate REVISED.xls, Garage Detail
Estimate General Summary Sheet Residential Project: Owner: Architect:
Regent Square- Block D Residential Tower GID Urban Development ZeiglerCooper ITEMS
Location: Area: Cost / Unit: MATERIAL
LABOR
Estimate Number:
2011-Conc
Date:
5/18/2011
Estimator: Type of Building: Duration: No. of Units ENR Cost Index:
Houston, TX
357,494 sf $184,071 SUB
TOTAL
MH Multi Use
87 Weeks 278
COST/SF
1. GENERAL REQUIREMENTS
$0
$0
$0
$0
$0.00
1a. CRANES & HOISTS
$0
$0
$817,002
$817,002
$2.29
2. DEMOLITION
$0
$0
$0
$0
$0.00
3. SITE EXCAVATION & PREPARATION
$0
$0
$0
$0
$0.00
4. FOUNDATION EXCAVATION
$0
$0
$0
$0
$0.00
5. SITE UTILITIES
$0
$0
$0
$0
$0.00
6. SITE IMPROVEMENTS
$0
$0
$0
$0
$0.00
7. LANDSCAPING
$0
$0
$0
$0
$0.00
8. SOIL POISONING
$0
$0
$2,520
$2,520
$0.01
9. CONCRETE FOUNDATIONS
$0
$0
$371,604
$371,604
$1.04
10. BUILDING CONCRETE
$0
$0
$6,242,947
$6,242,947
$17.46
11. FORMWORK
$0
$0
$0
$0
$0.00
12. RESTEEL/POST TENSIONING
$0
$0
$0
$0
$0.00
13. EXTERIOR CONCRETE/STONE
$0
$0
$470,851
$470,851
$1.32
14. MASONRY
$0
$0
$1,926,207
$1,926,207
$5.39
15. STRUCTURAL & MISC. STEEL
$0
$0
$1,328,614
$1,328,614
$3.72
16. ROUGH CARPENTRY
$95,393
$95,393
$0
$190,786
$0.53
17. FINISH CARPENTRY
$152,506
$182,508
$75,224
$410,238
$1.15
18. MAIN LOBBY FINISHES
$0
$0
$203,120
$203,120
$0.57
19. WATERPROOFING & SEALANTS
$0
$0
$864,805
$864,805
$2.42
20. BUILDING INSULATION
$0
$0
$0
$0
$0.00
21. ROOFING & SHEET METAL
$0
$0
$539,558
$539,558
$1.51
$0
$0
$96,880
$96,880
$0.27
23. HOLLOW METAL
$172,330
$58,125
$0
$230,455
$0.64
24. WOOD DOORS
$273,164
$113,564
$0
$386,729
$1.08
25. FINISH HARDWARE
$249,478
$91,169
$0
$340,647
$0.95
26. SPECIAL DOORS & DOCK EQUIPMENT
$0
$0
$12,000
$12,000
$0.03
27. BALCONY RAILINGS
$0
$0
$1,129,811
$1,129,811
$3.16
28. GLASS, GLAZING & STOREFRONT
$0
$0
$5,066,720
$5,066,720
$14.17
29. ROOF TOP ELEMENT
$0
$0
$0
$0
$0.00
30. DRYWALL
$0
$0
$5,458,405
$5,458,405
$15.27
31. ACOUSTICAL
$0
$0
$0
$0
$0.00
32. STUCCO/EIFS
$0
$0
$190,215
$190,215
$0.53
33. AMENITY, FITNESS, CLUB ROOMS
$0
$0
$812,742
$812,742
$2.27
34. CERAMIC TILE
$0
$0
$597,188
$597,188
$1.67
35. INTERIOR STONE WORK
$0
$0
$0
$0
$0.00
$17,223
$17,223
$415,466
$449,911
$1.26
37. FLOORING (CARPET/RESILIENT/WOOD)
$0
$0
$1,186,774
$1,186,774
$3.32
38. PAINT & WALLCOVERING
$0
$0
$1,091,044
$1,091,044
$3.05
$13,920
$2,900
$228,780
$245,600
$0.69
22. ENTRY CANOPIES
36. KITCHEN & BATH COUNTERTOPS
39. MISC. SPECIALTIES
$0
$0
$7,200
$7,200
$0.02
41. TOILET ACCESSORIES
$69,470
$12,619
$0
$82,088
$0.23
42. PARKING EQUIPMENT
$0
$0
$0
$0
$0.00
43. RESIDENTIAL CABINETS
$0
$0
$812,000
$812,000
$2.27
44. BLINDS & SHADES
$0
$0
$81,200
$81,200
$0.23
45. RESIDENTIAL APPLIANCES
$0
$0
$913,500
$913,500
$2.56
46. ELEVATORS
$0
$0
$1,000,000
$1,000,000
$2.80
47. PLUMBING
$0
$0
$2,374,426
$2,374,426
$6.64
48. H.V.A.C.
$0
$0
$3,420,880
$3,420,880
$9.57
49. FIRE PROTECTION
$0
$0
$717,196
$717,196
$2.01
50. ELECTRICAL
$0
$0
$4,224,660
$4,224,660
$11.82
51. IN-UNIT LOW VOLTAGE CABLING
$0
$0
$467,936
$467,936
$1.31
52. SWIMMING POOL
$0
$0
$347,945
$347,945
$0.97
53. TERRACE LEVEL IMPROVEMENTS
$0
$0
$1,441,729
$1,441,729
$4.03
54 EXTRA 1
$0
$0
$0
$0
$0.00
55 EXTRA 2 56 EXTRA 3
$0 $0
$0 $0
$0 $0
$0 $0
$0.00 $0.00
$44,937,149
$46,554,133
40. TOILET PARTITIONS
SUB TOTAL
$1,043,483
$573,501 Labor Burden Sales Tax
26.50% 8.25%
SUB TOTAL Contractor's Contingency Builder's Risk Insurance GL Insurance & Fees SDI/Subguard Program Building Permits
0.00% by owner 1.50%
SUB TOTAL Payment & Performance Bond
1.0000%
SUB TOTAL General Conditions
3.00%
Condo Insurance Premium Inflation/Escalation
0 0 2.50%
TOTAL
Fee
GRAND TOTAL
$151,978 $86,087
$130.22 $0.43 $0.24
$46,792,198 $0 $0 $394,022 $689,709 $81,875
$130.89 $0.00 $0.00 $1.10 $1.93 $0.23
$47,957,805 $511,717
$134.15 $1.43
$48,469,522 $1,454,086
$135.58 $4.07
$49,923,607
$139.65
$0 $0 $1,248,090
$0.00 $0.00 $3.49
$51,171,697
$143.14
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
1a. CRANES & HOISTS
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Material Hoisting Allotment Man/Material Hoist, Lull, etc. Tower Crane
QTY.
UNIT
371,604
LS
1
LS
MATERIAL
SUB TOTAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
$0 $0 $0 $0 $0 $0 $0 $0
$0
$0
TOTAL
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0
$1.00 $445,398.00
$0 $371,604 $0 $445,398 $0 $0 $0 $0
$0 $371,604 $0 $445,398 $0 $0 $0 $0
$817,002
$817,002
Line Item:
8. SOIL POISONING
Estimate #:
2011-Conc
Project: Residential
Line Item Summary UNIT/ DESCRIPTION
Termite Treatment
QTY.
UNIT
28,000
MATERIAL
UNIT/
MATERIAL
Project:
LABOR
$0
$0
$0 $2,520 $0 $0 $0 $0
$0 $2,520 $0 $0 $0 $0
$2,520
$2,520
$0.09
Line Item:
9. CONCRETE FOUNDATIONS
Estimate #:
2011-Conc
Residential
UNIT/
Foundations
QTY.
371,604
UNIT
SF
SUB TOTAL
TOTAL
SUB
SUB
$0 $0 $0 $0 $0 $0
Line Item Summary DESCRIPTION
1 of 1
UNIT/
LABOR
$0 $0 $0 $0 $0 $0
sf
SUB TOTAL
Sheet #:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0
$1.00
TOTAL
$0 $371,604 $0 $0 $0
$0 $371,604 $0 $0 $0
$371,604
$371,604
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
10. BUILDING CONCRETE
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Structure Area (Formed Area) Square footage is structure area
QTY.
UNIT
371,604
MATERIAL
UNIT/
MATERIAL
Project:
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$16.80
$0 $0 $6,242,947 $0 $0 $0 $0 $0 $0
$0 $0 $6,242,947 $0 $0 $0 $0 $0 $0
$6,242,947
$6,242,947
Line Item:
13. EXTERIOR CONCRETE/STONE
Estimate #:
2011-Conc
Residential
UNIT/
Cast Stone/Arch. Concrete ST (Stone) - Arriscraft
QTY.
1,015 11,444
UNIT
sf sf
SUB TOTAL
TOTAL
SUB
Line Item Summary DESCRIPTION
1 of 1
UNIT/
LABOR
$0 $0 $0 $0 $0 $0 $0 $0 $0
sf
SUB TOTAL
Sheet #:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0
$58.00 $36.00
$58,865 $411,986 $0 $0 $0
TOTAL $58,865 $411,986 $0 $0 $0
$470,851
$470,851
SUB
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
14. MASONRY
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Brick Veener
Trash Chute CMU
QTY.
UNIT
118,156
sf
5,574
sf sf
Interior Walls-CMU Storage Walls-CMU 4"?
7,462 9,632
sf sf sf
SUB TOTAL
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$14.00
$12.00 $35.00 $12.00 $12.00
$1,654,190 $0 $0 $66,889 $0 $0 $0 $89,544 $115,584 $0 $0 $0 $0 $0
TOTAL $1,654,190 $0 $0 $66,889 $0 $0 $0 $89,544 $115,584 $0 $0 $0 $0 $0
$1,926,207
$1,926,207
SUB
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
15. STRUCTURAL & MISC. STEEL
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
Miscellaneous Steel
371,604
sf
Metal Panels (NOW)
14,207
sf
1 1
LS LS
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 16,000
LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LF
14,110
SF
Stair Package: Stair & Rail 1 Stair & Rail 2 Elevator Divider Beams Elevator Sill Angles Elevator Guide Rail Support tubes Elevator Sump pit grating Elevator pit ladders (3) Stair #1 Mechanical Chase Stair #2 Mechanical Chase Steel support at service elevator machine room roof Steel support at passenger elevator machine room roof Elevator hoist beams Lav Counter support at L-8 TP support at L-8 Steel picket railing at L-1 steps Painted Aluminum Column Covers Galvanized Roof Tie Back Anchors Shelf angle at Brick Misc Steel Adj for Added Floor
SUB TOTAL
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$33.30
$271,231.00 $271,231.00 $13,607.00 $25,869.00 $6,002.00 $1,419.00 $2,859.00 $13,607.00 $13,607.00 $5,803.00 $12,573.00 $5,166.00 $1,693 $4,588.00 $33,769 $11,355.00 $27,046 $7.50 $1.00
TOTAL
$0 $0 $0 $0 $0 $473,079 $0 $0 $271,231 $271,231 $0 $13,607 $25,869 $6,002 $1,419 $2,859 $13,607 $13,607 $5,803 $12,573 $5,166 $1,693 $4,588 $33,769 $11,355 $27,046 $120,000 $0 $14,110
$0 $0 $0 $0 $0 $473,079 $0 $0 $271,231 $271,231 $0 $13,607 $25,869 $6,002 $1,419 $2,859 $13,607 $13,607 $5,803 $12,573 $5,166 $1,693 $4,588 $33,769 $11,355 $27,046 $120,000 $0 $14,110
$1,328,614
$1,328,614
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
16. ROUGH CARPENTRY
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Units Door Rough Bucks In-Wall Blocking @ upper cabinets Fair Housting Blocking Exterior Building Blocking - allow
QTY.
UNIT
MATERIAL
39,013 8,047 11,172
lf lf lf
$1.00 $1.00 $1.00
371,604
sf
$0.10
$0 $39,013 $8,047 $11,172 $0 $37,160 $0 $0 $0
LABOR
$1.00 $1.00 $1.00 $0.10
$95,393
SUB TOTAL
Project:
UNIT/
MATERIAL
Sheet #: UNIT/
LABOR
$0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $78,027 $16,094 $22,345 $0 $74,321 $0 $0 $0
$95,393
$0
$190,786
Line Item:
17. FINISH CARPENTRY
Estimate #:
2011-Conc
Residential
UNIT/ QTY.
UNIT
MATERIAL
6" Wood Base (was 4")
96,069
lf
$0.75
Wood Crown Molding Single Rod & Shelf - ventilated wire shelving Double Rod & Shelf - ventilated wire
47,488 876 4,587
lf lf lf
$1.20
Corridors/Common Areas: 6" Wood Base Crown Molding
12,035 12,035
Common Area Millwork Allowance
1
$0.75 $1.20 ls
SUB TOTAL
TOTAL
SUB
SUB
$0 $39,013 $8,047 $11,172 $0 $37,160 $0 $0 $0
Line Item Summary DESCRIPTION
1 of 1
UNIT/
MATERIAL
LABOR
$72,052 $0 $56,986 $0 $0
$1.00
$9,026 $14,442 $0 $0 $0 $0 $0
$1.00 $1.25
$152,506
$1.25
Sheet #:
1 of 1
UNIT/
LABOR
$96,069 $0 $59,360 $0 $0
$12,035 $15,044 $0 $0 $0 $0 $0
$182,508
$0 $0 $0 $3,943 $41,281
TOTAL $168,121 $0 $116,346 $3,943 $41,281
$0 $0 $30,000 $0 $0 $0
$21,061 $29,486 $0 $30,000 $0 $0 $0
$75,224
$410,238
SUB
SUB
$4.50 $9.00
$30,000.00
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
18. MAIN LOBBY FINISHES
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Main Lobby Finish Allowance
QTY.
UNIT
2,539
MATERIAL
UNIT/
MATERIAL
LABOR
SUB
$0 $0 $0 $0 $0
$0
$0
$80.00
Residential
Project:
$203,120 $0 $0 $0 $0
TOTAL $203,120 $0 $0 $0 $0
$203,120
$203,120
SUB
Line Item: Estimate #:
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
Waterproofing/Dampproofing
371,604
sf
Waterproofing Behind Stone Veneer Waterproofing Behind Brick Veneer Vapor Barrier Behind Stucco
11,444 116,530 1,491
sf sf sf
1 1 1 1 1 1
ls ls ls ls ls ls
Pedestrian Traffic Coating Fluid Applied Membrane Air Barriers Sheetmetal Flashing and Trim Flexible Flashing Joint Sealants Expansion Joint Cover Assemblies
SUB TOTAL
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
$0 $0 $0 $0 $0
sf
SUB TOTAL
Sheet #:
19. WATERPROOFING & SEALANTS
2011-Conc 1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$114,531 $477,413 $62,542 $48,216.26 $53,422 $108,680
SUB
TOTAL
$0 $0 $0 $0 $0 $0 $0 $0 $114,531 $477,413 $62,542 $48,216 $53,422 $108,680 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $114,531 $477,413 $62,542 $48,216 $53,422 $108,680 $0 $0
$864,805
$864,805
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
21. ROOFING & SHEET METAL
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
1
LS
2,500
SF
628
LF
Roofing (Chamberlain) Standing Seam Roof (Low Roof)
UNIT
Roof Walk Pads
MATERIAL
SUB TOTAL
Project:
Sheet #:
UNIT/
MATERIAL
LABOR
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$493,266.00 $15.00 $14.00
$0 $493,266 $0 $37,500 $0 $8,792 $0 $0
$0 $493,266 $0 $37,500 $0 $8,792 $0 $0
$539,558
$539,558
Line Item:
22. ENTRY CANOPIES
Estimate #:
2011-Conc
Line Item Summary
Entry Canopy
QTY.
UNIT
1
ls
SUB TOTAL
TOTAL
SUB
Residential
UNIT/ DESCRIPTION
1 of 1
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0
$0 $0 $0 $0
$0
$0
$96,880
SUB
TOTAL
$0 $96,880 $0 $0
$0 $96,880 $0 $0
$96,880
$96,880
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
23. HOLLOW METAL
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
MATERIAL
3080 HM Frame 4080 HM Frame 6080 HM Frame 3080 Common Area Doors 4080 Common Area Doors 6080 Double Common Area Doors
213 3 28 211 3 27
ea ea ea ea ea ea
$175.00 $175.00 $225.00 $280.00 $280.00 $280.00
Unit Entry door Frame
290
ea
$175.00
1
ls
$10,000.00
$37,275 $525 $6,300 $59,080 $840 $7,560 $0 $50,750 $0 $10,000 $0 $0
LABOR
$75.00 $75.00 $75.00 $75.00 $75.00 $75.00 $75.00
$172,330
SUB TOTAL
Project:
UNIT/
MATERIAL
Sheet #: UNIT/
$15,975 $225 $2,100 $15,825 $225 $2,025 $0 $21,750 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL $53,250 $750 $8,400 $74,905 $1,065 $9,585 $0 $72,500 $0 $10,000 $0 $0
$58,125
$0
$230,455
LABOR
SUB
SUB
Line Item:
24. WOOD DOORS
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
MATERIAL
Lovered Mechanical Room Door Bedroom/Bathroom doors 3080 Wood Closet Doors 3080 Double Door Coat Closet doors 2680 Wood Laundry Room doors 5080 Bifold Closet Doors 3080 Wood Office/Closet Door 4080 Double Door
290 757 361 271 96 175 51
ea ea ea ea ea ea ea
$187.00 $75.00 $125.00 $75.00 $75.00 $75.00 $75.00
Entry Door Unit
290
ea
$250.00
SUB TOTAL
1 of 1
UNIT/
MATERIAL
$54,230 $56,800 $45,117 $20,342 $7,198 $13,144 $3,834 $0 $72,500 $0 $0 $0
$273,164
LABOR
$35.00 $35.00 $35.00 $35.00 $35.00 $35.00 $35.00 $150.00
Sheet #:
1 of 1
UNIT/
$10,150 $26,507 $12,633 $9,493 $3,359 $6,134 $1,789 $0 $43,500 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL $64,380 $83,307 $57,750 $29,835 $10,557 $19,278 $5,623 $0 $116,000 $0 $0 $0
$113,564
$0
$386,729
LABOR
SUB
SUB
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
25. FINISH HARDWARE
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Entry Door-Hardware Set Res. Interior Door-Hardware Set Common Door Hardware
QTY.
UNIT
MATERIAL
290 2,002 241
ea ea ea
$350.00 $15.00 $350.00
84
ea
$400.00
Panic Device - Premium
UNIT/
MATERIAL
LABOR
$101,500 $30,028 $84,350 $0 $33,600 $0 $0 $0
$35.00 $35.00 $35.00 $30.00
$249,478
SUB TOTAL
Sheet #: UNIT/
$10,150 $70,064 $8,435 $0 $2,520 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0
TOTAL $111,650 $100,092 $92,785 $0 $36,120 $0 $0 $0
$91,169
$0
$340,647
LABOR
SUB
Residential
Project:
SUB
Line Item: Estimate #:
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
2
Steel Coiling Doors
MATERIAL
Project:
LABOR
SUB
$0 $0 $0 $0
$0
$0
QTY.
6,277
UNIT
LF
SUB TOTAL
1 of 1
$6,000.00
TOTAL
SUB
$0 $12,000 $0 $0
$0 $12,000 $0 $0
$12,000
$12,000
Line Item:
27. BALCONY RAILINGS
Estimate #:
2011-Conc
Line Item Summary DESCRIPTION
2011-Conc
Residential
UNIT/
Exterior Balcony Railing/Glass/SS Cap
26. SPECIAL DOORS & DOCK EQUIPMENT
UNIT/
LABOR
$0 $0 $0 $0
ea
SUB TOTAL
Sheet #:
UNIT/
MATERIAL
1 of 1
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0
$180.00
$1,129,811 $0 $0 $0 $0
TOTAL $1,129,811 $0 $0 $0 $0
$1,129,811
$1,129,811
SUB
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Residential
Project:
Line Item: Estimate #:
Line Item Summary UNIT/ DESCRIPTION
Storefront Residential Windows Mirrors Shower Door/Enclosure
QTY.
UNIT
61,762 15,933 20,524 61
MATERIAL
MATERIAL
SUB TOTAL
Project:
LABOR
LABOR
$0
$0
$63.00 $53.00 $12.00 $750.00
TOTAL $3,891,032 $844,434 $246,283 $45,971 $0 $0 $39,000 $0 $0 $0 $0
$3,000.00
$5,066,720
$5,066,720
Line Item:
30. DRYWALL
Estimate #:
2011-Conc
Residential
UNIT/ QTY.
UNIT
Interior Walls-3 5/8 x10' Low Walls @ Bar Sheetrock Ceilings (40% inside unit) Demising Walls Common Area Ceilings Corridor/Elec/Trash Room Walls 10' Exterior walls Exterior walls - thermal insulation Stair Walls Interior Walls - 6" x 10' Skim Coat (Ceilings @ 60% of units)
29,672 0 107,453 7,340 91,511 0 169,323 169,323 0 0 167,248
lf lf sf lf sf lf SF SF lf lf sf
Common Area Interior Walls Corridor Walls Exterior Stair Walls at Amenity Deck
3,745 11,997 110
lf lf lf
Drywall adjustment
371,604
SUB TOTAL
1 of 1
$3,891,032 $844,434 $246,283 $45,971 $0 $0 $39,000 $0 $0 $0 $0
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Line Item Summary DESCRIPTION
2011-Conc
UNIT/
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
sf sf sf ea
13 ea
Storefront Doors
Sheet #:
UNIT/
28. GLASS, GLAZING & STOREFRONT
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$42.00 $4.50 $95.00 $4.50 $65.00 $7.50 $1.25 $68.00 $45.00 $0.85 $65.00 $90.00 $65.00 ($0.90)
$1,246,240 $0 $483,537 $697,273 $411,798 $0 $1,269,925 $211,654 $0 $0 $142,161 $0 $243,395 $1,079,717 $7,150 $0 ($334,444) $0 $0 $0
$5,458,405
TOTAL $1,246,240 $0 $483,537 $697,273 $411,798 $0 $1,269,925 $211,654 $0 $0 $142,161 $0 $243,395 $1,079,717 $7,150 $0 ($334,444) $0 $0 $0
$5,458,405
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
32. STUCCO/EIFS
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
1,491 13,141
Stucco/Plaster Stucco/EFIS Soffit
MATERIAL
UNIT/
MATERIAL
Project:
LABOR
SUB
$0 $0 $0 $0
$0
$0
$13.00 $13.00
$19,382 $170,833 $0 $0
TOTAL $19,382 $170,833 $0 $0
$190,215
$190,215
SUB
Line Item:
33. AMENITY, FITNESS, CLUB ROOMS
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
2,359 2,721 630 141 1,463 311 471 1,990
sf sf sf sf sf sf sf sf
Retail Space (see recap sheet for pricing)
0
sf
Paver and Pedistal System (PV-4) - at fitness balcony
1
ls
Leasing Office Gym Theatre Laundry Internet Café Kitchen Dining Room Bar
SUB TOTAL
1 of 1
UNIT/
LABOR
$0 $0 $0 $0
sf sf
SUB TOTAL
Sheet #:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$65.00 $75.00 $90.00 $40.00 $75.00 $90.00 $80.00 $100.00
$18,597.00
SUB
TOTAL
$0 $0 $0 $153,335 $204,075 $56,700 $5,640 $109,725 $27,990 $37,680 $199,000 $0 $0 $0 $18,597 $0 $0 $0 $0 $0 $0
$0 $0 $0 $153,335 $204,075 $56,700 $5,640 $109,725 $27,990 $37,680 $199,000 $0 $0 $0 $18,597 $0 $0 $0 $0 $0 $0
$812,742
$812,742
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
34. CERAMIC TILE
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Public Restrooms floor tile Public Restrooms Wall Tile Units Shower/Bath Floors Tub/Shower Surrounds Noble Seal Crack Iso & WP Membrane Kitchen Backsplash Vanity backsplash
QTY.
UNIT
372 1,125
sf sf
18,135 36,753 18,135
sf sf sf
6,036 1,969
sf lf
MATERIAL
SUB TOTAL
Project:
Sheet #:
UNIT/
MATERIAL
LABOR
UNIT/
LABOR
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$7.00 $7.50
$7.00 $7.50 $3.50 $15.00 $15.00
$0 $0 $0 $2,604 $8,438 $0 $0 $126,948 $275,646 $63,474 $0 $90,536 $29,542 $0 $0
$0 $0 $0 $2,604 $8,438 $0 $0 $126,948 $275,646 $63,474 $0 $90,536 $29,542 $0 $0
$597,188
$597,188
Line Item:
36. KITCHEN & BATH COUNTERTOPS
Estimate #:
2011-Conc
Residential
Line Item Summary DESCRIPTION
QTY.
UNIT
12,860 3,939 424
sf sf sf
Plywood Substrate at Countertops
17,223
sf
1
ea
Common Area Tops-Allowance-Lobbies/Mailrooms
SUB TOTAL
TOTAL
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
UNIT/
Granite Kitchen Top Solid Surface Vanity Top 3cm Unit Desk Tops
1 of 1
MATERIAL
$1.00
UNIT/
MATERIAL
$0 $0 $0 $0 $0 $0 $0 $17,223 $0 $0 $0 $0 $0 $0
$17,223
LABOR
$1.00
Sheet #:
1 of 1
UNIT/
LABOR
$0 $0 $0 $0 $0 $0 $0 $17,223 $0 $0 $0 $0 $0 $0
$17,223
SUB
$24.00 $22.00 $24.00
$10,000.00
$308,643 $86,658 $10,165 $0 $0 $0 $0 $0 $0 $0 $10,000 $0 $0 $0
TOTAL $308,643 $86,658 $10,165 $0 $0 $0 $0 $34,445 $0 $0 $10,000 $0 $0 $0
$415,466
$449,911
SUB
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
37. FLOORING (CARPET/RESILIENT/WO OD)
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
65,960
sf
Engineered Wood Plank Floors
130,026
sf
Acoustimat
130,026
sf
Common Area Carpet (Corridors, Office)
21,884
sf
Back of House / Storage
14,755
sf
Carpet Units
MATERIAL
SUB TOTAL
Project:
Sheet #:
UNIT/
MATERIAL
LABOR
UNIT/
LABOR
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$1.78
$5.50 $1.75 $4.44
$2.00
$0 $0 $117,410 $0 $0 $715,145 $0 $227,546 $0 $97,164 $0 $0 $29,509 $0 $0 $0
$1,186,774
Paint Walls Paint Ceilings Skim Concrete Ceilings (with drywall) Sealed Concrete Mechanical Room Floor Deminising Walls (included with Paint Walls) Corridor Walls Interior side of Exterior wall (inc.w/ Paint Walls) Stair Walls Paint Elec/Trash/Storage/Other Room Walls Paint Doors/Frames Paint Wood Trim R&M Paint Paint Adjustment for Added Floors
UNIT
0 0 0 0 0 0 0 0 0 0 0
sf sf sf sf sf sf sf sf sf ea lf
1 14,110
LS SF
SUB TOTAL
$0 $0 $117,410 $0 $0 $715,145 $0 $227,546 $0 $97,164 $0 $0 $29,509 $0 $0 $0
$1,186,774
Line Item:
38. PAINT & WALLCOVERING
Estimate #:
2011-Conc
Residential
UNIT/ QTY.
TOTAL
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Line Item Summary DESCRIPTION
1 of 1
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$0.40 $0.45 $0.00 $0.25 $0.40 $0.40 $0.40 $0.40 $35.00 $2.00 $1,049,223.00 $2.96
TOTAL
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,049,223 $41,821 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,049,223 $41,821 $0
$1,091,044
$1,091,044
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
39. MISC. SPECIALTIES
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
Fire Extinguishers Mailbox/Dropbox/Parcel Locker-Allowance Trash Chutes Trash Sorter Dog Wash Sinks Graphic Allowance Lockers in Fitness room - allowance Bike Racks I Pod Dock & Wiring
UNIT
290 295 492 1 3 1
ea ea lf ls ea LS
1 1
LS ls
290
EA
MATERIAL
$48.00
Project:
UNIT/
MATERIAL
LABOR
$13,920 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$10.00
$13,920
SUB TOTAL
Sheet #: UNIT/
LABOR
SUB
$2,900 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$60.00 $115.00 $20,000.00 $3,500.00 $30,000.00 $2,000.00 $5,000.00 $300.00
$2,900
$0 $17,700 $56,580 $20,000 $10,500 $30,000 $0 $2,000 $5,000 $0 $87,000 $0 $0
TOTAL $16,820 $17,700 $56,580 $20,000 $10,500 $30,000 $0 $2,000 $5,000 $0 $87,000 $0 $0
$228,780
$245,600
SUB
Line Item:
40. TOILET PARTITIONS
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Toilet Partitions Amenity Deck
QTY.
UNIT
8
EA
SUB TOTAL
1 of 1
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0
$0 $0 $0 $0
$0
$0
$900.00
TOTAL
SUB
$0 $7,200 $0 $0
$0 $7,200 $0 $0
$7,200
$7,200
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
41. TOILET ACCESSORIES
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
MATERIAL
Toilet Paper Holder Towel Bar Towel Ring Shower Curtain Rod Medicine Cabinet H/C Grab Bar (4% of units) Shower Seat (4% of units)
361 361 361 331 361 14 14
ea ea ea ea ea ea ea
$10.00 $16.00 $12.00 $30.00 $100.00 $90.00 $50.00
Public Area Restrooms
11
ea
$700.00
Project:
UNIT/
MATERIAL
LABOR
$3,610 $5,776 $4,332 $9,930 $36,100 $1,300 $722 $0 $0 $7,700 $0 $0
$5.00 $5.00 $5.00 $5.00 $10.00 $10.00 $10.00
$150.00
$69,470
SUB TOTAL
Sheet #: UNIT/
$1,805 $1,805 $1,805 $1,655 $3,610 $144 $144 $0 $0 $1,650 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL $5,415 $7,581 $6,137 $11,585 $39,710 $1,444 $866 $0 $0 $9,350 $0 $0
$12,619
$0
$82,088
LABOR
SUB
SUB
Line Item:
43. RESIDENTIAL CABINETS
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Cabinets (allowance) Base Cabinets Upper Cabinets Kitchen Pantry Bathroom Storage Cabinets
QTY.
UNIT
290
ea
5,840 5,840 290 290
LF LF EA EA
SUB TOTAL
1 of 1
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$2,800.00
SUB
TOTAL
$0 $812,000 $0 $0 $0 $0 $0 $0 $0 $0
$0 $812,000 $0 $0 $0 $0 $0 $0 $0 $0
$812,000
$812,000
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
44. BLINDS & SHADES
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
290
Blind-Allowance/Unit
MATERIAL
UNIT/
MATERIAL
Project:
LABOR
SUB
$0 $0 $0 $0
$0
$0
$280.00
SUB
$81,200 $0 $0 $0
$81,200
UNIT
Appliances
290
ea
W/D
290
ea
Add Beverage Refrigerator
290
ea
MATERIAL
SUB TOTAL
Project:
Line Item: Estimate #:
2011-Conc
Sheet #:
UNIT/
MATERIAL
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$2,200.00 $500.00 $450.00
Passenger Elevators
Freight Elevator Cab Allowance Operator / Recertification
UNIT
2
EA
1
EA
3 1
EA LS
SUB TOTAL
TOTAL
SUB
$0 $638,000 $0 $145,000 $0 $130,500 $0 $0
$0 $638,000 $0 $145,000 $0 $130,500 $0 $0
$913,500
$913,500
Line Item:
46. ELEVATORS
Estimate #:
2011-Conc
Residential
UNIT/ QTY.
1 of 1
UNIT/
LABOR
Line Item Summary DESCRIPTION
$81,200
Residential
UNIT/ QTY.
TOTAL $81,200 $0 $0 $0 45. RESIDENTIAL APPLIANCES
Line Item Summary DESCRIPTION
1 of 1
UNIT/
LABOR
$0 $0 $0 $0
ea
SUB TOTAL
Sheet #:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$306,000.00
$346,000.00 $10,000.00 $12,000.00
SUB
TOTAL
$0 $612,000 $0 $0 $346,000 $0 $30,000 $12,000 $0 $0 $0
$0 $612,000 $0 $0 $346,000 $0 $30,000 $12,000 $0 $0 $0
$1,000,000
$1,000,000
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
47. PLUMBING
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
MATERIAL
UNIT/
MATERIAL
SUB TOTAL
Project:
LABOR
$0 $0 $0 $0 $0
$0
$0
SUB
$8,167 $20,000 $7,000.00
$0 $2,270,426 $20,000 $84,000 $0
$0 $2,270,426 $20,000 $84,000 $0
$2,374,426
$2,374,426
Line Item:
48. H.V.A.C.
Estimate #:
2011-Conc
Residential
UNIT/ QTY.
UNIT
MATERIAL
SUB TOTAL
Project:
Sheet #:
UNIT/
MATERIAL
LABOR
$0
$0
$11,960 $8,000
$0 $3,324,880 $96,000 $0
$0 $3,324,880 $96,000 $0
$3,420,880
$3,420,880
Line Item:
49. FIRE PROTECTION
Estimate #:
2011-Conc
Residential
UNIT/
Fire Sprinklers
QTY.
371,604
UNIT
SF
SUB TOTAL
TOTAL
SUB
SUB
$0 $0 $0 $0
Line Item Summary DESCRIPTION
1 of 1
UNIT/
LABOR
$0 $0 $0 $0
278 Apts 12
HVAC Added Units
TOTAL
SUB
Line Item Summary DESCRIPTION
1 of 1
UNIT/
LABOR
$0 $0 $0 $0 $0
278 Apts 1 LS 12 EA
Plumbing (Units) Teal System Structure Allowance Added Units
Sheet #:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
SUB
$0 $0 $0 $0 $0
$0 $0 $0 $0 $0
$0
$0
$1.93
TOTAL
$0 $717,196 $0 $0 $0
$0 $717,196 $0 $0 $0
$717,196
$717,196
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
50. ELECTRICAL
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Base Electrical Light Fixture Allowance Lightning Protection Adjust Electrical for Added Floor
QTY.
UNIT
1 1 1 14,110
MATERIAL
UNIT/
MATERIAL
LABOR
SUB
$0 $0 $0 $0 $0 $0
$0
$0
$3,750,000 $300,000 $90,000 $6
TOTAL
SUB
$0 $3,750,000 $300,000 $90,000 $84,660 $0
$0 $3,750,000 $300,000 $90,000 $84,660 $0
$4,224,660
$4,224,660
Line Item:
Project:
Residential
Line Item Summary UNIT/
Fire Alarm Telecom Access Control Adjust low voltage for added floor
QTY.
UNIT
1 1 1 14,110
MATERIAL
Project:
Sheet #:
UNIT/
MATERIAL
LABOR
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0
$0
$0
$175,000.00 $100,000.00 $175,000.00 $1.27
$0 $0 $175,000 $100,000 $175,000 $17,936 $0
$0 $0 $175,000 $100,000 $175,000 $17,936 $0
$467,936
$467,936
Line Item:
52. SWIMMING POOL
Estimate #:
2011-Conc
Residential
UNIT/
Swimming Pool Raised Pool Fountains Heated Pool Spa Integral Pool Fountain Aerator
QTY.
2,032 1 89 1 1
UNIT
sf ls sf ls ls
SUB TOTAL
1 of 1 TOTAL
SUB
Line Item Summary DESCRIPTION
2011-Conc
UNIT/
$0 $0 $0 $0 $0 $0 $0
LS LS LS SF
SUB TOTAL
51. IN-UNIT LOW VOLTAGE CABLING
2011-Conc Estimate #:
DESCRIPTION
1 of 1
UNIT/
LABOR
$0 $0 $0 $0 $0 $0
LS LS LS SF
SUB TOTAL
Sheet #:
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$135.00 $30,000.00 $125.00 $30,000.00 $2,500.00
SUB
TOTAL
$0 $274,320 $30,000 $11,125 $30,000 $2,500 $0 $0 $0
$0 $274,320 $30,000 $11,125 $30,000 $2,500 $0 $0 $0
$347,945
$347,945
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
REVISION DATE:
GID West Dallas Apartments COST TRACKING LOG ITEM NO. 1 2 3 4 5
DATE SUBMITTED 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/18/2011 5/25/2011 5/25/2011 5/25/2011 5/27/2011 5/26/2011
Original Budget - May 5, 2011 Schematic Design Plus one Floor $61,398,524 "Target" IMPACT ($454,525) ($148,774) ($258,289) ($26,056) ($754,657)
DESCRIPTION Revised bid for Rheinzink Panels Delete DCI from parking garage Provide king size brick in lieu of modular brick at all areas Provide $25,000 screen wall allowance in lieu of masonry wall at entry plaza Provide Kynar-finished square tube aluminum rail at $60/lf in lieu of glass rail as shown Provide 4" MDF base in living units in lieu of 6" MDF base Remove crown molding in living units Remove crown molding at common areas Delete pedestrian traffic coatings at balconies Provide Hamilton oval baths in lieu of Sterling Provide galvanized flashing in lieu of stainless steel flashings Provide urethane masonry sealant in lieu of silicone masonry sealant Provide chainlink at storage in lieu of drywall and hollow metal frames Provide mid range cabinets in lieu of specified cabinets Delete Low Emitting Paint Requirement Delete wine coolers Provide Pioneer brush nickle faucets with 20 gauge kitchen sinks Provide Pioneer brushed nickel faucet in lieu of Danze Provide Pioneer brushed nickel tub and shower valves in lieu of Danze Provide sub metering per PDI - Install Only LED Lighting in lieu of Metal Halide at Garage Allowance to provide builders risk insurance GOAL: Achieve $80,000 Landscape Allowance for Project Deduct phone wiring Remove utility relocation from the construction budget Deduct Payment and Performance Bond Provide wall barricadeat south side of garage in lieu of barrier cable Provide Laminate Flooring in lieu of Engineered Wood Flooring Deduct car charging stations Delete iPod dock requirements at kitchen HVAC Option 1: All split system DX 13 SEER HVAC Option 2: All DX 14 SEER HVAC Option 3: VRV Tower; Split System DX Midrise HVAC Option 4: Split DX everywhere possible; VRV where not HVAC Option 5: VRV Mid-Rise; Split DX Tower HVAC Option 6: Water source heat pump Delete Ducted Outside Air at Units Delete motorized dampers at outside air Delete requirement for Superduct Provide 7 ft. doors in lieu of 8' doors Amenity Deck Option 2: 1/L1.05 Amenity Deck Option 3: 2/L1.05 Add 21st Floor per E-mail dated 5/27/11 Changes in Drawings Dated 5/18/11
($19,569) ($135,465) ($46,207) ($113,432) ($24,347) ($13,479) ($5,387) ($28,825) ($172,330) ($53,233) ($129,248) ($82,974) ($33,910) ($15,859) $15,659 $78,295 $254,908 ($330,609) $0 ($935,005) ($619,605) ($53,077) ($193,168) ($206,631) ($86,165) ($1,324,980) ($1,204,561) ($129,429) ($988,330) ($795,092) $244,290 ($50,749) ($38,227) ($19,113) ($44,905) $0 $0 $1,426,321 $0 $0
0 0
GRAND TOTAL:
$
May 31, 2011
TOTAL PENDING
STATUS Rejected Pending Pending Pending Pending
$ $ $ $
(148,774) (258,289) (26,056) (754,657)
Pending Pending Pending Pending Pending Pending Pending Pending Pending Pending Pending Pending Pending Pending Pending Pending
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
(19,569) (135,465) (46,207) (113,432) (24,347) (13,479) (5,387) (28,825) (172,330) (53,233) (129,248) (82,974) (33,910) (15,859) 15,659 78,295
Pending Pending Pending Pending Pending Pending Pending Pending Pending
$ $ $ $ $ $ $ $ $
(330,609) (935,005) (619,605) (53,077) (193,168) (206,631) (86,165) (1,324,980)
Pending Pending Pending Pending
$ $ $ $
(50,749) (38,227) (19,113) (44,905)
TOTAL ACCEPTED
TOTAL STATUS/ REJECTED RESPONSIBILITY $ (454,525) Included in base number via VE #43 below.
Rejected
(7,516,737)
$ (5,870,320) $
Current Budget with all VE's taken
TOTAL WITH "ACCEPTED" ITEMS:
Sheet 1 of 1
-
$55,528,204
$
61,398,524
$
1,426,321 Included in base number above. Includes VE #1.
$
971,796
Due Date
Estimate General Summary Sheet Amenity Deck Break-Out Project: Owner: Architect:
Regent Square- Block D Amenity Deck Break-Out GID Urban Development ZeiglerCooper ITEMS
Location: Area: Cost / Unit: MATERIAL
LABOR
Houston, TX
357,494 sf $7,028 SUB
Estimate Number:
2011-Conc
Date:
5/17/2007
Estimator: Type of Building: Duration: No. of Units ENR Cost Index: TOTAL
MH Multi Use
87 Weeks 278 4,576.93 COST/SF
BOND AMOUNT
1. POOL AREA
$0
$0
$614,170
$614,170
$1.72
2. LAWN AREA
$0
$0
$301,868
$301,868
$0.84
$0
3. ZEN GARDEN
$0
$0
$229,253
$229,253
$0.64
$229,253
4. VEGETABLE GARDEN 5. SWIMMING POOL
$0 $0
$0 $0
$296,438 $347,945
$296,438 $347,945
$0.83 $0.97
$296,438 $347,945
$1,789,674
$1,789,674
$5.01
$873,636
$0 $0
$0.00 $0.00
$1,789,674 $0 $0 $15,044 $26,845 $3,126
$5.01 $0.00 $0.00 $0.04 $0.08 $0.01
$1,834,689 $19,538
$5.13 $0.05
$1,854,227 $51,918
$5.19 $0.15
SUB TOTAL
$0
$0 Labor Burden Sales Tax
26.50% 8.25%
SUB TOTAL Contractor's Contingency Builder's Risk Insurance GL Insurance & Fees SDI/Subguard Program Building Permits
0.00% by owner 1.50%
SUB TOTAL Payment & Performance Bond
1.0000%
SUB TOTAL General Conditions
2.80%
Condo Insurance Premium
0 0 2.50%
TOTAL Inflation/Escalation Fee
GRAND TOTAL
$1,906,146
$5.33
$0 $0 $47,654
$0.00 $0.00 $0.13
$1,953,799
$5.47
$0
Print Date: 5/31/2011
Print Time: 3:40 PM
Project:
Line Item:
53. TERRACE LEVEL IMPROVEMENTS
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Pool Terrace Sandwich Slab Metals: Terrace Trellis (ST-1) Cabana Trellis (ST-2) Ornamental Gates (FE-2) Steel Structure at Level 8 Pool Living Living Cabana (ST4) Pool Fencing Landscape/Irrigation Allowance Hot Fluid Applied Rubberized Ashphalt WP Stone Pavers (PV-2) Outdoor Fireplace (SF-2) PV 6 Stone pavers PV7 Precast Concrete pavers Landscaping Planter (PL4) DG Paving (PV-8) Cast Stone Hearth (WL-13) Outdoor Shower (SF-3) Cast Stone Planter Curb (WL10) Cast Stone step curb (WL-5) Runnel Fountain Basin (WL-7) Spa Screen Wall (WL-9) Cast Stone Steps (WL-11) Garden Seat Bench 15 X 24 (WL3) Rainwater Harvesting System 1,000 gal Masonry Garden Wall 42" tall (WL2) Runnel Wall (WL6) Outdoor Bar (SF6) Pool Planters (WL14) Concrete Wall w/cast stone cap (WL14) Outdoor Living Cabanas - small (ST2) Stainless Gas grilles (ST4) Sinks (ST4) Undercounter Refrigerators (ST4) Masonry raised counters w/ granite tops (ST4) Curb Gravel IPE Wood Deck Raised Vegtable Gardens Walls (PL2) Masonry Wall with IPE Wood Cap (WL1) Colored Concrete Paving @ pool deck Plumbing at Amenity Deck
QTY.
UNIT
25,130
sf
1 1 1 1 1 1 1 1 2,722 1 1,383 114 5,966 916 1 3 69 245 28 312 29 66 1 920 57 17 623 259 2 2 2 2 20 218 705 207 137 199 6,187 1
LS LS LS LS LS LS LS ls sf ls sf sf sf sf ea ea lf lf lf sf lf lf ls sf lf lf sf lf ea ea ea ea lf lf sf sf sf lf sf ls
SUB TOTAL
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$10.00
$11,514.00 $21,589.00 $2,805.00 $21,248.00 $50,000.00 $5,000.00 $350,000.00 $287,212.00 $15.00 $40,000.00 $15.00 $25.00 $5.00 $5.00 $20,000.00 $3,500.00 $75.00 $75.00 $100.00 $50.00 $200.00 $300.00 $10,000.00 $28.00 $100.00 $500.00 $5.00 $50.00 $10,000.00 $1,200.00 $450.00 $1,400.00 $450.00 $10.00 $5.00 $18.00 $50.00 $75.00 $10.00 $10,000.00
SUB
TOTAL
$0 $251,300 $0 $0 $11,514 $21,589 $2,805 $21,248 $50,000 $5,000 $350,000 $287,212 $40,830 $40,000 $20,745 $2,850 $29,830 $4,580 $20,000 $10,500 $5,175 $18,375 $2,800 $15,600 $5,800 $19,800 $10,000 $25,760 $5,700 $8,500 $3,115 $12,950 $20,000 $2,400 $900 $2,800 $9,000 $2,180 $3,525 $3,726 $6,825 $14,925 $61,870 $10,000 $0 $0 $0 $0
$0 $251,300 $0 $0 $11,514 $21,589 $2,805 $21,248 $50,000 $5,000 $350,000 $287,212 $40,830 $40,000 $20,745 $2,850 $29,830 $4,580 $20,000 $10,500 $5,175 $18,375 $2,800 $15,600 $5,800 $19,800 $10,000 $25,760 $5,700 $8,500 $3,115 $12,950 $20,000 $2,400 $900 $2,800 $9,000 $2,180 $3,525 $3,726 $6,825 $14,925 $61,870 $10,000 $0 $0 $0 $0
$1,441,729
$1,441,729
2011_05_31 Added Floor Estimate REVISED.xls, Residential Detail
Residential
Project:
Line Item Summary General Conditions UNIT/ DESCRIPTION
QTY
UNIT
Pool Terrace Sandwich Slab
1
LS
Metals: Terrace Trellis (ST-1) Cabana Trellis (ST-2) Ornamental Gates (FE-2) Steel Structure at Level 8 Pool Living Living Cabana (ST4) Pool Fencing Landscape/Irrigation Allowance Hot Fluid Applied Rubberized Ashphalt WP Paver and Pedistal System (PV-4) - at fitness balcony Stone Pavers (PV-2) Outdoor Fireplace (SF-2) PV 6 Stone pavers PV7 Precast Concrete pavers Landscaping Planter (PL4) DG Paving (PV-8) Cast Stone Hearth (WL-13) Outdoor Shower (SF-3) Cast Stone Planter Curb (WL10) Cast Stone step curb (WL-5) Runnel Fountain Basin (WL-7) Spa Screen Wall (WL-9) Cast Stone Steps (WL-11) Garden Seat Bench 15 X 24 (WL3) Rainwater Harvesting System 1,000 gal Masonry Garden Wall 42" tall (WL2) Runnel Wall (WL6) Outdoor Bar (SF6) Pool Planters (WL14) Concrete Wall w/cast stone cap (WL14) Outdoor Living Cabanas - small (ST2) Stainless Gas grilles (ST4) Sinks (ST4) Undercounter Refrigerators (ST4) Masonry raised counters w/ granite tops (ST4) Curb Gravel IPE Wood Deck Raised Vegtable Gardens Walls (PL2) Masonry Wall with IPE Wood Cap (WL1) Colored Concrete Paving @ pool deck Plumbing at Amenity Deck
0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS
SUB TOTAL
MATERIAL
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
LABOR
1. POOL AREA
2011-Conc
Sheet #:
UNIT/
MATERIAL
Line Item: Estimate #:
1 of 1
UNIT/
LABOR
SUBCONTRACT
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$62,825.00
$11,514.00 $21,589.00 $2,805.00 $21,248.00 $50,000.00 $5,000.00 $130,000.00 $71,803.00 $32,664.00 $40,000.00
$20,000.00 $10,500.00 $5,175.00 $18,375.00 $15,600.00 $5,800.00 $3,960.00
$8,500.00 $3,115.00 $12,950.00 $20,000.00 $2,400.00 $900.00 $2,800.00 $9,000.00
$3,726.00
$30,935.00 $2,500.00
SUBCONTRACT
$0 $62,825 $0 $0 $0 $21,589 $2,805 $21,248 $50,000 $5,000 $130,000 $71,803 $0 $32,664 $40,000 $0 $0 $0 $0 $20,000 $10,500 $5,175 $18,375 $0 $15,600 $5,800 $3,960 $0 $0 $0 $8,500 $3,115 $12,950 $20,000 $2,400 $900 $2,800 $9,000 $0 $0 $3,726 $0 $0 $30,935 $2,500
TOTAL $0 $62,825 $0 $0 $0 $21,589 $2,805 $21,248 $50,000 $5,000 $130,000 $71,803 $0 $32,664 $40,000 $0 $0 $0 $0 $20,000 $10,500 $5,175 $18,375 $0 $15,600 $5,800 $3,960 $0 $0 $0 $8,500 $3,115 $12,950 $20,000 $2,400 $900 $2,800 $9,000 $0 $0 $3,726 $0 $0 $30,935 $2,500
$0
$0
$0
$0
$0
$0
$614,170
$614,170
Project:
Line Item:
2. LAWN AREA
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
Pool Terrace Sandwich Slab
1
LS
Metals: Terrace Trellis (ST-1) Cabana Trellis (ST-2) Ornamental Gates (FE-2) Steel Structure at Level 8 Pool Living Living Cabana (ST4) Pool Fencing Landscape/Irrigation Allowance Hot Fluid Applied Rubberized Ashphalt WP Paver and Pedistal System (PV-4) - at fitness balcony Stone Pavers (PV-2) Outdoor Fireplace (SF-2) PV 6 Stone pavers PV7 Precast Concrete pavers Landscaping Planter (PL4) DG Paving (PV-8) Cast Stone Hearth (WL-13) Outdoor Shower (SF-3) Cast Stone Planter Curb (WL10) Cast Stone step curb (WL-5) Runnel Fountain Basin (WL-7) Spa Screen Wall (WL-9) Cast Stone Steps (WL-11) Garden Seat Bench 15 X 24 (WL3) Rainwater Harvesting System 1,000 gal Masonry Garden Wall 42" tall (WL2) Runnel Wall (WL6) Outdoor Bar (SF6) Pool Planters (WL14) Concrete Wall w/cast stone cap (WL14) Outdoor Living Cabanas - small (ST2) Stainless Gas grilles (ST4) Sinks (ST4) Undercounter Refrigerators (ST4) Masonry raised counters w/ granite tops (ST4) Curb Gravel IPE Wood Deck Raised Vegtable Gardens Walls (PL2) Masonry Wall with IPE Wood Cap (WL1) Colored Concrete Paving @ pool deck Plumbing at Amenity Deck
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS
SUB TOTAL
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$62,825.00
$75,000.00 $71,803.00
$2,850.00 $29,830.00 $4,580.00
$15,840.00
$2,180.00 $3,525.00
$30,935.00 $2,500.00
SUB
TOTAL
$0 $62,825 $0 $0 $0 $0 $0 $0 $0 $0 $75,000 $71,803 $0 $0 $0 $0 $2,850 $29,830 $4,580 $0 $0 $0 $0 $0 $0 $0 $15,840 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,180 $3,525 $0 $0 $0 $30,935 $2,500 $0
$0 $62,825 $0 $0 $0 $0 $0 $0 $0 $0 $75,000 $71,803 $0 $0 $0 $0 $2,850 $29,830 $4,580 $0 $0 $0 $0 $0 $0 $0 $15,840 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,180 $3,525 $0 $0 $0 $30,935 $2,500 $0
$301,868
$301,868
Project:
Line Item:
3. ZEN GARDEN
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
Pool Terrace Sandwich Slab
1
LS
Metals: Terrace Trellis (ST-1) Cabana Trellis (ST-2) Ornamental Gates (FE-2) Steel Structure at Level 8 Pool Living Living Cabana (ST4) Pool Fencing Landscape/Irrigation Allowance Hot Fluid Applied Rubberized Ashphalt WP Paver and Pedistal System (PV-4) - at fitness balcony Stone Pavers (PV-2) Outdoor Fireplace (SF-2) PV 6 Stone pavers PV7 Precast Concrete pavers Landscaping Planter (PL4) DG Paving (PV-8) Cast Stone Hearth (WL-13) Outdoor Shower (SF-3) Cast Stone Planter Curb (WL10) Cast Stone step curb (WL-5) Runnel Fountain Basin (WL-7) Spa Screen Wall (WL-9) Cast Stone Steps (WL-11) Garden Seat Bench 15 X 24 (WL3) Rainwater Harvesting System 1,000 gal Masonry Garden Wall 42" tall (WL2) Runnel Wall (WL6) Outdoor Bar (SF6) Pool Planters (WL14) Concrete Wall w/cast stone cap (WL14) Outdoor Living Cabanas - small (ST2) Stainless Gas grilles (ST4) Sinks (ST4) Undercounter Refrigerators (ST4) Masonry raised counters w/ granite tops (ST4) Curb Gravel IPE Wood Deck Raised Vegtable Gardens Walls (PL2) Masonry Wall with IPE Wood Cap (WL1) Colored Concrete Paving @ pool deck Plumbing at Amenity Deck
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS
SUB TOTAL
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$62,825.00
$50,000.00 $71,803.00
$20,745.00
$2,800.00
$12,880.00 $5,700.00
$2,500.00
SUB
TOTAL
$0 $62,825 $0 $0 $0 $0 $0 $0 $0 $0 $50,000 $71,803 $0 $0 $0 $20,745 $0 $0 $0 $0 $0 $0 $0 $2,800 $0 $0 $0 $0 $12,880 $5,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,500 $0
$0 $62,825 $0 $0 $0 $0 $0 $0 $0 $0 $50,000 $71,803 $0 $0 $0 $20,745 $0 $0 $0 $0 $0 $0 $0 $2,800 $0 $0 $0 $0 $12,880 $5,700 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,500 $0
$229,253
$229,253
Project:
Line Item:
4. VEGETABLE GARDEN
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
QTY.
UNIT
Pool Terrace Sandwich Slab
1
LS
Metals: Terrace Trellis (ST-1) Cabana Trellis (ST-2) Ornamental Gates (FE-2) Steel Structure at Level 8 Pool Living Living Cabana (ST4) Pool Fencing Landscape/Irrigation Allowance Hot Fluid Applied Rubberized Ashphalt WP Paver and Pedistal System (PV-4) - at fitness balcony Stone Pavers (PV-2) Outdoor Fireplace (SF-2) PV 6 Stone pavers PV7 Precast Concrete pavers Landscaping Planter (PL4) DG Paving (PV-8) Cast Stone Hearth (WL-13) Outdoor Shower (SF-3) Cast Stone Planter Curb (WL10) Cast Stone step curb (WL-5) Runnel Fountain Basin (WL-7) Spa Screen Wall (WL-9) Cast Stone Steps (WL-11) Garden Seat Bench 15 X 24 (WL3) Rainwater Harvesting System 1,000 gal Masonry Garden Wall 42" tall (WL2) Runnel Wall (WL6) Outdoor Bar (SF6) Pool Planters (WL14) Concrete Wall w/cast stone cap (WL14) Outdoor Living Cabanas - small (ST2) Stainless Gas grilles (ST4) Sinks (ST4) Undercounter Refrigerators (ST4) Masonry raised counters w/ granite tops (ST4) Curb Gravel IPE Wood Deck Raised Vegtable Gardens Walls (PL2) Masonry Wall with IPE Wood Cap (WL1) Colored Concrete Paving @ pool deck Plumbing at Amenity Deck
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS
SUB TOTAL
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$62,825.00
$11,514.00
$95,000.00 $71,803.00 $8,166.00
$10,000.00 $12,880.00
$6,825.00 $14,925.00 $2,500.00
SUB
$0 $62,825 $0 $0 $11,514 $0 $0 $0 $0 $0 $95,000 $71,803 $0 $8,166 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,000 $12,880 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,825 $14,925 $0 $2,500 $0 $0
$296,438
TOTAL $0 $62,825 $0 $0 $11,514 $0 $0 $0 $0 $0 $95,000 $71,803 $0 $8,166 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $10,000 $12,880 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,825 $14,925 $0 $2,500 $0 $0
$296,438
Project:
Line Item:
5. SWIMMING POOL
Estimate #:
2011-Conc
Residential
Line Item Summary UNIT/ DESCRIPTION
Swimming Pool Raised Pool Fountains Heated Pool Spa Integral Pool Fountain Aerator
QTY.
UNIT
2,032 1 89 1 1
sf ls sf ls ls
SUB TOTAL
MATERIAL
Sheet #:
UNIT/
MATERIAL
LABOR
1 of 1
UNIT/
LABOR
SUB
$0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0
$0
$0
$135.00 $30,000.00 $125.00 $30,000.00 $2,500.00
SUB
TOTAL
$0 $274,320 $30,000 $11,125 $30,000 $2,500 $0 $0
$0 $274,320 $30,000 $11,125 $30,000 $2,500 $0 $0
$347,945
$347,945
Regent Square Block D - Existing Apartments to Stay May 31, 2011
Cost Breakdown General Conditions Demolition Earthwork/Asphalt Paving Fencing Structure @ Existing Walkway Replace Existing Elevator Plumbing
50,125 89,685 188,880 142,500 50,000 50,000 25,000 $596,190
Sub total
New - Sales Tax On Material
0 0
Subcontractor Bonds
0
Payroll Tax
Sub total Insurance, Permits, & Fees
$596,190 9,323 $605,513
Sub total Contractor's Contingency Payment & Performance Bonds
18,165 9,995 $633,673 15,842 0
Subtotal Fee
GRAND TOTAL
$649,515
1. Cost above is for work associated with demoltion of existing structures to allow enough parking for apartments on Block D to remain during construction. Full impacts of phasing and material management for construction are being investigated, and will be an add to the budget estimate shown.
1 of 2
Block D Water Meter, Relocate
Parking for Block C Apartments
Relocate Visitor Parking to W. Dallas/Dunlavy. Add security gate and fencing for block C parking
Construction Lay Down Area
Parking Demo Block B Apartments for Block D Parking
Potential for remaining lay-down area
boiler loop issue, must address to demo existing building. Also, will lose elevator.
Parking for Block D
Demo two existing buildings with a total of 12 units, fence existing courtyard and pave and stripe area for ~38 parking spaces
Parking
Add Parking Access
Block D Apartment Power
Demo house and pave for 11 parking spaces Parking for
Block C Apartments