Greystones Harbour – Civil and Maritime Works

Sean Mason, FIEI

2nd May 2013


Contents 1. 2. 3. 4. 5. Images from 1996

2

Contents

History Bid Stage Preferred Bidder Stage Detailed Design Stage Construction Stage


Location

Dublin Greystones

• Design life: 100 years • MHWS/MLWS: 1.5m / -1.5 m OD Malin • Climate change: +0.9 m in 100 years • 100 year return period at 2015 +2.5m OD Malin . Hmo = 4.7 m . Tp = 10.7 s

3

History


Victorian Times

4

History


Developments • Quay Wall Extension • Kish Base • Northern Breakwater

5

History


Coastline

Problems Coastal Erosion

Storm Damage

Old Landfill

1.

Siltation of Harbour

2.

Damage to Breakwaters

3.

6

Coastal Erosion

Storm Damage

Harbour Siltation


Siltation of Harbour

7

History


Damage to Breakwater

• Collapse of Structures • Cavities within Breakwater • Remedial Works

8

History


Coastal Erosion – Railway • Route Selection – Earl of Meath • Isombard Kingdom Brunel • Bray Head – PreCambrian rocks • Tunnels and Bridges

9

History


Coastal Erosion – Railway

10

History


Coastal Erosion – Railway

11

History


Coastal Erosion – Cliffs • • • •

12

Dynamic Coastal ‘Cell’ Erosion Process – waves Erosion Process – rainfall 0.5m/year average retreat

History


[Pictures]

Coastal Erosion – Storm Events • 1929/31 Storms • Houses Lost • Coastal Defences destroyed

13

History


The Power of the Sea [Video Clip]

14

History


The Power of the Sea

15

History


Bid Stage • 1999 - Greystones (and Delgany) Local Area Plan designated site for new Harbour/Marina.  make safe and restore existing harbour,

 Address coastal erosion, and;  provide new major public amenity. • 2001 – Wicklow County Council decision to procure through a PPP model.  230 Berth Marina  360 Residential Units  6,000m² Commercial  16 acre public park  Public Harbour, Public Square  Coastal Protection Works 16

Bid Stage


Public Private Procurement (PPP) Model • 30 year concession period – Design, Construction and Operation • Award of Preferred Bidder status preplanning • EU Public Procurement • WCC provide land, concessionaire provides public amenities • Hand-back to WCC all public space • Significant new facilities for local clubs

17

Bid Stage


Ground Conditions • • • •

Desk Study Ground Investigations Ground Model Made Ground

+10m OD Malin

Laminated Fluvioglacial Sands & Gravels

Beach Shingle 0m OD Malin

-6m OD Malin Brown Boulder Clays varies

Greywacke Bedrock 18

Bid Stage


Reference Design and Outline EIS • • • • •

19

Refurbished Harbour New Marina Landslide Development Public Amenities Coastal Protection

Bid Stage


Bid Design - Layout • Minimizing cut and fill

• Buildings more protected Coastal protection 02 Marina 03 North breakwater 04 Harbour 05 South breakwater 06 Public slipway 07 Coastguard

08 Yacht clubs

20

Bid Stage


Bid Design – Harbour Entrance • •

Simplify geometry (cost) Retain dynamic ‘spending’ beach

Reference design N

21

Bid Stage

Bid design


Wave disturbance in the harbour (1-year storm)


Bid Design – Breakwaters • Height and Width constraints • Structure options:  Embankment  Sheet-piled Cofferdam  Precast Caisson (marine access)  Precast Block • Seaward Revetment

23

Bid Stage


Coastal Protection Existing Situation Scheme Objectives: • Protect landfill and heritage area • Preserve coastal cliff walk • Overall scheme should preserve or enhance amenity value and minimise adverse environmental impact Key Constraint Avoid increased erosion of coastline to north of scheme.

Assumes no interventions to existing coastline

Existing cliff top

Existing beach

Perspective View

24

Bid Stage

Elevation

NTS

Section 1


Coastal Protection Reference Design

Section 1

New cliff top

Engineered slope

Perspective View

25

Bid Stage

Elevation

Rock Revetment

• Highly engineered approach to halt natural process over only part of north beach • Significantly increased erosion forecast over northern section threatening railway and impacting on cliff walk • Complete loss of much of north beach and replacement with an unsightly and inaccessible shoreline, with loss of amenity, natural cliffs and bird habitat • Safety issue with regard to access over and around revetments • Given uncertainty in future maritime conditions a highly engineered approach is not sensible as there is no flexibility in the solution


Coastal Protection Design Development • Solution is to work with nature rather than against it • Managed Retreat solution • More sustainable solution for entire north beach • Landfill protected with revetment and groynes to create recreational beach area • Single beach replenishment will supply material to the coastal system, reducing erosion behind berm and to lesser extent to the north by gradual shingle spread • Existing north beach amenity preserved in its entirety • Subject to detailed design and modelling off shore ‘reefs’ may be added to further reduce erosion over area protected. • Reefs may be visually intrusive at low tide and potential safety issue

26

Bid Stage

Section 1 Showing Beach Replenishment Only

Section 1 Showing Optional Reefs


Coastal Protection Design Development

Existing cliff top

Shingle beach

A: Perspective View Showing Beach Replenishment Only

27

Bid Stage

A: Elevation Showing Beach Replenishment Only


DO NOTHING

Railway

Archaeological Site

Landfill site

MANAGED RETREAT

HOLD THE LINE

Proposed Coastal Protection strategy

28

Bid Stage


Preferred Bidder Stage • Preliminary Design and EIA

• Planning Process • Stakeholder Management • Contractor Input

29

Preferred Bidder Stage


Preliminary Design and EIA • Traffic and Access (Batching Plant) • Protected Views • Ecology (sand-martins and sea-kale) • Archaeology (St. Crispin’s Cell and Rathdown Castle) • Coastal Erosion • Old Landfill • Flooding

30

Preferred Bidder Stage


Planning Process • WCC application to ABP • CPO included in application • Foreshore Acquisition included, Foreshore Lease/License not required • Dredging and reclamation included in application • Oral Hearing in March/April 2006 • Request for Further Information in August 2006. Submitted in October 2006 • 2nd Oral Hearing in March/April 2007 • Planning Granted in August 2007 31

Preferred Bidder Stage


Stakeholder Management – Harbour users • OPW Coastguard Facilities • Greystones Sailing Club (HUGs) • Greystones Rowing Club • Sea Scouts • Ridge Anglers • Diving Club • Moorings Licences • Public (adjoining residents, local area, wider community)

32

Preferred Bidder Stage


Stakeholder Management • Harbour residents with real impacts • Resistance to change – ‘Victorian Feel’ • Giving Public Amenity to Private Interests • GPDA: Greystones Protection and Development Association

• GUBOH: Give Us Back Our Harbour (twitter @guboh)

33

Preferred Bidder Stage


Contractor Input • Construction Methodology (by land) • Programme • Participation in Planning Process • Value Engineering

34

Preferred Bidder Stage


Borrow Pit • Materials Balance • Economics of handling/processing • Granted as part of the planning permission

35

Preferred Bidder Stage


Detailed Design • Planning permission granted August 2007

• Concession Agreement signed December 2007 • Detailed Design:  Breakwater Structures  Harbour & Marina

36

Detailed Design Stage


Design risk: 1. Limited modelling for reference design

2. Hand calculations & limited modelling for bid design

3. Numerical modelling completed 4. Physical modelling (in progress when application made)

5. Hand calculations for revised layout

Bid stage

Planning stage

Detailed design stage


Detailed Design • Sispar appointed Sisk – Lagan JV for ‘Civil and Marine Works Contract’ • Fixed Price D&B Contract (largely designed already) • Arup both Employer’s (Sispar) Representative and Contractor (SLJV) designer!

38

Detailed Design Stage


Breakwaters - Stability • Design for sliding, overturning, settlement

• Granular (porous) base – Goda Equations • ‘Free standing’ Stacks to take out differential settlements • Grout ‘socks’ with in-situ slab

39

Detailed Design Stage


Breakwaters – Physical Modelling • DHI Copenhagen

40

Detailed Design Stage


Flume Tests on Breakwater and Revetment

41

Detailed Design Stage


Design Wave Conditions

42

Detailed Design Stage


Scale Model Testing

43

Detailed Design Stage


Harbour Entrance • Reflected waves – turbulence and water depth • ‘Porous’ roundheads • Uplift pressures – anchor piles Wave disturbance in the harbour: A solid vs a porous harbour entrance

Difference compared to original design

44

Detailed Design Stage


Harbour/Marina Wave Climate • Seiching (reflected standing wave) within Marina

• Sloped revetments around Marina under boardwalk

45

Detailed Design Stage


Breakwater – Design Development • Breakwater crest height • Curved seaward – facing wave-wall • Wider base blocks (with voids to manage weight) • Antifer sizes and underlying rock fill sizes

46

Detailed Design Stage


Breakwater Layout

47

Detailed Design Stage


Civil & Marine Works Contract • Contract signed between Sispar and SLJV

48

Construction Stage


Construction Stage • Demolitions

• Batching Plant • Breakwater Construction • Dredging and Reclamation • Piling Works • Old Landfill • Beaches and Erosion Protection • Value Engineering • Statistics

49

Construction Stage


Demolitions • Pier, Kish base, north breakwater • Gap Bridge (cut-stone retained)

50

Construction Stage


Batching Plant (S.M. Morris) • Agreed early and part of planning as Contractor onboard • Flexibility in materials (concrete) delivery to site • Tolerance on 5m x 3m x 1m blocks of 1mm • Maximised design using pre-cast elements • Continuous environmental monitoring

51

Construction Stage


Breakwater Construction Plan • General Approach – land based operation • Temporary Causeway to allow breakwater construction on 3 fronts • Bed preparation using frames (minimize divers required) • Work out with block stacks, return with slab

52

Construction Stage


Breakwater Settlement

53

Construction Stage


Breakwater Construction - Reality • Issue with leading edge of Temporary Causeway

• Bed preparation – levelling frame and divers • Vulnerability of ‘free-standing’ stacks

54

Construction Stage


Storm Damage • September 2008 • Gusting Force 9 gale • Significant damage over 9 rows of blocks • Temporary support to stacks inadequate • Scour protection around base inadequate

55

Construction Stage


‌ the day after

56

Construction Stage

North breakwater


South Breakwater 57

Construction Stage


Storm Protection • Timber spacer blocks • End-frame • Levelling Frame for 6 stacks • Scour protection slabs • Revetment as close as deemed safe behind

58

Construction Stage


Breakwater Tolerances • • • • •

59

Diver checked formations Precise levelling of bed Diver assisted crane placement of blocks Very tight tolerances on block placement Visual impact (client and architect)


Dredging • Need for floating plant • Temporary load-out quay • Hopper barges for transfer • Machine excavation of boulder clay (GPS on bucket)

60

Construction Stage


Reclamation • Granular below MHWL, cohesive (boulder clays) above

61

Construction Stage


Borrow Pit 62


Landside Earthworks • Marine Works delay impact on sequencing • Compaction of fill • Use of lime on wet • boulder clays

63

Construction Stage


Piling Works • Tubular Steel Piles • Driven to set (+ minimum penetration) • Hydraulic Hammer • Anticipate Driven Precast Piles for buildings

64

Construction Stage


Piling Works

65

Construction Stage


Old Landfill • No CH4, traces CO2, granular curtain • Above water table with porous capping – all mobile containments longsince leached to sea • Risk Assessment to leave in-situ as parkland • Approved by WCC and ABP

66

Construction Stage


Old Landfill

67

Construction Stage


Beaches and Erosion • Where reclaimed, shingle removed for re-use • 10,000m3 imported shingle at start of construction • Predicted movement pattern

68

Construction Stage


Beaches and Erosion • Observed pattern during construction • 6,000m3 accreted shingle relocated in 2009 • 4,500m3 accreted shingle relocated in 2012

69

Construction Stage


70

Construction Stage


Value Engineering Porous Roundheads

71

Construction Stage


Value Engineering Porous Roundheads

72

Construction Stage


Precast Recurve Wall

73

Construction Stage


March 2009 74

Construction Stage


22 January 2010 75

Construction Stage


26 March 2010 76

Construction Stage


13 May 2010 77

Construction Stage


13 May 2010 78

Construction Stage


23 July 2010 79

Construction Stage


22 September 2010

80

Construction Stage


22 September 2010 81

Construction Stage


18 January 2011 82

Construction Stage


Statistics • Concrete Volume 125,000 cu meters, greater than Dundrum SC

• 5,100 breakwater blocks • 3,900 antifers • 90,000 tons of 3-6 ton imported rock armour • 115,000 cu metres dredging /excavation • 203,000 cu metres reclamation fill • Contract Value approx. €50m, €1m over tender • Total spend on development to date circa €70million

83

Construction Stage


Construction Completion Civil & Marine Works contract Started March 2008 Completed Feb 2011

84

Construction Stage


Acknowledgements • Wicklow County Council – Sean Quirke • Employer’s Rep Jacobs (now Leigh Fisher) • Sispar – John Sisks & Park Developments • Sisk Lagan JV (and subcontractors) • Design Team (OMP, Broadway Malyan, Terry Durney) • Subconsultants (COWI, DHI) • Arup Staff (office and site) • Greystones Public Representatives • Greystones people • Jimmy Quinn photography and Derek Paine books 85

Acknowledgements


Thank You

86