Cheryl Brackett, Lead Work Package Engineer, Cianbro Constructors Eric Crivella, Plant Construction Executive, Bentley Systems, Inc.


•  Create $10 million, state-of-the-art Eastern Manufacturing Facility. •  Build and ship 54 prefabricated modules, totaling 9,000 tons of steel and 200,000 lineal feet of pipe. •  The modules average 40-feet-by-40-feet in cross section, about 120-feet long, and weigh up to 700 tons each. •  ConstructSim to visualize and interpret the module, plan construction, and generate parts lists and other information


Materials Management Feasibility Study

Priorities

Priorities

Construction Work Areas

Expedite Install Work to Ready a System for Testing

Work Packs

Turnover Systems Test Packs

Issued

Shop Fab

Track Spools Track Modules Work Complete Location

Work Pack Reports •  Spool List •  Field Matl Issue •  Steel Hang List •  Jobcards

Expediting Reports •  Dwgs Not Released •  Spools Not Fab •  Field Mat’ls Not Onsite

System Reports Pressure Test Record Systems Completion


•  •  •  •  •  •  •  •  •  •  •

PDS 3D CAD Module definition & tracking Isometrics ISO transmittal database Line List Bentley Equipment list CIS/2 & piecemark Fabrication status iTrack on-site & progress Pipe unit rates IMS QA/QC and weld tracking

Jacobs

Cianbro


The VPM is distributed into a shared workgroup environment. User Machine #1

Uses

User Machine #2

A “Master Copy� of the VPM is archived on a server, with local copies resident on the user and data processing machines.

User Machine #3


•  3D Visualization, Interactive Planning & Construction Sequencing •  WorkFace Planning –  Steel and Pipe (fab, install & hydro) Work Packs

•  •  •  •  •

Material & Constraint Analysis Rapid Queries Status Tracking & Progressing Crane Logistics planning Quality Assurance


•  Spool fabrication •  Equipment installation •  ISO release status •  Pipe material availability •  Work step tracking •  Test pack status •  QA/QC status •  Work package constraints




•  Top down management support and bottom up buy in from field supervision is key •  Don’t underestimate the systems integration effort and the learning curve involved –  Start as early in the project as possible

•  VPM Admin role is critical –  Always train a backup Admin

•  Data validation is always a problem •  Changing people & work processes is hard!


•  Improved constructability analysis, interactive planning and coordination between engineering office and site office in using Virtual Plant Model •  Visually plan optimal steel and pipe work crew packages •  Streamline material, equipment & sequencing •  Reduce rework / out-of sequence work •  Speed time to start-up by systems tracking •  Automated task estimates / automate data entry •  Reduce time looking for information via visual monitoring the status of engineering, materials and construction execution progress




•  Had direct comparison data because CIS/2 data was not available for 3 modules •  Steel MTOs – substantially reduced time and human error (shin plates and bolts often get overlooked) •  CSim steel work pack in 4 hours; to do same work pack manually would require 40+ hours •  CSim saved a ton of time, effort and money on the structural steel •  Bottom Line on the Business Case: •  ConstructSim saved Cianbro ~$7M and helped ensure the project Key Performance Indicators of cost, schedule, safety and quality were met!!


If you would like more information contact: Cheryl Brackett

Eric Crivella

Lead Work Package Engineer

Plant Construction Executive

Cianbro Constructors

Bentley Systems

+ 1 207 907 7405

+1 713 249 4407

CBRACKETT@cianbro.com

Eric.crivella@Bentley.com


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.