The Clash Report 2014_Spring Edition

Page 1

2014 THE

clash report spring edition

in this issue •

CADENCE AT UNION STATION

LANE CENTER FOR ACADEMIC HEALTH SCIENCES

THE BROADMOOR WEST

SPECIAL PROJECTS TELLER COUNTY 911 EL POMAR PPHC MUSEUM PENROSE CANCER CENTER START BUS


The Clash Report

CADENCE AT UNION STATION Location: Size: Architect:

Denver, CO 300,000 SF JG Architects

Background

This 13-story, 219-unit, high-end apartment building is located in the Central Platte Valley west of Denver’s Union Station. The projected consisted of one underground level of resident parking, lobby level retail, parking on levels 2-3 and residential units on floors 4-13. A rooftop amenity deck with swimming pools and exercise facilities are included for resident use. The project has been designed and planned to achieve USGBC LEED Gold certification.

Photo: Construction Progress

Field Coordination Drawings

Photo: Sleeve Coordination through foundation

Project Status

The Project was completed on December 31, 2013.

Team

The project team consisted of Superintendants Roger Wieck, Alan Myzer and Mike Littell, Project Manager Todd Raper, Project Engineer Chris Schillinger, and Building System Coordinators Brent Bieker and Joshua Ward

Navisworks Model: MEP/ Structural Coordination


2014

spring edition “...GE Johnson’s (SIG) efforts allowed the design team to focus on conflict and clash detection at a much earlier stage of the construction process when modifications were less impactful to construction schedules and budgets...” -JOHN GAGNON architect Photo: Exterior finishes

(SIG) Services

The Cadence Apartments at Union Station presented many unique challenges and opportunities. From the beginning, the project design was delivered primarily in a 2D format. Only the structural information was given to (SIG) in a 3D format that was of use. (SIG) modeled the architectural information from the construction documents as well as all of the MEP. Fire protection was modeled through Design/Build which provided its own unique challenges throughout coordination. (SIG) also provided the coordination of all the self-performed concrete work. Sleeve coordination and penetrations were issued on documents used by the field team to ensure quality and clarity of installation. Additional coordination of all the post tensioned concrete decks with sleeves and penetrations provided critical coordination around stud rails and PT strands. The MEP coordination process was done in house and then issued to the subcontractors. The subs doing the installation of the systems were new to the 3D BIM coordination process – at times this showed. Though they participated in all coordination meetings and provided useful information to the team in how things would truly be installed, there was still a challenge with quality control and process. Supplemental Documents were provided to these teams in the field by (SIG) and would be utilized on site, whether in the trailer or taped to the walls in the area of work. These documents proved to be useful in assisting those in the field, and all involved, by providing greater clarity. The coordinated field use drawings were then implemented into an official design document. (SIG) provided the backgrounds to which the engineer would later adjust their drawings. The project team was very instrumental in communicating the challenges and resolving them with all parties involved. The process of using the EDM and the Navisworks model simultaneously in the meetings provided an efficient method of documenting and illustrating RFC’s and issues in the field. Working with the Architect, (SIG) was involved in the envelope review. Details were analyzed with product data that was issued to compare the intent of the design with the final buy out. Materials were also analyzed as to how they would connect, ensuring proper protection from water infiltration. Through this process, a design flaw was discovered in a product that was later sent back to the manufacturer to be corrected. Overall, the project was challenging but very rewarding in regards to the coordination. Working together with the design team, (SIG) was able to build a relationship that created a successful project through collaboration. -Joshua Ward Building Systems Coordinator


The Clash Report

lane center

center for academic health sciences Location: Size: Architect: Total Cost:

Colorado Springs 56,000 SF AMD architects 12 Million

Background

Located on the University of Colorado Colorado Springs (UCCS) campus, this 4-level building provides a exible, collaborative, interdisciplinary environment, fostering unique research, in which the sum of all efforts exceeds those of individuals. The Lane Center consists of multiple occupancy groups, all focused on integrated healthcare for the senior population. The building occupants include: CU Aging Center, Gerontology Center, Peak Vista Community Health Centers, CU School of Medicine and selected Beth-El College of Nursing and Health Sciences programs. Core Lab areas will be designed so as to play an important role in developing chance interactions and collaborations among building occupants.

Project Status

The Project was completed on December 31, 2013.

Team

The project team consisted of Superintendant Kirk Sausman, Project Managers Scott Miller and David Eagle, Project Engineer Ryan Kaplanek, and Building System Coordinator Joshua Ward

Coordination Model Overlay

Concrete Lift Drawings: Full coordination of all embeds and sleeves at Elevator Cores

During Construction


2014

spring edition

(SIG) Services

Coordination began early with the creation of Concrete Lift Drawings which were utilized in the field to provide a clearer understanding of all self-performed concrete work done by GE Johnson. Coordination of the sleeves and the embed plates were critical on this complex design, as each pour was unique. Graphics were used in the field and in the jobsite trailer to illustrate the wall pours, and the steel erection sequencing. (SIG) led the efforts in MEPF coordination, working with the subcontractors. The team was able to identify and resolve the majority of the clashes before they were installed in the field. While every effort was made to resolve clashes ahead of time, some items required field coordination, while others needed input from the design team. Technology was an integral part of the project. Electronic Document Management (EDM), iPads, Prolog Converge and other tools were utilized throughout the job. Navisworks was part of the daily meetings and useful in communication with owner and project teams. Having a project team on site capable of utilizing the software was a huge asset to the coordination process as well as the overall success of the -Joshua Ward Building Systems Coordinator project and coordination efforts

“Hey! You showed up to my jobsite without DONUTS !?!”

-Kirk Sausman

Completed Project

[

Photo: Looking down east corridor through reception area. Coordination efforts that translate into reality.

“(SIG) was instrumental in coordinating both mechanical and structural efforts on the UCCS Lane Center Project. Through their efforts, hundreds of clashes were avoided in the field which ultimately led to cost savings due to potential rework, and an overall improved installation efficiency.”

-Ryan Kaplanek Project engineer

]


The Clash Report THE

Broadmoor west

Location: Size: Architect: Total Cost:

Colorado Springs 223,488 SF CSNA Architects 45 Million

Background

This extensive renovation and addition to the western complex of the historic hotel and resort added 28,096 square feet to Broadmoor West, while updating 195,392 square feet. Guestrooms were added to the existing 5th floor, with two entirely new guestroom floors added atop the structure. Additionally, existing guestrooms were renovated, along with the first floor lobby, restaurant and bar. GE Johnson constructed the original Broadmoor West in 1976.

Project Status

The project was completed on May 19th, 2013.

Team

The project team consisted of Senior Superintendant Tim Redfern, Superintendants Dave Pastier, Tony Abernathy, Dale Zerr, Wayne Saiz, Matt Runnels Project Managers Rob Dean and Scott Miller, Project Engineers Tyler Clements, Brian Harley, Sara Reese, Aron Wallin & Dan Martin, MEP Coordinator Pete Kautza and Building System Coordinator David Wilt. MODEL: Egg Rock Coordination

PHOTO: Egg Rock Installation

5/8” TYPE “X” GYPSUM BOARD METAL STUD FRAMING R-11 BATT INSULATION 5/8” EXT. GYPSUM SHEATHING R-5 RIGID INSULATION WEATHER BARRIER 3 COAT STUCCO SYSTEM

METAL CLAD WOOD WINDOW LIGHTGAUGE STUD TRUSS SNOW CLIP

CLAY ROOF TILE SELF ADHERED SHEET WATERPROOFING TREATED PLYWOOD SHEATHING STRUCTURAL METAL DECK

MEPF Coordination through existing hallway

STEEL BEAM WITH SPRAY FIREPROOFING TREATED PLYWOOD SOFFIT

METAL STUD FRAMING 5/8” EXT. GYPSUM SHEATHING 3 COAT STUCCO SYSTEM TREATED WOOD FASCIA PREFINISHED METAL GUTTER METAL DRIP EDGE FLASHING ALUMINUM CLAD WOOD DOOR TRAFFIC COATING ON CONCRETE SLAB 3 COAT STUCCO SYSTEM ON UNDERSIDE OF CONCRETE PREFINISHED METAL FLASHING DECORATIVE METAL GUARDRAIL

Envelope Review

“With the Broadmoor being such a fast paced project, having SIG assist and coordinate in preconstruction and during construction was invaluable. During weekly coordination with the subcontractors and designers SIG helped to eliminate the need for producing RFCs, which took a lot of weight off of the project team. SIG helped in coordinating new systems that were being integrated into existing systems, such as MEP, structural, Eggrock pods and elevators. They also helped in identifying errors or discrepancies that were in the design team’s model saving time and problems down the road. ”

-Brian Harley Project Engineer


2014

spring edition

(SIG) Services

Broadmoor West’s 26-week construction schedule greatly benefited from (SIG)’s coordination efforts. (SIG)’s contributions to this project were primarily concentrated on MEPF coordination, but also included a virtual mockup, brief building enclosure review, drawing QA/QC review, roof truss coordination, prefabricated bathroom pod coordination, and concrete lift drawings. MEPF coordination kicked off approximately 2 months prior to construction, and continued for around 5 months. One of the challenges for this project was verifying existing conditions for all MEPF systems, which we were not able to fully verify until demolition began in early November 2013. Even then, asbestos removal slowed the pace of the demolition. All new systems were laid out virtually on existing floors, requiring additional rework in certain areas once existing conditions were verified. 175 prefabricated bathroom pods provided a much easier coordination effort for MEPF connections. A number of precast panels had to be cored to allow mechanical and fire protection routing to pass through. With a model locating all reinforcing and plates for the panels, (SIG) located all locations where coring was required. The initial design called for an exterior pipe chase running up the west face of the building, then across the roof, for connections to the new construction on the upper floors. The project team requested (SIG)’s assistance in determining whether alternate routing, internally, was possible to allow not only for large cost and time savings, but provide for a more aesthetically pleasing look to the building. (SIG) was able to work with the subcontractors and the structural engineer to provide a reroute that worked. PLAN

3'  3"

Revision:

-David Wilt Building Systems Coordinator

Laundry Shoot Coordination Broadmoor West RenovationPrecast Panels LINEN CHUTE COORDINATION GEJCC−(SIG) Project Number

5613 DTC Parkway, Suite 450 Greenwood Village, CO 80111 Tele: (303) 221−1249 www.gejohnson.com

[

25 North Cascade Avenue, Suite 400 Colorado Springs, CO 80903 Tele: (719) 473−5321 www.gejohnson.com

2013

Structural Steel: Digital Overlay

Videos

MEP/Panel Coordination

1307 Date

12.11.13 Sheet No.

75 El Pomar Road Colorado Springs, Colorado

Z2.1

Site Wall: Digital Overlay

4D animation: https://www.youtube.com/watch?v=N0nW5OQF54A Final Overview: https://www.youtube.com/watch?v=pMsfBG24uHE

]


The Clash Report

Teller County Location: Size: Architect: Total Cost:

911

Colorado Springs, CO 13.200 SF HB&A 3.2 Million

Team

The project team consisted of Superintendant Don Tornquist, Project Manager Jason Berning, Project Engineer Adam Windler, and Building System Coordinator Ken Bracken

(SIG) Services

[

“The GE Johnson SIG Department was a huge asset on the front end of this project. With their help, we were able to find, coordinate, and resolve several “major” clashes with our MEPF trades. This proved to be a huge time saver and made the installation process and subcontractor install coordination much easier.” -ADAM WINDLER Project engineer

]

“SIG was instrumental in working with a budget and providing value to the MEP coordination process at the El Paso/Teller County 911 Dispatch Center Addition in Colorado Springs. The design team provided the base model through the construction documents created in Revit. A coordination meeting was held with the architect, engineers, and the MEP subcontractors. SIG located over 80 clashes allowing us to resolve structural conflicts and above ceiling clearance issues months ahead of the scheduled work. The entire team benefited as the architect and engineers were not inundated with RFCs at the time of installation, MEP subcontractors were setup for an efficient rough-in, and the GE Johnson team could plan beyond the rough-in stage and focus on the finishes.” -Jason Berning Superintendant

Coordination Model

Coordination Model


2014

special projects

El Pomar

PPHC Museum Location: Size: Architect: Total Cost:

Colorado Springs, CO 6.200 SF CSNA Architects 3.1 Million

Team

The project team consisted of Superintendant James Childers, Project Manager Mike Kosters, Project Engineer Brad Densmore, and Building System Coordinator Ann Szynskie

(SIG) Services

Models supplied by the design team and subcontractors were used to coordinate key MEPF systems and were also used in coordinating all penetrations in the precast deck. This process allowed for prefabrication and more efďŹ cient installation of both the MEPF systems and precast structure.

Coordination Model

Precast Desk Penetrations

Coordination Model


The Clash Report

Penrose

Cancer Center Location: Size: Architect: Total Cost:

Colorado Springs, CO 12,400 SF RTA Architects 4.7 Million

Team

The project team consisted of Superintendant Ben Schlick, Project Manager Ashley Fritz, Project Engineer Rachel Lipton, and Building System Coordinator Stephanie Carey

(SIG) Services

SIG performed the typical MEPF 3D coordination on the Penrose Cancer Center by engaging the MEPF subcontractors and using their model in the process. One exception was the mechanical sheet metal subcontractor did not have 3D modeling capabilities so SIG performed modeling of the duct work for the coordination efforts on the project. Once these systems where coordinated, SIG created ďŹ eld use drawing to assist the mechanical sheet metal subcontractor in both fabrication and ďŹ eld installation.

Coordination Model

Coordination Model


2014

Location: Size: Architect: Total Cost:

Jackson, WY 41,995 SF RNL Architects 13.9 Million

special projects

Start Bus

Team

The project team consisted of Superintendant Roger McConaha, Project Manager Jason Berning, Project Engineer Jacob Condon, and Building System Coordinator Ken Bracken

(SIG) Services

3D Revit models were received from the Architect, Structural Engineer, and MEP consultant. SIG compiled these models into a composite model and ran clash detection to determine major constructability issues versus minor ďŹ eld coordination issues. A detailed report of these issues was created and a meeting involving the design team, MEPF subcontractors and GEJCC project team was setup to review the model and the report. The goal of this process was to have one meeting to review all issues and get all major issues on the table for resolution or write RFC’s to get resolution before construction was to begin. To achieve this goal the meeting was held via GoToMeeting/Video conference. This allowed for an interactive meeting for all to see the model and also to be involved in the live discussion. This entire process proved to be valuable in helping both the design team and construction team in correcting issues before they became problems.

Composite Model


The Clash Report

the team The Systems Integration Group (SIG) is a GE Johnson specialty team of nationally recognized leaders in the effective utilization of Building Information Modeling technologies. Unlike our competition, the SIG team was assembled with a singular focus: provide Tangible Value-Added to our project partners. Fundamental to this return is improving the design, construction and communication process.

KEN BRACKEN

JOSHUA WARD

TOM STRAUB

JOHN SCHWARZ

BRENT BIEKER

DAVID WILT

SHANNON ROGERS

Showcase Video 2014

https://www.youtube.com/watch?v=hpvB5qh3t8s


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.