THIRD STREET STREETSCAPE TRAFFIC CORRIDOR STUDY AUGUST 7, 2010
CITY OF COLUMBUS GERMAN VILLAGE SOCIETY
Third Street Streetscape Traffic Corridor Study 1.27.2010
1
acknowledgements
executive summary
Many German Village residents, individuals, committees and
The City of Columbus authorized Kinzelman Kline
City administrators contributed their time and ideas to this
Gossman to prepare the Third Street Corridor Study in
planning effort. The following individuals and groups are to be
early 2009. This study addresses the public right-of-way
recognized for their significant contribution of thoughts, ideas
with a focus on the pedestrian environment. Third Street
and collaboration that were integral to the development of a
was resurfaced with asphalt pavement in 2005 and the
responsive, successful Traffic Corridor Study
City does not intend to re-surface or rebuild the street pavement in the near future. The German Village Society
PROJECT TEAM
German Village Residents
obtained the grant that made this study possible; one of
German Village Society
their primary goals is to restore the street to the historic
German Village Streetscape Committee
brick surface. Resurfacing the street with historic brick
German Village Board of Trustees
pavement must be funded through sources other than the
German Village Commission
Columbus Public Services Department.
Dr. Brian Santin, German Village Streetscape Committee Chair Mark Kelsey, Director of Columbus Public Service Department
This study resulted from a typical planning process with
Tim Bell, Transportation Division, City of Columbus
significant public input throughout the process. Key
Susan Delay, Columbus Department of Development
initial tasks included understanding the German Village
Gary Wilfong, Columbus Transportation Division Project Manager
community vision for the Third Street Corridor and
Cristina Parady, Columbus Utility Coordinator
conducting a thorough review of the historic archival material to understand the historic streetscape conditions.
design team
This was followed by an assessment of the physical
Kinzelman Kline Gossman, project lead, corridor design and
conditions. Preliminary concepts were generated to test
planning
various strategies for the physical development of the
Chambers, Murphy & Burge, historical appropriateness
corridor. The best ideas were further developed into the
Prime Engineering, site base preparation
final preferred Third Street Corridor Concept described in this document. The design team researched potential funding sources available through grants and other programs to assist the implementation of the project. An implementation strategy was generated, including phasing and preliminary budgets for each phase of work.
Third Street Streetscape Traffic Corridor Study 1.27.2010
FIND IT
table of contents Historical precedents ..............................................1
Sustainable.....................................................34
Urban Assessment
Composite Concept.........................................35
Building Density.................................................4
Key Areas
Building Heights................................................4
Livingston Gateway..........................................37
Building/Land Uses............................................5
Commercial District.........................................43
Circulation................................................5
Village Green.................................................49
Village Districts..................................................6
Residential District / Schiller Park Gateway........54
Existing Conditions............................................7
Implementation Strategy
Existing Utilities..................................................8
Phasing/
German Village Vision .................................................9
Budgets..................................................................60
Third Street Corridor Vision.........................................13
Funding Sources.............................................71
Corridor Concept.....................................................15
Next Steps......................................................79
Streetscape Components
Appendix
Roadway........................................................19
Composite Plan..............................................81
Sidewalks.......................................................23
Historical Photography.....................................82
Utilities..........................................................26
Early Concepts & Studies.................................86
Lighting.........................................................29
Private Development Recommendations............88
Plantings........................................................30
Furnishings...................................................32
Signage.........................................................33
Third Street Streetscape Traffic Corridor Study 1.27.2010
3
HISTORICAL PRECEDENT
Third Street Streetscape Traffic Corridor Study 1.27.2010
4
Historical Setting German Village is listed on the National Register of Historic Places and is also designated as a Preserve-America neighborhood. It was and continues to be characterized by narrow brick streets and homogeneous brick architecture. The Third Street Corridor has retained many of its historic attributes: a 47’ pavement width, lack of setbacks for structures, stone curbs, tidy private gardens, primarily residential use with scattered businesses and civic uses. The street was originally paved with brick; the parking lanes remained brick until the 1990’s. Key features of the Third Street Corridor that need to be protected include: • The street width and curb location; localized adjustments for traffic calming purposes are acceptable. • The existing historic brick contained within the asphalt pavement profile must be protected. • If funding becomes available, the historic brick should be reset to re-establish the historic street pavement. • New curbs should be stone curbs to match the existing. • The sidewalks should be re-surfaced with brick. • Brick should be laid to replicate the existing patterns. • Pavements, landscaping and hardscape features should be designed to retain the eclectic nature of the corridor.
Third Street Streetscape Traffic Corridor Study 1.27.2010
5
URBAN ASSESSMENT
Third Street Streetscape Traffic Corridor Study 1.27.2010
6
Building Density
LIVINGSTON
LIVINGSTON
The density and building placement contribute greatly to
Key LIVINGSTON
1-Story
Key 1-
2-Story
the historic feel and charm of the streetscape
2-
3-Story
3-
The density and building sizes are fairly consistent for the length of the corridor; minor variations contribute to the human scale and feel of the corridor.
BECK
BECK
BECK
Building Height Building heights range from one to four story structures The majority of the structures are one and a half or two
SYCAM
SYCAM
ORE
ORE SYCAM
ORE
stories.
FR
FRANK
RT ANKFO
U KOSS
FRANK
KOSS
TH
I WHITT
FORT
UTH
WHITT
ER
KOSS
Figure Ground
WHITT
IER
LER SCHIL R PA K
LER SCHIL P A RK
Building Height
Building Heights Third Street Streetscape - Traffic Corridor Study Third Street Streetscape - Traffic Corridor StudyBuilding Heights Third Street Streetscape - Traffic Corrid
Third Street Streetscape Traffic Corridor Study 1.27.2010
UTH
IER
LER SCHIL P A RK
Building Density
FORT
7
Building / Land Use
Key LIVINGSTON
The predominant land use along Third Street is residential Secondary land uses include office, commercial and institutional
Circulation
BECK
BECK
Key
Key
L I V I N G S T O NCivic
Civic
LIVINGSTON
Office
Office
Retail
Retail
Residential
Residential
Open Space
Open Space
Parking Lot
Parking Lot
BECK
LIVINGSTON
Key Vehicular Circulation
Vehic Circu
Pedestrian Circulation
Pede Circu
Traffic Light
Traffi
Bus Stop
Bus S
BECK
Third Street is the primary north/south vehicular spine of
Existing Street Parking Spaces Existing Stree
German Village
approx. 215
approx. 215
Traffic signals at Livingston Avenue and Whittier Street Third Street is two way traffic with parallel parking on both
SYCAM
ORE
SYCAM
ORE
SYCAM
ORE
SYCAM
ORE
sides Most side streets that intersect Third Street are two-way traffic
FRANK
FORT
FRANK
FORT
FRANK
FORT
FRANK
FORT
Small parking lots feed into Third Street at the north end of the corridor Transit stops for COTA and buses for St. Mary’s school are
KOSS
UTH
KOSS
UTH
KOSS
UTH
KOSS
located along the corridor
UTH
Existing on-street parking is approximately 215 spaces WHITT
IER
WHITT
IER
LER SCHIL P A RK
Building / Land Use Land Use
Land Use
WHITT
IER
IER
LER SCHIL P A RK
LER SCHIL K R A P
LER SCHIL K R A P
Circulation
- Traffic Corridor Study- Traffic Corridor Stu Third Street Streetscape TrafficStreetscape Corridor Study Third-Street -Circulation Traffic Corridor Study Circulation Third Street StreetscapeThird Street Streetscape
Third Street Streetscape Traffic Corridor Study 1.27.2010
WHITT
8
RE
•Anomaly in streetscape character Commercial District Commercial District •Consistent high density on west side of street •Gaps in building frontage and density on • in building and density •Gaps Building frontage frontage breaks down on easton side north endO R E M A C S Y •Only surface parking lots along the corridor north end of street
LIVINGSTON
LIVINGSTON
(8 lots) •More generous front and side yards •Two 1-story structures & eight 3-story
• parking along the corridor •Only Largesurface setbacks for St. lots Mary’s, outdoor (8 lots) structures out of 81 courtyards and other yards •22 parcels contain office, commercial or • generous front and side3-story yards •More One 1-story structures & four civic uses
BECK
KFOR
T
•Two 1-story structures structures out of 23 & eight 3-story structures out of 81 • 6 parcels contain office, commercial or civic T R O F •22 FRANK usesparcels contain office, commercial or “Village Green” uses are residential •civic 55 parcels •Anomaly in streetscape character 27 parcels are residential •Consistent high density on • west side of street pedestrian • Significant activity •27 parcels are residential
SYCAM
ORE
•Building frontage breaks down on east side of street
OSSU
TH
KOSS
WHITT
KFOR
structures out of 23 •6 parcels contain office, commercial or civic uses UTH
•Consistent building frontage, scale and use S K OareS residential •55 parcels •Structures are predominately placed on “Village Green” •Significant pedestrian activity ROW •Anomaly in streetscape character •Zero 1-story structures & one 3-story Residential District •Consistent high density on west side of street •Consistent building frontage, scale and use structures out of 44 •Structures are predominately placed on •Building frontage breaks down on east side ROW •5 parcels are office or commercial use street 3-story •Zero 1-story structures & oneof •39 parcels are residential structures out of 44 •Large setbacks for St. Mary’s, outdoor •5 parcels are office or commercial use •39 parcels are residential and other yards ER I courtyards WHITT •One 1-story structures & four 3-story
UTH
IER WHITT
•Anomaly in streetscape character •Consistent high density on west side of street •Building frontage breaks down on east side of street •Large setbacks for St. Mary’s, outdoor courtyards and other yards •One 1-story structures & four 3-story structures out of 23 •6 parcels contain office, commercial or civic uses 17 parcels are residential •55 •Significant pedestrian activity
Residential District
FORT
FRANK
RE
•Large setbacks for St. Mary’s, outdoor courtyards and other yards •One 1-story structures & four 3-story
“Village Green”
IER
T
Residential District •Consistent building frontage, scale and use •Structures are predominately placed on ROW •Zero 1-story structures & one 3-story structures out of 44 •5 parcels are office or commercial use •39 parcels are residential
structures out of 23 •6 parcels contain office, commercial or civic Third Street Streetscape - Traffic Corridor Study LER uses SCHIL P A RK Third Street Streetscape Traffic Corridor Study •55 parcels are residential LER SCHIL R PA K
Village Districts District Zones
rict Zones
LER SCHIL P A RK
1.27.2010
Third Street Streetscape - Traffic Corridor •Significant pedestrianStudy activity
9
Pavement
Key
Approximately 50 percent of the sidewalk pavement is
LIVINGSTON
Brick Pavement
LIVINGSTON
brick and the other half is concrete
Key
Key
Key
Brick Pavement
Brick Pavement
Brick Paveme
Street Tree
Street Tree
Street Tree
Street Tr
Crosswire
Crosswire
Crosswire
Crosswi
Architectural Landmarks
Architec Landma
Open Yard
Open Y
LIVINGSTON
Areas of both brick and concrete pavement are in poor
Architectural Landmarks
conditions and are a danger to pedestrians
Architectural Landmarks
Open Yard
Open Yard
FR
RT ANKFO
Brick pavement consists of a variety of different paver types, colors and patterns, including herringbone, running bond and basketweave
Trees There are numerous street trees of varying species and in varying conditions
BECK
BECK
BECK
KOSS
UTH
The street tree are located on an irregular spacing with large areas of sidewalk having no trees at all
Utility Lines There are approximately 70 utility lines that cross Third Street WHITT
Utility poles are wooden and many are not plumb Street lights are attached to the poles along the east side
SYCAM
ORE
SYCAM
ORE
SYCAM
IER
ORE
of the street only
LER SCHIL P A RK
Existing Conditions - Northern Half
Existing Conditions - Southern Half
Landscape Features Landscape Features Features Third Street Streetscape - Traffic Study Third Street Streetscape - Traffic Study- Traffic Corridor Stu Third StreetCorridor Streetscape - Landscape Traffic Corridor Study Landscape Features Third StreetCorridor Streetscape
Third Street Streetscape Traffic Corridor Study 1.27.2010
10
Existing Utilities
Telecommunications
City of Columbus Department of Public Utilities: Division of Sewers & Drainage -Inventory: -Combined Storm/Sanitary Main Line -Storm Inlets: 33 and Manholes: 17. -Size: Main Combined Storm/Sanitary Lines: 24”-48” -Clearance: 1’ Vertical (5’ if brick) and 3’ Horizontal (10’ if brick) -Depth: Varies from 6’-15’
MELP
AEP
Storm/Sanitary Main Storm/Sanitary Clearance
Gas Main
City of Columbus Department of Public Utilities: Division of Water -Inventory: -Main Water Line -Fire Hydrant: 10 -Size: Main Water Line: 6” -Clearance: 1’ Vertical and 3’ Horizontal
Gas Clearance
Water Main Water Main Clearance
Gas Main Gas Clearance
City of Columbus Department of Public Utilities: Division of Power -Inventory: -MELP owned and operated poles within Third St ROW: 28 (+10?) -MELP owned and operated Transformers within Third St ROW: 12 AEP: American Electric Power -Inventory: -AEP owned and operated poles within Third St ROW: 33 -AEP Transformers within Third St ROW: 16 Columbia Gas -Inventory: -Main Gas Line along both East and West Sidewalks -Size: Main Gas Line: 3” -Clearance: 1’ Vertical and 3’ Horizontal Telecommunication Companies -Time Warner -ATT Ohio (formerly SBC) -WOW
Third Street Streetscape Traffic Corridor Study 1.27.2010
11
RESIDENTS’ VISION
Third Street Streetscape Traffic Corridor Study 1.27.2010
12
The following ideas were generated by the German Village Society, residents and the design team during the Corridor Walk-through and the Visioning Session. General 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22.
A celebrated, vibrant downtown neighborhood- historic integrity - a charming, pedestrian-friendly streetscape Balance a more pedestrian friendly street with the historic character Third Street should accommodate Oktoberfest German Village as the #1 tourist destination in Central Ohio Enhance the gateway at Livingston Avenue and Schiller Park Explore options for something like Worthington’s summer market Current interesting individuality & diversity should be preserved Don’t turn Third Street into Disney Main Street… be careful not to be too sterile Address the historic Gothic Revival Church of St. Mary’s as the defining landmark of the street The Schwartz Castle is a landmark, which could become part of the Gateway Explore methods to increase the available parking without increasing pavement Explore putting angled parking in certain, more commercial areas along Third Street. Favor the pedestrian environment over vehicles, if a choice must be made. Sidewalks must be ADA accessible the entire length of the corridor. Identify and address major crossings along Third Street that should have crosswalks Resolve safety issues for dangerous intersections (Beck and Third). Explore curb extensions Explore mid street traffic calming Address high speed traffic Consider COTA bus stops and routes as part of overall design Re-grade curb ramps where needed to eliminate buildup of mud and debris. Explore variations of width of Third Street, curb-to-curb.
Third Street Streetscape Traffic Corridor Study 1.27.2010
13
Pavements/Materials 23. 24. 25. 26. 27. 28. 29. 30. 31. 32. 33.
Make Third Street all brick again. Brick at the intersections to enhance traffic calming and announce the pedestrian zone Explore long-term options for providing brick parking lanes Explore historic, aesthetic and traffic calming effects of brick streets Provide stone curbs and brick pavement in the street and sidewalks Restore the appropriate elevation of the stone curb Replace the brick where it was taken out when the new curb ramps were installed. One should know German Village by its high quality materials and charming environment The residents do not want concrete or asphalt pavement Maintain the same scale, proportions and materials of the surrounding predominant architecture. Brick seems to be the unifying element in the diverse German Village
Utilities 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45. 46. 47.
Bury all utilities Explore options to remove cross-wires and any unnecessary lines Short term, can the utility poles be straightened or the material changed? Possibly use taller, metal poles so that fewer poles are needed and wires are higher and out of view. Explore if the utility lines can be moved to the rear of properties Solve the drainage issues and diminish maintenance costs to the City Provide better street lighting that addresses both sides of the street for safety. Explore using pedestrian scale lights and eliminating the traditional tall street lights. Sidewalks need to be better lit, using a pedestrian scale light. Address the combined sewer that runs through Third Street as much as this project will permit. Consider long-term streetscape solutions for utilities, drainage, materials and so on. Pedestrian lamps reminiscent of the cast iron gas lamps are desired. There are still some remains of cast stone storm sewer inlet installed at the curb. Some of them dated to . Keep the design elements of this drainage system because of its historic significance.
Third Street Streetscape Traffic Corridor Study 1.27.2010
14
Landscape Features 48. 49. 50. 51. 52. 53. 54. 55. 56. 57. 58. 59. 60. 61. 62.
Establish a minimum acceptable level of richness of materials, details and plantings Discourage turf grass in R.O.W. Place benches in the public R.O.W. so people feel comfortable sitting in them. Provide guidance on acceptable methods for tree plantings to prevent root upheaval. Address portions of the corridor that lack streetscape and pedestrian amenities. Strengthen the edge between the public and private property to maintain the scale and density of the corridor. Prevent successive properties from having a break in fencing/building frontage to preserve the historic urban character. Maintain the variety and diversity of brick patterns, details and plantings to maintain the charm of German Village. Organize magazine and newspaper stands and locate at strategic points. Group post office boxes and benches to encourage community. Provide opportunities for residents to hang plants and banners from new pedestrian lights Establish appropriate locations for bike racks throughout the corridor. Place street trees sporadically and with different species. Consider eliminating street trees in front of commercial properties to be true to the historic character Incorporate historic hitching posts, columns and limestone stepping stones to the extent possible.
Signage 63. 64. 65. 66. 67.
Reduce the amount of directional and regulatory street signage along Third Street. Change the appearance to minimize the visual impact. Explore unique street signage for German Village. Consider putting street signage on the side of buildings. Minimize the visual clutter at the Livingston gateway GVS Guidelines should be recognized but not perceived as confining the streetscape design.
Third Street Streetscape Traffic Corridor Study 1.27.2010
15
CORRIDOR VISION
BALANCE
create a between contemporary function and historic integrity
Third Street Streetscape Traffic Corridor Study 1.27.2010
16
SAFETY
HISTORIC CHARACTER
FUNCTIONALITY
4 requirements to ensure
balanced design safety historic character functionality sustainable community
SUSTAINABLE COMMUNITY
Third Street Streetscape Traffic Corridor Study 1.27.2010
17
CORRIDOR CONCEPT
ECLECTIC: a range of patterns and colors of brick, plantings, and other furnishings DISTRICTS: commercial and residential VILLAGE GREEN: celebration of open space COMMUNITY: a thriving, urban community Third Street Streetscape Traffic Corridor Study 1.27.2010
18
Intersections & Gateways
Districts
Composite LIVINGSTON
KEY
AVENUE
KEY
KEY COMMERCIAL DISTRICT
GATEWAY
VILLAGE GREEN MAJOR INTERSECTION
BLENKNER
STREET
HOSTER
STREET
BECK
STREET
COMMERCIAL DISTRICT VILLAGE GREEN
RESIDENTIAL DISTRICT
RESIDENTIAL DISTRICT
MINOR INTERSECTION
*
*
*
GATEWAY WILLOW
STREET
BUS STOP
SYCAMORE
STREET
STIMMEL
STREET
FRANKFORT
STREET
*
*
MAJOR INTERSECTION
MINOR INTERSECTION
*
BUS STOP
Precepts
• Retain eclectic character. COLUMBUS
• Celebrate the corridor with gateways.
STREET
• Distinguish major intersections with
*
*
KOSSUTH
LANSING
STREET
WHITTIER
STREET
CONCORD
PLACE
REINHARD
Third Street Streetscape Traffic Corridor Study 1.27.2010
STREET
*
*
curb extensions. • Commercial District: fewer street trees, more pavement. • Village Green: visually ‘borrow’ the open space for community. • Residential District: more green, tree lawns
AVENUE
19
Utility Corridors
Street Trees
Composite LIVINGSTON
KEY
AVENUE
KEY
KEY
OVERHEAD UTILITIES
SIGNIFICANT TREES TO REMAIN
UNDERGROUND UTILITIES
PROPOSED TREES
BLENKNER
STREET
HOSTER
STREET
BECK
STREET
OVERHEAD UTILITIES UNDERGROUND UTILITIES SIGNIFICANT TREES TO REMAIN PROPOSED TREES
WILLOW
STREET
SYCAMORE
STREET
STIMMEL
STREET
FRANKFORT
STREET
Precepts • Clean up and eliminate visual utilities COLUMBUS
STREET
where possible. • Retain existing trees that are healthy and have reasonable life spans.
KOSSUTH
STREET
LANSING
STREET
WHITTIER
STREET
CONCORD
PLACE
REINHARD
AVENUE
Third Street Streetscape Traffic Corridor Study 1.27.2010
• Tree planting varies per district.
20
STREETSCAPE COMPONENTS
-Roadway -Sidewalk -Utilities -Lighting -Plantings -Furnishings -Signage Third Street Streetscape Traffic Corridor Study 1.27.2010
21
ROADWAY MATERIALS
Three options of roadway materials
brick
asphalt
brick parking lanes and asphalt travel lanes
ASPHALT
SPLIT
BRICK
Third Street Streetscape Traffic Corridor Study 1.27.2010
22
ROADWAY
HISTORIC CURBS
Maintain existing curb layout between all major intersections
maintain historic road width
replace with stone curbs
reestablish full height curbs
+/- 46’
Third Street Streetscape Traffic Corridor Study 1.27.2010
23
ROADWAY
CURB EXTENSIONS
Provide curb extensions at all major intersections
safer pedestrian crosswalks
protection to on-street parking spots
broaden cone of vision for stopped traffic at cross streets
6’ 34’ 6’
Third Street Streetscape Traffic Corridor Study 1.27.2010
24
enhance pedestrian travel
PARKING
BIKE LANE
encourages an active lifestyle
CAR LANE
CAR LANE
calm traffic by narrowing the width of the travel lanes
BIKE LANE
MULTI-MODAL
PARKING
ROADWAY
Promote multiple modes of transportation
9’
Third Street Streetscape Traffic Corridor Study 1.27.2010
4’
10’
10’
4’
9’
25
walkway zone generally provides an 8 foot wide path free of objects and meets ADA standards
amenity zone includes all furnishings, lights, and signs
clear zone allows for the people to move between their car and the amenity zone AMENITY ZONE CLEAR ZONE
ZONES
WALKWAY
SIDEWALK
The sidewalk has three primary zones
+/-8’
5’
2’
Third Street Streetscape Traffic Corridor Study 1.27.2010
26
SIDEWALK MATERIALS
Sidewalk materials:
brick sidewalks with varying patterns
reuse existing brick when possible
variety of colors that matches the existing brick
match textures and styles of the existing brick
match or maintain existing patterns of brick
Third Street Streetscape Traffic Corridor Study 1.27.2010
27
SIDEWALK
ACCESSIBILITY
Maximize the accessibility along the entire corridor
follow ADA guidelines to ensure accessibility to all pedestrians
provide curb ramps at all intersections
provide a smooth surface
design a consistent cross slope across sidewalk
Third Street Streetscape Traffic Corridor Study 1.27.2010
28
UTILITIES EXISTING
Existing utilities
overhead utility lines crisscross the street and clutter the environment
other utilities run below the pavement and parallel to the curb
Third Street Streetscape Traffic Corridor Study 1.27.2010
29
UTILITIES OVERHEAD OPTION 1
Overhead utility lines
consolidate overhead wires and eliminate cross wires
provide fewer, taller metal poles to reduce visual clutter
eliminate all signs and lights from utility poles
Third Street Streetscape Traffic Corridor Study 1.27.2010
30
UTILITIES OVERHEAD OPTION 2
Below grade utility lines and transformer vaults
bury all overhead utilities underneath street
bury transformers within vaults at curb extensions as needed
Third Street Streetscape Traffic Corridor Study 1.27.2010
31
LIGHTING PEDESTRIAN ROADWAY MAST ARMS
General characteristics of the lighting design
provide even light distribution to increase visibility
black poles and fixtures with appropriate character: recommend City standard fixtures
accessorize light poles with banners and hanging baskets
all pedestrian lights preferred; or provide roadway lights on one side of street, pedestrian lights on the pother side
Third Street Streetscape Traffic Corridor Study 1.27.2010
32
PLANTINGS
LANDSCAPE BEDS
General characteristics of the landscape beds
raised stone curbing around proposed trees
flush planters around existing trees
tree lawn south of Kossuth Street
plant low groundcovers and perennials in all tree planters
EXISTING
PROPOSED
TREE LAWN
Third Street Streetscape Traffic Corridor Study 1.27.2010
33
PLANTINGS
STREET TREES GROUNDCOVERS PERENNIALS
General characteristics of the plant palette
street trees: urban tolerant, high canopy, and seasonal color
groundcovers: low, evergreen, and salt tolerant
perennials: array of seasonal colors and textures
Third Street Streetscape Traffic Corridor Study 1.27.2010
34
FURNISHINGS SEATING BIKE RACK WASTE/RECYCLING NEWS CORRALS
General characteristics of the furnishing design
furnishings should compliment historical context
durable furnishings with black finish
family of benches, waste/recycling receptacles, and bike racks
historic remnants
Third Street Streetscape Traffic Corridor Study 1.27.2010
35
SIGNAGE
INFORMATIONAL DIRECTIONAL REGULATORY
General characteristics of the signage design
family of signs distinct to Third Street
pick up on traditional German Village symbols and colors
simplify signs and posts
Third Street Streetscape Traffic Corridor Study 1.27.2010
36
SUSTAINABLE GREEN INFRASTRUCTURE
General characteristics of the sustainable design
recycle/reuse of material
use of local/regional materials
promote walkability and community
green methods to treat stormwater quality
Detain water in planters Brick Sidewalk
Drainage
Drainage
Third Street Streetscape Traffic Corridor Study 1.27.2010
37
COMPOSITE COMPOSITE CONCEPT
Third Street Streetscape Traffic Corridor Study 1.27.2010
38
1
2 3
4
KEY AREAS 1 Livingston Gateway 2 Commercial District 3 Village Green 4 Residential District / Schiller Park Gateway Third Street Streetscape Traffic Corridor Study 1.27.2010
39
LIVINGSTON GATEWAY LIVING STON AVEN UE
-Brick Piers -Flush Brick Intersection
COLDWELL BANKER
-Simple, Elegant Materials
KATZINGER’S DELI
-Mast Arms
Third Street Streetscape Traffic Corridor Study 1.27.2010
40
LIVINGSTON GATEWAY
-Expanded Dining -Variety of Paving Patterns -Brick Crosswalks Mast Arm Planters
Outdoor Dining
Plant Bed News Corral
Third Street Streetscape Traffic Corridor Study 1.27.2010
41
LIVINGSTON GATEWAY
LIVING STON AVEN UE
-Asphalt Street Option
COLDWELL BANKER
KATZINGER’S DELI
-Flush Brick Intersection
Third Street Streetscape Traffic Corridor Study 1.27.2010
42
LIVINGSTON GATEWAY
SIDEWALK
CURB EXTENSION
BIKE LANE
ROADWAY
BIKE LANE
CURB EXTENSION
Third Street Streetscape Traffic Corridor Study 1.27.2010
SIDEWALK
43
LIVINGSTON GATEWAY
Third Street Streetscape Traffic Corridor Study 1.27.2010
44
LIVINGSTON GATEWAY: ASPHALT OPTION
Third Street Streetscape Traffic Corridor Study 1.27.2010
45
COMMERCIAL DISTRICT
-Trees and Perennials in Planters -Maintain Significant Trees -More Random Tree Planting -Enhance Visibility
STARBUCKS
SYCA MORE STREE T
Third Street Streetscape Traffic Corridor Study 1.27.2010
46
COMMERCIAL DISTRICT
Bus Shelter
Bench
-Transit Stop Enhances Community:
-News Corrals
-Post Office Box
Planter Bed Litter Receptacle
-Benches
Informational Sign
Third Street Streetscape Traffic Corridor Study 1.27.2010
47
COMMERCIAL DISTRICT
-Asphalt Street Option
STARBUCKS
SYCA MORE STREE T
Third Street Streetscape Traffic Corridor Study 1.27.2010
48
COMMERCIAL DISTRICT
SIDEWALK
PARKING
BIKE LANE
ROADWAY
BIKE LANE
PARKING
Third Street Streetscape Traffic Corridor Study 1.27.2010
SIDEWALK
49
COMMERCIAL DISTRICT
Third Street Streetscape Traffic Corridor Study 1.27.2010
50
COMMERCIAL DISTRICT: ASPHALT OPTION
Third Street Streetscape Traffic Corridor Study 1.27.2010
51
VILLAGE GREEN
SAINT MARY’S CHURCH
-German Village “civic” area -Open Lawn Area -Private Ownership
SAINT MARY’S ELEMENTARY SCHOOL
-Semi-Public Use -Visual Open Space
Third Street Streetscape Traffic Corridor Study 1.27.2010
52
VILLAGE GREEN SAINT MARY’S CHURCH
-Asphalt Option
SAINT MARY’S ELEMENTARY SCHOOL
Third Street Streetscape Traffic Corridor Study 1.27.2010
53
VILLAGE GREEN
SIDEWALK
PARKING BIKE LANE
ROADWAY
BIKE PARKING LANE
SIDEWALK
Third Street Streetscape Traffic Corridor Study 1.27.2010
VILLAGE GREEN
54
VILLAGE GREEN
Third Street Streetscape Traffic Corridor Study 1.27.2010
55
VILLAGE GREEN: ASPHALT OPTION
Third Street Streetscape Traffic Corridor Study 1.27.2010
56
RESIDENTIAL DISTRICT & SCHILLER PARK GATEWAY CONCORD PLACE
-Tree Lawns -More Street Trees -More Residential -More Green Transitions to the Park
REINHARD STREET
SCHILLER PARK
Third Street Streetscape Traffic Corridor Study 1.27.2010
57
RESIDENTIAL DISTRICT & SCHILLER PARK GATEWAY
CONCORD PLACE
-Asphalt Option
REINHARD STREET
SCHILLER PARK
Third Street Streetscape Traffic Corridor Study 1.27.2010
58
RESIDENTIAL DISTRICT & SCHILLER PARK GATEWAY
FRONT YARD
SIDEWALK
PARKING
BIKE LANE
ROADWAY
BIKE LANE
Third Street Streetscape Traffic Corridor Study 1.27.2010
PARKING
SIDEWALK
59
RESIDENTIAL DISTRICT & SCHILLER PARK GATEWAY
Third Street Streetscape Traffic Corridor Study 1.27.2010
60
RESIDENTIAL DISTRICT & SCHILLER PARK GATEWAY: ASPHALT OPTION
Third Street Streetscape Traffic Corridor Study 1.27.2010
61
BUILD IT
STRATEGY
develop a that will enable the implementation of the streetscape to occur either as a single, large project; or as a series of smaller projects, over time, to respond to funding opportunities
Third Street Streetscape Traffic Corridor Study 1.27.2010
62
PHASING / BUDGETING
Survey
Geotechnical Investigation
Preliminary Engineering
This Traffic Corridor Study is the first part of an extensive design and documentation process that must be completed before any construction can actually begin. The next steps that must be budgeted for and executed are a survey and Preliminary Engineering. The Columbus Division of Transportation has indicated that the soft costs for this project should be in the range of 10% to 14% of the construction value; including survey, geotechnical investigations, preliminary and final engineering, and permits
Re-assess Budgets and Project Phasing
Final Engineering
This Traffic Corridor Study has been prepared using available base maps and record documents to determine the locations of utilities and other physical features This information is reasonably accurate; sufficient for a high level planning document such as this. An actual survey that includes topography, easements, underground and overhead utilities and all physical features must be procured before Preliminary Engineering can begin. Preliminary Engineering is a much more detailed design and engineering exercise. It will be valid to the extent that current, accurate survey information serves as the basis for those activities. The Preliminary Engineering will also require the collection and assessment of geotechnical information about the conditions of the existing soils and base materials. Preliminary engineering will address the corridor as a whole. Sufficient information will be developed during this phase of work to generate more detailed and precise estimates of probable construction costs. The potential phasing of the project can then be re-evaluated and fund-raising can be targeted to better-defined projects and capital costs. The Final Engineering can be performed for the entire corridor or broken down by phase.
Fund Raising
Fund Raising
Phase One Construction
Future Phased Construction
Third Street Streetscape Traffic Corridor Study 1.27.2010
Final Engineering
63
Reinhard
Whittier
Kossuth
Frankfort
Sycamore
Beck
Livings
This page outlines a conventional phasing strategy that accomplishes complete sections of the Third Street corridor over time. A major benefit of this strategy is that the streetscape environment is completed, albeit in only a portion of the Third Street Corridor. This would demonstrate the benefits of the upgrades and potentially could enhance fund-raising efforts. Certain features of the proposed streetscape enhancements are challenging to implement in a piecemeal fashion: especially grading and utilities. There would likely be additional costs incurred to provide temporary transitions to fit the new systems into the existing conditions.
ton
PHASING / BUDGETING
These preliminary budgets are order-of-magnitude estimates of likely costs and are based on the limited information available at the time of this design study. The budgets are based on 2010 construction costs and include a modest design contingency. These budgets should be updated when Preliminary Engineering is conducted and actual survey information is available. The estimated probable cost of the construction for the Corridor will range between $7.8M and $10M. If the utilities are all buried underground and the street is rebuilt with brick, the overall cost will increase to $23.6M to $26.9M. The cost breakdown for this phasing strategy is as follows: Base Project With Upgrades Livingston Gateway $550,000 - $650,000 Livingston to Sycamore $2.5M to $3.2M $8.0M to $9.1M Sycamore to Kossuth $2.5M to $3.2M $8.0M to $9.1M Kossuth to Reinhard $2.1M to $2.7M $6.8M to $7.8M Reinhard Gateway $250,000 to $300,000
Livingston Gateway
Livingston Gateway to Sycamore Avenue
Sycamore Avenue to Kossuth Avenue
Third Street Streetscape Traffic Corridor Study 1.27.2010
Kossuth Avenue to Reinhard Gateway
Reinhard Gateway
64
PHASING / BUDGETING Above Ground
This page and the subsequent diagrams outline a phased systems construction strategy that can be accomplished in smaller pieces, over time. This will allow progress to be made in achieving the vision with more modest fund-raising targets. Each phase of work indicated in this plan is described and budgeted as a complete project in itself. Phasing the work will require some duplication of efforts and temporary measures. If the project can be accomplished in fewer, larger phases, the costs, temporary measures and complexity of the process will be reduced.
Curbs
The gateway improvements are listed in this sequential phasing, but would be great stand-alone projects that would be strong physical manifestations of the vision and planning process for the Third Street Corridor. Early implementation of the recommended gateway improvements could continue the momentum generated by this planning process and build enthusiasm for the fund raising and completion of the Corridor Plan.
Sidewalks*
Roadway
Utilities
Gateways Below Ground
Planting
The cost range for each phase of work and any potential upgrades is indicated on each of the phase diagram sheets that follow.
Lighting Furnishings Signage *The decision for above ground vs below ground utilities shall be made prior to the Sidewalk Improvements Project to ensure that appropriate connections for buried utilities can be designed.
Third Street Streetscape Traffic Corridor Study 1.27.2010
65
CURBS DESCRIPTION The first phase of work will be replacement of the existing curbs with new stone curbs on both sides of Third Street for the entire corridor between East Livingston Avenue and Reinhard Avenue. The new stone curbs will be set at the same location and elevation as the existing curbs. A narrow strip of street pavement and sidewalk pavement on each side of the curb will need to be removed and replaced to enable the construction process. We recommend that when the street pavement is patched, the surface be sloped down towards the face of the curb to provide a consistent 4” to 6” exposed curb face. This will facilitate better drainage of the street pavement and re-establish a legitimate curb edge along Third Street until the street pavement can be replaced at some future date. • Stone curbs • Repair 18-inch width sidewalk • Repair 18-inch width pavement with asphalt • Salvage historic brick • Replace 50% curb inlets ASSUMPTIONS •All historic brick that is embedded within the existing street pavement in the affected area will need to be salvaged and stored for future use. •The new curb shall have downspout drain sleeves provided at appropriate locations to accommodate future sidewalk and drainage improvements. •The street drainage primarily occurs in curb inlet drainage structures. Any curb inlets that do not meet current City standards or that are in poor condition should be replaced and/or repaired at this time. Stone Curb
•Any conduit needed for future utility work should be placed beneath the new curbs at this time.
Adjacent Pavement
•New curbs shall extend around the radius at cross-street intersections. Drainage Sleeve
•Recently installed ADA wheelchair ramps will remain in place unless their location directly conflicts with future crosswalk locations. CONSTRUCTION BUDGET:
$800,000 - $1,000,000
Third Street Streetscape Traffic Corridor Study 1.27.2010
66
SIDEWALKS DESCRIPTION This phase of work centers on rebuilding the sidewalks on both sides of the street for the entire corridor between East Livingston Avenue and Reinhard Avenue. The existing sidewalks are approximately half brick and half concrete over the corridor. Most of the existing walks do not meet ADA because the surface is very uneven due to the pavement heaving from tree roots and poor base conditions. The existing sidewalk surface material and base will be removed. The subbase will be removed and/ or repaired where needed to correct the situation. All new or salvaged brick shall be placed on an asphalt setting bed over a concrete base. Existing tree and plant beds will be removed if they conflict with the new design. Where new plant beds surround existing trees to remain, edging, curbs or walls shall be completed per the design. • Re-use existing brick • All brick surface • Utility conduit placed • Some plant bed edging • Foundations for future structures, poles • Structural topsoil in plant beds ASSUMPTIONS •The type and pattern of existing brick sidewalks will be documented, for salvage and resetting in the same location. New Plant Bed
•Private and public utilities will have the opportunity to upgrade and repair their services while the sidewalk pavement is open. •Underground downspout connections will be provided between the curbs and the R.O.W. line.
Brick Pavement
•Conduit shall be placed for future underground electric, cable, telephone and other utilities that are currently overhead. •Private drive aprons shall be rebuilt with brick to fit within the re-graded sidewalk surface.
Downspout Connection
•Where existing trees are designated to remain, the plant beds shall be fully constructed, including structural topsoil, curbs and other edge treatments. •No new landscaping is included, except seeding of all new plant beds and tree lawns. CONSTRUCTION BUDGET: $3.5M - $3.8M
Third Street Streetscape Traffic Corridor Study 1.27.2010
67
OVERHEAD UTILITIES
Telecommunications
AEP
MELP
DESCRIPTION This phase of work focuses on reducing the visual impact of overhead utilities on both sides of the street for the entire corridor between East Livingston Avenue and Reinhard Avenue. Currently AEP has lines on one side of the street and Columbus Division of Power has lines on the opposite side of the street. Each utility serves mostly customers on the opposite side of the street from where their lines are located. There are approximately 70 occurrences of utility lines crossing this section of Third Street. The existing utility poles have numerous lines attached; some of which may be redundant or inactive. We recommend that the existing wooden utility poles be replaced with metal poles. The metal poles should be taller and hopefully fewer in number. All inactive, redundant lines shall be removed. The majority, if not all, of the cross wires shall be eliminated. • Replace wooden poles with high mast arm metal poles • Eliminate cross wires • Remove unneeded lines ASSUMPTIONS •The new metal utility poles will have no signs or light fixtures attached to them. •Overhead utility lines on cross streets that intersect Third Street are not included in this work. •Any street lights or signs currently mounted on utility poles will need to be relocated to dedicated posts. CONSTRUCTION BUDGET: $1.8M - $2.1M
Third Street Streetscape Traffic Corridor Study 1.27.2010
68
UNDERGROUND UTILITIES DESCRIPTION A potential upgrade to clean up the overhead utilities is to bury them. The existing overhead lines, located on both sides of Third Street, include AEP, Columbus Division of Power, AT&T, Sprint, WOW and other cable and telecommunications companies. Each private or public utility that is required to bury its lines must be reimbursed for the expense as part of the project costs. Existing utilities beneath the pavement reduce the available space for underground electric lines to a ten-foot strip adjacent to the curb on both sides of the street. Preliminary investigations indicate that the electric service may require the entire width, other utilities such as cable and telecommunications would need to be placed beneath the sidewalk pavement. This 10-foot wide parking aisle is where historic brick is buried beneath the asphalt pavement. Transformers that are currently mounted on utility poles will need to be located in underground vaults. The number of transformers should be able to be reduced, but these must be carefully located to reduce the visual impact. • Bury overhead utilities • Sub-grade vaults for transformers • Street repaired with asphalt • Sidewalk repaired with brick to match existing ASSUMPTIONS •The historic brick in the street pavement will be salvaged and stored for future use. •Overhead utility lines on cross streets will remain.
Underground Utilities
•The underground connections will go back to the nearest existing utility pole on cross streets and other perpendicular connections. Connection to Property
•Private property owners will likely be caused to move and/or upgrade their electric panels. CONSTRUCTION BUDGET: $13.8M - $15.8M
Underground Utilities
PROJECT UPGRADES •Repair street pavement with historic brick. Additional cost: $1.2M - $1.4M
Third Street Streetscape Traffic Corridor Study 1.27.2010
69
GATEWAYS DESCRIPTION The Plan calls for enhanced gateways at the intersections of Livingston Avenue and Reinhard Avenue to announce the entrance onto this important corridor. Brick pavement is to be provided in the intersections of Livingston Avenue and Reinhard Avenue with Third Street. Brick and stone piers are located on the north side of Livingston Avenue to frame that entrance. If the street pavement is surfaced in brick, we recommend that the brick pavement in these intersections be a different color and pattern to further distinguish the intersections. The mast arms at Livingston Avenue will be relocated into the curb extensions to maintain the appropriate relationship to the traffic lanes. Benches, planters and special planting will further enhance both of the gateways. •Livingston Avenue intersection •Reinhard intersection •Brick pavement in intersection, distinct color •Brick crosswalks •Relocate mast arms •Benches, planters, plantings •Brick piers at Livingston Avenue •Provide pedestrian signals ASSUMPTIONS •The curb extensions on Third Street at these intersections shall be constructed as part of this phase of work. •The Livingston Avenue gateway has been coordinated with current plans for the I-71/I-70 Improvements. Further coordination will be required as the highway plans advance and are implemented. •We recommend this work be deferred until the decision is made on whether or not to bury overhead utilities along the Third Street Corridor, but the gateways improvements could be completed as stand-alone projects at almost any point. •This budget assumes that the curbs, street improvements and overhead utility work have been completed in previous phases of work. CONSTRUCTION BUDGET:
Livingston Avenue Gateway $550,000 - $650,000
Reinhard Avenue Gateway $250,000 - $300,000
Third Street Streetscape Traffic Corridor Study 1.27.2010
70
PLANTINGS DESCRIPTION Plant street trees and other plant materials in plant beds and tree lawns. Plants will primarily consist of trees, low evergreen ground covers and some seasonal perennials that are tolerant of urban conditions such as drought, salt and alkaline soils. •Street Trees •Evergreen Groundcovers •Seasonal Perennials ASSUMPTIONS •Plant beds and tree lawns will have been constructed during the previous sidewalk phase. •Structural topsoil will have been provided during the previous sidewalk phase. •All new plants will be watered and maintained during the initial one-year period by the German Village Society and resident volunteers to provide consistent, timely maintenance and enhance the establishment of the plant materials. •All permanent planting in plant beds and tree lawns shall be installed as part of the planned streetscape improvements in accordance with the approved design. CONSTRUCTION BUDGET: $275,000 - $350,000
Street Tree Planting Bed
Third Street Streetscape Traffic Corridor Study 1.27.2010
71
LIGHTING DESCRIPTION Replace existing street lights with a combination of new pedestrian and street lights. The existing City of Columbus standard light fixtures are very compatible with the historic setting of German Village and are recommended for the Third Street corridor. The Plan calls for taller street light fixtures on one side of the street and shorter pedestrian scale pole lights on the opposite side of the street. We recommend the corridor be evaluated to ascertain if pedestrian scale pole lights on both sides of the street will provide adequate light levels. If pedestrian scale lights provide adequate lights; these should be provided instead of standard street lights as an upgrade to the project. •Street lights •Pedestrian light poles
Pedestrian Light
ASSUMPTIONS •New lights shall be connected and powered via underground lines installed in conduit. •The conduit was previously installed in the sidewalk phase of work. •All existing light poles and foundations shall be removed as part of this work. •Foundations for new light poles have been constructed during the sidewalk phase of work. CONSTRUCTION BUDGET: $750,000- $850,000
Third Street Streetscape Traffic Corridor Study 1.27.2010
72
FURNISHINGS DESCRIPTION Provide comprehensive streetscape furnishings including seating, bike racks, kiosks, transit shelters, news corrals, waste and recycling containers, and planters. The furnishings will help to further define the special environment of German Village. •Seating •Bike Racks •Kiosks •Transit Shelters •News Corrals •Waste and Recycling Containers •Planters ASSUMPTIONS •All needed electrical conduit will be installed during the sidewalk phase of work. •All needed foundations will be installed during the sidewalk phase of work. •All furnishings will be bolted down to the concrete sub-base and will not require an additional foundation (except transit shelters). CONSTRUCTION BUDGET: $150,000 - $200,000 Bike Rack
Planter Bench
Litter Receptacle
Third Street Streetscape Traffic Corridor Study 1.27.2010
73
SIGNAGE DESCRIPTION Provide comprehensive streetscape signage including informational and historical signage, seasonal banners, directional signs, and regulatory signs. The signage will help to further define the historic legacy of German Village while providing direction to both pedestrian and vehicular traffic. •Historical Signs •Seasonal Banners (to be placed atop pedestrian light poles) •Directional Signs •Regulatory Signs
Informational Sign
ASSUMPTIONS •All signs will be core drilled through concrete sub-base and set within aggregate sub-grade below the sidewalk. No further foundations will need to be poured.
Banner
Directional / Regulatory Sign
•Signs will not be illuminated and therefore not require conduit to be run prior to completing the sidewalk phase of work. CONSTRUCTION BUDGET: $80,000 - $120,000
Third Street Streetscape Traffic Corridor Study 1.27.2010
74
ROADWAY DESCRIPTION Build new curb extensions and patch existing pavement as needed on Third Street with a surface of asphalt. The brick that currently exists within the pavement profile in the curb extension areas will be salvaged and stored for future use. The existing subbase and base materials may be replaced or repaired as needed to provide for sound construction. Curb extensions shall be provided at designated intersections to slow traffic and enhance pedestrian safety. The curb extensions will require that some catch basins be added or relocated to preserve and enhance the drainage patterns. • Provide curb extensions • Stripe in bike lanes on existing pavement and when construction occurs ASSUMPTIONS • Any remaining historic brick in the street pavement will be salvaged and cleaned for re-use. • Private and public utilities will upgrade and/or repair any utilities in need of attention while the street pavement is open. • The gateway improvements are not included as part of the basic work of this phase. • Existing mast arms will be relocated at the Whittier Street intersection. • Assume 20% of subbase will need to be removed and replaced. CONSTRUCTION BUDGET: $475,000 - $600,000 POTENTIAL UPGRADES • Construct the street surface with salvaged historic brick. The quantity available may need to be supplemented. Additional Cost: $3,800,000 - $4,200,000
Third Street Streetscape Traffic Corridor Study 1.27.2010
75
FUNDING SOURCES
Third Street is a significant streetscape project; it will be complex, expensive and will require a joint public and private effort to come to fruition. The City of Columbus Public Utilities Department has indicated that certain upgrades desired by the local community, such as brick pavement and burial of utilities are beyond the normal scope of improvements funded by the City. These upgrades must be paid for with private funds, grants and other sources of financing outside of the Columbus capital budget.
Columbus Capital Funds
Fund raising will be significant task in the implementation of the Third Street Corridor Plan. The funding needed to complete the engineering and construction of the recommendations will likely come from a number of sources, both public and private. The Implementation Strategy has been devised to respond to the potential funding and enables the construction to progress in smaller, incremental steps. The Preliminary Engineering process should address the corridor as a whole: many of the streetscape components are systemic features that span the length of the corridor and greatly impact one another.
Private Donations
Grants
Preliminary Engineering Final Engineering
This section provides a summary of potential funding sources that may be possible for the Implementation of the Third Street Corridor improvements. Some of the grants and other sources identified apply to the design and engineering process; others are targeted towards actual capital expenditures.
Phased Construction
Third Street Streetscape Traffic Corridor Study 1.27.2010
76
In this country’s bicentennial year, German Village and many other historic centers, were fortunate enough to take advantage of preservation funding made available by the Historic Preservation Act of 1966 and the excitement of the bicentennial celebrations. Almost four decades later, the fruits of those investments are apparent as the concepts touted by the HPA of 1966 have become more mainstream. For those who have been proponents of recycling and restoring our built environment, each project that brings a few more people to the reality of preserving our history is a milestone worth marking. However, the ways of “doing business” have changed. Clearly, the voice of the United States government echoes these sentiments in unique programs like the Save America’s Treasures and Preserve America programs. Not every grass roots effort can meet the criteria for these programs. Raising funds to continue the good work is a continuous struggle. The included information is a condensed version of research toward that end. The granting and financing opportunities that are listed herein represent the beginning of a concentrated effort to secure funding for preservation programs for Third Street and for German Village. It should be understood that most major projects cannot be funded by grants alone. Most projects require a good sound base of support that includes volunteers, staffers, private and public funding, grants, loans, community fund-raising events, and generally good fund-raising counsel. And there is one more thing… …effort. The information included herein is divided into three categories – State Programs, Non-Profit Programs, and Corporate and Family Foundation Programs. Each program is noted with its application date or the cycle on which it is reviewed or awarded. The grant amounts are listed, if they are fixed, with the contact information, the match amounts and the eligibility restrictions. It is important to note that the eligibility restrictions do not always eliminate possibilities. With creative counsel and open-minded trustees, often public and private partnerships can be established which expand the opportunities. One significant piece of information listed herein is the DESCRIPTION. The descriptions often address the goals or the mission of the agency or of the particular fund. If the goal of the particular project accurately addresses the goals of the fund or funding agency, the chances are greatly increased for an award. To be quite pointed, in the past, there was an expectation of cash falling from the sky just because it is a “great project”. Reality will demonstrate that the organizations who are the most successful at receiving grants are those who are not afraid to 1) ask, 2) do homework, 3) work collaboratively, 4) expect restrictions, and 5) be patient. It is important to note as well, groups who work closely with the agency are more likely to understand the shared goals. What is it that makes this project worth funding?
FINDING OPPORTUNITIES FOR GERMAN VILLAGE SOCIETY AND CITY OF COLUMBUS ORGANIZATION/GRANT PROGRAM
APPLICATION DATES
DESCRIPTION
GRANT AMOUNT
MATCH
ELIGIBILITY
CONTACT
STATE PROGRAMS
Ohio Historical Society/Ohio Historic Preservation Office Certified Local Governments CFDA Projects to develop comprehensive plans for the preservation of #15.904 historic, architectural, and archaeological resources, to survey and/or nominate properties to the NRHP, to develop master plans and/or feasibility studies for NRHP properties, to acquire and to develop properties listed on the NRHP, and conduct public education June 1, 2010 programs related to historic preservation.
Ohio General Assembly State Capital Appropriations Bill
Ohio Department of Development Economic Development Program
Biennial state capital appropriations bill funds acquisitions, rehabilitation, restoration, and exhibit curation for local historical Talk to your organization improvement projects sponsored by state legislators. Bill legislator by enacted spring of even numbered years. Funded projects are summer of odd administered by the Ohio Cultural Facilities Commission. Although numbered years. there is not a formal application process, the commission offers (Capital Bill guidance on how to pursue funding on its web site: enacted spring www.culture.ohio.gov of even numbered years.)
$5,000 minimum request. Grants typically $9,000 to $15,000
CLG
State Senator or Representative from your district. www.ohio.gov
Varies
Provides funds to units of local government to provide gap financing for local business development. Except for local infrastructure needs, Economic Development Program funds are repaid to the local community's Revolving Loan Fund to provide funding for additional Open Window business assistance activities. Cycle
Microenterprise Business Development Program
60 / 40
Grants Manager Ohio Historic Preservation Office Ohio Historical Society 567 E. Hudson Street Columbus, OH 43211-1030 (614) 298-2000 (614) 298-2037 (Fax) www.ohiohistory.org/resource/histpres ohpo@ohiohistory.org
Provides grants to eligible cities and counties and non-profit organizations to assist in the development of local microenterprise businesses and to create and retain long-term jobs in the private sector. Microenterprises are defined as for-profit entities with five or fewer employees, one of whom owns the business. FY 2010: August 6, 2010
None
LG
Office of Housing and Community Partnerships Economic and Community Development Ohio Dept. of Development 77 S. High Street Columbus, OH 43216 (614) 466-2285 www.odod.state.oh.us
Office of Housing and Community Partnerships Economic & Community Development Ohio Dept. of Development 77 S. High Street Columbus, OH 43216 (614) 466-2285 LG, NP, NPO www.odod.state.oh.us
Ohio Department of Natural Resources Chambers, Murphy & Burge copyright 2010
FUNDING OPPORTUNITIES‐‐THIRD STREET CORRIDOR‐‐KKG
Third Street Streetscape Traffic Corridor Study 1.27.2010
1 of 6
77
FINDING OPPORTUNITIES FOR GERMAN VILLAGE SOCIETY AND CITY OF COLUMBUS ORGANIZATION/GRANT PROGRAM
APPLICATION DATES
Natureworks February 1, 2010 Yearly Cycle
DESCRIPTION
GRANT AMOUNT
MATCH
ELIGIBILITY
Nature Works provides up to 75% state reimbursement funds for acquisitions, development or rehabilitation of public park and recreation areas. 75/25
LG, PD, CD
Ohio Department of Transportation Transportation Enhancement Program
The Federal Highway Administration's Transportation Enhancement Program provides funds for projects that enhance the transportation Solicitations experience by improving the cultural, historic, aesthetic and environmental aspects of transportation infrastructure. Each state begin January 1 Yearly decides how to use it's enhancement funds. In Ohio, funds are split Cycle; Letter of between Ohio's 17 MPOs and the rest of the state. MPO and Interest due to statewide funds are distributed competitively. Funds can be used for District office construction or major rehabilitation only. February 1 Yearly Cycle
National Scenic Byways
April (Applications available in February)
Ohio Arts Council (OAC) Capacity Building
Ongoing
The National Scenic Byways Program provides technical and financial assistance to help preserve America's scenic roads and promote tourism and economic development. The National Scenic Byways Discretionary Grants program provides funding for byway-related projects each year, as part of the Federal Highway Administration's Discretionary Grants Program. Projects to support and enhance National Scenic Byways, All-American Roads and State-designated byways are eligible. Applications are prepared online but submitted through the State's byway program agency.
Capacity building funds are designed to strengthen Ohio's non-profit arts and cultural sector by helping applicants improve internal governance and leadership, cultivate strategic community linkages, and develop financial and human resources for long-term stability. Building organizational capacity is a long-term, evolutionary process that organizations must engage in purposefully. The program provides funding for work in three areas of capacity: Organizational Governance and Leadership, Strategic Community Linkages and Assets and Resources Development.
Typical: $500,000 to 80/20 $1,000,000, cash only No Max
Varies
GE, MPD
CONTACT Mary Fitch ODNR, Real Estate & Land Management 2045 Morse Road, Bldg. C-4 Columbus, OH 43229-6693 (614) 265-6477 mary.fitch@dnr.state.oh.us Randy Lane, Program Manager Ohio Dept. of Transportation Office of Local Projects 1980 W. Broad St., 2nd Floor Columbus, OH 43223 (614) 644-8211 www.dot.state.oh.us/local
Paul Staley Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 (614) 728-5078
80/20
Ohio Arts Council 727 E. Main St. Columbus, OH 43205-1796 (614) 466-2613 www.oac.state.oh.us $500 to $5,000
50/50
CAC, CE, LI, NPO
Ohio Humanities Council (OHC)
Chambers, Murphy & Burge copyright 2010
FUNDING OPPORTUNITIES‐‐THIRD STREET CORRIDOR‐‐KKG
Third Street Streetscape Traffic Corridor Study 1.27.2010
2 of 6
78
FINDING OPPORTUNITIES FOR GERMAN VILLAGE SOCIETY AND CITY OF COLUMBUS ORGANIZATION/GRANT PROGRAM
APPLICATION DATES
Major Grants
February 1 September 1 (Proposals considered twice a year.)
Regular Grants
DESCRIPTION
GRANT AMOUNT
MATCH
ELIGIBILITY
Humanities must be the central focus. Best suited for projects with regional or statewide impact; those which attract large & diverse audiences, humanities institutes for teachers or professionals, film/video documentaries and media projects. $5,001$20,000
50/50
NP
Short term projects of limited scope; one component of a larger project which receives funding from several sources, lectures for special occasions, panel discussion, and other singe-site programs. First business day of each month (minimum 8 weeks prior to project start).
Mini-Grant Applications accepted yearround (minimum of 5 weeks prior to project start).
$2,001$5,000
50/50
NP
Short term projects of limited scope; one component of a larger project which receives funding from several sources, lectures for special occasions, panel discussion, and other singe-site programs.
Up to $2,000
50/50
NP
CONTACT Jack Shortlidge Ohio Humanities Council 471 E. Broad Street, Suite 1620 Columbus, OH 43215-3857 (614) 461-7802 (800) 293-9774 (614) 461-4651 (Fax) www.ohiohumanities.org
Frank Dunkle or Jack Shortlidge Ohio Humanities Council 471 E. Broad Street, Suite 1620 Columbus, OH 43215-3857 (614) 461-7802 (800) 293-9774 (614) 461-4651 (Fax) www.ohiohumanities.org
Frank Dunkle Ohio Humanities Council 471 E. Broad Street, Suite 1620 Columbus, OH 43215-3857 (614) 461-7802 (800) 293-9774 (614) 461-4651 (Fax) www.ohiohumanities.org
NON-PROFIT PROGRAMS Heritage Ohio Ohio Main Street Program
A program of professional advice and guidance in the use of the proven Main Street Four-Point Approach to start or strengthen revitalization efforts. 1. Call for Application Workshop 2. Letter of Intent
Chambers, Murphy & Burge copyright 2010
noncash technical assistance
LG
FUNDING OPPORTUNITIES‐‐THIRD STREET CORRIDOR‐‐KKG
Third Street Streetscape Traffic Corridor Study 1.27.2010
Heritage Ohio 846 1/2 East Main Street Columbus, OH 43205 (614) 258-6200 www.heritageohio.org
3 of 6
79
FINDING OPPORTUNITIES FOR GERMAN VILLAGE SOCIETY AND CITY OF COLUMBUS ORGANIZATION/GRANT PROGRAM
APPLICATION DATES
National Trust for Historic Preservation Joanna Favrot Fund
February 1, 2010
Provides nonprofit organizations and public agencies grants for projects that contribute to the preservation or the recapture of an authentic sense of place. Individuals and for-profit businesses may apply only if the project for which funding is requested involves a National Historic Landmark. Funds may be used for professional advice, conferences, workshops and education programs.
February 1, June 1 and October 1
Established by the Jeffris Family Foundation to support important historic preservation projects in the states of Iowa, Illinois, Indiana, Michigan, Minnesota, Missouri and Ohio. Applicants must be able to demonstrate the viability of their project through the submittal of early planning studies, and must be ready for the preparation of a Historic Structure Report or other advanced planning studies, leading toward a community-centered capital fund drive.
Jeffris Heartland Fund
National Trust Preservation Funds
DESCRIPTION
February 1, June 1 and October 1 (Contract the NTHP Regional Office prior to submitting application).
National Trust Community Investment Corporation (NTCIC) N/A
GRANT AMOUNT
$2,500 $10,000
MATCH
50/50 Cash only
$5,000 $50,000
National Trust Preservation Funds provide two types of assistance to nonprofit organizations and public agencies: 1) matching grants for preservation planning and educational efforts, and Matching 2) intervention funds for preservation emergencies. Matching grant grants funds may be used to obtain professional expertise in areas such as are $500 architecture, archeology, engineering, preservation planning, land-use $5,000 planning, fund raising, organizational development and law as well as to provide preservation education activities to educate the public. The NTCIC makes equity investments in real estate projects that qualify for federal historic rehabilitation tax credits and when available, state historic tax credits and New Markets Tax Credits. NTCIC works with a wide variety of property owners including for-profit developers, non-profit organizations and local governments. Our focus is on projects that have a strong economic revitalization impact on the surrounding community. The timing of the equity contributions is flexible and negotiable. Frequently used pay-in benchmarks include admission to the LLC, placement in-service, Part 3 approval, and project stabilization.
ELIGIBILITY
NP, GE
NP, LG
50/50 Cash only
N/A
CONTACT
National Trust for Historic Preservation Midwest Regional Office 53 W. Jackson Blvd., Suite 350 Chicago, IL 60604 (312)-939-5547 mwro@nthp.org
Koren Vanzo, Program Assistant National Trust for Historic Preservation Midwest Regional Office 53 W. Jackson Blvd., Suite 350 Chicago, IL 60604 (312)-939-5547 mwro@nthp.org
National Trust for Historic Preservation Midwest Regional Office 53 W. Jackson Blvd., Suite 350 NP, LG, CDC, Chicago, IL 60604 (312) 939-5547 CE mwro@nthp.org
National Trust Community Investment Corporation 1785 Massachusetts Ave., NW Washington, DC 20036 (202) 588-6001 NP, LG, CDC, (202) 588-6436 (Fax) CE ntcicfunds.com ntcic_mail@ntcicfunds.com
National Park Service - Department of the Interior
Chambers, Murphy & Burge copyright 2010
FUNDING OPPORTUNITIES‐‐THIRD STREET CORRIDOR‐‐KKG
Third Street Streetscape Traffic Corridor Study 1.27.2010
4 of 6
80
FINDING OPPORTUNITIES FOR GERMAN VILLAGE SOCIETY AND CITY OF COLUMBUS ORGANIZATION/GRANT PROGRAM
APPLICATION DATES
Preserve America Most recent: Application deadline February 12, 2010
National Endowment for the Humanities (NEH) Challenge Grant CFDA # 45.130
May 5, 2010
DESCRIPTION The Preserve America matching-grant program provides funding to designated Preserve America Communities to support preservation efforts through heritage tourism, education and historic preservation planning. NOTE: Designated Preserve America communities, neighborhoods, SHPOs, THPOs, CLGs that have applied for PA status
GRANT AMOUNT
$20,000 $250,00
NEH challenge grants help institutions and organizations secure longterm improvements in and support for their humanities programs and resources. Awards are made to museums, public libraries, colleges, research institutions, historical societies and historic sites, public television and radio stations, universities, scholarly associations, state $30,000 humanities councils, and other nonprofit entities. Where clearly $1,000,000 related to the humanities, direct expenditures from Challenge Grant awards are allowable for items that have inherent longevity such as renovation of facilities.
MATCH
50/50
ELIGIBILITY
See note in description
CONTACT Heritage Preservation Grants National Park Service 1201 Eye Street NW (2256) Washington, DC 20005 (202) 354-2020 www.preserveamerica.gov
Office of Challenge Grants National Endowment for the Humanities Room 420 1100 Pennsylvania Avenue N.W. Washington, DC 20506 (202) 606-8309 www.neh.gov challenge@neh.gov
25/75
CORPORATE and FAMILY FOUNDATION PROGRAMS
Corporate Grant Programs American Electric Power (AEP)
N/A
The Eaton Charitable Fund
N/A
Chambers, Murphy & Burge copyright 2010
AEP Sponsors special programs to encourage economic development, education, the environment, hunger, housing, health, and safety within its traditional service territory. Priority is based on the perceived overall benefit to the community in Arkansas, Indiana, Kentucky, Louisiana, Michigan, Ohio, Oklahoma, Tennessee, Texas, Virginia, West Virginia. The highest priority is local organizations that serve the needs of Eaton employees and offers to them the opportunity to provide leadership, voluntary services, and personal financial support. Program support and capital grants are given to health, human services, civic, and cultural organizations. Support to educational institutions is given but the trust has a preference for engineering, scientific, technological and business-related projects. The fund also has expressed interest in arts and cultural programs, higher education, children and youth services, family services, community development, neighborhood development, and economic development. Eaton lends it support through general or operating funds, capital campaigns, building/ renovation, program development, employee matching gifts and in-kind gifts.
NP
Varies
NP
FUNDING OPPORTUNITIES‐‐THIRD STREET CORRIDOR‐‐KKG
Third Street Streetscape Traffic Corridor Study 1.27.2010
Varies
Deffers by State… Ohio Contact Info: AEP Ohio 850 Tech Center Drive Gahanna, OH 43230 http://www.aep.com/citizenship/comm unity/corpGive/ Eaton Charitable Fund Eaton Center 1111 Superior Avenue Cleveland, OH 44114-2584 216/523-4944 http://www.eaton.com/ecm/groups/pu blic/@pub/@eaton/@corp/documents/ content/ct_242488.pdf
5 of 6
81
FINDING OPPORTUNITIES FOR GERMAN VILLAGE SOCIETY AND CITY OF COLUMBUS ORGANIZATION/GRANT PROGRAM
APPLICATION DATES
JP Morgan Chase
DESCRIPTION
Coporate and Family Foundations Duke Energy Foundation Applications for following year reviewed middle of current year
Surdna
Varies
Varies
The Nationwide Foundation makes operating, project and capital grants. Capital grants are limited and considered on a case-by-case basis. In order of emphasis, Nationwide supports efforts that meet: Sept. 1, 2010 emergency and basic needs, stabilization needs, individual (Application not development needs, and community enrichment needs (such as arts available until and culture organizations, higher education and civic improvement). May 2010)
CONTACT
NP (with additional restrictions)
Deffers... Central Ohio Contact Info: Jeffrey Lyttle P.O. Box 710157 Columbus, OH 43271-0157 jeffrey.r.lyttle@chase.com Questions regarding Cybergrants / application process, please e-mail damion.d.heron@chase.com http://www.jpmorganchase.com/corpo rate/Corporate-responsibility/ corporate-responsibility.htm
NP, GE
Lisa Teasdell Duke Energy Foundation Manager Lisa.Teasdell@duke-energy.com MUST APPLY ONLINE http://www.duke-energy.com/ community/foundation.asp
MUST APPLY ONLINE http://www.nationwide.com/aboutus/nationwide-foundation.jsp Varies
NP
(212) 557-0010 questions@surdna.org MUST APPLY ONLINE http://www.surdna.org Varies
FUNDING OPPORTUNITIES‐‐THIRD STREET CORRIDOR‐‐KKG
Third Street Streetscape Traffic Corridor Study 1.27.2010
ELIGIBILITY
The Duke Energy Foundation seeks to improve the quality of life in its community through the areas of environment, economic development and community vitality.
The Surdna Foundation makes grants to nonprofit organizations in the areas of environment, community revitalization, effective citizenry, Review in Feb, the arts, and the nonprofit sector. May, & Sept. Submit 3 to 4 months prior to desired review
Chambers, Murphy & Burge copyright 2010
MATCH
JP Morgan Chase awards funding in the following areas: community asset development, youth education and community life.
N/A
Nationwide Foundation
GRANT AMOUNT
NP, 501(c)(4)
6 of 6
82
WHAT ARE THE NEXT STEPS
Publicize the plan (all) Conduct preliminary engineering (City) Capital budgeting (City) Assign fund raising tasks (GVS) Prepare grant applications (GVS) Final design and engineering (City) Phase Construction Third Street Streetscape Traffic Corridor Study 1.27.2010
83
APPENDIX COMPOSITE PLAN HISTORICAL PHOTOGRAPHY EARLY CONCEPTS & STUDIES PRIVATE DEVELOPMENT RECOMMENDATIONS
Third Street Streetscape Traffic Corridor Study 1.27.2010
84
1.27.2010
Third Street Streetscape Traffic Corridor Study REINHARD AVENUE
LANSING STREET
WHITTIER STREET
LANSING STREET
KOSSUTH STREET
COLUMBUS STREET
COLUMBUS STREET
FRANKFORT STREET
SYCAMORE STREET
WILLOW STREET
AVEN UE
BECK STREET
HOSTER STREET
BLENKNER STREET
LIVING STON
COMPOSITE PLAN
85
HISTORICAL PHOTOGRAPHY
475 S Third
LIVINGSTON
479 S Third
1975
480 S Third
492 S Third
Third Street Streetscape Traffic Corridor Study 1.27.2010
86
HISTORICAL PHOTOGRAPHY
541 S Third
571 S Third
1880’s 1990
1963 624 S Third
BECK
595 S Third 1960’s
Third Street Streetscape Traffic Corridor Study 1.27.2010
1960’s
87
HISTORICAL PHOTOGRAPHY
627 S Third
631 S Third
1961
650 S Third
664 S Third
RE
SYCAMO
1890
1912
Third Street Streetscape Traffic Corridor Study 1.27.2010
88
HISTORICAL PHOTOGRAPHY
769 S Third
793 S Third
858 S Third
911 S Third
KOSSUTH
R
WHIT TIE
Third Street Streetscape Traffic Corridor Study 1.27.2010
89
Concept 1: LIVINGSTON
AVENUE
BLENKNER
STREET
HOSTER
STREET
BECK
STREET
Concept 3:
Concept 2: LIVINGSTON
• Minimalist approach • Mixture of brick and concrete sidewalks • Curb extensions • Striped crosswalks • Flush brick intersection at Reinhard Avenue • Variety of street tree planting treatments
LIVINGSTON
AVENUE
BLENKNER
STREET
HOSTER
STREET
BECK
STREET
• Brick “threshold” at Livingston Avenue • Brick sidewalks • Striped crosswalks • Consistent street width • Uniform street tree planting
FRANKFORT
AVENUE
BLENKNER
STREET
HOSTER
STREET
BECK
STREET
• Brick sidewalks • Curb extensions • Gateway crosses Livingston • Flush brick intersections at Livingston, Whittier and Reinhard • Raised brick intersections at Blenkner, Sycamore and Frankfort • Striped crosswalks at all other intersections • Landscape reflects different districts
STREET
STREET
WILLOW
STREET
WILLOW
STREET
SYCAMORE
STREET
SYCAMORE
STREET
SYCAMORE
STREET
COMMERCIAL DISTRICT
WILLOW
COLUMBUS
STREET
COLUMBUS
COLUMBUS
STREET
STREET
STIMMEL
STREET
FRANKFORT
STREET
FRANKFORT
STREET
FRANKFORT
STREET
COLUMBUS
STREET
COLUMBUS
STREET
COLUMBUS
STREET
KOSSUTH
STREET
KOSSUTH
STREET
KOSSUTH
STREET
LANSING
STREET
LANSING
STREET
LANSING
STREET
KOSSUTH
LANSING
STREET
KOSSUTH
STREET
LANSING
STREET
STREET
WHITTIER
STREET
WHITTIER
STREET
WHITTIER
STREET
CONCORD
PLACE
CONCORD
PLACE
CONCORD
PLACE
REINHARD
AVENUE
REINHARD
Concept 1: Eclectic Concept 1: Concept 1: Eclectic
L I VThird I N G Street S T O NStreetscape A V E N U -E Traffic Corridor Study
REINHARD
AVENUE
Concept 2: Uniformity Concept 2:
Concept 2: Uniformity
• Minimalist approach • Mixture of brick and concrete sidewalks • Curb extensions • Striped crosswalks B L E N K N E R S T R E E T • Flush brick intersection at Reinhard Avenue • Variety of street tree planting treatments HOSTER STREET
BECK
STREET
L I V IThird N G S Street T O N Streetscape A V E N U E- Traffic Corridor Study
HOSTER
STREET
B E C K S T R E E T Traffic Corridor Study Third Street Streetscape
1.27.2010
FRANKFORT
STREET
STREET
LANSING
STREET
AVENUE
Concept 3: Districts Concept 3:
Concept 3: Districts
• Brick “threshold” at Livingston Avenue • Brick sidewalks • Striped crosswalks BLENKNER STREET • Consistent street width • Uniform street tree planting
KOSSUTH
RESIDENTIAL DISTRICT
STIMMEL
COMMERCIAL DISTRICT
STREET
VILLAGE GREEN
STIMMEL
STREET
Third Street Streetscape - Traffic Corridor Study
• Brick sidewalks • Curb extensions • Gateway crosses Livingston • Flush brick intersections at Livingston, Whittier and Reinhard • Raised brick intersections at Blenkner, Sycamore and Frankfort • Striped crosswalks at all other intersections • Landscape reflects different districts 90
46’ 4’ 10’ 10’ 4’ 9’
THIRD STREET
46’ 14’
9’
14’
Parking
Drive Lane
9’
9’
Parking
Drive Lane Parking
Bike
Drive Lane
Drive Parking Lane Bike
Detectable warning pavers, typ.
THIRD STREET
THIRD STREET
Striped crosswalk, typ.
5’
9’
9’
Concrete band, typ. Brick paved crosswalk, typ. Curb extension, typ. Detectable warning pavers, typ.
Flush Intersection w/ Brick Intersection Studies
Bike
Drive Lane
Parking
9’
10’
Parking
Drive Lane
Bike
46’ 8’ Median
10’ Drive Lane
9’ Parking
Curb extension, typ. Detectable warning pavers, typ.
9’
Flush Intersection with Paved Crosswalks
5’
Drive Lane
46’ 10’ 4’ 9’
Concrete band, typ. Brick paved crosswalk, typ.
THIRD STREET 5’
Brick paved intersection
Parking
THIRD STREET
Flush Intersection w/ Striped Crosswalks
4’ 10’
9’
5’
Curb extension, typ. Detectable warning pavers, typ.
Designated Bike Lanes
Existing Conditions
Existing Condition
10’ Wide slope transition 6’ Wide slope transition
Brick paved intersection
Channelized Intersection
Curb Extensions
9’
10’
46’ 8’
10’
9’
Parking
Drive Lane
Turn Lane
Drive Lane
Parking
9’
10’
49’ 13’
Parking
Drive Lane
Drive Lane
17’ Parking
Concrete band, typ. Brick paved crosswalk, typ. Curb extension, typ. Detectable warning pavers, typ.
9’
Raised Intersection with Brick
Third Street Streetscape - Traffic Corridor Study Early Intersection Studies
Turn Lane / Flush Median
Third Street Streetscape - Traffic Corridor Study Early Traffic Calming Studies
Traffic Calming Studies
Third Street Streetscape Traffic Corridor Study 1.27.2010
Back In Parking
91
PRIVATE DEVELOPMENT
•Stone or terra cotta planters •Stone or terra cotta planters General characteristics of the private development
maintain building frontage line with wrought iron fencing,
hedge row and landscaping
express owner’s individuality in front yard gardens
stone or terra cotta planters
Private Development
Third Street Streetscape - Traffic Corridor Study
Third Street Streetscape Traffic Corridor Study 1.27.2010
92