Canadian Consulting Engineer September October 2023

Page 42

Water Resources Award of Excellence

Woodworth Dam Optimization BBA

Getting the green light In the initial stages of the project, there were successes; however, the challenges and costs associated with building a new dam in a remote region, with limited road access, tested its future. The firm’s team 42

CANADIAN CONSULTING ENGINEER

undertook a comprehensive value engineering review, optimized the initial design for the new dam and reduced the project budget by nearly 17%. The budgetary reduction was achieved by using multiple three-dimensional (3-D) printed dam and CNC-routed riverbed models, which were tested in hydraulic flumes to confirm their flow characteristics. This analytic approach allowed the team to optimize the design to meet the specific project goals, a process which reduced rock anchor quantity by 40%, concrete volume by 25% and rock excavation volume by 18%. This was also a more sustainable solution. Reducing costs would help get the ‘green light’ for the project, but the team’s goal was also to incorporate the interests of the environment and of local communities. By way of example, reusing foundation rock saved 500 trips on the remote service road; the reduction in rock excavation limited the amount of debris entering the stream; and the team ensured special attention and care by protecting Indigenous ceremonial trees, traditional wetlands and other culturally significant features. Implementing industry best practices ensured climate resilience and dam safety. Prince Rupert is known for significantly heavy rainfall, so a focus was placed on predicting and allowing for future

changes to ‘flow regimes’ within the river system as a result of climate change. The spillway capacity was oversized to allow for future flood flows and demand.

“They’ve provided a sustainable source of clean drinking water where there wasn’t one before.” – Jury

Site challenges The site is located 7 km from a tidal barge landing. All equipment, concrete, rock, aggregate and other items for the project needed to be delivered by barge to this landing, which could only be accessed to load and unload equipment during high tide—a three-hour window each day. From there, the items needed to be trucked the 7 km up a single-lane forestry service road. The discovery of weak shale rock above the north abutment meant slope stabilization was required before the team could fully access the dam site. Additional measures were taken to ensure safety during mudslides; while these are considered one-in-75-years to one-in-50-years rainfall events, they did indeed occur during the project! Collaboration with First Nations The project is located on Indigenous land. Local communities were involved throughout the project, in a collaborative effort that ensured special attention was given to respect their culture. These communities hold traditional ceremonies using sections of cedar trees. So, the project team September/October 2023

PHOTO COU RT E SY B BA.

T

he City of Prince Rupert needed to replace the aging Woodworth Dam on British Columbia’s northwest coast, along with water supply lines. This 100-year-old critical piece of infrastructure has served as a reservoir and primary freshwater source for the community. The municipal government turned to Austin Engineering, now part of BBA, to optimize the dam’s redesign, help secure the multi-year project and develop a state-of-theart freshwater distribution facility. Prince Rupert had been under boil-water advisories in recent years, due to turbidity in the water system pumping from Shawatlan Lake. The completion and commissioning of the Woodworth Dam were celebrated on Oct. 14, 2022. Beginning in February 2023, for the first time in seven years, drinking water could be taken directly from the city’s original supply in Woodworth Lake and transported—via high-density polyethylene (HDPE) pipeline—down and across the harbour, entering the city’s water system. This has been a life-changing project for the community.


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Digital Acceleration Initiative

6min
pages 60-62

CHUSJ Phase 2 Redevelopment

3min
pages 58-59

Calgary Cancer Centre Phases 1 - 3

4min
pages 56-57

Espace Montmorency Energy Loop

4min
pages 52-55

Pellet Plant Biofuel

3min
pages 50-51

We care enough to do it right

0
pages 49-50

Caribou Falls Block Dam 2 Reconstruction

2min
pages 48-49

Comox Valley Water Treatment Plant

3min
pages 46-47

La Baie Landslide and Embankment Restoration

4min
pages 44-45

Woodworth Dam Optimization

3min
pages 42-43

Port Saint John Westside Modernization

4min
pages 40-41

Transportation Tank Hill Emergency Restoration

4min
pages 38-39

Waaban Crossing

4min
pages 34-37

Vendôme Station Entry and Pedestrian Link

4min
pages 30-31

Centerm Expansion

4min
pages 26-29

Nancy Pauw Bridge

4min
pages 24-25

Million Meals Campaign

4min
pages 22-23

REFAM Argan Predictive Model

4min
pages 20-21

Standing Column Wells for Clé-des-Champs School

3min
pages 18-19

LAC Preservation Storage Facility

4min
pages 16-17

WHY SPECIFY UPONOR?

2min
pages 15-16

K3 Expansion – South Shaft Headframe

5min
pages 12-14

Canadian Consulting Engineering Awards Jury

4min
pages 10-12

2023 CANADIAN CONSULTING ENGINEERING AWARDS / PRIX CANADIENS DU GÉNIE-CONSEIL

1min
page 9

RAHIM AHMAD IS THE 2024 ALLEN D. WILLIAMS SCHOLARSHIP AWARD WINNER RAHIM AHMAD IS THE 2024 ALLEN D. WILLIAMS SCHOLARSHIP AWARD WINNER

5min
page 7

LEON BOTHAM HONOURED WITH BEAUBIEN AWARD FOR LIFETIME ACHIEVEMENT

3min
page 6

CELEBRATING EXCELLENCE IN THE CONSULTING ENGINEERING INDUSTRY

2min
page 5

Cause for celebration

3min
page 4

Digital Acceleration Initiative

6min
pages 60-62

CHUSJ Phase 2 Redevelopment

3min
pages 58-59

Calgary Cancer Centre Phases 1 - 3

4min
pages 56-57

Espace Montmorency Energy Loop

4min
pages 52-55

Pellet Plant Biofuel

3min
pages 50-51

Caribou Falls Block Dam 2 Reconstruction

3min
pages 48-50

Comox Valley Water Treatment Plant

3min
pages 46-47

La Baie Landslide and Embankment Restoration

4min
pages 44-45

Woodworth Dam Optimization

3min
pages 42-43

Port Saint John Westside Modernization

4min
pages 40-41

Transportation Tank Hill Emergency Restoration

4min
pages 38-39

Waaban Crossing

4min
pages 34-37

Vendôme Station Entry and Pedestrian Link

4min
pages 30-31

Centerm Expansion

4min
pages 26-29

Nancy Pauw Bridge

4min
pages 24-25

Million Meals Campaign

4min
pages 22-23

REFAM Argan Predictive Model

4min
pages 20-21

Standing Column Wells for Clé-des-Champs School

3min
pages 18-19

LAC Preservation Storage Facility

4min
pages 16-17

WHY SPECIFY UPONOR?

2min
pages 15-16

K3 Expansion – South Shaft Headframe

5min
pages 12-14

Canadian Consulting Engineering Awards Jury

4min
pages 10-12

2023 CANADIAN CONSULTING ENGINEERING AWARDS / PRIX CANADIENS DU GÉNIE-CONSEIL

1min
page 9

RAHIM AHMAD IS THE 2024 ALLEN D. WILLIAMS SCHOLARSHIP AWARD WINNER RAHIM AHMAD IS THE 2024 ALLEN D. WILLIAMS SCHOLARSHIP AWARD WINNER

5min
page 7

LEON BOTHAM HONOURED WITH BEAUBIEN AWARD FOR LIFETIME ACHIEVEMENT

3min
page 6

CELEBRATING EXCELLENCE IN THE CONSULTING ENGINEERING INDUSTRY

2min
page 5

Cause for celebration

3min
page 4
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.