Six years late, Union Station revitalization a case study in what can go wrong
It can’t have surprised many last year when the yardsticks were moved yet again for Toronto’s Union Station Revitalization Project. The rail hub’s perennial state of construction has been a running joke for Torontonians for years.
Retrofits started in 2010 and were slated to be complete by 2015. Nearly five full years after that misjudged mark, the end seemed in sight, with the city expecting contractors to complete the $824 million overhaul by September 2020. Still, the station wasn’t finished last fall and a revised, end of 2020 completion date came and went with crews still working on-site.
More than a decade into the five-year project, with costs settled just short of 30 per cent over budget, the saga is now officially over. Toronto Mayor John Tory dropped the curtain on the job July 27, alongside other government officials, though workers will be doing final touch-ups through the end of the month.
“After years of extensive work on this difficult project, the Union Station revitalization is now complete,” Tory said in a release, before thanking residents and commuters for their patience.
The city-led expansion and retrofit of the station, which opened in 1927, covered several hundred thousands square feet. It added new space for rail passengers and retail, restored heritage elements, and carved out better connections between GO Transit, Via Rail and the Toronto subway. Though hardly excusing its doubled timeline, parts of the job were tremendously complicated, requiring major excavation beneath rail lines that carried hundreds of thousands of commuters in and out of the station each day.
Estimated at $640.2 million when approved in 2009, city reports over the course of the project cite contractor performance issues, inadequate cost contingencies, as well as city resource shortages that made management of the project insufficient. The onset of the COVID19 pandemic injected new layers of complexity.
It’s dragged on longer than most, but the delays at Union Station aren’t unique. The missed marks on schedule and budget are part of an industry-wide problem with over-promising, under-delivering, or both. According to an oft-cited McKinsey study, 98 per cent of megaprojects run at least 30 per cent over budget, and 77 per cent are handed over no less than 40 per cent behind schedule. McKinsey’s research pulls in only megaprojects – those costing over $1 billion – so while the Union Station revitalization doesn’t quite meet that criteria, it shares many of the hallmarks of a big infrastructure job, including considerable complexity, multiple stakeholders and over-optimism about what can be delivered at what cost. Among other top issues, McKinsey points to poor organization, flawed performance management, inadequate communication, insufficient risk management and contractual misunderstandings as several of the key challenges megaprojects face. With more and more of these big-ticket projects in transit, health care and infrastructure cropping up across Canada, all stakeholders should be working to address these pitfalls by improving collaboration, integrating the proper risk allocation into contracts and, as McKinsey puts it, “overinvesting” in planning.
Teams will get a second chance at hitting their targets at Union Station shortly. The city-led project is complete, but the upcoming Union Station Enhancement Project, headed by Metrolinx, will put crews to work on a pair of new platforms and concourse areas at the southern end of the station. Estimated at between $500 million and $1 billion, the work, likely to start this fall, means there will be little reprieve from the construction noise emanating from Canada’s busiest rail hub for the past 11 years.
MEET OUR CONTRIBUTORS FOR THIS ISSUE
SAUL CHERNOS / Freelance writer
On the rise of community benefits agreements:
“While construction is generally a strong provider of local and regional employment, infrastructure proponents – typically governments – are increasingly turning to community benefits programs to counter longstanding employment equity imbalances and improve the everyday lives of people living near major projects.”
NATE HENDLEY / Freelance writer and author
On the priority mobile elevated work platform makers are putting on safety:
“New regulations from the CSA Group and ANSI (American National Standards Institute) have accelerated the move towards high-tech safety features in boom lifts.”
JACOB STOLLER / Principal, StollerStrategies
On estimating software’s role in reducing risk:
“More contractors are turning to estimating software as jobs get more complex, and estimators collaborate more closely with other teams in the organization. However, given the interactive nature of estimating and the number of players involved, the change management component is considerable.”
MARIN LECI AND ARBA RADAJ / Borden Ladner Gervais LLP
On upcoming prompt payments rules for Alberta:
“As Alberta moves toward modernizing its existing construction lien legislation, industry players should apprise themselves of the differences between Bill 37 and Ontario’s Construction Act.”
DAVID BOWCOTT / Global Director – Growth, Innovation & Insight, Global Construction and Infrastructure Group at Aon Risk Solutions
On carbon-adjusted pricing finding its way into construction:
“Building emissions and construction combine for close to 40 per cent of all carbon emissions, and with these two sectors clearly identified as prime emitters of carbon, governments are starting to find ways to reduce emissions in both sectors.”
VOLUME 66, NO.5/AUGUST 2021 www.on-sitemag.com
READER SERVICE
Print and digital subscription inquiries or changes, please contact Urszula Grzyb, AUDIENCE DEVELOPMENT MANAGER Email: ugrzyb@annexbusinessmedia.com Tel: (416) 510-5180 Fax: (416) -510-6875 Mail: 111 Gordon Baker Road, Suite 400, Toronto, ON M2H 3R1
PUBLISHER | Peter Leonard (416) 510-6847 pLeonard@on-sitemag.com EDITOR | David Kennedy (416) 510-6821 dkennedy@on-sitemag.com MEDIA DESIGNER | Svetlana Avrutin savrutin@annexbusinessmedia.com
ASSOCIATE PUBLISHER | David Skene (416) 510-6884 dskene@on-sitemag.com ACCOUNT COORDINATOR | Kim Rossiter (416) 510-6794 krossiter@on-sitemag.com COO | Scott Jamieson sjamieson@annexbusinessmedia.com
Established in 1957, On-Site is published by Annex Business Media 111 Gordon Baker Road, Suite 400, Toronto, ON M2H 3R1 Publications Mail Agreement No. 40065710
ISSN: 1910-118X (Print) ISSN 2371-8544 (Online)
SUBSCRIPTION RATES Canada $49.50 per year, United States $113.00 per year, Other foreign $136.50, Single Copy Canada $13.50. On-Site is published 7 times per year except for occasional combined, expanded or premium issues, which count as two subscription issues. Occasionally, On-Site will mail information on behalf of industry-related groups whose products and services we believe may be of interest to you. If you prefer not to receive this information, please contact our circulation department in any of the four ways listed above. Annex Business Media Privacy Officer privacy@annexbusinessmedia.com Tel: 800-668-2374
Content copyright ©2021 by Annex Business Media may not be reprinted without permission.
On-Site receives unsolicited materials (including letters to the editor, press releases, promotional items and images) from time to time. On-Site, its affiliates and assignees may use, reproduce, publish, re-publish, distribute, store and archive such unsolicited submissions in whole or in part in any form or medium whatsoever, without compensation of any sort.
DISCLAIMER This publication is for informational purposes only The content and “expert” advice presented are not intended as a substitute for informed professional engineering advice. You should not act on information contained in this publication without seeking specific advice from qualified engineering professionals.