Monthly Report October 2024

Page 1


STATUS REPORT TA 2025

KEY HIGHLIGHTS:

96% OF PM MATERIAL RESERVATION COMPLETED CAPEX & MODS HYBRID MEETINGS.

REROUTING OF TA MANPOWER/EQUIPMENT PRS WITH THE ACTUAL AMOUNT; ASSIGNED TO THE RELEVANT TA/MODS & CAPEX ENGINEERING ACCOUNT.

REPORT- OCTOBRER 2024

366 DAYS TO TA 2025

ACTIVITY STATUS

Completed Activities:

Started first round meeting for Job List discussions.

Conducted Combined Meeting Presentation #3

Conducted meeting with Procurement & Warehouse #5.

Conducted TA Audit meeting #06.

Issuance of Package Contracts PRs (for Recurrent Services): Total 41 Nos of PRs been routed to Procurement and other 01 No. of PR is currently under signature/preparation

Issuance of Vendor (FSE) PRs: Total 38 Nos of PRs have been routed to Procurement and other 02 Nos. of PRs are currently under signature/preparation.

Issuance of Vendor (Spare Part) PRs: Total 15 Nos of PRs have been routed to Procurement, 11 Nos. of POs has been issued by Procurement and 04 Nos. of POs need to be issued by procurement.

Activities In Progress:

Major machines spare parts checking by vendor/OEM is in progress.

Issuance of TA Roadmap (Rev-04) is in progress

Material reservation for Inst/Elect/Civil static Eqpt/NRVs are in progress.

Issuance of Major Jobs bar charts (Rev-01) are in progress

Technical evaluation & issuance of final recommendation memos for package contracts services are in progress, 15 Nos of final recommendation memos have been issued to procurement and 01 No. of PO has been issued by Procurement.

Technical evaluation & issuance of final recommendation memos for vendor services (FSEs) are in progress, 13 Nos. of final recommendation memos have been issued to procurement

Material reservation for PM orders and CM orders are in progress, completed 96% and 75% respectively

Turnaround CM order assessment is in progress, completed 80%.

Updating the list of CAPEX and modifications for TA2025 are in progress Meetings with the Operations, Engineering, Maintenance and Inspection team have been conducted and are ongoing We have achieved approximately 100% of our target

ACTIVITY STATUS

Planned Activities - November 2024:

To Start Issuance of P.Os for Vendor Services

Prepare lists of Vendors & Package Contracts Services Initiated by Technical Services

To Start Shelf Life Item Procurement + Belt Joints

To Conduct Overseas FAT

Concerns:

Completion of Technical Final Evaluation for 21 Nos of PRs - POs to be issued Required funds from Engineering was partially received. PRs are rerouted for actual amount. Material reservation for PM and CM orders are as follows:

PM Reservation Status: 96%.

CM Reservation Status: 75%

TA 2025 ROADMAP S-CURVE

Planned = 49.55%

Completed = 45.99%

Slippages = 3.56%

Slippages Due to the Following:

Issuance of TA Roadmap Rev-04 (70 % Completed)

Complete Issuance of PRs for Package Contracts i/p (90% completed)

Complete issuance of final recommendation for Package contracts i/p (41/42 Issued)

Complete issuance of final recommendation for manpower and equipment i/p (Manpower - 16 Issued; Equipment - 3 Issue)

Complete issuance of POs for manpower and equipment i/p

Complete Issuance of PRs for Vendor services i/p (38/40 Issued)

Complete Issuance of Package Contracts Services POs

Start the trade test for the Local Manpower

Start Kick-off Meeting with Manpower & Equipment

Suppliers

2025 WO

TA 2025 PR STATUS

EXPECTED DELIVERY FOR CAPEX PROJETCS

REFURBISHMENT STATUS

Refurbishment

Issued PO status

Refurbished&received

Repaircompleted,tobeshipped

UnderRefurbishment

Repaircompleted,tobeshipped

Refurbished&received

TA MATERIAL RESERVATION STATUS

Major Rotary Reservation Status

PendingOrders 194 Pending

CompletedOrders

PendingOrders

Minor Rotary Reservation Status

CompletedOrders 572

TA MATERIAL RESERVATION STATUS

TA 2025 CONFIRMED MAJOR JOBS

Ammonia Plant

TA 2025 CONFIRMED MAJOR JOBS

Methanol Plant

TA 2025 CONFIRMED MAJOR JOBS

Urea Plant

Management Meeting to discuss the Replacement of two end and two side walls at the Methanol Reformer (North & East Walls) in TA 2025.

Meeting with Operations, Engineering & Maintenance: To discuss TA 2025 Urea Plant Jobs - Mods + Capex

Meeting with Medical Team - Turnaround Preparation

Meeting with Logistics Team - Turnaround Preparation