W 3 alex gilbert on ppps and transportation

Page 1

PPP: Construction Planning Design A designer’s perspective RMIT Presentation | 6 August 2013

Alex Gilbert – Technical Director - Aurecon


Agenda 1.  Transport PPPs over the last 15 years – my experience 2.  The past – East Link 3.  The present – Peninsula Link 4.  The future – East West Link 5.  Summary 6.  Discussion


Personal Project Experience Year Year

Major Major Project Project

Country Country

Procurement Procurement type type

1998

Bute AvenuePFI PFI Bute Avenue

UnitedKingdom Kingdom United

PPP (PFI model) model)

1999

Roads in Dubai

UnitedArab Arab Emirates Emirates United

Traditional “construct only”

2000

New Providence Road Improvement Project

Bahamas Bahamas

D&C

2001-2

A43 Towcester to M40 Dualling

United Kingdom Kingdom United

D&C

2002-3

A303 Stonehenge Improvement

United Kingdom Kingdom United

ECI

2004

M1 Westlink Westlink

United UnitedKingdom Kingdom

PPP (DBFO model) model)

2004

PPP Motorways MotorwaysininSlovak SlovakRepublic Republic

Slovakia Slovakia

PPP (study (studyof ofoptions) options)

2005-6 2005-6 2006 2006

EastLink EastLink Calder Calder Freeway Freeway

Australia Australia Australia Australia

PPP PPP (Tolled) (Tolled) D&C D&C

2007 2007 2009-12 2009-12

Acacia Ridge Grade Road / Rail separation Acacia Ridge Grade Road / Rail separation Peninsula PeninsulaLink LinkPPP PPP

Australia Australia Australia Australia

Alliance Alliance PPP PPP (availability (availabilitymodel) model)

2013 2013 2014 2014

Port Port Capacity Capacity Project Project – – Roads Roads and and Services Services East West Link East West Link

Australia Australia Australia Australia

D&C D&C (novated) (novated) PPP (Tolled) PPP (Tolled availability model)


East Link – Project Summary •  39 km of tollway •  3 freeway to freeway connections •  Twin, 3-lane 1.6km tunnels under the Mullum Mullum Creek •  Additional 6kms of untolled connecting roads Ringwood Bypass •  Dandenong Bypass •  17 interchanges •  88 bridges •  2 railway crossings


East Link – PPP Structure Victorian Government SEITA Independent Reviewer Operations & Maintenance Transfield Services

ConnectEast

Design & Construction Thiess John Holland

Designers CW D&S, PB & Hyder

Tolling System Supplier SICE

Construction SubContractors & Suppliers


East Link Planning and design challenges •  Availability or resources •  Engineering (Design and Construction) •  Plant •  Materials •  Coordination of design •  3 major consultants •  Consistency and high quality •  External stakeholders


East Link Specific issues associated with PPP model •  Performance spec vs detailed spec •  Maximise traffic volumes •  Programme pressure •  Tolling issues •  Whole of Life costs


Peninsula Link Strategic Context

East Link

Peninsula Link


Project Benefits •  Up to 40 minutes travel time savings in peak periods •  Ease congestion on existing roads •  Bypass eight sets of traffic lights, six major roundabouts and a rail crossing •  Completion of missing link •  Road safety •  New Shared Use Path


PenLink– Project Description •  27 kilometres of freeway standard road •  Two traffic lanes in each direction •  On and off ramps to 11 roads including three freeway to freeway connections •  28 bridges (45 separate structures) •  Three million cubic metres of earthworks •  Around 1.5 million trees and plants requiring 80,000 cubic metres of mulch •  25 kilometre shared walking and cycling path •  High standard urban design, environmental management and community information


Procurement Model Availability PPP What is an Availability PPP? •  1st of its kind in Australia •  Toll free – payment based on lane availability and a series of KPI’s •  $759 million fully underwritten (debt and equity) •  Concession period – Delivery (D&C) + 25 years


Contractual Framework


Project Lifecycle EOI Released

31 March 2009

EOI Submitted

5 May 2009

RFP Released

24 June 2009

RFP Submitted

20 October 2009

Preferred Bidder

15 January 2010

Financial Close

8 February 2010

First Sod Turn

17 February 2010

Date of Completion

18 January 2013

Hand back to State

18 January 2038


Design Management Challenges •  110 Design packages •  6 Stages of review •  600+ Design Deliverables in 14 months •  Over 5,000 construction drawings •  14 Consultants •  Multiple stakeholders


Design Team Structure


Resourcing •  200 designers (75 FTE at peak)


Review Process


Programme


Interface Management


Technical Challenges


Soft ground

DESIGN CRITERIA •  Impact on Plains Grassy Wetlands •  Geotechnical •  Major flood catchment

EastLink Interchange The Challenge 21


EastLink Interchange The Solution

ink East L

Retaining walls Major art piece Peninsula Link

22

Straighten alignment

Relocate watercourse


How it should look 23


24

How it looked during construction


Stony Point Rail Bridge

25


Stony Point Rail Bridge

26


Peninsula Link – PPP issues •  Whole Life Cost •  Optimise Pavement •  Efficient Maintenance •  Sculpture programme •  Commercial opportunities

27


The next PPP East West Link

28


PPP Structure

29


Conclusion •  PPPs have been around for about 20 years are evolving •  PPPs are a popular way to deliver major Transport Infrastructure and becoming more so •  Most of the challenges in planning, designing and constructing major transport projects occur irrespective of procurement model •  With PPPs, WLC and operational considerations are built into the design more effectively


Discussion


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.