GULIN DERMAN CAMAS SELECTED WORKS
email: gulin@camaslondon.co.uk mobile: 07340211388
email: gulin@camaslondon.co.uk mobile: 07340211388
GULIN DERMAN CAMAS Birth
Born in April, 1985.
Education
ITU - Istanbul Technical University 2010 - 2012 - Architecture Master Program High Honour Student_ First Degree Graduate ISTANBUL - TURKEY YU - Yeditepe University 2004 - 2008 - Department of Architecture ISTANBUL - TURKEY
Awards
Bursa Metropolitan Municipality Orhangazi Square and Surrounding Urban Design Project Competition 5. Honorable Mention I 2012
Association Membership
In Professional Societies Chamber of Architects (Istanbul, TURKEY)
Work Experience
Alarga Architecture & Construction January 2018- June 2019 Leading Architect
YU - Yeditepe University 2003 - 2004 - English Prep School ISTANBUL - TURKEY
Bakirkure Architects October 2017 - January 2018 Leading Architect
Dogus High School 1996 - 2003 ISTANBUL - TURKEY Languages Software Knowledge
Key Qualificiations
Certificates
TA_ Tabanlioglu Architects October 2011 - October 2017 Senior Architect
Turkish English Autocad Photoshop Indesign SketchUP Revit MS Office Concept Design & Design Development Construction Drawings & Detail Design SMEP & Site Coordination Client Relations Team Management BIM Modelling RFI & RFP Preparation Prota Education Center (Revit) Istanbul, TURKEY I 2013 Akademya Education Center (Archicad) Istanbul, TURKEY I 2007 Anglo-Continental School of English Bournemouth,UK I 1998
EAA_Emre Arolat Architecture October 2008 - August 2011 Architect Freelance Work Experience
Serra Apartment Urban Transformation Project Facade Proposal I 2015 Ataman Construction Urban Transformation Projects Interior Design & 3D Visualisation Studies I 2014 Lineadecor Kitchen Manufacturer Warehouse Building Concept Design & Construction Drawings I 2014
Inspiring Trips
Austria Bulgaria Cyprus Denmark France Germany Greece Ireland Italy Montenegro
Netherlands Portugal Qatar Spain Sweden Switzerland South Africa UAE UK USA
W O R K 10+ Years
E X P E R I E N C E
ALARGA ARCHITECTURE January 2018June 2019
o Zorlu Energy Techno Store Interior Design Studies o Koctas Cafe Interior Design Studies o Koctas Head Office Entrance Lobby Interior Design Studies o Gerry Weber New Office Building General Arrengement Plans & Refurbisment Project o Barilla Office Area & Kitchen Interior Design Studies -Following up and coordinate design process, preparing general arrangement plans and FF&E projects, visiting and coordinating site and also ensuring employer relations. -Adapting showroom and service buildings of various brands in the automotive industry such as Ford, Opel, Hyundai, Citroën, Renault to existing buildings or designing new buildings in acoordance with company needs and preparing country-based corporate drawings inline with design standards and specifications.
BAKIRKURE ARCHITECTS October 2017January 2018
o Turgut Aydin Holding Interior Design and FF&E Package o Lila Paper Interior Design and FF&E Package -Contribution to material finish layouts -General Sections (1/50) -System Sections & Elevations (1/20, 1/10, 1/5) -Fixed furniture detail design & drawings (1/20, 1/10, 1/5) -Presentation Preparation
TABANLIOGLU ARCHITECTS October 2011October 2017
o Orientalist Museum I Schematic Design & Design Development I Doha, Qatar I 65.392m² -Design Coordination -SMEP Coordination -Interior Design of BOH areas in coordination with HdM. -Presentation Preparation -Detail Drawings (1/20, 1/10) -Design Development & Construction Drawings -QA / QC -Document Control -RFI & RFP Preparation -General Building Modelling in LOD300.
o Natural History Museum I Concept Development I Istanbul, Turkey I 60.000m² -Contribution to Concept Design & Development of Project -General Arrangement Plans&Section Development
TABANLIOGLU ARCHITECTS October 2011October 2017
-Preparing data and graphics for presentations and layouts -Presentation Preparation
o QWEC Office Towers+Retail Area Design Competition I Invited Competition I Doha, Qatar I 200.000m² -Contribution to Concept Design &Development of Project -General Arrangements Plans -Area Calculations -Presentation Preparation -SMEP Coordination
o Verra Suites I Residential I Under Construction I Istanbul, Turkey I 9.783 m² -Contribution to Concept Design & Design Development -Area Calculations -Municipal Approval Project -Client & Municipal Relations -General Arrangements Plans&Housing Units -Preparing data and graphics for presentations -Sketch-up mass modelling -Presentation Preparation -SMEP Coordination
o Dakar Business Hotel I Concept Design I Dakar, Senegal I 5.648m² -Contribution to Concept & Design Development of Project -General Arrangement Plans&Section Development -Area Calculations -SMEP Coordination -Preparing data and graphics for presentations and layouts -Presentation Preparation
o Akzirve Mixed-use Development I Hotel+ Residence+ Mosque+ Cultural Center+ Apartments I Design Competition I Istanbul, Turkey I 490.000m² -Contribution to Concept Design & Design Development -General Arrangements Plans&Housing Units -Area Calculations
o TEB Headquarters Office Tower I Invited Competition I Izmir, Turkey I 57.368 m² -Contribution to Concept Design & Development of Project -General Arrangement Plans&Section Development -Area Calculations -SMEP Coordination
TABANLIOGLU ARCHITECTS October 2011October 2017
-Preparing data and graphics for presentations and layouts -Presentation Preparation
-Presentation Preparation
oFatih Cultural Center I Construction & Detail Drawings I Istanbul, Turkey I 40.5151m²
o Aegen World Trade Center Mixed-use Development I Residence+Retail+Office+City Hall I Invited Competition I Izmir, Turkey I 234.635m² -Contribution to Concept Design & Design Development of Project -General Arrangements Plans & Housing Units -Area Calculations -SMEP Coordination -Preparing data and graphics for presentations and layouts -Presentation Preparation
o Halaskargazi Mixed-use Building I Residence +Hotel+Retail I Under Construction I Construction & Detail Drawings I Istanbul, Turkey I 86.500m² -SMEP Coordination -Detail Drawings & Construction Drawings
o Nida Tower I Office I Built in 2013 I Istanbul, Turkey I 54.992m² -Contribution to Concept Design, Design Development & Construction Drawing Phases -Area Calculations & Municipal Approval Project -General Arrangements Plans&Detail Drawings -SMEP Coordination -Preparing data and graphics for presentations and layouts -Partial Sketch-up modelling in order to solve geometrical problems and develop interior design studies. -Presentation Preparation
o Selcuk Ecza Headquarters I Office I Built in 2014 I Construction & Detail Drawings I Istanbul, Turkey I 26.451m² -Contribution to Construction Drawings and FF&E Package -Reflected Ceiling Plan Arrangements&Coordination -Detail Design & Interior Design Drawings (1/50, 1/20, 1/10...) -SMEP Coordination -Presentation Preparation
o Yenikapi Transfer Point & Archeo-park I Invited Competition I Istanbul, Turkey I 277.000m² -Contribution to Concept Design -General Arrangements Plans&Detail Drawings -Preparing data and graphics for presentations and layouts -Site Analysis
-Contribution to Construction Drawings -Reflected Ceiling Plan Arrangements&Coordination -Detail Design & Interior Design Drawings (1/50, 1/20, 1/10...)
EAA_ EMRE AROLAT ARCHITECTURE October 2008August 2011
o Zorlu Center Mixed-use Complex I Residence+ Hotel+Shopping Mall+ Office+ Carpark I Built in 2014I Construction &Detail Drawings I Istanbul, Turkey I 720.000m² -Contribution to Construction Drawings & Detail Design Drawings (1/100, 1/50, 1/20, 1/10) -SMEP Coordination of Office Units -Superposed Reflected Ceiling Plan Drawings
o EAA Office Building I Built in 2010 I Istanbul, Turkey -Contribution to Construction Drawings & Detail Design Drawings (1/100, 1/50, 1/20, 1/10) -Interior Design & Fitout Drawings -Site Control & Coordination -SMEP Coordination -3D Study Modelling
o Eyup Cultural Center & Marriage Hall I Built in 2010 I Construction & Detail Drawings I Istanbul, Turkey I 6.500m² -Contribution to Construction Drawings & Detail Design Drawings (1/100, 1/50, 1/20, 1/10) -Interior Design & Fitout Drawings -SMEP Coordination -3D Study Modelling
o Emre Arolat Residence I Built in 2009 I Interior Desing I Istanbul, Turkey I 213m² -Interior Design & Fitout Drawings -3D Study Modelling -Site Control & Coordination
o Kagithane Office Park I Built in 2012 I Construction & Detail Drawings I Istanbul, Turkey I 213m² -Contribution to Construction Drawings & Detail Design Drawings (1/100, 1/50, 1/20, 1/10)
o Folkart Narlidere Housing I Built in 2009 I Construction & Detail Drawings I Izmir, Turkey, 55.000m² -Contribution to Construction Drawings & Detail Design Drawings (1/100, 1/50, 1/20, 1/10)
S E L E C T E D
W O R K S
OFFICE
RESIDENTIAL
MIXED-USE
CULTURAL
HOTEL
TRANSPORT
QEWC
Verra Suites
AegeanWorldTradeCenter
Orientalist Muesum
Dakar Business Hotel
Yenikapi Transfer Point
TEB Headquarters
Folkart Narlidere Houses
Zorlu Center
Natural History Museum
Nida Office Tower
Selcuk Ecza Headquarters
Orientalist Museum
_ Confidential Project
DOHA, QATAR
Period : 2013 - 2017 Building Type : Mueseum Status : Schematic Design Design Development Construction Documentation Total Area
: 65.392 m²
Client Client Agent Project /Construction Management
: Qatar Museum Authority : Lusail Real Estate Development : Qatar Project Management
Consultants
: Buro Happold Engineering (SMEP Engineering) Anne Minors & Sound Space Design (Performance & Theater) Portland (Way finding & Signage) CICO (Local Architect) Tricon (Kitchen & Catering ) Proge + Rider Levett Bucknall (Cost Control & QC) Dalokay Design Studio (Landscape & Water Features)
Design Architect Executive Architect
: Herzog & de Meuron (HdM) : Tabanlioglu Architects (TA)
Personal Responsibilities
: Design Coordination with HdM SMEP Coordination Interior Design of BOH areas General Building Modelling in LOD300.
Architectural Team
: Salih Yilgorur, Selcen Tuncer, Zeynep Kocdur, Emre Ozberk, Derya Tezel, Nihal Congur, Funda Tezel, Cetin Ayik, Esen Bozdemir, Melis Muratoglu, Kaan Karabay, Mustafa Gurbuz, Hatice Cagiran, Muge Yalcin, Sedef Avunduk, Selin Baykal, Yeliz Arslantas, Deniz Arikan, Figen Akyuz, Gurkan Dogan, Cansu Yeni, Cigdem Durmayaz, Dogancan Demir, Pelin Serin, Ozge Duzgun, Reyhan Devran, Tunay Tuncer KÄąr , Seyhan Deniz, Meryem El Mejjad, Zeynep Yilgorur.
Presentation Preparation Detail Drawings Design Dev. & Construction Drawings RFI & RFP Preparation
With respect to the confidentiality issues of this project, studies can not be presented clearly. Seperate hardcopy will be presented in the interview. As the design architect, the scope of work of HdM, was to design front of house areas (FOH), meanwhile, the scopes of TA was to design back of house areas (BOH). TA was coordinating and organising all the consultants and also responsible from all processes, as an executive architect. During the process, the project has been suspended, as per the client demand, for several times from 2013 to 2018. Each time, they have decided to continue with major changes, in order to reduce the cost. As this is a long term and large scale project, a crowded architectural BIM team has been organised in TA. By the time passes, new collegues joined to our team. With the contribution of Revit based consultants, all the drawing phases of the project have been created in LOD300 BIM model.
QE WC DOHA, QATAR Period Building Type Status Total Area Client Consultants Architectural Team Personal Responsibilities
: : : : : : :
2017 Office + Retail Invited Competition 200.000 m² Qatar Electricity & Water Co. BERM (Structural Engineering) Barbanel (Mechanical & Electrical Services) : Gokhan Catikkas, Beyza Yazici : Contribution to Concept Design & Development of Project General Arrangements Plans Area Calculations Presentation Preparation SMEP Coordination
Aiming to illustrate one of the most significant symbols of the modern day, Twin Towers are designed to embrace the skyline in the upmarket Lusail, emerging high-end district with extensive contemporary architectural and urban projects of Doha, Qatar. Picturesque quarters of the city, the canal, the cityscape and the sea view are all a part of the panoramas of the towers and they will contribute to urban view. Building a dynamic and impressive gateway visually, the new development will also define the experience of contemporary downtown urban living. The complex consist of two towers with a shared base; yet, instead of towers sitting on the podium, two towers are designed with a minimal footprint on the ground, forming the base in interaction with each other, resulted in a shaded pedestrian circulation area. Getting higher, both towers slightly swell out and wane, giving a twisting expression, yet in terms of engineering, the structure stays feasible. Together with the vertical slabs, the curved form of the towers provides shading, particularly on the west, ensuring protection against direct sunlight. Glazed openings at various floors, at lower floors of the base or at the high rises, provide panoramic views while protecting from wind (sand storm) and heat. Granting %80 efficiency in the building use, potential land use patterns considered from an ecological perspective in addition to topological and functional references. Building infrastructure and urban development concerns solved in the framework ecological concerns. To achieve the best solutions, GSAS rating system is adopted as a manner of demonstrating the commitment to meeting the development requirements across the site.
Period Building Type Status Total Area Client Museum Consultant Architectural Team
: : : : : : :
Personal Responsibilities
: Contribution to Concept Design & Development of Project General Arrangement Plans & Section Development Preparing data and graphics for presentations and layouts Presentation Preparation
2017 Muesum Concept Development 60.000 m² Istanbul Mertopolitan Municipality Ralph Applebaum Associates New York Gokhan Catikkas, Beyza Yazici
NATURAL HISTORY MUSEUM
ISTANBUL, TURKEY
Istanbul Natural History Museum proposal merges conventional museum and a public park experience. It is not a museum you visit once, it is a place where you want to go every weekend for different activities on the lake, ceremonies, lectures, concerts or may be even agricultural activities. The property is surrounded with dense residential area, rendering the project a breathing point for the residents and also with existing public transportation opportunities broadens the target visitors to the whole city for visiting the lake, museum, botanical garden even arboretum and academy.
The balance between natural and human made has to be found, at first the project plot was a natural stone formation, then humans interacted with it by building a stone quarry as the human interaction continued we formed the terraces, buildings, tunnels and carved out a huge chunk of land. When human activities finished nature again took over, filling the land with water and generating beautiful fauna with birds and fishes living in harmony. Now its our turn, but this time as we request to use this precious landscape for breathing, which is left in the middle of a 16 million city, we wont “build� it, the decision is to embrace the nature, touch it gently and follow the existing outlines.
The museum, where the main entrance is designed at the upper level of the quarry, follows the terraces in the traces of the topography up to the the pond and settles towards the lower elevations. Also the content of the museum is parallel to the museum circulation that needs to be followed. As you go down from the upper level, the oldest layers of history are presented to the visitors. The panoramic elevators, that wellcomes the visitors on the upper level, takes you to a journey in time and history as it goes down to the lowest level of the museum. It feels like as you are going down in a gap towards the beginning of the history. While going down, the first amazing moments are experienced to the visitors, by the spectacular objects like flying pre-historic birds, ceratures and fossils. Also astonishing projections are presented during the vertical travel in the elevator that embraces the visitors.
DAKAR BUSINESS HOTEL Period Building Type Status Total Area Client Architectural Team Personal Responsibilities
: : : : : :
DAK AR, SENEGAL
2015 Hotel Concept Project & Design Development 5.648 m² Summa Basak Uysal, Erman Ucaroglu, Utkan Yonter
: Contribution to Concept & Design Development of Project General Arrangement Plans & Section Development Area Calculations SMEP Coordination Preparing data and graphics for presentations and layouts Presentation Preparation
STANDARD ROOM
STANDARD SUITE
CORNER SUITE
TEB HEADQUARTERS ISTANBUL, TURKEY Period Building Type Status Total Area Client Architectural Team
: : : : : :
2014 Office Invited Competition 57368 m² TEB Ahmet Corapcıoglu, Enes Yucepur, Sertac Tumer, SelinBaykal, Ali Riza Sacan, Esra Can, Onur Tanik
Personal Responsibilities
: Contribution to Concept Design & Development of Project General Arrangement Plans & Section Development Area Calculations SMEP Coordination Preparing data and graphics for presentations and layouts Presentation Preparation
AREA SCHEDULE & BUILDING PROGRAM
6th FLOOR PLAN ANLYSIS
The functions are visible on the elevation; the protruding low-rise structure houses basically the public spaces, mainly the 250-seat auditorium at the north end of the new building, conference halls next to BNPP office areas. This low-rise portion of the building is also elevated like the prow, signaling the entrance of the lobby to the exhibition hall, and to the egg-shaped auditorium on the first floor. The very edge of the prow serves as the foyer, overlooking the adjacent woods.
AEGEAN WORLD TRADE CENTER IZMIR, TURKEY Period Building Type Status Total Area Client Consultants Architectural Team Personal Responsibilities
: : : : : : : :
2016 Mixed-use Development (Office, Residence, City Hall, Fitness Center, Retail) Invited Competition 234.635 m² Folkart Buro Happold Engineering Ali Caliskan, Utkan Yonter, Firat Gunes Balci, Cigdem Yarikkas. Contribution to Concept Design & Design Development of Project General Arrangements Plans & Housing Units Area Calculations SMEP Coordination Preparing data and graphics for presentations and layouts Presentation Preparation
As per the Client request, this high-rise building is planned to be the tallest building in Europe , with a height of 315m, in 2016. 81 storey tower features several open space areas with at times double volume voids at various levels. The layout of the office floors allows for utmost functionality with open spaces and high ceilings. The top and penultimate floors are respectively VIP lounge and a rooftop garden serves as a terrace lounge.
SELCUK ECZA HEADQUARTERS ISTANBUL, TURKEY Period Building Type Status Total Area Client Architectural Team
: : : : : :
2012-2014 Office Built 26.451 m² Selcuk Ecza Holding Ali Caliskan, Utkan Yonter, Gokce Gunduz, Tugce Gulec, Zeynek Dundar, Ismail Ulukaya, Sema Turker, Fatma Ural, Ali Riza Sacan, Onur Tanik, Zeynep Eker Yilgorur.
Personal Responsibilities
: Contribution to Construction Drawings and FF&E Package Reflected Ceiling Plan Arrangements & Coordination Detail Design & Interior Design Drawings (1/50, 1/20, 1/10...) SMEP Coordination Presentation Preparation
DYNAMIC MASSING, SPACIOUS INTERIORS The owner of the pharmaceutical company is an elderly couple who would like the house feeling at the office; accordingly, scales, organization and aesthetics refer to residential settings, traditional İstanbul mansions. Juxtaposition of seven house-like volumes with hipped roofs forms the campus. The individual ‘houses’ integrate to each other either through gardens, roof gardens, upper or lower patios and paths and atriums. The brown color of the exterior brings up the soft wood effect and unifies the structure. Daylight enters through roofs and all transparent sides, creating a diffused lighting mood in the spacious internal space until the basement floor. To provide the balance of light and shadow and to increase the efficiency of passive climate control, the masses are enveloped with a designed mesh system. Three floors for office use and two underground floors are reserved for car parking of the five-storey structure. Above the car park, first basement floor is at the sunken garden level; besides offices, multi-purpose halls, staff dining hall, sports and lounge zone are located, with an easy access to the green landscape. In addition to the wide windows, interiors of the basement floor receive daylight also through atriums. The main entrance to the building is provided at the ground floor, by way of a bridge, side bridges link the roof terraces. Atriums and interior gardens create social zones between offices, located at the ground floor. “Private world” of both partners constructed as mezzanine duplexes at two ends of the top floor.
NIDA TOWER ISTANBUL, TURKEY Period Building Type Status Total Area Client Architectural Team Personal Responsibilities
: : : : : : :
2013 Office Built 54.992 m² Tahincioglu Ali Caliskan, Utkan Yonter, Canan Saridal, Cem Berdan, Ali Olgu Ceylan. Contribution to Concept Design, Design Development & Construction Drawing Phases Area Calculations & Municipal Approval Project General Arrangements Plans & Detail Drawings SMEP Coordination Preparing data and graphics for presentations and layouts Partial Sketch-up modelling in order to solve geometrical problems and develop interior design studies. Presentation Preparation
The tower will consist of commercial office space with a public piazza before its entrance on the ground floor. Nidakule Levent is an A+ office project on the main axis of the Central Business District of Istanbul, on the european side of the city.
YENIKAPI TRANSFER POINT AND ACHAEO-PARK ISTANBUL, TURKEY Period Building Type Status Total Area Client Consultants
Architectural Team
Personal Responsibilities
: : : : : :
2012 Transport Invited Competition 277.000 m² Greater Istanbul Municipality Buro Happold Engineering (All Engineeering Services) Martha Schwartz Partners (Landscape) Dinnebier Licht (Lighting) BurcakMadran (Museum & Exhibition) Baykan Gunay (Urban Planning) Rustem Aslan (Archeological) : Ali Caliskan, Utkan Yonter, Caglayan Cagbayir, Ahmet Corapcioglu, Murat Cengiz, Cagri Akay, Nur Cikla, Fatma Aliosman, Dide Dinc, Enes Yucepur, Goktug Turkkan, Meral Yilmaz, Ozge Kaya, Gozde Kaya, Ceyda Gokoglu, Berna Ataman. : Contribution to Concept Design General Arrangements Plans & Detail Drawings Preparing data and graphics for presentations and layouts Site Analysis Presentation Preparation
THE NEXUS IN THE 21ST CENTURY Istanbul In Yenikapı, infrastructure is ideal in terms of functional rapport yet what’s missing was the articulation of the urban space; as a method of styling the joints in between the formal elements, architectural design was the major requirement to build the relation; city space is expected to extend from surface to subsurface, and vice versa. Avoiding imposing an icon, the structure is not aimed to perform a dominant attitude; on the contrary, the structure is considered as one of the elements in building the space. The objects of urban living integrate seamlessly with sunken public piazzas of the Center, being its coupling interface with the city. Yenikapı becomes the nexus of all underground connections related to the city surface smoothly in the course of the lower piazzas created under a semipermeable roof system. The protecting shield designates the space; the permeable elements filter the daylight into the sunken piazza that creates a holly vision, besides feeling of spaciousness, exploring new possibilities of contemporary temples where people meet. The passer-by’s or the stroller’s curiosity is first piqued by the display units of the City Archive, located in the piazza; challenged with the first encounters at this strata, one may choose to become a stalker towards the Archeopark* and the main expedition area that is designed as the site museum; the units of exhibition is stretched towards the Archeopark area, preserving the street level building relation. Museum is designed in relative pieces which may be consumed separately or totally in an order. *Excavations undertaken during the application of the transportation projects, both the remains of a 1600 year old “Theodosius Port” together with the “35 antique ship remains” of the World’s largest fleet collection and more than 10,000 archeological founding were unearthed. At the same excavation area, 8500 years old settlements of first Neolithic age were also found.
VERRA SUITES ISTANBUL, TURKEY
Period Building Type Status Total Area Architectural Team
: : : : :
2016 Residential Concept Project, Design Development & Municipal Approval Project 9.783 m² Gokhan Catikkas, Taner Berber
Personal : Contribution to Concept Design, Design Development Responsibilities Area Calculations & Municipal Approval Project Client & Municipal Relations General Arrangements Plans & Housing Units Preparing data and graphics for presentations Sketch-up mass modelling Presentation Preparation SMEP Coordination
sales office
ZORLU CENTER ISTANBUL, TURKEY Period Building Type Status Total Area Client Personal Responsibilities
: 2014 : Mixed-use Complex (Shopping Mall, Residence, Office, Terrace Houses, Hotel, Cultural Center, Car Park) : Built : 720.000 m² : Zorlu Real Estate Investment Company : Contribution to Construction Drawings & Detail Design Drawings (1/100, 1/50, 1/20, 1/10) System sections of Cultural Center SMEP Coordination of Office Units Superposed Reflected Ceiling Plan Drawings for Residence, Office, Terrace Houses and Car Park
FOLKART NARLIDERE HOUSING Period Building Type Status Total Area Client Personal Responsibilities
: : : : : :
2009 Residential Built 55.000 m² Folkart
IZMIR, TURKEY
Contribution to Construction Drawings & Detail Design Drawings (1/100, 1/50, 1/20, 1/10)
A-A Section
B-B Section
Parcel 2 1 Main entrance 2 Elevator 3 Entry 4 Living Room 5 Kitchen 6 Bedroom 7 Master Bedroom 8 Bathroom 9 Changing Room 10 Terrace 11 Garden 12 Pool
Parcel 2_ Ground Floor Plan
Parcel 2_ 1st-7th Floor Plan
GULIN DERMAN CAMAS S E LECTED WORKS gulin@ca m aslo ndo n.co.u k 073 40211388