In the last edition of the HORAN magazine, we announced our expansions in the Dayton and Columbus markets. Since then, both teams have settled in and continued to provide specialized expertise to our clients.

Here’s a look at the work that’s been done to renovate both locations. We look forward to hosting clients, partners and friends at our new offices soon.

Dublin Office Renovation Timeline

October 2020 Demolition began on the office space.

December 2020

A fresh coat of paint on the walls before the new carpet goes in.

February 2021

The new office furniture gets installed.

March 2021 6805 Avery-Muirfield Drive is ready to host clients!

Dayton Office Renovation Timeline

December 2020 Aaron Reiff, VP of IT & Facilities, beginning demolition.

January 2021 Demolition continues at 7475 Paragon Road.

February 2021 Construction begins as walls are reinstalled to create a collaborative work space.

March 2021 The concrete floor is sealed in the Paragon Conference Room area—perfect for hosting events.

May 2021 The furniture has been installed and the office is ready to welcome our employees.