CONTRACTORS’ CORNER SUCCESSFUL TAKE-OFF FOR AIRPORT IRRIGATION INSTALLATION Brisbane irrigation company TIS recently completed the design and installation of a pumping and irrigation system at Brisbane Airport, as part of a new runway development. By anyone’s estimation, the project was a major one that included installing 3800 above-ground sprinklers, more than 100 km of pipework and a 105 L/sec Grundfos pump station. We spoke to Brett Peel, owner of TIS, to find out about the job. IA. What was the background to the job and how long did it take to complete? Brett. Early design of the irrigation works started about twelve months before breaking ground on site. While the lead time was long, it was what would normally be expected for a landmark project of this type. From project award and start of design and offsite fabrication, the project period was just over two years. IA. What equipment was used, particularly during installation? Brett. The project used a dedicated 4 ML irrigation dam next to which we installed a Grundfos MPC variable-speed pump station. As the pumping system was a critical component of the project, it was housed in a 12 m shipping container with the pump set, controls, filtration and metering system all fitted off site and delivered ready to plug and play.

The pumping system was fitted off-site in a shipping container and delivered ready to plug and play.

Once the pump was in place, a 400 mm suction line was connected to the pump station power supply and we were able to provide water to the site within two days. Buttwelded HDPE up to 400 mm was used in our mainline layout with Toro P220 solenoid valves and VYRSA impact sprinklers used throughout the site at the pointy end of the system. IA. What were the key issues that you had to consider when designing the job? Brett. As most of the areas to be irrigated were either seeded or stolonised, it was extremely important that we were able provide reliable irrigation when and where it was needed.

A successful take off for a new runway development at Brisbane Airport that included a significant irrigation installation.

36


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Bookshelf

2min
page 50

New Products

7min
pages 51-54

ICID Insights

3min
page 49

Business Feature

2min
page 48

How water is used in the Murray-Darling Basin

4min
pages 46-47

Murray-Darling Basin water markets in need of major changes

4min
pages 44-45

Calculating Readily Available Water

5min
pages 40-41

Professional Development

3min
pages 42-43

State Roundup

1min
page 37

Contractors' Corner

4min
pages 38-39

Future-proofing Western Australia’s south-west

9min
pages 34-36

Around Industry

6min
pages 30-31

Waterway health and urban design

5min
pages 28-29

The Big Issue

4min
pages 32-33

Rainwater Harvesting Australia looking to consolidate achievements in 2020-21

2min
page 27

IAL News

11min
pages 23-26

Precision agriculture shows promise for vegetable production

5min
pages 20-21

Irrigation scheduling options: pros and cons

2min
page 22

Technology: Rural

4min
pages 10-11

SMART IRRIGATION FEATURE

3min
pages 18-19

Pumping system supplies farm’s water needs

4min
pages 14-17

Chairman's Message

2min
page 5

Research

5min
pages 12-13

Technology: Urban

2min
page 8

From the CEO

2min
pages 6-7

FEATURE ARTICLES

2min
page 9
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.