Oilsands Review Project Status October 2012

Page 1

P R o J E C t S tAt u S

project status

10 12

Athabasca Region Industrial Heartland Region Cold Lake Region

Sourced from company releases, the Energy Resources Conservation Board, and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.

Peace River Region Northwestern Saskatchewan

For even more details on all of these projects, visit www.oilsandsreview.com.

CuRREnT PRoJECT

CaPaCiTy

sTaRT-uP

REGulaToRy sTaTus

135,000

2008

operating

10,000

2014

approved

Phase 2B

45,000

TBD

approved

Phase 3

80,000

TBD

approved

5,000

2012

operating

millennium Debottlenecking

Phase 1

110,000

2012

Construction

Phase 2

110,000

2015

Construction

Phase 3 Debottleneck

70,000

2020

approved

Shell Albian Sands Jackpine

Updated: Aug 2012

The Government of Canada’s joint review panel reviewing the proposed Jackpine mine expansion has determined that it has sufficient information to proceed to a public hearing. The hearing will commence on oct. 29, 2012, at macDonald island Park in fort mcmurray. Expansion

100,000

2017

application

Phase 1a

100,000

2010

operating

100,000

TBD

Muskeg River

approved Updated: Aug 2012

shell reports that the athabasca oil sands Project (muskeg River and Jackpine) has now reached the milestone of 500 million barrels of cumulative production.

sTaRT-uP

REGulaToRy sTaTus

Commercial

155,000

2002

operating

Expansion & Debottlenecking

115,000

TBD

approved

Pierre River

Updated: Aug 2012

a joint review panel of the Canadian Environmental assessment agency and Energy Resources Conservation Board has been established to review the proposed Pierre River mine project. The timeline for the joint review panel to submit its report is 550 days (18 months) from coming into force in July 2012. Phase 1

100,000

2018

application

Phase 2

100,000

TBD

application

Updated: Jul 2012

2008

operating

294,000

1967

operating

north steepbank Extension

180,000

2012

operating

4,000

2007

operating

steepbank Debottleneck Phase 3

23,000

Fort Hills

Updated: Jul 2012

suncor expects to present development plans to the board of directors for a sanctioning decision in 2013.

Updated: Jul 2012

imperial oil says that as of the end of Q2/2012, Kearl Phase 1 is 94 per cent complete, with construction 88 per cent complete. all modules fabricated in Korea and transported through north america have now arrived at site and are being reassembled and integrated into the plant.

Phase 1B

CaPaCiTy

millennium mine

Debottleneck

kearl

NEW INFORMATION THIS MONTH

suncor says it has its tailings reduction operations (TRo) infrastructure project and commenced operations. it is also in the process of starting up the hydrotreating unit and hydrogen plant of the new millennium naphtha unit, which is expected to stabilize secondary upgrading capacity and provide flexibility during maintenance activities for secondary upgrading units in the future.

Imperial Oil Limited

Base Operations Updated: Aug 2012

Canadian natural says its third ore preparation plant, now fully operational, is contributing to safe, steady and reliable operations. The staged expansion to 250,000 barrels per day continues to progress on track, although Canadian natural has reduced its 2012 project capital for Horizon by $330 million to $1.55 billion. The company says this is a result of overall cost reductions and strategic deferrals to achieve greater cost certainty.

Tranche 2

NEW EXPORT PIPELINES

Suncor Energy Inc.

Horizon

Phase 2a

INDUSTRIAL HEARTLAND REGION

COLD LAkE REGION

CuRREnT PRoJECT

Canadian Natural Resources Limited

Phase 1

SASkATCHEWAN REGION

SOUTH ATHABASCA REGION

PEACE RIVER REGION

NORTH ATHABASCA REGION — MINING •

NORTH ATHABASCA REGION

Phase 1

25,000

TBD

approved

165,000

2016

approved

Voyageur South

Updated: May 2012

suncor considers Voyageur south to be a “longer-term” project and has not confirmed a start-up date. Phase 1

120,000

TBD

application

Syncrude Canada Ltd. •

Mildred Lake/Aurora North & South

Updated: Aug 2012

lead partner Canadian oil sands says Coker 8-3, the newest part of the syncrude upgrader, has achieved a run length of 36 months. Coker 8-2 achieved the same last year. average coker run lengths at syncrude over the past five years have been 28 months. aurora south Train 1

100,000

2016

approved

aurora south Train 2

100,000

2018

approved

Base mine stage 1 & 2 Expansion

290,700

1978

operating

116,300

2006

operating

stage 3 Expansion Teck Resources Limited Frontier

Updated: Jul 2012

Teck says it anticipates receiving the final supplemental information requests relating to the frontier regulatory application in Q3/2012 and responding in Q4. Phase 1

75,000

2021

application

Phase 2

80,000

2024

application

Phase 3

80,000

2027

application

Phase 4 Equinox

40,000

2030

application

Total E&P Canada Ltd. Joslyn North Mine

Updated: Jul 2012

Project partner suncor Energy says development plans will be submitted to the companies’ respective boards of directors for a sanctioning decision in 2013. Phase 1

100,000

2018

approved

OCTOBER 2012 | oilsanDsREViEW.Com 45


P R o J E C t S tAt u S

CuRREnT PRoJECT

CaPaCiTy

sTaRT-uP

REGulaToRy sTaTus

CuRREnT PRoJECT

CaPaCiTy

sTaRT-uP

REGulaToRy sTaTus

application

NORTH ATHABASCA REGION — IN SITU

Dover south Phase 4

50,000

2022

Athabasca Oil Corporation

Dover south Phase 5

50,000

2024

Birch

Updated: Jul 2012

aos says that $26.3 million was spent on Birch in the first half of the year on its winter drilling and 3-D seismic programs. These both support the filing of its regulatory application, which is anticipated by the end of 2012. Phase 1

12,000

TBD

Dover West Carbonates (Leduc)

announced Updated: Jul 2012

aos says testing of its TaGD technology has demonstrated proof of concept. Design basis memorandum engineering for the demonstration project is wrapping up, and engineering design specifications work has begun. Construction has started on a heater assembly facility outside of strathmore, alta. Phase 1 Demonstration

6,000

2015

Phase 2 Demonstration

6,000

TBD

Dover West Sands & Clastics

application application Updated: Jul 2012

aos says the first round of supplemental information requests relating to its application have been received and design basis memorandum engineering is progressing. Phase 1

12,000

2015

application

Phase 2

35,000

2018

announced

Phase 3

35,000

2020

announced

BP p.l.c. Terre de Grace

Updated: May 2012

BP says that ongoing appraisal activities include delineation drilling, seismic acquisition and appraisal of water sources. Pilot

10,000

TBD

approved

Canadian Natural Resources Limited Birch Mountain

Updated: Jul 2012

Canadian natural says geological scoping is underway. Phase 1

60,000

2019

announced

Phase 2

60,000

2023

announced

Cenovus Energy Inc. •

Mackay River

application Updated: Apr 2012

ERCB project approval granted January 2012. Dover opCo says construction is underway. Phase 1

35,000

2014

Construction

Phase 2

40,000

2017

approved

Phase 3

40,000

2019

approved

Phase 4

35,000

TBD

approved

E-T Energy Ltd. Poplar Creek

Updated: Jun 2012

The ERCB has released its decision on the 10,000-barrel-per-day project application. it says E-T has not demonstrated the technology is capable of obtaining or sustaining commercial production rates and the application is not approved. The ERCB says E-T can reapply based on more performance data, which the company says it has (the application did not include data from the current test). Experimental Pilot

1,000

2007

operating

Phase 1

10,000

TBD

announced

Phase 2

40,000

TBD

announced

Husky Energy Inc. Saleski

Updated: Jul 2012

Husky says evaluation work continues, as does design basis memorandum work for the pilot plant and initial field environmental monitoring. These activities will support a regulatory application. Carbonate Pilot

TBD

2016

Sunrise

announced Updated: Jul 2012

Husky says drilling of its planned 49 saGD well pairs is now complete. Detailed engineering is also complete, and construction of field facilities has reached 50 per cent completion. Phase 1

60,000

2014

Construction

Phase 2

50,000

2016

approved

Phase 3

50,000

TBD

approved

Phase 4

50,000

TBD

approved

Ivanhoe Energy Inc.

Telephone Lake Borealis

Updated: Aug 2012

Cenovus says it has finished its search for a strategic partner for Telephone lake and instead will go it alone on the project. Phase a

45,000

TBD

application

Phase B

45,000

TBD

application

Dover Operating Corp. Dover

Updated: Jul 2012

The director of environmental assessment has notified the ERCB that the environmental impact assessment report for the project is complete.

Tamarack

Updated: Jul 2012

ivanhoe says it has received and responded to the second round of supplemental information requests regarding its project application from the ERCB. it continues to expect approval in 2012. Phase 1

20,000

2013

application

Phase 2

20,000

TBD

application

Marathon Oil Corporation Birchwood

Updated: Jul 2012

marathon says that based on results of completed appraisal drilling, a regulatory application will be filed in 2012.

Dover north Phase 1

50,000

2016

application

Dover north Phase 2

50,000

2018

application

Dover south Phase 2

50,000

2022

application

Lewis

Dover south Phase 3

50,000

2020

application

Pilot

Demonstration

12,000

2016

1,720

2013

application

Oak Point Energy Ltd. Updated: Mar 2012

Engineered Fabric Building Solutions

application

Warehousing

Proven, reliable and responsive building solutions. Over 12,000 structures in 90 countries worldwide.

Calgary, Alberta

www.sprung.com/oilgas 46 oilsanDs REViEW | OCTOBER 2012

1.403.601.2292 Toll Free:

1.800.528.9899


P R o J E C t S tAt u S

CuRREnT PRoJECT

CaPaCiTy

sTaRT-uP

REGulaToRy sTaTus

CuRREnT PRoJECT

SilverWillow Energy Corporation •

Audet

12,000

2016

announced •

Southern Pacific Resource Corp. STP-Mckay

Updated: Aug 2012

a Phase 1

10,000

2015

application

a Phase 2

20,000

2018

announced

B Phase 1

20,000

2021

West Ells

announced Updated: Aug 2012

12,000

2012

operating

a Phase 1

5,000

2013

Construction

6,000

TBD

application

a Phase 2

5,000

2014

approved

Phase 2a

12,000

2015

application

Phase 2B

6,000

TBD

application

a Phase 3

20,000

2018

announced

B Phase 1

20,000

2020

announced

B Phase 2

20,000

TBD

announced

C Phase 1

30,000

TBD

announced

Phase 1 Expansion

Suncor Energy Inc. Firebag

Updated: Jul 2012

suncor says construction of the stage 4 expansion is 90 per cent complete. Production from firebag’s combined phases is now approaching 100,000 barrels per day. Cogeneration and Expansion

25,000

2007

stage 1

35,000

2004

operating

stage 2

35,000

2006

operating

stage 3

62,500

2011

operating

stage 3-6 Debottleneck

23,000

TBD

application

stage 4

62,500

2013

Construction

stage 5

62,500

2018

approved

stage 6

62,500

2019

Lewis

SOUTH ATHABASCA REGION — IN SITU

operating

Alberta Oilsands Inc. Clearwater West

Phase 1 Pilot Phase 2

approved

40,000

TBD

application

Phase 2

40,000

TBD

application

Mackay River

40,000

2016

application

Phase 1

33,000

2002

operating

Harper

Updated: May 2012

1,000

2011

Legend Lake

B Phase 1

Updated: Jul 2012

Phase 1

12,000

2014

application

Phase 2

35,000

2017

announced

Phase 3

35,000

2019

announced

operating Updated: Aug 2012

10,000 20,000 20,000

2016 TBD TBD

Blackrod

Updated: Aug 2012

BlackPearl is planning to drill a second horizontal well pair at its operating pilot in the first quarter of 2013 in order to test alternative operating strategies to those that have already provided commercial production rates. The company is nearing completion of fEED for the commercial project, which will lead to the award of an EPC contract later this year. Phase 1

20,000

2015

application

Phase 2

30,000

2018

application

announced

Phase 3

30,000

2021

application

announced

Pilot

800

2011

operating

sunshine says it has received a supplemental information request from the ERCB relating to the project application and will respond in the near term. a Phase 2

announced

BlackPearl Resources Inc.

sunshine says that steam cycle injection operations at Harper have proved thermally induced oil mobility.

a Phase 1

application

2016

Hangingstone

Sunshine Oilsands Ltd.

Carbonate Pilot

TBD

aos says fEED and procurement are underway, with orders now placed for all major long-lead items needed for plant construction. approval anticipated later in 2012.

Updated: Jul 2012

mR2

4,350 25,000

Athabasca Oil Corporation

Updated: Dec 2010

Phase 1

Updated: Jun 2012

alberta oilsands says it has responded to a third round of supplemental information requests from the ERCB regarding the project application. The company expects the regulator will hold a public hearing into the project due in part to its proximity to the fort mcmurray airport.

suncor plans to complete routine planned maintenance at macKay River over the end of Q3 and the start of Q4/2012.

Thickwood

REGulaToRy sTaTus

sunshine says constuction at West Ells is on time and on budget. The central processing facility site has been cleared, fEED is complete, all long-lead equipment has been ordered and 75% of secondary long-lead equipment has been procured. no major delays have been encountered to date.

Updated: Jul 2012

southern Pacific says steaming has begun at the sTP-mcKay project. Phase 1

sTaRT-uP

sunshine says fEED has been initiated for the Thickwood project. The company has also submitted its responses to the ERCB’s supplemental information requests relating to the project application.

Updated: Aug 2012

silverWillow says it is continuing the analysis of data gained from the winter field program and has initiated reservoir simulation studies and a geo-mechanical evaluation program to better assess caprock. Tender packages for preliminary engineering of production facilities and environmental and regulatory support have been prepared, to be awarded in Q3. Regulatory application to be filed in 2013. Pilot

CaPaCiTy

application

CUSTOMER FOCused. engineering driven.

and Competitive like it’s always the playoffs

eXperienCe • eXCellenCe • eXeCution

As SAGD specialists, PROJEX brings proven rigor to oil sands thermal engineering projects. What we don’t bring is red tape and bureaucracy. Give us a call. We’d welcome the chance to show you the PROJEX difference. Contact Scott Rempel at 403.705.4151.

OCTOBER 2012 | oilsanDsREViEW.Com 47


P R o J E C t S tAt u S

CuRREnT PRoJECT

CaPaCiTy

sTaRT-uP

REGulaToRy sTaTus

Canadian Natural Resources Limited Updated: Jul 2012

Canadian natural says geological scoping is underway.

Updated: Jul 2012

While regulators review the commercial application, Cenovus continues development work at its pilot. it is currently installing a third steam generator, and anticipates steam injection at its second well pair to start in Q3/2012.

40,000

2021

announced

Phase a

60,000

2017

application

40,000

2025

announced

Phase B

60,000

TBD

application

Updated: Aug 2012

Phase C

60,000

TBD

application

600

2011

operating

Grouse

50,000

2018

kirby North

application Updated: Aug 2012

Canadian natural says the 2012 stratigraphic test well drilling program is complete and procurement of long-lead items is progressing. Phase 1

40,000

2016

Phase 2

40,000

2019

kirby South

application application Updated: Aug 2012

Canadian natural says construction of Phase 1 was 53% complete at the end of Q2 and remains on schedule. Drilling is nearing completion on the fourth of seven pads with wells confirming geological expectations. Phase 1

40,000

2013

Construction

Phase 2

20,000

2020

application

Cavalier Energy Inc. •

REGulaToRy sTaTus

Phase 2

Commercial

sTaRT-uP

Phase 1

Canadian natural says design basis memorandum engineering is progressing on track with completion targeted this year.

CaPaCiTy

Pelican Lake Grand Rapids

Gregoire Lake

CuRREnT PRoJECT

Hoole

Updated: Aug 2012

Cavalier says it remains on schedule to submit the regulatory application for Hoole’s first phase in Q4/2012. Phase 1

10,000

2015

announced

Phase 2

30,000

TBD

announced

Phase 3

30,000

TBD

announced

Phase 4

30,000

TBD

announced

Cenovus Energy Inc. Christina Lake

Updated: Jul 2012

Cenovus says it has commissioned more than 90 per cent of the Phase D plant and expects first production in Q3. Construction of Phase E is more than 50 per cent complete, with initial production expected in Q3/2013. site preparation continues for Phase f. Phase H capacity has been increased from 40,000 to 50,000 barrels per day due to the addition of a fifth steam generator that will incorporate boiler blowdown technology.

Pilot Connacher Oil And Gas Limited Algar

Updated: Jul 2012

Connacher reports that, with its budget constrained for 2012, operational activities include increasing netbacks by reducing operating costs and increasing realized bitumen prices, maintaining production within its announced guidance, de-risking and preparing various short-term projects for bitumen production increases, and improving production with technology innovations such as saGD+ at algar and gas re-injection at Great Divide. The company’s strategic review process continues. Pod 2

10,000

2010

Great Divide

operating Updated: Jun 2012

Connacher reports that, with its budget constrained for 2012, operational activities include increasing netbacks by reducing operating costs and increasing realized bitumen prices, maintaining production within its announced guidance, de-risking and preparing various short-term projects for bitumen production increases, and improving production with technology innovations such as saGD+ at algar and gas re-injection at Great Divide. The company’s strategic review process continues. Expansion 1a

12,000

2014

application

Expansion 1B

12,000

2016

application

Pod 1

10,000

2007

operating

ConocoPhillips Canada Limited Surmont

Updated: Jul 2012

ConocoPhillips Canada says engineering is 90 per cent complete on its surmont 2 expansion. Phase 1

27,000

2007

operating

Phase 2

109,000

2015

Construction

1,200

1997

operating

Pilot Devon Canada Corporation Jackfish

Updated: Jul 2012

Devon says construction of the Jackfish 3 project is now approximately 40 per cent complete.

Phase 1a

10,000

2002

operating

Phase 1

35,000

2007

operating

Phase 1B

8,800

2008

operating

Phase 2

35,000

2011

operating

Phase C

40,000

2011

operating

Phase 3

35,000

2015

Phase D

40,000

2012

Construction

Pike

Phase E

40,000

2013

Construction

Phase f

50,000

2016

approved

Phase G

50,000

2017

approved

Phase H

50,000

2019

Foster Creek

announced Updated: Jul 2012

Cenovus says fabrication and facility construction for Phase f is more than 50 per cent complete. Earthworks and site preparation are also underway for Phase G and design engineering for Phase H. alberta regulators have issued the final terms of reference for Phase J. Phase a Phase B Debottleneck

24,000

2001

operating

6,000

2003

operating

Construction Updated: Jul 2012

Devon filed the regulatory application for all three phases of the Pike project in June. The company says facility construction and saGD drilling for the first phase will begin in late 2013 or early 2014, pending corporate approvals. The company has also submitted its environmental impact assessment report for the project. 1a

35,000

2016

application

1B

35,000

2017

application

1C

35,000

2018

application

Grizzly Oil Sands Ulc Algar Lake

Updated: Jul 2012

Road, plant and civil site construction expected to be complete imminently. saGD well pair drilling and completions scheduled to be complete in Q3, with in-field plant assembly complete in Q4. Commissioning to be complete and steam circulation initiated in Q1/2013.

Phase C stage 1

10,000

2005

operating

Phase C stage 2

20,000

2007

operating

Phase D

30,000

2009

operating

Phase E

30,000

2009

operating

Phase f

45,000

2014

Construction

Phase G

40,000

2015

approved

Phase H

40,000

2016

approved

Phase 1

10,000

2013

application

Phase J

50,000

2019

announced

subsequent Phases

90,000

TBD

Disclosed

Narrows Lake

Updated: Jun 2012

narrows lake regulatory approval granted in late may. sanction by partners Cenovus and ConocoPhillips Canada anticipated later this year.

Phase 1

5,650

2013

Phase 2

5,650

2014

May River

Construction approved Updated: Jul 2012

Grizzly plans to submit a new regulatory application using its saGD development model at may River in mid-2013.

Harvest Operations Corp. BlackGold

Updated: Jul 2012

Harvest expects approval for its 20,000-barrel-per-day Phase 2 at BlackGold this year.

Phase 1

45,000

2017

approved

Phase 2

45,000

TBD

approved

Phase 1

10,000

2014

Construction

Phase 3

40,000

TBD

approved

Phase 2

20,000

TBD

application

48 oilsanDs REViEW | OCTOBER 2012


P R o J E C t S tAt u S

CuRREnT PRoJECT

CaPaCiTy

sTaRT-uP

REGulaToRy sTaTus

CuRREnT PRoJECT

Husky Energy Inc. McMullen

Updated: Jul 2012

Husky says that during Q2, eight slant wells that were drilled in late 2011 were put on cold production. Drilling operations for 32 further slant wells began in June. at the air injection pilot, the reservoir process is proceeding with production start-up anticipated in Q3. air injection Pilot-Experimental

755

2012

Construction

Updated: Aug 2012

The director of environmental assessment has notified the ERCB that the environmental impact assessment for the expansion project is complete. JaCos owner Japan Petroleum Exploration says it will make a final investment decision by the end of this year, pending approvals from alberta regulators. 35,000

2016

Hangingstone Pilot Pilot

application Updated: Jan 2012

11,000

1999

Muskwa

operating

Updated: Jun 2012

Koch’s Canadian subsidiaries are seeking a strategic investor to advance development and monetize certain oilsands interests including the muskwa asset. 10,000

2015

application

Laricina Energy Ltd. •

Germain

Updated: Aug 2012

5,000

2013

Construction

Phase 2

30,000

2015

application

Phase 3

60,000

TBD

application

Phase 4

60,000

TBD

application

Saleski

Updated: Aug 2012

laricina says testing on its latest well pair at saleski has resulted in greatest bitumen production achieved to date at 1,200 barrels per day. The company says it is now in the final stages of proving commerciality of saGD in bitumen carbonates. it also says it is now considering incorporating cyclic steam stimulation (Css) into the 10,700-barrel-per-day project application. Experimental Pilot Phase 1

72,000

2008

operating

Phase 2

72,000

TBD

approved

Phase 3

72,000

TBD

application

Phase 4

72,000

TBD

announced

1,800 10,700

2011 2014

Corner

40,000

2017

approved

Corner Expansion

40,000

TBD

application

Hangingstone

20,000

TBD

application

leismer Commercial

10,000

TBD

approved

leismer Demonstration

10,000

2010

operating

leismer Expansion

20,000

TBD

approved

leismer northwest

20,000

TBD

application

leismer south

20,000

TBD

application

Thornbury

40,000

TBD

application

Thornbury Expansion

20,000

TBD

application

40,000

TBD

Chard Phase 1

Updated: Dec 2010

Meadow Creek

announced Updated: Dec 2010

Phase 1

40,000

TBD

approved

Phase 2

40,000

TBD

approved

12,000

2015

Surmont Energy Ltd. Wildwood Phase 1

Updated: Apr 2012 announced

Value Creation Inc. Advanced TriStar

Updated: Aug 2012

operating

application

Value Creation says it is preparing the regulatory application for the advanced Tristar project. alberta Environment has issued its final terms of reference for the project’s environmental assessment.

MEG Energy Corporation Christina Lake

Updated: Jun 2012

Suncor Energy Inc.

laricina says detailed engineering is essentially complete, 28 of 77 modules have been installed on site, approximately 50 per cent of modules are under fabrication, and regulatory consultation for the 150,000-barrel-per-day expansion continues as planned. Phase 1 CDP

Phase 1

statoil says its next projects will be an expansion to leismer, and the Corner project. Corner will be sanctioned late in 2013 or early in 2014.

koch Exploration Canada Corporation

Pilot

REGulaToRy sTaTus

kai kos Dehseh

Hangingstone

Expansion

sTaRT-uP

Statoil

Japan Canada Oil Sands Limited •

CaPaCiTy

Updated: Jul 2012

aTs-1

15,000

2016

announced

as of June 2012, mEG says detailed engineering on the Phase 2B expansion is 99 per cent complete, and over 100 of 140 modules have been installed, with the remainder expected to be complete in 2012. all materials have been ordered, with delivery and on-site construction expected to be complete in 2013. approximately 60 per cent of the horizontal wells for the 42 saGD well pairs have been drilled.

aTs-2

30,000

2019

announced

aTs-3

30,000

2022

Phase 1 Pilot

TriStar

Value Creation is providing the ERCB with additional information supporting its application.

3,000

2008

operating

Phase 2a

22,000

2009

operating

Phase 2B

35,000

2013

Construction

COLD LAkE REGION — IN SITU

Phase 3a

50,000

2016

approved

Birchwood Resources Inc.

Phase 3B

50,000

2018

approved

Phase 3C

50,000

2020

approved

Surmont

Updated: Jul 2012

The final terms of referece for the environmental impact assessment report for the surmont project have been issued by alberta Environment.

announced Updated: Jan 2011

Pilot

1,000

2014

Sage

application

Updated: Jun 2012

Birchwood has released its public disclosure document and has held an open house with area residents, some of whom were concerned by the development. Pilot

5,000

2015

announced

Canadian Natural Resources Limited

Phase 1

60,000

2018

announced

Phase 2

60,000

TBD

announced

Canadian natural says pads at Primrose are now entering back into the production cycle. The company targets to maximize steam plant capacity through the completion of low-cost pad-add projects. Projects currently under construction are on schedule and on budget.

N-SOLV Corporation Dover

Updated: Jun 2012

Reports are that first results from a $60-million n-solv field test are expected in spring 2013. Demonstration Plant

500

2012

announced

Nexen Inc. Long Lake

Updated: Jul 2012

nexen says it has achieved first production from pad 12 at long lake and began steaming pad 13 ahead of expectations. The company says a major turnaround commencing in mid-august will result in lower Q3 production. long lake south (Kinosis) Phase 1

40,000

TBD

approved

long lake south (Kinosis) Phase 2

40,000

TBD

approved

Primrose & Wolf Lake

Updated: Aug 2012

Primrose East

32,000

2008

operating

Primrose north

30,000

2006

operating

Primrose south

45,000

1985

operating

Wolf lake

13,000

1985

operating

Devon Canada Corporation Walleye

Updated: Jun 2012

Devon filed its regulatory application for Walleye in June. The company says construction will start in 2013. Phase 1

9,000

2016

application

OCTOBER 2012 | oilsanDsREViEW.Com 49


P R o J E C t S tAt u S

CuRREnT PRoJECT

CaPaCiTy

sTaRT-uP

REGulaToRy sTaTus

Husky Energy Inc. Updated: Nov 2010 10,000

TBD

30,000

2006

Tucker Phase 1

approved Updated: May 2012

Cold Lake

Peace River

Cadotte lake

operating

Updated: Jul 2012

imperial says that the nabiye expansion was 22 per cent complete at the end of Q2. 110,000

1985

operating

Phase 11-13

30,000

2002

operating

Phase 14-16

40,000

2014

Construction

Gemini

stage 1

1,200

TBD

approved

stage 2

10,000

TBD

approved

OSUM Oil Sands Corp. Taiga

Updated: Jul 2012

osum says that Cold lake first nations has withdrawan its objection to the Taiga project. it was the only official intervener in the project’s regulatory hearing. Pending regulatory approval, osum says it will go ahead with development.

1986

operating

40,000

2015

application

Carmon Creek - Phase 2

40,000

2018

application

Red Earth

Commercial

10,000

TBD

announced

Pilot

1,000

2009

operating

Pilot Expansion

3,000

TBD

announced

Oilsands Quest Inc. Axe Lake

Commercial

2016

application

Reservoir Test

Phase 2

22,000

2017

application

saGD Pilot

30,000

TBD

on Hold

600

2008

on Hold

TBD

TBD

on Hold

NORTH ATHABASCA REGION — UPGRADER

Lindbergh

Updated: Aug 2012

Phase 1 Commercial

12,500

2015

application

Phase 2 Commercial

17,500

2016

announced

1,200

2012

operating

Royal Dutch Shell plc

BP p.l.c. Terre de Grace

Updated: Jun 2012

shell is looking to sell the orion property, reportedly to focus on in situ operations at Peace River. Phase 1

10,000

2007

operating

Phase 2

10,000

TBD

approved

PEACE RIVER REGION — IN SITU Andora Energy Corporation Sawn Lake

Updated: Aug 2012

Panorient Energy Corp. has increased its ownership of andora Energy from 52.5% to 71.8%. Panorient says activities are underway to commence steam injection at the sawn lake saGD demonstration in the second quarter of 2013, with production anticipated in the fourth quarter of 2013. 1,400

2013

approved

Updated: May 2012

BP says that ongoing appraisal activities include delineation drilling, seismic acquisition and appraisal of water sources. Pilot

8,400

TBD

Horizon

Updated: Aug 2012

Canadian natural says its third ore preparation plant, now fully operational, is contributing to safe, steady and reliable operations. The staged expansion to 250,000 barrels per day continues to progress on track, although Canadian natural has reduced its 2012 project capital for Horizon by $330 million to $1.55 billion. The company says this is a result of overall cost reductions and strategic deferrals to achieve greater cost certainty. Phase 1

114,000

2009

operating

Phase 2a

10,000

2014

approved

Phase 2B

45,000

TBD

approved

Phase 3

80,000

TBD

approved

5,000

2012

operating

Tranche 2 Ivanhoe Energy Inc. Tamarack

Northern Alberta Oil Ltd. Sawn Lake

Updated: Mar 2012

Company owner Deep Well oil & Gas says DeGolyer & macnaughton Canada has completed its reservoir modelling for a proposed horizontal cyclic steam stimulation pilot at sawn lake, concluding the project would yield commercial viable extraction. Deep Well is currently preparing a pilot plan and options for capitalization. 700

TBD

approved

Petrobank Energy And Resources Ltd. Dawson

Updated: Jul 2012

Petrobank says it is awaiting regulatory approval to initiate cold production on its two well demonstration project to condition the reservoir prior to THai operations.

approved

Canadian Natural Resources Limited •

Orion

Css Pilot

Updated: Jun 2012

oilsands Quest says that some of the bids received to acquire, restructure or recapitalize its business could, if subject to further negotiation, be capable of being brought before the court for approval. The company and its court-appointed monitor, Ernst & young inc., have agreed that the best interests of oilsands Quest and its stakeholders will be best served if Ernst & young takes over operational responsibilities including completion of a transaction.

23,000

saGD Demonstration

Updated: May 2012

SASkATCHEWAN REGION — IN SITU

Pengrowth says its two well pairs at lindbergh are now producing after a faster-than-anticipated reservoir response.

12,500

Carmon Creek - Phase 1

Phase 1

Pengrowth Energy Corporation

Updated: Dec 2011

southern Pacific is analyzing results from its latest Css test at Red Earth. The company says it will finalize future development plans by the end of Q2.

Updated: Jun 2012

Koch’s Canadian subsidiaries are seeking a strategic investor to advance development and monetize certain oilsands interests including the Cold lake (Gemini) asset.

Pilot

REGulaToRy sTaTus

Southern Pacific Resource Corp.

koch Exploration Canada Corporation

sTaRT-uP

alberta’s environmental assessment director has deemed complete shell Canada’s environmental impact assessment report for the Carmon Creek expansion.

Imperial Oil Limited

Phase 1-10

CaPaCiTy

Royal Dutch Shell plc

Caribou Demonstration

CuRREnT PRoJECT

Updated: Jul 2012

ivanhoe says it has received and responded to the second round of supplemental information requests regarding its project application from the ERCB. it continues to expect approval in 2012. Phase 1

34,784

2014

application

Suncor Energy Inc. Base Operations

Updated: Jul 2012

suncor says it has its tailings reduction operations (TRo) infrastructure project and commenced operations. it is also in the process of starting up the hydrotreating unit and hydrogen plant of the new millennium naphtha unit, which is expected to stabilize secondary upgrading capacity and provide flexibility during maintenance activities for secondary upgrading units in the future. millennium Coker unit

97,000

2008

operating

Experimental THai Demonstration

10,000

2013

Construction

millennium Vacuum unit

35,000

2005

operating

Phase 2

10,000

TBD

announced

u1 and u2

225,000

1967

operating

50 oilsanDs REViEW | OCTOBER 2012


P R o J E C t S tAt u S

CuRREnT PRoJECT

CaPaCiTy

sTaRT-uP

Fort Hills

REGulaToRy sTaTus

Updated: Jul 2012

suncor expects to present development plans to the board of directors for a sanctioning decision in 2013. Phase 1

145,000

TBD

on Hold

Phase 2 & 3

145,000

TBD

on Hold

Voyageur Upgrader 3

Updated: May 2012

suncor says that current work is on validating project scope, developing the project execution plan, engineering and progressing site preparation. The company and its partner plan to submit development plans to their respective boards of directors for sanction in 2013. Phase 1

127,000

2016

approved

Phase 2

63,000

TBD

approved

Syncrude Canada Ltd. •

Updated: Aug 2012

lead partner Canadian oil sands says Coker 8-3, the newest part of the syncrude upgrader, has achieved a run length of 36 months. Coker 82 achieved the same last year. average coker run lengths at syncrude over the past five years have been 28 months.

stage 3 Debottleneck stage 3 Expansion (uE-1)

CaPaCiTy

sTaRT-uP

REGulaToRy sTaTus

Value Creation Inc. •

Advanced TriStar

Updated: Aug 2012

Value Creation says it is preparing the regulatory application for the advanced Tristar project. alberta Environment has issued its final terms of reference for the project’s environmental assessment. aTs-1

12,750

2016

announced

aTs-2

25,500

2019

announced

aTs-3

25,500

TBD

TriStar

announced Updated: Jan 2011

Value Creation is providing the ERCB with additional information supporting its application. Pilot

840

2014

application

INDUSTRIAL HEARTLAND REGION — UPGRADER North West Upgrading Inc.

Mildred Lake/Aurora North & South

Base Plant stage 1 & 2 Debottleneck

CuRREnT PRoJECT

Redwater Upgrader

Updated: Jul 2012

Project partners north West upgrading and Canadian natural Resources say a sanction decision is expected in Q3/2012. Phase 1

77,000

TBD

approved

250,000

1978

operating

Phase 2

77,000

2018

approved

75,000

TBD

announced

Phase 3

77,000

TBD

approved

100,000

2006

operating

SOUTH ATHABASCA REGION — UPGRADER

Shell Albian Sands Scotford Upgrader 1

Updated: Jul 2012

summer 2012 marked the 10th anniversary of the opening of the athabasca oil sands Project.

Nexen Inc. Long Lake

Updated: Jul 2012

nexen says it has achieved first production from pad 12 at long lake and began steaming pad 13 ahead of expectations. The company says a major turnaround commencing in mid-august will result in lower Q3 production.

Commercial Expansion

158,000

2003

operating

91,000

2011

operating

Value Creation Inc. Heartland

Updated: Nov 2010

Phase 1

58,500

2008

operating

Phase 2

58,500

TBD

approved

Phase 1

46,300

TBD

on Hold

Phase 3

58,500

TBD

application

Phase 2

46,300

TBD

approved

Phase 4

58,500

TBD

announced

Phase 3

46,300

TBD

approved

Construction was suspended in september 2008.

Did you know... Alberta’s energy producers recycle up to 95 percent of the water used in the extraction of oil sands.

I do! Anna - Environmental Engineering and Regulatory Affairs

a Wood Group company

IMV Projects is a proud contributor to the Canadian energy industry

imvprojects.com

OCTOBER 2012 | oilsanDsREViEW.Com 51