Triggers and Pitfalls - Overage Agreements

Page 1

TRIGGERS AND PITFALLS: AN INTRODUCTION TO OVERAGE AGREEMENTS DAVID SCHMITZ

1.

The purpose of overage is to enable the seller of land to participate in profits which the purchaser or in some cases a successor will receive if specified events occur – often, though not always, including the grant of planning permission – and the value of the land thereby increases. Its appeal for the seller lies in the fact that he may ultimately receive more for his land than he would if he sold it at its current value, even if that value reflected the possibility that the events might later come to pass; while its appeal to the buyer lies in the fact that the presence of an overage clause will persuade the seller to demand less up front than would otherwise be the case.

2.

There are, however, a number of problems which can arise, and often they are not properly considered. As observed in the leading book on the subject 1, “In practice, overage provisions are often included as a ‘bolt on’, particularly where the prospect of planning consent is remote. The main purpose which the parties have in mind is an immediate sale for a price representing current use value, but sometimes during the discussions, a provision is added to cover the possibility of future development. At the time of the original sale, this may be a distant prospect, and, therefore, the parties may not think it worth paying much attention to or worth going into overage issues in detail.”

1

Jessel, Development Overage and Clawback (2001) page 197


It is therefore not surprising that significant caselaw on mistake and rectification concerns overage provisions. See, for example, Chartbrook Ltd. v Persimmon Homes Ltd. [2009] AC 1011.

3.

Needless to say, if the hoped-for event should come to pass, but the expectations of either party are disappointed, any failure on the part of the solicitor to secure his client’s position could lead to liability in negligence. The principal sources of difficulty are as follows: (1)

The clause may fail to trigger a right to receive overage in circumstances where the seller might reasonably have expected it to do so.

(2)

The clause may encumber the buyer with an obligation to pay overage in circumstances where he might reasonably not have expected to be so encumbered.

(3)

The wording may fail correctly to define the amount which the seller is supposed to receive.

(4)

Above all, there may be a failure to preserve the seller’s rights where the property is transferred to a third party.

It is not possible to enumerate all of the ways in which an agreement may fail, in any of the ways outlined above, to protect the parties, but it is useful to elaborate each of the of the above categories and, by way of some cautionary tales, to give examples of some useful precautions to take.


The general approach

4.

The nature of the risks will depend upon the nature of the trigger which the parties choose – be it, to take the most common examples, the grant of planning permission, the building of the development or the sale of the property. The form of trigger which is adopted is, of course, a matter for negotiation between the parties in the light of their commercial interests, but it is possible to indicate the kinds of problem to which each can give rise.

5.

Where the trigger consists of the grant of planning permission, a problem generally will only arise, firstly if there is a question as to whether the permission which is obtained matches the specification in the agreement, or secondly if payment is to be deferred and the payer defaults. Where the trigger requires the completion of a development or its sale, the position is less straightforward. The seller may therefore prefer to have the overage triggered by the grant of planning permission and for it to be paid immediately thereafter.

6.

On the other hand, the buyer may not be in a position to agree to payment of overage on the grant of planning permission, because the grant of permission does not, of itself, produce money. It is only if the buyer is confident of being able to raise sufficient finance upon obtaining permission, both to pay the overage and to pay the development costs that this can be a practical solution. For this reason, or simply because the buyer may wish to accept certain risks in


exchange for being able to obtain a greater reward after the completion of the development, the parties may choose to define the trigger in terms of the completion of the development or of its sale. If this is the case, then the following problems must be addressed: (1)

It may be difficult to determine when the works are done. There may be no certificate of practical completion, which settles the question.

(2)

The buyer may become insolvent and a mortgagee may exercise its powers of sale to an onward purchaser who may not be bound by the obligation (see below with regard to the position as against successors in title).

(3)

The buyer, moreover, may simply decide not to build within the period during which the trigger is expressed to operate.

7.

For these reasons, it is wise to consider incorporating into the agreement an obligation to build in accordance with the planning permission, and to complete the building on or before the date when overage is to become payable. Provision can be made for a valuation to be made as at that time, either of the building as built or of the notional building which ought to have been built. See Stephens v Cannon [2005] EWCA Civ 222, where valuations were done on such a notional building in the assessment of damages for breach of obligations to build in accordance with the planning permission and to pay overage on the value of what was built. If a term such as this cannot be achieved, it is especially important to draft so as to avoid ambiguity as to when the obligation to pay overage is triggered. In this regard, consideration should


be given to some of the drafting matters dealt with below, with a view to reducing the parties’ risks.

8.

It is also necessary, in all circumstances, to consider the means by which the obligation to pay overage can be secured for the benefit of the seller, both against the buyer’s mortgagees and against the buyer’s onward purchasers. Ideally, the obligation to secure the payment will be secured by a charge, which will protect the seller’s rights not only as against the buyer’s creditors but also as against the buyer’s onward purchasers. If the charge is expressed to secure contingent liabilities, it will then protect the seller’s rights, even if they are dependent upon a contingency which has not yet occurred – Re Rudd & Son Ltd. [1986] 2 BCC 98, 955. However, a first charge will seldom be possible to achieve, because the buyer’s mortgagee will almost certainly object to any charge which has priority to its own charge; indeed the buyer’s mortgagee may object to there being any charge at all. In such a case it is a matter for negotiation as to the extent, if at all, to which the buyer and his mortgagee are willing to subordinate their respective interests to the seller in exchange for the advantage of paying a lower purchase price which is only subject to increase upon the happening of certain (possibly remote) contingencies. If it is not possible to negotiate such a charge, it will be necessary at the least for the buyer to be required to furnish any relevant information promptly so that the seller will know, immediately the buyer’s obligations become enforceable. The solicitor will also need to try to protect the seller’s position by other means as against onward purchasers, or failing that to advise the seller that his position is


exposed and that he may therefore prefer to give up the idea of overage altogether and to hold out instead for a higher price, payable once and for all, which reflects the current “hope value” of the contingency occurring, but which does not otherwise seek to share the benefits of the contingency. These points are dealt with further below.

Failure of the trigger 9.

The description of the kind of development which, if built, will trigger the obligation to pay overage, may be expressed too restrictively and may therefore be treated as excluding developments which might otherwise be expected to fall within the description. In Walker v Kenley [2008] EWHC 370 (Ch) the agreement was for overage to be payable if the buyer obtained planning permission to develop the property as residential flats and if he carried out that development within five years. The buyer obtained permission to build properties which were restricted to use as “holiday apartments.” It was held that holiday apartments did not fall within the description of “residential flats” as per the agreement, and that overage therefore was not payable. As with other cases on points of construction, this case does not support any rule of law to the effect that to describe a property “residential” will always import the idea of full-time unrestricted residential occupancy – ie that the property must be capable of being a full-time home in order for it to be described thus. In this particular case, the buyer was aided by the fact that the parties at the time of the agreement were well aware of the distinction between holiday and permanent accommodation because there was an issue with the local planning authority on that very point. In other cases, by contrast,


there may be circumstances which aid the seller and lead to the opposite conclusion. Walker v Kenley, however, does show how a casually placed adjective (“residential� n this instance) can land the parties into protracted litigation.

10.

Drafting errors which lead to the overage trigger being drawn too narrowly can occur because very often the obligation to pay overage is not the only contingency for which a contract of sale may provide. For example, the grant of planning permission to effect a certain type of development, may be a condition of the contact becoming binding in the first place, while the actual building of the development may be the event which triggers the obligation to pay overage. In such a case, a careless draftsman may unnecessarily equate the description of the required planning permission with the description of the building works which trigger the overage obligation. The risk to the seller is that the buyer, having obtained permission, may change his mind and seek permission to build something else. It is unlikely that a buyer could get out of the obligation to pay overage by unilaterally abandoning the planning permission, because the Court would view the commercial purpose for overage as providing for the sharing of development profits, the form which the development takes being irrelevant to this object. Nonetheless, unnecessary litigation can ensue if the building works that are intended to trigger the overage obligation are described with unnecessary particularity, and the draftsman should therefore be alert to the possibility of doing this inadvertently.


11.

Expectations may be disappointed if unforeseen events make it impossible for the contractual terms to be carried out. Paradoxically, the more detail in which the purchaser’s obligations are described, the more readily the purchaser may be enabled to plead supervening impossibility. In Hildron Finance Ltd. v Sunley Holdings Ltd. [2010] EWHC 1688, an agreement was made in 1986 for the sale of a block of flats, in which all but one of the flats was let out under long leases and the one remaining flat was retained as a porter’s flat. The agreement provided that if the flat should not be required for use as a porter’s flat within the 21 years immediately following, the buyer should sell it and share the proceeds of sale with the seller. In 1993, Parliament passed the Leasehold Reform, Housing and Urban Development Act which gave the tenants of a block of flats the right to acquire their landlord’s interest through the exercise collective enfranchisement. In November, 2004, the tenants served a notice under the Act, as a result of which it thereafter became unlawful, and indeed impossible, for the buyer to sell the property or to dispose of it otherwise than in accordance with the Act. In proceedings between the buyer and the tenants, it was held that £200,000 was the portion of the of the value of the block which was to be attributed to the value of the flat, while the expert witnesses of the buyer and the tenants agreed it to be worth £300,000 on the open market. The flat in the meantime ceased to be used as a porter’s flat. The block was subsequently acquired by the tenants on terms that included the payment of £200,000 for the flat. Although the seller contended that an acquisition by the tenants under statutory powers should be treated as equivalent to the sale of the flat, it was held that the buyer was not bound to share the proceeds. The agreement had spelled out exactly what had to be done following the trigger event (the cesser of use as porter’s accommodation), namely the granting of a long lease, the marketing of the lease, and the sale of the lease at a price approved by the seller. These events having become impossible, the obligation lapsed; the Court held that the compulsory disposal via of the flat via the statutory machinery at a price below market value was not equivalent to a sale over which the parties had control.


It is therefore wise for the seller to seek to have the agreement provide that overage shall be payable, whether the land is sold or acquired compulsorily by the exercise of a public or private right, entitlement or power. The general lesson for the seller’s solicitors is that the description of the trigger for the overage obligation should be drafted in terms that are as broad as possible.

12.

It sometimes happens that land which is purchased, subject to an overage agreement is not itself developed, but is instead kept as open space in order to facilitate an application for permission to develop neighbouring land, which the developer happens to own or subsequently acquires. Alternatively, the overage land may be used to provide access or parking for neighbouring land, in which case it will either not be sold off or be sold at a relatively low price in comparison to the land which is built upon. This can happen especially where parcels of land are being assembled in order to provide a large site for later development. If the seller envisages the possibility of this occurring, he should ensure that the agreement provides for overage to be payable as a share of the uplift of the whole of any land which obtains planning permission and which includes the land that is sold.

13.

Where the overage obligation is expressed to comprise a share of the buyer’s profits, particular caution is required, as it would be in the case of a joint venture. First of all, due diligence is required. Secondly, if there is not to be a joint venture in which the seller is placed in a position to veto over what is spent, regard must be had to the fact that the buyer may be doing the building


works through persons who are connected with him and paying those persons accordingly. In order for the profits not to be seen to be depressed artificially, there must at least be provision for disclosure by the buyer of all bills, payments and architects’ and surveyors certificates. The solicitor must take pains to tell the client, especially if the client is not experienced in these matters, that the client will stand at the end of the queue and will only be paid (if at all) once the mortgagees and the builders have been paid in full.

The trigger going off unexpectedly

14.

It should be remembered that anyone can apply for planning permission to develop land, whether he owns it or not. Therefore, if the grant of planning permission is to trigger an obligation to pay overage, care should be taken to avoid imposing the obligation to pay overage where planning permission is obtained which the buyer neither seeks nor wants. In Micro Design Group Ltd. v BDW Trading Ltd. [2008] EWCA Civ 448 the seller sold land under a contract which provided that overage should be payable if “improved planning permission” were granted and which did not specify at whose behest the planning permission should be acquired in order for the overage obligation to be triggered. Following the sale, the seller obtained a further planning permission and then claimed an overage payment from the buyer. The first instance judge allowed the claim. Although the Court of Appeal subsequently dismissed it and observed (at paragraph 22) that , “no person would enter into an agreement to buy development land with planning permission and then give the seller the right after completion to obtain further payments by seeking and obtaining planning permission itself which the buyer might not want.” it is nonetheless strongly arguable that the buyer only succeeded because the contract contained other features which enabled the Court to infer, as a matter of the construction of that


particular contract, that only permission sought by the buyer would “count.” Had those features been absent, the Court might have had to find that the seller was entitled to overage on the true construction of the agreement. Micro Design was a close run thing which went as far as the Court of Appeal. The moral for the draftsman, therefore, is not to leave this issue to chance.

14.

Sometimes it may be in the buyer’s interest, rather than the seller’s, to contend that the trigger has gone off. In Hallam Land Management Ltd. v UK Coal Mining Ltd. [2002] 2EGLR 80 the claimant was granted an option which was exercisable upon submitting an application for the development of a 42.5 acre site at a price to be governed by the number of “developable acres” as determined by the terms of the planning permission. The claimant submitted an application to develop just 2.5 acres and this was granted. The claimant then purported to exercise the option to buy the whole 42.5 acres on the basis that only 2.5 acres was developable. It was held that by the Court of Appeal affirming the judge at first instance that there had been no application for development within the meaning of the agreement, and that therefore there had been no exercise of the option. Although the seller’s interest was in fact protected, a Court of Appeal decision was required. It is therefore important that close attention be given to the definition of the planning permission which is to trigger the overage provision and that provision be made for repeated payments of overage whenever any part of the land may receive planning permission, lest the buyer be able to get out of the obligation too cheaply.

15.

Where the overage agreement provides that it will not be payable in certain circumstances, the Court will not stretch the meaning of that provision,


especially if the buyer seeks to have it apply in circumstances where it was within the buyer’s control whether the requisite circumstances arose or not. In Ministry of Defence v County & Metropolitan Homes Conveyancing [2002] NPC 130, the buyer agreed to pay overage if it obtained planning permission for residential land forming part of a 70 hectare site, but it was also provided that overage would not be payable if 37 houses in a portion of the land were demolished. The buyer demolished 35 of them but converted two of them into a village shop to comply with a planning requirement that a village shop should be provided. The seller claimed overage and the buyer sought to defend on the basis that the conversion of the houses amounted to a demolition for the purposes of the agreement. The Court held that the terms of agreement should be given their full effect, that the conversion was not a demolition and that it had been the buyer’s choice that the two houses should remain undemolished.

How much is the seller to receive

15.

Often, the amount of overage payable will be determined by a formula which specifies a percentage. In such cases, the difficult question which can arise is, “a percentage of what?” Normally these cases will turn solely upon the terms of the particular agreements which have given rise to them, or upon the facts which give rise to claims for relief on the basis of mistake or misrepresentation or to claims for rectification. Four general points, however, are worth making.

16.

Firstly, it is necessary to define with care the land which, when sold, will be subject to the overage obligation. In Bride Hall Estates Ltd. v St. George North London Ltd. [2004] EWCA Civ 141, a dispute arose as to whether the overage should represent a percentage of the sale proceeds of a flat, or whether it


should also include a share of the proceeds of the car parking. The Seller succeeded, but in the Court of Appeal.

17.

Secondly, it is risky to provide without elaboration that the overage is to be calculated as a percentage of the proceeds of sale. The sale may be made at an undervalue because the onward purchaser Is connected to the buyer, or because it is done as a loss-leader in aid of another transaction. It is therefore wise to provide for the seller to be able to require a valuation. Further, it is necessary to provide for the possibility that the buyer will grant a lease over the land, rather than sell it, or that the buyer might occupy the land himself. One way in which these cases could be met would be by providing that if the land is not sold by a given date, overage will be based upon a valuation to be obtained as of that date.

18.

Thirdly, if one party is relatively inexperienced in these transactions, while the other party has substantial experience, the Court will be slow to grant the experienced party relief on the ground of mistake. In George Wimpey UK Ltd v VI Construction Ltd. [2005] EWCA Civ 77, there was an overage agreement based upon the sale proceeds of flats. Negotiations proceeded on the basis that the value of certain enhancements to the individual flats would be taken into account in the formula and thereby reduce the overage payable. The seller omitted this provision and the draft agreement was approved without it. The Judge at first instance found that the seller had shut its eyes to an obvious mistake and ordered rectification. The Court of Appeal however overruled the Judge and held that in the absence of convincing evidence that it had shut its eyes to the obvious, an inexperienced party would be able to resist a claim by a far more experienced one for the rectification of a contract that had been negotiated at arms’ length. The fact that


there had been a late change in the draft which operated to the substantial disadvantage of the experienced party was not sufficient to enable that party to succeed. The case is particularly significant because of the fact that a decision of the trial judge on a question of fact was overturned as wrong in principle.

19.

Fourthly, as in any other contract, the Court will intervene where it is apparent from the face of the document that the wording as gone wrong, in the sense that if taken literally it deprives the contract of commercial sense. However, it is only in rare cases that the Court will find that the wording has gone wrong in a professionally drawn document. In Chartbrook Ltd. v Persimmon Homes Ltd. [2009] AC 1101, the House of Lords, overruling the first instance judge and the Court of Appeal, held that this was one of the rare cases where the literal wording of the agreement made no commercial sense and where it could be deduced from the document what the parties had in mind. In that case, it was apparent from the terms used by the parties in setting out the formula for calculating overage that their intention was to pay the seller for the current value of the land, and thereafter to pay the seller a further sum for the value of the land if the flats in the development were sold for more than they were expected to reach. However, the formula which was employed, when viewed in accordance with conventional syntax, provided that the price payable as overage (or the “additional retail payment” as was stated in the agreement) should be far greater than any increased value of the land. What it contemplated was that the additional payment for a flat should equal 23.4 % of the price achieved less the initial price payable to the buyer for the land value of the flat, this being called the “minimum guaranteed residential unit value” (or ‘MGRUV’), which was set at £53,438 per flat. The seller, however, contended that the formula should be applied literally. Thus applied, it would have required payment of 23.4% of the difference between the sale price (less marketing costs) and MGRUV – a vastly higher sum bearing no relation to the land value.


This can be demonstrated thus: the flats were expected to fetch about £200,000 and MGRUV represented a percentage which was only slightly over 23.4% of that figure (it was exactly 23.4% of £228,000). Therefore it was apparent that the 23.4% of the actual sale price (less costs) minus MGRUV would represent the increase in the value of the land, and that an enormous windfall to the seller would be produced if he were instead to receive 23.4% of the difference between the sale price (less costs) and MGRUV. To put rival contentions in algebraic notation, the seller was claiming 23.4% x (price – costs – MGRUV), while the buyer was claiming to be liable for no more than 23.4% (price – costs) – MGRUV. To give an example as to how the formulae worked, the first (the seller’s) formula on a sale at £240,000 (net of costs) would have produced an overage figure of £43,655.50, while the second (the buyer’s) formula would have produced a figure of £2,722, which is far more in line with expectations, where the flat sells for only slightly more than the predicted price. The House of Lords found for the buyer for three reasons. Firstly, the literal interpretation of the provision was totally at variance with the commercial sense of the contract, secondly the commercial sense of the contract could be determined from the choice of words used in the formula itself (“minimum guaranteed residential unit value” and “additional residential payment”) and thirdly the literal interpretation would make the structure and wording of other provisions in the agreement arbitrary and irrational – see Lord Hoffman at page 1113 G. The House also reaffirmed, however, that evidence of pre-contractual negotiations is inadmissible in cases of contractual interpretation, unless it is intended to show either that there had been a definite antecedent agreement which the later written agreement did not correctly embody or else that the parties had negotiated on certain agreed assumptions (for example as to the meaning of a word) so as to raise an estoppels by convention. For such contentions to succeed, they would have to be clearly pleaded and proved.

Overage and successors in title

20.

As mentioned above, the most effective means of securing a right to the payment of overage is by means of a legal charge. However, as also noted, it is


not always possible to achieve this in negotiation. In the absence of such a charge, there is only one other way in which the seller’s rights can be effectively secured against a third party, that is by ensuring that that the contract provides that: (1)

successors in title of the buyer should be liable to pay overage to the seller if the trigger event occurs during their ownership of the land;

(2)

the buyer should agree to the entry of a Restriction on the Land Registry title under Section 43 of the Land Registration Act 2002 to protect that obligation by providing that no disposition of the land should be made without the consent of the seller.

The agreement should also specify the terms under which the seller will be obliged to give his consent to the registration of the onward disposition. Generally the seller will be entitled to require that the onward purchaser enter personally into the overage agreement and in turn permit the entry of a Restriction which will prevent the entry of further disposition from him without the consent of the original seller. Although the matter has not been settled definitely, it is highly likely that such a device will be effective to protect the seller’s interests – see Akasuc Enterprise Ltd. v Farmar & Shierreff (a Firm) [2003] EWHC 1275 (Ch), Peter Smith J, paragraphs 85 – 7. Note that from the buyer’s point of view it is necessary to define those classes of purchaser who are to be subject to this requirement, lest leaseholders of relativel;y short terms, for example be caught.


21.

Attempts to make the overage agreement binding on the buyer’s mortgagee, may meet with resistance from mortgagees for the same reasons as apply in the case of charges. In particular, the mortgagee will be concerned that any purchaser who buys subject to overage will pay less up front than he would otherwise do, and this could accordingly lead to a shortfall at the expense of the mortgagee. The mortgagee might therefore choose to insist that the obligation should not be binding upon any purchaser who purchases from the mortgagee under its powers of sale. This would be unattractive to the seller/overage owner. A possible alternative might be to allow the Restriction to operate in all cases (including sales by a mortgagee), but for the shortfall in the mortgagee’s recovery (ideally up to an defined limit) to be secured by a charge over any sums which may become due by way of overage from the onward purchaser. Another possibility may be for the overage agreement to provide that any surplus after the repayment of the mortgage should be paid into a joint account inm the names of the buyer and seller and used to the discharge of the overage when it is eventually ascertained. Once again, though, all would depend upon negotiation. Whatever inadequacies there may be in securities which are subordinated to the interests of the mortgagee, it is still important to obtain whatever security one can, because there is plenty of scope for a solvent buyer to attempt to defeat the seller’s rights, as in the Akasuc case itself.


What does not protect the seller?

22.

An obligation to make payments, whether or not expressed to bind successors in title, will not be protected by the registration of a unilateral notice under Section 34 of the 2002 Act, just as a caution was insufficient to protect such a right under earlier legislation – see the Akasuc case (above). The reason is that the right is not an interest in land.

23.

In certain circumstances, a restrictive covenant could protect the seller’s rights, but such protection cannot be relied upon. It must be remembered, firstly, that a positive covenant will not bind successors in title of the person who has the benefit of the covenant – Rhone Trust v Stephens [1994] 2 AC 310. Therefore, if it is to be binding upon a successor it must be expressed negatively – for example in terms of a covenant not to do a particular thing together with an agreement to release the covenant upon payment of a given sum. Two difficulties arise here, however. Firstly, the covenantee will not be able to enforce the covenant if he does not retain any land which is capable of benefiting from it, and secondly the covenant can be challenged on the basis that it is not necessary to protect the land retained, and will therefore stand or fall on its own merits.

The Solicitor’s position

24.

In the Akasuc case, Peter Smith J held that:


“[Security] is a matter of a solicitor discharging her retainer. The retainer is to use all reasonable endeavours to obtain security for the overage. It is not a matter of advice in that sense. The solicitor has to come up with a suitable method of securing the overage (assuming that [the buyer] would accept it).” To this, I would add that the solicitor is also under a duty to inform the client of the extent to which the overage entitlement is not secured, and to enumerate the circumstances where the entitlement could be left unsatisfied.

Failure to obtain adequate security: claims for damages

25.

A claim by a client who has not received adequate security will aim at first to recover the benefit which the contract would have provided, had adequate security been in place. However, because the claim is one of professional negligence, the question for the Court will be, ”what contractual terms would have been obtained and what security would have been provided if the solicitor had not acted negligently and what benefits would such terms have yielded to the client?”

26.

In addressing the first part of that question, the terms of the actual contract will merely be evidence of what the hypothetical contract would have contained, and the evidence which the actual contract provides may not be very strong. After all, a buyer who knows that he can sell to an onward purchaser at a price which is not depressed by the presence of an overage obligation affecting the onward purchaser may be willing to make the most extravagant promises, secure in the knowledge that they will not have to be


honoured. It will therefore be necessary for the client to give evidence as to the sort of bargain which he had been in a position to strike. The presence of rival bidders and the client’s own state of financial health (relevant to the question of whether he could have bided his time until a good offer came along) will be important considerations, as of course would the state of the market. If the receipt of the overage money was frustrated by the insolvency of the buyer at the time of his onward sale, it will also be necessary to consider whether there were cash buyers (who did not have to please mortgagees) among the potential purchasers and whether there were mortgagees in the market who would have been willing to lend in circumstances where the right to overage was be binding upon onward purchasers. Finally, it would be necessary and useful to know the value of the land at the time of the agreement, and the amount by which that value exceeded the actual sale price which – a price which by definition would have been discounted because the then current hope value would have been left out in favour of the overage provisions. This is especially important in the case of a claim by any client who would have been likely to have taken a safe course rather than a risky one.

27.

Limitation The failure by a solicitor to secure an entitlement to overage falls within that class of case where a person has, through professional negligence, been caused to part with property on terms which are less advantageous than would have been the case if the negligence had not occurred. That being so, the cause of action accrues, and the limitation period begins to run, when the contract of sale becomes binding – see Law Society v Sephton [2006] 2 AC 543.


This, of course, does not prevent the limitation being extended in cases of negligence under the Limitation Act 1980 Section 14B, or the postponement of the limitation period in cases of fraud or concealment under Section 32.

ŠDavid Schmitz - July 2011


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.