Project Management Portfolio

Page 1


PROJECT PORTFOLIO

2016 ~ 2024

KHOIRUL AZMI

PublicationI,October2024

Copyrightontheauthor.Republishingortransferringofthispublicationinanyformisprohibited withoutthepermissionoftheauthors.LawNumber28of2014concerningCopyright.

KHOIRUL AZMI

ARCHITECT, PROJECT CONTROL, COST CONTROL

Nationality Indonesian

Date of Birth August 19, 1997

Phone +6281229990937

Email khoirul.azmi7@yahoo.com khoirul.azmi77@gmail.com

Address Jalan Jatihandap Barat No.121 RT06 RW05, Jatihandap, Mandalajati, Bandung 40195 Linkedin khoirulazmi7 Instagram khoirulazmi7

I am 27 years old and i am an architecture graduate from Pancasila University.

I was born and raised in Bandung. I believe my multicultural background gives me a unique understanding and open-minded approach to diversity and sustainability in construction based on my experience in the construction world for approximately 8 years.

PERSONAL DATA

ACADEMIC BACKGROUND

Pancasila University Architecture

Jakarta, Indonesia

CAPABILITIES AND SKILLS

Adobe InDesign

Adobe Photoshop

Autodesk Autocad

Autodesk Revit (Basic) Trimble SketchUp Vray

Lumion

Microsoft Office

SAP S/4Hana

Commitment Teamwork Communication Creativity Time Management Analitycals

Negotiation & Persuasion Confidence

PT Acset Indonusa Tbk

Cost Monitoring Control

Jakarta, Indonesia

PT Arah Gaya Perkaza Site Engineer Jakarta, Indonesia

PT Djasa Ubersakti Tbk Cost Control Jakarta, Indonesia

PT Nindya Karya (Persero) Cost Control Jakarta, Indonesia

PT Sejahtera Adil Bersama Drafter and Assistant Supervisor Jakarta, Indonesia

HOBBIES AND INTERESTS

Chapter 1

Infrastructure Project

This chapter covers the projects that have been implemented:

Roads and Bridges

• Engineering, Procurement, and Construction (EPC) of Benete Public Road Overpass and Primary Access Road Extension, West Sumbawa, West Nusa Tenggara, Indonesia

Earth Retaining Structure

• Engineering and Construction (EC) of Slope Stabilization of Tongo Government Road – Tailing Corridor Post 160, West Sumbawa, West Nusa Tenggara, Indonesia

Infrastructure Project Road and Bridge

EPC of Benete Public Road Overpass and Primary Access Road Extension

About

Contractor : PT Acset Indonusa Tbk

Position : Cost Monitoring Control

Consultant : PT Mitrapacific Consulindo International

Client : PT Amman Mineral Nusa Tenggara

Location : West Sumbawa, West Nusa Tenggara, Indonesia

Size Area : 12.445 m2

Agreement Number : BH2300200co

Date of Contract : 01 January 2023

Construction Finish Date : 20 October 2023

Maintenance Period Date : 31 July 2024

Type of Contract : Unit Price

Amount of Contract : IDR 60.856.645.846

Terms of Payment : 15% Down Payment, Payment Percentage Progress, 5% Retension

Scope of Work : Civil, Structure, Mechanical, Electrical

Tender Budget Plan : IDR 49.899.709.057

Gross Profit Margin Tender : 18,005%

Project Budget Plan : IDR 49.560.211.760

Gross Profit Margin Project : 18,562% *All prices are excluding tax

Project Performance

Date of Change Order : 28 November 2023

Date to Finish Change Order : 27 December 2023

Maintenance Period Date CO : 31 August 2024 Amount of Change Order : IDR 15.003.894. 282

: Completed

Gross Profit Margin : 34,95% Achievements : 1st Winner SAPPCC

Infrastructure Project

Earth Retaining Structure

EC of Slope Stabilization of Tongo Government Road – Tailing Corridor Post 160

Project Performance

Date

:

Position : Cost Monitoring Control

Consultant : PT Mitrapacific Consulindo International

Client : PT Amman Mineral Nusa Tenggara

Location : West Sumbawa, West Nusa Tenggara, Indonesia

Size Area : 150 m1

Agreement Number : BH2402100co

Date of Contract : 10 January 2024

Construction Finish Date : 10 June 2024

Maintenance Period Date : 10 June 2025

Type of Contract : Unit Price

Amount of Contract : IDR 19.443.413.980

Terms of Payment : 20% Down Payment, Monthly Progress Payment, 5% Retension

Scope of Work : Civil and Structure

Tender Budget Plan : IDR 15.583.469.589

Gross Profit Margin Tender : 19,85%

Project Budget Plan : IDR 15.154.303.459

Gross Profit Margin Project : 22,06% *All

This chapter covers the projects that have been implemented:

Industrial Project

Factory

• Civil Work Main Bays & Substation (Hot Strip Mill # 2 Project), Cilegon, Banten, Indonesia

Chapter 2

Industrial Project Factory

About

Contractor : PT Nindya Karya (Persero)

Position : Cost Control

Consultant : SMS Group

Engineering : PT Krakatau Engineering

Client : PT Krakatau Steel Indonesia (Persero) Tbk

Location : Cilegon, Banten, Indonesia

Size Area : 250.000 m2

Agreement Number : 38/KONTR/2751/DU-KE/III/2017

Date of Contract : 14 March 2017

Construction Finish Date : 28 February 2018

Maintenance Period Date : 28 February 2019

Type of Contract : Unit Price

Amount of Contract : IDR 125.840.546.000

Terms of Payment : 10% Down Payment, Monthly Progress Payment, 5% Retension

Scope of Work : Civil and Structure

Project Budget Plan : IDR 108.418.981.895

Gross Profit Margin Project : 13,84% *All

Project Performance

Date of Change Order : -

Date to Finish Change Order : -

Amount of Change Order

Total Amount

Chapter 3

Building Project

This chapter covers the projects that have been implemented:

Education

• Completion Renovation of Learning Center Bank DKI, South Jakarta, DKI Jakarta

• Reconstruction of The Islamic State University (UIN) Palu, Palu City, Central Sulawesi

Warehouse

• Construction of the KPK Building for Storing Confiscated and Looted Goods, East Jakarta, DKI

Jakarta

Laboratory

• Construction of Pontianak Police Forensic Laboratory, Pontianak City, West Kalimantan

• Construction of Manado Police Forensic Laboratory, Manado City, North Sulawesi

Terminal

• Revitalize Patria Blitar Type A Terminal, Blitar, East Java

• Revitalize of Banjar Type A Terminal, Banjar, West Java

Mall

• Mall Boxies 123, Bogor, West Java

Apartment

• The Spring Residence, South Tangerang, Banten

Hospital

• Completion of Utility Building Construction, West Jakarta, DKI Jakata

• Cikalong Wetan Regional General Hospital, Bandung, West Java

Building Project Education

Completion Renovation of Learning Center Bank DKI Building

About

Contractor : PT Arah Gaya Perkaza

Position : Site Engineer

Consultant : PT US&P Architects, and PT La’mally

Construction Management : PT Bina Karya (Persero)

Client : PT Bank DKI

Location : South Jakarta, DKI Jakarta, Indonesia

Size Area : 1.447 m2

Agreement Number : 01.1/PKS/DIR/PPA/VIII/2022

Date of Contract : 11 August 2022

Construction Finish Date : 09 November 2022

Maintenance Period Date : 08 February 2023

Type of Contract : Unit Price

Amount of Contract : IDR 7.448.970.716

Terms of Payment : Termijn Progress Payment, 5% Retension

Scope of Work : Architecture, Interior, Mechanical, Electrical, Plumbing

Project Budget Plan : -

Gross Profit Margin Project :

Project Performance

Date

Reconstruction of The Islamic State University (UIN) Palu

About

Contractor : PT Totalindo Eka Persada Tbk - PT Djasa Ubersakti Tbk (KSO)

Position : Cost Control

Consultant : PT Pola Data Consultant

Client : PPK Pengembangan Sarana Prasarana Pendidikan Olahraga

Location : Palu, Central Sulawesi, Indonesia

Size Area : 17.398 m2

Agreement Number : HK.02.01/SPMK/SPPP.ST/PSPPOP/05/2020

Date of Contract : 18 December 2020

Construction Finish Date : 12 December 2021

Maintenance Period Date : 10 June 2022

Type of Contract : Unit Price

Amount of Contract : IDR 93.266.318.000

Terms of Payment : 15% Down Payment, Termijn Progress Payment, 5% Retension

Scope of Work : Structure, Architecture, Mechanical, Electrical, Plumbing

Project Budget Plan : IDR 93.851.516.636

Gross Profit Margin Project : -00,62%

Project

Building Project Warehouse

Construction of the KPK Building for Storing Confiscated and Looted Goods

About

Contractor

: PT Djasa Ubersakti Tbk

Position : Cost Control

Consultant : PT Pandu Persada

Construction Management : PT Yodya Karya (Persero)

Client : Komisi Pemberantasan Korupsi

Location : East Jakarta, DKI Jakarta, Indonesia

Size Area : 10.206 m2

Agreement Number : PRJ/22/123/953/05/2021

Date of Contract : 31 May 2021

Construction Finish Date : 26 December 2021

Maintenance Period Date : 24 June 2022

Type of Contract : Unit Price

Amount of Contract : IDR 59.999.000.722

Terms of Payment : Termijn Progress Payment, 5% Retension

Scope of Work : Architecture, Structure, Mechanical, Electrical, Plumbing

Project Budget Plan : IDR 57.352.613.288

Gross Profit Margin Project : 3,32%

*All prices are including tax

Project Performance

Date of Addendum : 14 December 2021

Date to Finish Addendum : 31 December 2021

Maintenance Period Date Add : 29 June 2022

Amount of

:

5.181.962.278

Amount : IDR 65.180.963.000

Project Budget Plan Add :Gross Profit Margin Project Add : -

Status : Completed

Amount Gross Profit : IDR - 9.613.609.754

Gross Profit Margin : - 20,08% Achievements : -

Building Project Laboratory

Construction of Manado Police Forensic Laboratory (Bidlabfor)

About

Contractor

: PT Djasa Ubersakti Tbk

Position : Cost Control

Consultant : PT Prada Cipta Areco

Construction Management : -

Client : PT Mitrel Berkat Utama

Location : Manado City, North Sulawesi, Indonesia

Size Area : 6.000 m2

Agreement Number : 01/SPPP/MBU-DU/PTK/Struktur, Arsitek, dan MEP/III/2021

Date of Contract : 25 March 2021

Construction Finish Date : 30 April 2022

Maintenance Period Date : 30 April 2023

Type of Contract : Lumpsum Fixed Price dan Lumpsum of System and Function

Amount of Contract : IDR 30.118.181.818

Terms of Payment : 10% Down Payment, Monthly Progress Payment, 5% Retension

Scope of Work : Structure, Architecture, Mechanical, Electrical, Plumbing

Project Budget Plan : IDR 27.471.893.098

Gross Profit Margin Project : 9,63%

*All prices are excluding tax

Project Performance

Date of Change Order : -

Date to Finish Change Order : -

Maintenance Period Date CO : -

Amount of Change Order : -

Total Amount : -

Project Budget Plan CO : -

Gross Profit Margin Project CO : -

Project Status : Completed

Last Amount Gross Profit : IDR - 842.293.079

Last Gross Profit Margin : - 5,32% Achievements : -

Construction of Pontianak Police Forensic Laboratory (Bidlabfor)

About

Contractor

: PT Djasa Ubersakti Tbk

Position : Cost Control

Consultant : PT Prada Cipta Areco

Construction Management : -

Client : PT Mitrel Berkat Utama

Location : Pontianak City, West Kalimantan, Indonesia

Size Area : 8.280 m2

Agreement Number : 01/SPPP/MBU-DU/PTK/Struktur, Arsitek, dan MEP/III/2021

Date of Contract : 25 March 2021

Construction Finish Date : 30 April 2022

Maintenance Period Date : 30 April 2023

Type of Contract : Lumpsum Fixed Price dan Lumpsum of System and Function

Amount of Contract : IDR 30.518.181.818

Terms of Payment : 10% Down Payment, Monthly Progress Payment, 5% Retension

Scope of Work : Structure, Architecture, Mechanical, Electrical, Plumbing

Project Budget Plan : IDR 27.956.604.599

Gross Profit Margin Project : 9,16%

*All prices are excluding tax

Project Performance

Date of Change Order : -

Date to Finish Change Order : -

Maintenance Period Date CO : -

Amount of Change Order : -

Total Amount : -

Project Budget Plan CO : -

Gross Profit Margin Project CO : -

Project Status : Completed Last Amount Gross Profit : IDR - 1.471.583.617 Last Gross Profit Margin : - 3,50% Achievements : -

Building Project Terminal

Revitalize Patria Blitar Type A Terminal

About

Contractor : PT Djasa Ubersakti Tbk

Position : Cost Control

Consultant : -

Construction Management : PT Paradigma Nusantara Membangun

Client : Balai Pengelola Transportasi Darat Wil.XI Provinsi Jawa Timur

Location : Blitar City, East Java, Indonesia

Size Area : 14.945 m2

Agreement Number : 01/MYC.20-22/PPK.PRAS/BPTD-XI/XII/2020

Date of Contract : 18 December 2020

Construction Finish Date : 17 March 2022

Maintenance Period Date : 13 September 2022

Type of Contract : Lumpsum and Unit Price

Amount of Contract : IDR 59.090.909.091

Terms of Payment : 15% Down Payment, Termijn Progress Payment, 5% Retension

Scope of Work : Structure, Architecture, Mechanical, Electrical, Plumbing

Project Budget Plan : IDR 43.663.697.982

Gross Profit Margin Project : 35,33%

*All prices are excluding tax

Project Performance

Date of Addendum : -

Date to Finish Addendum : -

Maintenance Period Date Add : -

Amount of Addendum : -

Total Amount : -

Project Budget Plan Add : -

Gross Profit Margin Project Add : -

Project Status : Completed Last Amount Gross Profit : IDR - 795.332.885

Gross Profit Margin : - 1,82% Achievements : -

Revitalize of Banjar Type A Terminal

About

Contractor : PT Djasa Ubersakti Tbk

Position : Cost Control

Consultant : -

Construction Management : PT Sangkuriang

Client : Balai Pengelola Tranportasi Darat Wil.IX Provinsi Jawa Barat

Location : Banjar City, West Java, Indonesia

Size Area : 22.206 m2

Agreement Number : PL.107/32/BPTD-IX/XI/2020

Date of Contract : 23 November 2020

Construction Finish Date : 31 December 2022

Maintenance Period Date : 31 December 2023

Type of Contract : Lumpsum and Unit Price

Amount of Contract : IDR 50.817.244.557

Terms of Payment : 15% Down Payment, Termijn Progress Payment, 5% Retension

Scope of Work : Structure, Architecture, Mechanical, Electrical, Plumbing

Project Budget Plan : IDR 43.711.553.883

Gross Profit Margin Project : 16,26%

*All prices are excluding tax

Project Performance

Date of Addendum : -

Date to Finish Addendum : -

Maintenance Period Date Add : -

Amount of Addendum : -

Total Amount : -

Project Budget Plan Add : -

Gross Profit Margin Project Add : -

Project Status : Completed Last Amount Gross Profit : IDR 662.464.009 Last Gross Profit Margin : 17,77% Achievements : -

Building Project Mall

Mall Boxies 123

About

Contractor : PT Djasa Ubersakti Tbk

Position : Cost Control

Consultant : -

Construction Management : PT Mitrakarya Antarbuana

Client : PT Sinar Indonesia Loka

Location : Bogor City, West Java, Indonesia

Size Area : 30.000 m2 / 5 Storey 1 Mezzanine

Agreement Number : SPK-SIL/003/V/2018

Date of Contract : 28 May 2018

Construction Finish Date : 22 April 2019

Maintenance Period Date : 21 April 2020

Type of Contract : Lumpsum

Amount of Contract : IDR 146.818.181.818

Terms of Payment : 10% Down Payment, Monthly Progress Payment, 5% Retension

Scope of Work : Structure and Architecture

Project Budget Plan : IDR 137.461.183.115

Gross Profit Margin Project : 6,81%

Project Performance

Date of Change Order : -

Date to Finish Change Order : -

Maintenance Period Date CO : -

Amount of Change Order : -

Total Amount : -

Project Budget Plan CO : -

Gross Profit Margin Project CO : -

Status

Building Project Apartment

The Spring Residence

About

Contractor : PT Djasa Ubersakti Tbk

Position : Cost Control

Consultant : -

Construction Management : PT Ciriajasa Cipta Mandiri

Client : PT Kembang Sari Buana

Location : South Tangerang, Banten, Indonesia

Size Area : 23.372 m2 / 1 Podium, 22 Storeys

Agreement Number : 005/LGL-KSB/SPK/I/2017

Date of Contract : 23 January 2017

Construction Finish Date : 16 August 2018

Maintenance Period Date : 16 August 2019

Type of Contract : Lumpsum Fixed Price

Amount of Contract : IDR 113.500.000.000

Terms of Payment : 12,5% Down Payment, Monthly Progress, 5% Retension

Scope of Work : Structure, Architecture, and Plumbing

Project Budget Plan : IDR 102.345.002.506

Gross Profit Margin Project : 10,90%

*All prices are excluding tax

Project Performance

Date of Addendum : -

Date to Finish Addendum : -

Maintenance Period Date Add : -

Amount of Addendum : IDR 22.006.000.000

Total Amount : IDR 135.506.000.000

Project Budget Plan Add : IDR 119.901.002.506

Gross Profit Margin Project Add : 13,01%

Project Status : Completed

Last Amount Gross Profit : IDR - 992.028.068

Last Gross Profit Margin : 0,77%

Achievements : -

Building Project Hospital

Completion of Utility Building Construction

About Contractor

Position : Cost Control

Consultant : PT Darena Prakarsa Utama & PT Sigmatech Tatakarsa

Construction Management : PT Artefak Arkindo

Client : RSJPD Harapan Kita

Location : West Jakarta, DKI Jakarta, Indonesia

Size Area : 8 Storeys

Agreement Number : BN.01.01/IX/SP/PKPKJK.05/563/2017

Date of Contract : 22 May 2017

Construction Finish Date : 17 December 2017

Maintenance Period Date : -

Type of Contract : Lumpsump and Unit Price

Amount of Contract : IDR 71.413.352.862

Terms of Payment : 20% Down Payment, Termijn Progress Payment, 5% Retension

Scope of Work : Structure, Architecture, MEP

Project Budget Plan : IDR 63.343.644.006

Gross Profit Margin Project : 9,36% *All

Project Performance

Cikalong Wetan Regional General Hospital

About

Contractor : PT Nindya Karya (Persero)

Position : Cost Control

Consultant : PT Pandu Persada

Construction Management : PT Module Tri Arba

Client : Dinas Kesehatan Kab. Bandung Barat

Location : Bandung, West Java, Indonesia

Size Area : 25.000 m2 / 8 Buildings

Agreement Number : -

Date of Contract : 7 December 2015

Construction Finish Date : 28 February 2017

Maintenance Period Date : 28 August 2017

Type of Contract : Lumpsum and Unit Price

Amount of Contract : IDR 90.902.805.455

Terms of Payment : 15% Down Payment, Termijn Progress Payment, 5% Retension

Scope of Work : Structure, Architecture, MEP

Project Budget Plan : IDR 79.976.187.751

Gross Profit Margin Project : 13,66%

*All prices are excluding tax

Project Performance

Date of Addendum : -

Date to Finish Addendum : -

Maintenance Period Date Add : -

Amount of Addendum : -

Total Amount : -

Project Budget Plan Add :

Gross Profit Margin Project Add : -

Project Status : Completed