UNIVERSITY OF WESTMINSTER
OLGA KOROLKOVA (W1686546)
2018 - 2019
SITE DIARY
80 CHARLOTTE ST
MY OPINION Hello! My name is Olga Korolkova and this is my Site Diary about 80 Charlotte St. If you want to know my personal opinion on the project, look into these yellow boxes.
CONTENT
1.0 MAKING SENSE OF SITE 2.0 THE DESIGN TEAM 3.0 STATUTORY APPROVALS 4.0 BUILDING THE BUILDING 5.0 TIME LAPSE CONSTRUCTION SEQUENCE DRAWING 6.0 CONCLUSIONS AND THE FUTURE
01.
MAKING SENSE OF SITE
Section 1.0
01
02
Site Diary 5
03
Location
01
LONDON, UK
CHARLOTTE APARTMENTS
Sectors
Exterior proposal Whitfield St/Chitty St Corner
RESIDENTIAL, RETAIL, WORKPLACE Client DERWENT LONDON
02 GROUND FLOOR CAFE Interior proposal
Main contractor MULTIPLEX
03 RECEPTION AREA Interior proposal
Contract value £220 MILLION Area 50,200 M²/540,300 FT² Project length
Architect
Q1 2007 - Q1 2020
MAKE ARCHITECTS
ON
ST
RE
RE
ET
ET
RI
NT
ET
U MO
L MA
DG
HI
S
NS
D
TO
IE L
GD
TF
ST
RE
RI
ET
DG
U MO
M
ET
HA
RE
EN TT
M
ST
C
U
NT
O
HA
FR
ST
AL
RT
ED
RO
AC
D
PL
A
E
CH
LE
AR
LO
O
TT
GO
ST
AT
E
DG
T IT C
F IE L
D LAN OR T AT P
G OS
GR E
ET RE ST
OG
N NS O
GR E
PLA
ST
L
H F IE
RE
LD
ET
B5
NA
S TR
E ET
T D S
S TR
EET
RE L
E WS E M
S TR
TH M
CE
MO U
LEY
POL
T MO
S
06
SS
AU
EET
S MA N
A ND
F IE L
TH
EL
E
RW
AD
MO
RA
ST
T D S
BO
N
BE
L
E
ST
ER
ST
RN
S
RD
RE
ER
S
ST
W ME
Y
W
D
D
AN
AN
EL
EL
EV
ET
CL
RE
ST
ST
AY
EV
NE M
EET
S TO
CL
C L IP
S TR
ND
EET TR M S LLA
T LA
HA
P OR
WE Y
HA R
W IM
WE S
EN
GO
UA
W
S
LE
OY
NW
ER
E C
EET
W IM
H
ET
SQ
IE
GO
EN
NT
ZR
CO
S OV
H IR
S TR
B ON E S
EP
RE
ET RE ST
CH
HU
F IT
B OL
01
ONS
NT
MA R Y L E
B 50
C HA
POL
6
E
LL
H
N DO
E
T
AN
RA
WM
WE
S
B
S EW S M
NE
ST
N
ST
O
00
SQ
N
ST
TO
RD
A4
R GH S T REET
H
VI
22
ST
6
A 42
DE V
U MO
S
IG
TA
GO
B5
O S NA B U
LE
ET
AY
1
CE
ST M WE
P LA
PL M BEA
L
DS
RE
NW
B 50
20
H IR E
H IR E
H IR E
AL
EN
ST
CO
A 420 1
Y WA ER
T EAS
A4
T
W
W
SQ
PET O PL
A4201
RK
E W UA R K SQ
N
ER
GO
A 40 0
PA
PAR
ONS
ONS
ONS
H IG H S T
A
S S
M
LS EL ST
TH
TR O
DE V
DE V
DE V
ONE
B
S
G
R
ES NG LA
RC PE
ER RI OU
MO
ST
E ST LS'
S
RE S
E U
HO D ING
Y BA ET E R W
IN
DM
IL L
S
Y LE
ST
T EE TR M S L AN
G HA
S
IM RT EET STR
EET STR HES
P
E
EY
IS H
L FO C
C DU
DF BE DG
E
ST
R
T EE
O GO
ST
E RE
T
T
T REE ST ND AV E
NE W
ST
OR
E
GO
W
ER
ME
T EE SC
T OT
C
R ST 2 A5
04 ST A AL
AM H EN
R ST
H T MO U WE Y
CH
O
PST
T EE
T EE STR
IE
S A Y IT T
CLI
T
N HE
T R ST
EE M R LF
ED
W HO
ST
NE
ND LA EE R ST
W
DE
C AR
BU
ET
I RR TO
ON T NG
E MA
PL
E ET S TR N RTO
E PL
AC
C
T EE R ST
ER P AP
PA R K
S
H IR E
ST E C
Z F IT
E TR
T EE S TR
NS E VO D
NE AN N EE QU
ST
UL S
P TE R
Y ST R LE U HA
TER K
T EAS E RAC
ES CR
G
I UN
VE
R
TY SI
F RA
T
ON A
Y RO
S
E TR
ET AY W EN RR WA
501
ET RE ST
EN
D
E SL
IG
H R WE GO
E AC
S TR E E T
N TO
PL
L ONG FOR D
RO EP
D
S EU
DS EN AD H
O ND
ST S QUAR E
G H IG LE ON S EN
S EN D AR S EU
T EE R ST MU NS T E R
01
M R UM
ST N TO
W
O
Section 1.0
[1.01]
Site Diary 7
P
LOCATION
CHARLOTTE APARTMENTS
80 CHARLOTTE ST
02
[1.01] Where is the site, what is the purpose of the building? Located in Fitzrovia near London’s West End, the site is bounded by four streets – Charlotte St, Howland St, Whitfield St and Chitty St. The building is multi-purpose, and the Site is split into 3 areas: 80 Charlotte Street (Commercial Block), The Charlotte Apartments (Residential Block) and “Asta House” (Residential Block).
T
W
FO
EL
B
In my Site Diary I will be focusing on researching about the Commercial Block Construction. There are 2 Main Entrances to 80 Charlotte Street, 1 VIP Discreet Car Entrance and 2 Alternative Entrances. The finished building will be partly refurbished and partly new build, with 30% of the original structures retained, including retained façade. The scheme is a major step forward the wider regeneration of the area and completion is expected in H1 2020.
01 FITZROVIA MAP
02 SITE SCHEME
CH AR LO TT ES
T
Y IT T CH
ST
ASTA HOUSE
Section 1.0
[1.02]
01
[1.02] How did the project originate? Who is the client? The client of this project is Derwent London. Their initial intent was to retain most of the Saatchi&Saatchi Block, but during the design stage it turned out that the structure was not stable enough, as the construction technologies have changed significantly from that time. Moreover, it was decided to dig down to increase the height of the building, so boundary walls were demolished except for the corner of the Charlotte Apartments, located in conservation area. The building previously belonged to LMS, but the company became merged with Derwent London. Client describes the former building as a “square donut with lots of buildings inside with different qualities”. In fact, there were a lot of extensions of different style and even some Vicrorian buildings.
SAATCHI&SAATCHI Saatchi & Saatchi is a global communications and advertising agency network, founded in 1970 and headquartered in London. 80 Charlotte Street has been the home of Saatchi & Saatchi London for more than 40 years since the year 1975, over which time the building has been the home of some of the most famous creativity. Now the building is in need of a makeover. Architects are transforming this set of 1960s, single-use blocks into a contemporary, fully integrated development of office, residential, retail and vibrant public space.
01 SAATCHI&SAATCHI In front of the old building
04 80 CHARLOTTE ST Before the reconstruction
Site Diary 8
02
03
MY OPINION I reckon, that the concept was dictated by these prerequisites. Combination of various styles, textures, heights and qualities – this messiness gained its’ new reading in the new project..
Section 1.0
Project origins DIRECT APPOINTMENT
Site Diary 9
04
Building/site area GIA OFFICE = 434,822FT2 / 40,395M2 NIA OFFICE = 320,626 FT2 / 29,786M2 Height 9 STOREYS PLUS LOWER GROUND Planning Authority: CAMDEN
NEW LIFE Client’s brief:
03
• Regeneration and extension of existing ‘city block’. • New office, residential (including affordable housing), retail, new public pocket park
80 CHARLOTTE ST Design proposal
Client’s design intent: • Exposed concrete elements and steel beams • Communications left visible • Corten elements
04 CHARLOTTE ST/CHITTY ST Before and after
Section 1.0
[1.04]
VIABILITY
01 [1.04] What makes the project financially viable? How is it funded and why? The project is funded by Derwent London, who made it financially viable by smart use of space. Their intent was to clear the site of everything and make it super efficient. Inside the yard was a car park, which was replaced with a central core with staircases, lifts and toilets, it gave a way for spacious open-space office spaces around the core. Former building was around 200.000 square ft of space - this was incresed up to 380.000 square ft in a new building. The corner building is to become a residential building with 19 flats. Old building had a pretty terrible structure, so the planning application suggesting to increase the height of the building was submitted to the authorities. Levels G-05 will be 3 m high from floor finishing to soffit, Levels 06-08 2.9 meters high. For maximum use of height it was decided to lower the basement – every wall around the basement went deeper and beautiful lightwells appeared. Following this intent, all of the basement walls were to be rebuilt. So, the basement was digged out and the temporary structures, holding the ground around was put. That made a project 6 months longer to build, but 1,8 meters heigher. For the same reason of height usage, the ground level went down and the ramp was built, so now reception is lower then the ground. To earn money on residential block, 2 extra floors were built on top – now there will be penthouses.
Site Diary 10
Section 1.0
[4.10]
Site Diary 11
ADDED VALUE
02
What is the added value? •
3.3m floor-to-floor
•
accommodated to provide 3m floor to soffit with highly efficient 6x9m steel frame and precast planks.
•
Air supply from central core in 150mm raised floor.
What are the project key features? •
315,000ft2 NIA CAT A office
•
55 residential apartments, including 14 affordable units
Which sustainability features project has? •
Designed to achieve BREEAM ‘Excellent’
•
Code for Sustainable Homes level 4
01 INCREASED HEIGHT Scheme provided by Make Architects
02 INCREASED OFFICE SPACE Scheme provided by Make Architects
[1.04]
What is the contract value of the project? What is the time scale?
Derwent London is a Real Estate Investment Trust, specializing mostly in commercial buildings and less in residential sector. The project is the biggest residential scheme in portfolio of the client. It is a long-term investment.
Architectural statement
CONTRACT VALUE
£190 MILLION
CONSTRUCTION COST
2011
“Make” is appointed for the project
SECTION 106 AGREEMENT My Name is John Doe Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et minim veniam, quis.
RIBA STAGE 2 RIBA STAGE 1
2013
2014
20 CONDITIONS My Name is John Doe Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et minim veniam, quis.
RIBA STAGE 0
2012
PLANNING PROCESS & CONCEPT CHANGES
2008
The time scale of any project is never known exactly before the project start. Changings of the client’s plans changes the project’s parameters, which, in turn, changes the project time scale. The unpresicatable conditions may also take place. For example, they may be an underground water or any other weather conditions, which expand the time scale.
2010
Back to planning process
PROJECT START
Construction cost – a total amount that has to be paid for the man-hours and building materials in order to build a building.
In this project particularly, a high water table was detected while the construction, forcing main contractor to build the temporary drainage system.
2009
Structure not stable enough
Contract value (Contract sum) - is the price agreed with the contractor and entered into the contract. However, the contract sum does not constitute a ‘fixed price’ even if the contract is described as a fixed price contract, a lump sum contract or a guaranteed maximum price contract.
2007
First planning application
It is essential to tell the difference between the contract value and the construction cost.
Tender start
£220 MILLION
RIBA STAGE 3
The 1st contract period was August 2018, now the practical completion date is planned for 20 December 2019 with a small lead time till the end of February. Project timeline was dependent on several various factors. Firstly, planning applications took longer. Declined by the Committee, the project was forwarded for further jurisdiction to GLA to be supported by mayor – this took twice as much time. The second major issue was a 2 year pause in the project. The reason for that was that the lease for Saatchi&Saatchi was ending and their office should have been relocated to another Derwent’s building. However, Derwent needed to finish construction of that building first to put Saatchi there. Once it had been finished and Saatchi&Saatchi had moved, the work was resumed in 2014 with RIBA stage 3.
Q4
Q1 Q1
Q2
Q3
Q2
Q4
RIBA STAGE 5
Concrete slabs installation starts
Design and Build Contract with “Multiplex”
Sreelwork installation starts
“AFK” was employed during the render.
RIBA STAGE 4
Q1 Q2
Q3
Q2
Q3
Q4
Q4 Q1
2018
Ground works
Demolition starts Piling starts
Phaze 1 Hearing erected
Planning granted
RIBA STAGE 3
Q4 Q1
2016
Client has signed the Demolition Contract long before the Main Contractor was assigned, which is rather a common practice.
Q3
Q2
Q3
2020
MY OPINION It is interesting, that it took only around 3 years to erect the main structure of the building. The rest of project time was deicated to the planning, changing of concept and tendering processes.
Residential site to be finished
Q3
2019
Electricity came in site
Q2
2017
Commercial site to be finished
First tower crane erected
Phaze 2 Hearing
No, the project is delayed.
Tender agreement
2015 Q1
[4.10] Is the project on course to be completed within the contract period? If not why?
RIBA STAGE 6
RIBA STAGE 7
Section 1.0
Access
Logistics
Structural Engineer
Site Diary 14
SUBCONTRACTORS & SUPPLIERS
DESIGN TEAM
CONTRACTURAL DIAGRAM
[1.06]
H&S
CLIENT
Building control
MEP
Architect
MEP
Drywall
Scaffolding
Demolition
Brickwork
Facade system
Concrete
Steel
SLW
D&C CONTRACTOR
EMPLOYERS AGENT
(Non-contructual link)
CLIENT COST CONSULTANT (QS)
Architect
Facades
Comissioning
MEP
Structural Engineer Borough Council AUTHORITIES
COMPLIANCE & MONITORING TEAM
MAIN ON-SITE MEETINGS
Design coordination meeting
Daily Activity Brief (DAB)
Individual meetings
[1.05]
DESIGN &BUILD
Section 1.0
is a term describing a procurement route in which the main contractor is appointed to design and construct the works, as opposed to a traditional contract, where the client appoints consultants to design the development and then a contractor is appointed to construct the works.
Site Diary 15
[1.05.] Who are the key professionals and companies involved in the project? In this project the key companies could be split into 3 major groups: the Design Team, the Compliance and Monitoring Team and Subcontractors & Suppliers. It is not difficult to guess, that the DT designs, while the CMT monitors and checks for compliance. The DT consists of Architects, and Service & Structure engineers, and is usually appointed by the Client, but in this project particularly it was appointed by the Main Contractor. The quantity of Consultants increase with complexity of the project.
There is also a design co-ordinator or Project Manager. All the subcontractors were also appointed by the Main Contractor. However, Multiplex has a noncontractual link with the CMT, which means they can negotiate, but the members of the CMT are out of contractor’s control.
ARCHITECT
CLIENT
MAIN CONTRACTOR
In September 2007 Make was first appointed to work with this project. There was a small competition, but the choice has been done by the client long before.
Client wants this control of the development of the work, so they would rather prefer “Design and Build” contract type to a traditional one. Design and build can be seen as giving a single point of responsibility for delivering the entire project. Some clients, however, consider it is only appropriate for simple projects, where design quality is not the main consideration.
Multiplex was appointed in November 2014, as a result of a two-stage tendering.Before working on site the main contractor usually does risk estimating, as a huge of responsibility is transferred once the contract is signed.
Working in “Design and Build” conditions was uncomfortable for Make: a lot of documents, too many people involved, long confirmations and dependence on the contractor. From the architect’s point of view, reality is that sometimes contractor makes the decisions, which are not correct. Of course, traditional contract is of more preference for an architect, and “Design and Build” is better for simple projects, where the main contractor acts as an architect.
I was interested, which type of contract is of highest preference for each side of this project. I have asked whether they prefer Design and Build or not.
Multiplex would like to prefer “Design and Build” contract type, because even though they have most of risk, they can manage it and earn more money, so, in this case, risk becomes a profit. The contractor may use their own in-house designers to design the building, or they can appoint consultant designers, or the client’s designers can be employed by the contractor to complete the design (either by novation or consultant switch). In this project, apart from “Make”, there is an inhouse designer from the main contractor’s side and novated designer – “AFK”.
PROJECT TEAM
BEFORE ON-SITE
ON-SITE
2007-2016
RIBA STAGE 0-2
SINCE 2016 RIBA STAGE 4+
RIBA STAGE 2-4
PROJECT LEAD
PROJECT LEAD Make Partner
Manages the whole project. Controls that there is enough people on the job, checks fees and appointments with the Client.
Project Lead
5 PACKAGE LEADS Part ll
PACKAGE LEADS + JUNIOR ARCHITECTS Part I/ll
These people are developing the basic design from the very early stages, usually for the competition. The concept is provided by the Lead Architect.
These 5 architects are also called Package Leads. Every Lead has their own element of the project (facade, basement, roof, etc) which they work on to produce all the needed project documentation before the building is on site.
RESIDENTIAL LEAD
OLIVER HALL
Make Partner
COMMERCIAL LEAD
Leads the Residential Block at the 80 Charlotte St., which is smaller, but more comlicated.
Make Partner
Leads the main Project of Commercial Block at the 80 Charlotte St.
[1.07]
Section 1.0
[1.08]
Site Diary 17
MAKE ARCHITECTS
MY OPINION I think it is rather convenient, that main architect has a laid-back position, while their project is being developed by 3rd parties, however, the quantity of drawings to review increases and sometimes it is more difficult to address the idea to other people rather then to draw it. The quality of design may fail.
“Make is a different kind of architecture practice. Founded by Ken Shuttleworth in 2004, we’re an employee-owned firm pursuing a democratic design process that values everyone’s input. Today we have more than 150 people in London, Hong Kong and Sydney providing architecture, interior and urban design services from concept to completion.”
[1.07] What is the architect’s appointment and role on the whole project? The way Derwent chooses architect is a very organic process. “Make” was appointed directly in the early stages and the Design process was a collaborative work with client. The contract type is standard RIBA. This architect has been designing the project until RIBA Stage 4, until the AFK has been appointed by Multiplex to take on the further development of the project.
[1.08] What is the architect’s role whilst the project is on site? Is it effective? Under the traditional contract there is no influence from the Main Contractor, Architect is the key professional in the project. The role of “Make Architects” in this particular project whilst on-site is to review the drawings from novated architect AFK and check their compliance with the initial design. Architects do their job rather effectively, even though only 3 people are engaged now.
MAKE ARCHITECTS OFFICE
Section 1.0
Site Diary 18 THIS DRAWING IS COPYRIGHT OF AND SHALL REMAIN THE PROPERTY OF:
H31
H33 120 120 EQ EQ EQ EQ EQ EQ
H29
1490
10480
20
ARNEY FENDER KATSALIDIS NOTES CHECK AND VERIFY ALL DIMENSIONS PRIOR TO COMMENCEMENT OF WORK. THIS DRAWING SHALL BE READ IN CONJUNCTION WITH ALL OTHER CONTRACT DOCUMENTS INCLUDING THOSE BY OTHER CONSULTANTS, AND INCLUDING SPECIFICATIONS. SEEK CLARIFICATION OF INCONSISTENCIES/ CONFLICTS. FIGURED DIMENSIONS SHALL TAKE PRECEDENCE TO SCALED DIMENSIONS.
DIVIDE 2835 INTO 23 EQUAL PARTS (APPROX. 123) REFER TO A-44-C4401
FFL LEVEL 02
FACADE LEGEND
+33.640 m AOD. 1490
20
SJ
STACK JOINT
PJ
PANEL JOINT
750
MJ - MOVEMENT JOINT
2240
FIRE CURTAIN ON DELAYED ACTION BRICKWORK BONDS ARE SHOWN AS INDICATIVE. REFER TO A-44-3215 FOR BRICKWORK BOND SETOUT.
EWS-150 (H11) GLAZING UNIT
SLAB EDGE
2495
FRIT/BACKPAINTED GLASS TO HIDE FIRE AND ACOUSTIC BARRIER
EWS-122 (H11) PRECAST CONCRETE
3D VIEW - MAIN ENTRANCE 3
EDGE OF UPSTAND BELOW
SCALE: NTS NOTES 1. ALL PRECAST PANEL JOINTS TO BE 20MM WIDE AND RECESSED SILICONE SEALED 2. REFER TO 65 SERIES STRUCTURAL OPENING ON DOOR SCHEDULE
20
3. BEACONS AND FIRE ALARMS REFER TO 40 SERIES PLANS AND READ IN CONJUNCTION WITH ELECTRICAL ENGINEER'S DRAWINGS AND SPECIFICATIONS 4. REFER TO A-30 SERIES FOR WATERPROOFING TO LOWER LEVELS
CCTV 700
CORTEN PLATE
5. REFER TO MEP AND SECURITY ENGINEERS DRAWINGS AND SPECIFICATIONS FOR DETAILED SERVICES DESIGN LAYOUT
FFL LEVEL 01
6. REFER TO LIGHTING CONSULTANTS DRAWINGS FOR EXTERNAL LIGHTING DESIGN AND SPECIFICATION.
+30.305 m AOD.
DIVIDE 6170 INTO 50 EQUAL PARTS (APPROX.123) REFER TO A-44-C4419
7. REFER TO A-47 & A-48 SERIES FOR KITCHEN EXTRACT CLADDING DRAWINGS
EDR-125
FIXED GLAZING UNIT
8. AUTOMATED OPENING WINDOWS TO SUBCONTRACTOR DESIGN AND MUST COMPLY WITH FIRE STRATEGY REQUIREMENTS
EDR-124 (H11) REVOLVING DOOR
9. PROVISION FOR CCTV. READ IN CONJUNCTION SECURITY DRAWINGS AND SPECIFICATIONS. FINAL LOCATIONS TO BE CONFIRMED BY SUBCONTRACTOR.
EWS-150 (H11) AUTOMATIC FULL HEIGHT GLAZING FOR SMOKE AND NATURAL VENTILATION
10. FOR 6TH & 7TH FLOOR TERRACES, FIRE ALARM AND FLASHING XENON BEACONS TO BE MOUNTED DIRECTLY ON TOP OF ONE ANOTHER AT APPROXIMATELY 2400MM AFFL AND ALIGNED TO CLOSEST FULL BRICK WHERE APPLICABLE.
1500
FOR 9TH FLOOR TERRACES, FIRE ALARM AND FLASHING XENON BEACONS TO BE MOUNTED DIRECTLY ON TOP OF ONE ANOTHER AT APPROXIMATELY 3000MM AFFL.
FACADE SERVICES LEGEND
3D VIEW - MAIN ENTRANCE CORTEN FLOOR WITH S/S STRIPS WITH REQUIRED SLIP RATING RESISTANCE TO SUBCONTRACTOR DESIGN
900
240 20
H28
EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ 120 120
240 20 240
H25
4
SCALE: NTS
FA - FIRE ALARM. MOUNTED AT MIN 2.3M AFFL, ALIGNED TO CLOSEST FULL BRICK UNLESS NOTED OTHERWISE RED BREAK GLASS UNIT/ MANUAL CALL POINT MOUNTED AT 1.0M AFFL
FFL LEVEL PAVEMENT
DISABLED REFUGE CALL POINT MOUNTED AT 0.9M AFFL
+27.570 m AOD. CCTV
SCALE: 1 : 20
PROVISION FOR FIXED CCTV CAMERA VIDEO INTERCOM AT 1.5M AFFL M=MASTER, SM=SUB MASTER, S=SLAVE
VIC
10.1 SQM OF COMBINED FREE AREA TO BE PROVIDED BY AUTOMATED SMOKE VENTS. SUBCONTRACTOR TO ENSURE COMPLIANCE
EXTERNAL ELEVATION - LEVEL 00 TO 01 - CHARLOTTE ST MAIN ENTRANCE 2
FIRE TELEPHONE MOUNTED AT 1.3M AFFL
4 A-42-C4203
1 A-42-C4203
2 A-42-C4203
MANIFESTATION MARKINGS GRAPHIC DESIGN TO BE CONFIRMED
FLASHING XENON BEACON MOUNTED AT MIN 2.4M AFFL RAINWATER PIPES
RWP
ELECTRIC OUTLET POINTS
EXTERNAL LIGHTING INTERNAL
H29
1368
1300
1700
HC
- CORTEN BOX SETTING OUT UPDATED - REVOLVING DOORS POSITION CHANGED - LEGEND ADDED
150
SCALE: NTS
450
LOCATION PLAN
100
1320
CORTEN FLOOR WITH S/S STRIPS WITH REQUIRED SLIP RATING RESISTANCE TO SUBCONTRACTOR DESIGN
27.610
CHITTY STREET
EDR-124 (H11) GLASS REVOLVING DOOR
2030
2280
WHITFIELD STREET
EWS-150 (H11) AUTOMATIC FULL HEIGHT GLAZING FOR SMOKE AND NATURAL VENTILATION HOWLAND STREET
3550
HOWLAND MEWS EAST
EWS-101A (F10) BRICK FACING EXTERNAL
1:48
100
CONCEALED RAINWATER DRAINAGE SLOT
150
27.590
27.590
9518
50
50
9618
2 A-42-C4203
LINE OF UPSTAND TO STRUCTURE ENGINEER'S DESIGN
CONCRETE PAVERS LAID TO FALLS
REVOLVING DOOR PIT 2
1 A-42-C4203
LINE OF REVOLVING DOOR MACHINERY PIT BELOW
ASTOR COLLEGE
CONCEALED RAINWATER DRAINAGE SLOT
80
27.590
50
CHARLOTTE STREET
EDGE LIGHTING STRIP UNDERNEATH REFER TO ELECTRICAL ENGINEER'S AND EQ2 DRAWINGS AND SPECIFICATIONS
960
80
CORTEN PLATE
CHARLOTTE MEWS
N
CORTEN PLATE
EDGE LIGHTING STRIP UNDERNEATH REFER TO ELECTRICAL ENGINEER'S AND EQ'2 DRAWINGS AND SPECIFICATIONS
EXT-202 (Q10) S/S SLOT DRAIN
STAGE F UPDATE PL PV UNITIZED FACADE STAGE F ISSUE JML PV STAGE E ISSUE GL PV DRAFT STAGE E ISSUE GL PV CLADDING DRAFT ISSUE 2 JML PV CLADDING DRAFT ISSUE 1 JML PV DESCRIPTION DRAWN BY:CHECK BY
3D VIEW - MAIN ENTRANCE
ENTRY PANEL TO SECURITY ENGINEER SPECIFICATION AND EMPLOYER REQUIREMENTS. COVER PANEL TO BE CORTEN PANEL TO BE SUPLIED BY CORTEN BOX SUB CONTRACTOR
LINE OF DRAINAGE CHANNEL ABOVE
05 11/05/2018 04 24/03/2017 03 28/10/2016 02 07/10/2016 01 23/09/2016 00 16/09/2016 REV DD/MM/YY
5 150
EWS-122 (H11) PRECAST CONCRETE FACADE
EXT-410 (Q40) METAL FENCING TO LIGHTWELL AREAS
3 A-42-C4203
4 A-44-C4406
R1 12 5
R1 12 5
SOFFIT MOUNTED CCTV CAMERA REFER TO SECURITY ENGINEER'S DRAWINGS AND SPECIFICATIONS
RWP TO COLLECT AND DRAIN CORTEN BOX RAINWATER TO LIGHTWELL BELOW LOCATION TO BE COORDINATED BY SUBCONTRACTORS
FT TYPE
750
REVISION 05 COMMENTS
EDR-125 (H11) AUTOMATED PASSDOOR & SMOKE VENT
HA
1050
FV TYPE
EWS-101A (F10) BRICK FACING EXTERNAL
1200 MIN
1 A-44-C4433 1270
LIN-120 (H42) CONCRETE WALL LINING SYSTEM
1950
FP TYPE
H33
27.590
115
HC
1500
H31
EMERGENCY DOOR RELEASE BUTTON
1:21
H28
REMOVABLE CORTEN BOX FLOOR TO ACCESS REVOLVING DOOR FLOOR BOX. SIZE TO BE CONFIRMED WITH FACADE SUBCONTRACTOR
50
RWP TO COLLECT AND DRAIN CORTEN BOX RAINWATER TO LIGHTWELL BELOW LOCATION TO BE COORDINATED BY SUBCONTRACTORS EXT-410 (Q40) METAL FENCING TO LIGHTWELL AREAS
Arney Fender Katsalidis T / +44 20 3772 7320 E/ info@afkstudios.com W / afkstudios.com 44-46 Scrutton Street, London, EC2A 4HH.
4 A-42-C4203
CLIENT:
A-42-A3235
EXTERNAL
PROJECT
PLAN - LEVEL 00 - CHARLOTTE ST MAIN ENTRANCE 1
SCALE: 1 : 20
80 CHARLOTTE STREET
3D VIEW - MAIN ENTRANCE 6
SCALE: NTS DRAWING TITLE
CHARLOTTE ST MAIN ENTRANCE CORTEN BOX PROJECT NO.
44034 05
STATUS
SCALE
FOR CONSTRUCTION
As indicated@A0
DRAWING NO.
REVISION
A-42-A3235
05
CCTV
440
4
FACADE LEGEND FACADE SERVICES LEGEND MANUAL CALL POINT MOUNTED AT 1.0M AFFL
RED BREAK GLASS UNIT/ MANUAL CALL POINT AT MJ MOUNTED - MOVEMENT JOINT FIRE TELEPHONE MOUNTED 1.0M AFFL
AT 1.3M AFFL
PROVISION FOR FIXED CCTV CAMERA CONFIRMED
CCTV BONDS ARE SHOWN AS FIRE TELEPHONE BRICKWORK MOUNTED EDR-125
JUNCTIONS
1.3M AFFL INDICATIVE. REFER TO A-44-3215 FOR ALIGNED TO COLUMN BEHIND VIDEO INTERCOM AT 1.5M AFFL VERTICAL SECTION AT -VIC MAIN ENTRANCE INTERNAL ELEVATION BRICKWORK BOND SETOUT.
3
PROVISION FOR FIXED CCTV CAMERA
FLASHING XENON BEACON LIN-120 M=MASTER, SM=SUB MASTER, S=SLAVE MOUNTED AT MIN 2.4M AFFL GLASS TO HIDE (H42) CONCRETE FLASHING XENONFRIT/BACKPAINTED BEACON AND BARRIER This part of the drawing isACOUSTIC always to MOUNTED AT MIN FIRE 2.4M AFFL WALL LINING SYSTEM RAINWATER PIPES RWP
HC
PIPES be read, contains fundamental RWPas itRAINWATER EDGE OF UPSTAND BELOW ELECTRIC OUTLET POINTS OUTLET POINTS information,ELECTRIC which applies to the whole 4 page or series of drawings. EXTERNAL LIGHTING EWS-122 NOTES
PRIMARY STRUCTURE
A-42-C4203
LIGHTING (H11) PRECAST CONCRETE EXTERNAL FP TYPE FPPANEL TYPE 1. ALL PRECAST JOINTS TO BE 20MM WIDE AND FV TYPE EWS-150 RECESSED SILICONE SEALED 10.1 SQM OF COMBINED (H11) GLAZING UNIT FV TYPE FT TYPE FREE AREA TO BE PROVIDED 2. REFER TO 65 SERIES STRUCTURAL OPENING ON DOOR SCHEDULE BY AUTOMATED SMOKE
3 A-42-C4203
FFL LEVEL 01
4 A-44-C4406
INTEGRATED RAINWATER
31.025
DETAIL
1:21
EMERGENCY DOOR GUTTER +30.305 m AOD. RELEASE BUTTON
REMOVABLE CORTEN BOX FLOOR TO ACCESS REVOLVING DOOR FLOOR BOX. SIZE TO BE H31 CONFIRMEDBY WITH FACADE A-42-C4203/4 SUPERSEDED A-42-A3235/2 CONFIRMED SUBCONTRACTOR
EXTERNAL ELEVATION - LEVEL 00 TO 01 - CHARLOTTE5 ST MAIN NTS ENTRANCE 4 SCALE: CONCEALED RAINWATER FIXED GLAZING UNIT
A-44-C4433
1050
SCALE: 1 : 20
7. REFER TO A-47 REVISION 05 COMMENTS
& A-48 SERIES FOR KITCHEN EXTRACT CLADDING DRAWINGS
CORTEN SIDE PLATE
30.925
1300
1700
LOCATION PLAN
D
WHITFIELD STREET
5
10. FOR 6TH & 7TH FLOOR TERRACES, FIRE ALARM AND FLASHING XENON BEACONS TO BE MOUNTED DIRECTLY ON TOP OF ONE ANOTHER AT LOCATION PLAN APPROXIMATELY 2400MM AFFL AND ALIGNED TO EWS-150 CLOSEST FULL BRICK WHERE APPLICABLE. (H11) GLAZING UNIT SOMKE VENT
H28
1368
DOOR & SMOKE VENT
27.590
H31
1050
REVISION AND COMMENTS FACADE SERVICES LEGEND
FA - FIRE ALARM. MOUNTED AT MIN 2.3M AFFL, ALIGNED TO CLOSEST FULL BRICK UNLESS NOTED OTHERWISE CHITTY STREET
EXT-410 (Q40) METAL FENCING TO LIGTHWELL AREAS
1270
900
27.610
FX-302 (N20) ENTRANCE MATWELL REFER TO A-55 SERIES
1200 MIN
27.610
WHITFIELD STREET
ASTOR COLLEGE
In this footnote architect suggests that FLOOR TO BE Once the drawing has been revised, all the CONCRETE BREAK GLASS UNIT/ list, as CANTILEVERED AND 1 the corten box should be removable changes should be RED added to the MANUAL CALL POINT MOUNTED AT SUPPORTED VIA SECONDARY A-44-C4433 5 FX-302 Katsalidis 1.0M SUPPORT FIXED TO with its’ size to be confirmed withSTEEL facade well as Arney theFender number of AFFL revision, date andN A-44-C4433 CONCRETE BEAM(N20) ENTRANCE MATWELL T / +44 20 3772 7320 DISABLED REFUGE CALL POINT E/ info@afkstudios.com subcontractor once it is developed. name of its’ author. 100 MOUNTED AT 0.9M AFFL REFER TO A-55 SERIES 100
PAVEMENT
EDGE LIGHTING STRIP UNDERNEATH +27.570 m AOD.27.590 A-42-C4203 REFER TO ELECTRICALEDR-125 ENGINEER'S AND SLOT DRAIN + 27.320 EQ2 DRAWINGS AND SPECIFICATIONS (H11) AUTOMATED SSL PASS-
FLASHING XENON BEACONS TO BE MOUNTED DIRECTLY ON TOP OF ONE ANOTHER AT APPROXIMATELY 3000MM AFFL. 1950
1500 115
R1 12 5
SCALE: NTS
SYSTEM this junction, specifying the number of the 50 50(J40) WATERPROOFING MEMBRANE SUBCONTRACTOR DESIGN EXT-410 (Q40) METAL FENCING TO LIGHTWELL FFL LEVEL CORTEN PLATE FLOOR page inside CORTEN PLATEthe circle. AREAS
INTERNAL
HOWLAND MEWS EAST
REFERENCE TO OTHER DRAWINGS3D VIEW - MAIN ENTRANCE COMMUNICATION RWP TO COLLECT AND DRAIN CORTEN STRIPS WITH REQUIRED SLIP BOX RAINWATER TO LIGHTWELL LIN-120 CORTEN FLOOR WITH S/S STRIPS WITHTO RATING RESISTANCE This marking refers to detailed drawing of BELOW LOCATION TO BE 27.590 (H42) CONCRETE WALL LINING SUBCONTRACTOR DESIGN REQUIRED WPS-212 SLIP RATING RESISTANCE TO COORDINATED BY SUBCONTRACTORS
3 FFL LEVEL 01 +30.305 m AOD. A-42-C4203
CHARLOTTE MEWS
EMERGENCY DOOR N FIRE FOR 9TH FLOOR TERRACES, ALARM AND RELEASE BUTTON CHARLOTTE STREET
HC
RIGID INSULATION TO RFS-101
H29
3315
450
CHITTY STREET
HOWLAND STREET
CONCEALED RAINWATER DRAINAGE SLOT
4 A-42-C4203
CHARLOTTE STREET
HC
9. PROVISION FOR CCTV. READ IN CONJUNCTION SECURITY DRAWINGS AND SPECIFICATIONS. FINAL LOCATIONS TO BE CONFIRMED BY SUBCONTRACTOR.
1270 3550
EWS-150 EDR-125 (H11) AUTOMATIC FULL HEIGHT GLAZING EWS-150 (H11) AUTOMATED PASS-DOOR FOR SMOKE AND NATURAL VENTILATION SCALE: NTS & SMOKE VENT (H11) AUTOMATIC FULL HEIGHT CORTEN FLOOR WITH S/S STRIPS WITH GLAZING FOR SMOKE AND ENTRY PANEL TO SECURITY REQUIRED SLIP RATING RESISTANCE TO NATURAL VENTILATIONSUBCONTRACTOR DESIGN ENGINEER SPECIFICATION COVER PANEL TO BE CORTEN CORTEN PLATE PANEL TO BE SUPPLIED BY EWS-101A CORTEN BOX EDGE LIGHTING STRIP UNDERNEATH (F10) BRICKSUBCONTRACTOR FACING EXTERNAL REFER TO ELECTRICAL ENGINEER'S AND ENTRANCE SIGNAGE FEQ2 I T Z DRAWINGS R O V I A WAND 1 SPECIFICATIONS EWS-150 REFER TO DRAWING R1 1 12 CONCEALED RAINWATER DRAINAGE A-66-C6694 FOR SETTING (H11) 80 AUTOMATIC FULL HEIGHT GLAZING 5 SLOT A-44-C4435 4 OUT AND DETAILS CORTEN FLOOR WITH S/S FOR SMOKE AND NATURAL VENTILATION
PAVEMENT 4
F
750
1:21
2280
UPSTAND TO CORTEN BOX TO STRUCTURAL ENGINEER'S
W / afkstudios.com 44-46 Scrutton Street, London, EC2A 4HH. MOUNTED FIRE TELEPHONE AT 1.3M AFFL
CHARLOTTE MEWS
CHARLOTTE STREET
PAVEMENT
ASTOR COLLEGE
SLOT DRAIN
CLIENT:
CCTV RWP TO COLLECT AND
R1 12 5
PROVISION FOR FIXED CCTV CAMERA
CHARLOTTE MEWS
N
- CORTEN BOX SETTING OUT UPDATED - REVOLVING DOORS POSITIONWINDOWS CHANGED TO SUB8. AUTOMATED OPENING - LEGEND ADDED DESIGN AND MUST COMPLY WITH FIRE CONTRACTOR
HOWLAND STREET
EWS-101A
LIN-120 (H42) CONCRETE WALL LINING SYSTEM
DETAIL A-42-C4203/4 SUPERSEDED BY A-42-A3235/2 1 EWS-101A A-42-C4203 (F10) BRICK FACING EXTERNAL
H33
3D VIEW - MAIN ENTRANCE
REVOLVING DOOR ERY PIT BELOW
ALIGNED TO COLUMN BEHIND
HOWLAND MEWS EAST
(F10) BRICK FACING EXTERNAL (H11) REVOLVING DOOR
TO
TO
STRATEGY REQUIREMENTS
A-44-C4406 EDR-124 AOD. +30.305 m
EDR-124 (H11) GLASS REVOLVING DOOR
INTERIOR
GUTTER
4 LEVEL 01 FFL
590
WHITFIELD STREET
PV 045. 24/03/2017 UNITIZED STAGE F ISSUE JML PV REFER TO MEP AND FACADE SECURITY ENGINEERS REVISION 05 COMMENTS 03DRAWINGS 28/10/2016 AND STAGE E ISSUE GL PV SPECIFICATIONS FOR DETAILED - CORTEN BOX SETTING OUT UPDATED 02SERVICES 07/10/2016 DRAFTLAYOUT STAGE E ISSUE GL PV DESIGN - REVOLVING DOORS POSITION CHANGED 01 23/09/2016 CLADDING DRAFT ISSUE 2 JML PV - LEGEND ADDED RECESSED AUTOMATIC DOOR SENSOR 6. 16/09/2016 REFER TO LIGHTING CONSULTANTS DRAWINGS FOR PV 2 MANIFESTATION MARKINGS 00 CLADDING DRAFT ISSUE 1 JML 31.025 INTEGRATED RAINWATER EXTERNAL LIGHTING DESIGN AND SPECIFICATION. REV DD/MM/YY DESCRIPTION DRAWN BY:CHECK BY GRAPHIC DESIGN TO BE A-42-C4203
LIN-120 (H42) CONCRETE WALL LINING SYSTEM
3D VIEW - MAIN ENTRANCE
DRAINAGE SLOT 1950
HOWLAND MEWS EAST
HOWLAND STREET
INTERNAL
ENGINEER'S DRAWINGS AND SPECIFICATIONS 04 24/03/2017 UNITIZED FACADE STAGE F ISSUE JML PV 03 28/10/2016 STAGE E ISSUE GL PV 02 07/10/2016 DRAFT STAGE ETO ISSUE GL FOR PV 4. REFER A-30 SERIES WATERPROOFING 01 23/09/2016 CLADDING ISSUE 2 JML PV LOWERDRAFT LEVELS 00 16/09/2016 05 CLADDING DRAFT ISSUE 1 JML PV 11/05/2018 STAGE F UPDATE PL REV DD/MM/YY DESCRIPTION DRAWN BY:CHECK BY
+30.305 mALIGNED AOD.TO COLUMN BEHIND
FIXING BRACKETS TO CORTEN BOX TO SUBCONTRACTOR & STRUCTURE ENGINEER'S DESIGN
PAVEMENT
This technical drawing of the corten entrace by AFK +27.570 m AOD. serves a good example of a typical drawing to be sent to subcontarctors for further development. It can also LOCATION PLAN be05 used on meetings (not for construction) when marked “for reference only”. Once the drawing is finally confirmed, it goes on-site.
VENTS. SUBCONTRACTOR 3. BEACONS AND FIRE ALARMS REFER TO 40 SERIES PLANS AND READ IN CONJUNCTION WITH ELECTRICAL TO ENSURE COMPLIANCE 05 11/05/2018 STAGE F UPDATE PL PV EXTERIOR
FFL LEVEL 01
REVOLVING DOOR
interaction with subcontractors and suppliers belong to AFK, while Make only reviews their documents. FFL LEVEL
FT TYPE
900
VAPOUR BARRIER
3 A-42-C4203
LINE OF REVOLVING
- DETAIL A-42-C4203/4 SUPERSEDED DOOR MACHINERY PIT FLOOR PIT RATING RESISTANCE TO The responsibilities of developing the drawings and - LEGEND UPDATED SUBCONTRACTOR DESIGN
HA
STRUCTURAL SLAB
1500
INTERIOR
EWS-101A (F10) BRICK FACING EXTERNAL
RECESSED WEATHER SEAL
2
M=MASTER, SM=SUB MASTER, S=SLAVE CCTV NOTES AND LEGEND VIDEO INTERCOM SLAB AT 1.5MEDGE AFFL
SCALE: 1 : 20
VIC
CORTEN PLATE
OMKE VENT
MANIFESTATIONS MARKINGS
DISABLED REFUGEFIRE CALLCURTAIN POINT ON DELAYED ACTION GRAPHIC DESIGN TO BE MOUNTED AT 0.9M AFFL
HA
EPDM SEALCORTEN PLATE
H29
CALL POINT MOUNTED AT 0.9M AFFL
+27.570 m AOD.
HC
PL PV JML PV 03 24/03/2017 UNITIZED FACADE STAGE F ISSUE JML PV 02 28/10/2016 STAGE E ISSUE GL PV [1.09] What documents and drawings 01 07/10/2016 DRAFT STAGE E ISSUEare beingGL PV 00 23/09/2016 DRAFT ISSUE 2 JML PV referred to on-site and inCLADDING meetings? REV DD/MM/YY DESCRIPTION DRAWN BY:CHECK BY 900
Unique of this project is that there are two architectural REVISION 05 COMMENTS 3D VIEW - MAIN ENT practices involved: “Make”(compliance architect) and - REVOLVING UPDATED 4 CORTEN FLOORDOOR WITHDETAILS S/S SCALE: NTS “AFK” (novated architect). - DIMENSION AND NOTESSLIP UPDATED STRIPS WITH REQUIRED
SJ ALARM. MOUNTED STACK JOINT FA - FIRE AT MIN 2.3M AFFL, ALIGNED TO CLOSEST FULL BRICK DISABLED REFUGE UNLESS PJ NOTED OTHERWISE PANEL JOINT
3 A-42-C4203
(H11) GLAZING UNIT
HC
CONSULTANTS, AND INCLUDING SPECIFICATIONS.
FIRE AND ALARM. MOUNTED AT MIN 2.3M FOR 9TH FLOOR TERRACES, FA FIRE- ALARM SEEK CLARIFICATION OF INCONSISTENCIES/ FLASHING XENON BEACONS AFFL, TO BE MOUNTED ALIGNED TO CLOSEST FULL BRICK FIGURED DIRECTLY ONCONFLICTS. TOP OF ONE ANOTHER ATDIMENSIONS SHALL TAKE UNLESS NOTED OTHERWISE PRECEDENCE TO SCALED DIMENSIONS. APPROXIMATELY 3000MM AFFL.
FFL LEVEL PAVEMENT
EWS-101A MINERAL WOOL INSULATION (F10) BRICK FACING EXTERNAL 750
FACADE SERVICES LEGEND
10.1 SQM OF COMBINED FREE AR TO BE PROVIDED BY AUTOMATE SMOKE VENTS, SUBCONTRACTO TO ENSURE COMPLIANCE
EWS-150 (H11) AUTOMATIC FULL HEIGHT 05 11/05/2018 STAGE F UPDATE GLAZING FOR SMOKE AND 900 04 25/05/2017 STAGE F UPDATE NATURAL VENTILATION
APPROXIMATELY 3000MM AFFL.
10. FOR 6TH & 7TH FLOOR TERRACES, FIRE ALARM AND CHECK AND VERIFY ALL DIMENSIONS PRIOR TO FLASHING XENON BEACONS TO BE MOUNTED OFATWORK. THIS DRAWING SHALL BE DIRECTLY ONCOMMENCEMENT TOP OF ONE ANOTHER READ IN CONJUNCTION WITH APPROXIMATELY 2400MM AFFL AND ALIGNED TO ALL OTHER CONTRACT CLOSEST FULL BRICK WHEREINCLUDING APPLICABLE. THOSE BY OTHER DOCUMENTS
MINERAL WOOL INSULATION
SUBCONTRACTOR DESIGN
EWS-122 (H11) PRECAST CONCRETE
H33
1500
900
AOD. +27.570 m
In this drawing architect provides the It is extremely important to explain subEWS-122 STRUCTURAL SLAB contractors how their products should be sub-contractor(H11) with the guidelines by PRECAST CONCRETE 3D VIEW - MAIN ENTRANCE 3 built into the main structure or joined with SCALE: NTS specifying that dimensions should be EXTERIOR 1 other customized items. A-42-C4203 PRIMARY STRUCTURE equal.
TER
TER
FFL LEVEL PAVEMENT
INTERIOR
EWS-150 VERTICAL SECTION - REVOLVING DOOR
10.1 SQM OF COMBINED FREE AREA TO BE PROVIDED BY AUTOMATED SMOKE VENTS. SUBCONTRACTOR TO ENSURE COMPLIANCE
ARNEY FENDER KATSALIDIS
STRUCTURAL SLAB
SCALE: NTS
FT TYPE EDR-124 (H11) REVOLVING DOOR
9. PROVISIONFLASHING FOR CCTV. READ IN CONJUNCTION XENON BEACONS TO BE MOUNTED SECURITY DRAWINGS AND SPECIFICATIONS. FINAL N BE O CONFIRMED T E S ON BY DIRECTLY TOP OF ONE ANOTHER AT LOCATIONS TO SUBCONTRACTOR.
RED BREAK GLASS UNIT/
DIVIDE 6170 INTOCORTEN 50 FLOOR WITH S/S EQUAL PARTSSTRIPS WITH REQUIRED SLIP (APPROX.123)RATING RESISTANCE TO REFER TO A-44-C4419
DOCUMENTS FP TYPE FIXED GLAZING UNITFV TYPE FROM ARCHITECT
FOR 9TH FLOOR TERRACES, FIRE ALARM AND
SSL + 26.820
3D VIEW - MAIN ENTRANCE
+30.305EXTERNAL m AOD. LIGHTING
CONTRACTOR DESIGN AND MUST COMPLY WITH FIRE STRATEGY REQUIREMENTS
VAPOUR BARRIER
+27.570 m AOD. EXTERIOR
1
FIRE ALARM AND FLASHING XENON BEACONS TO BE MOUNTED 7. REFER TO DIRECTLY A-47 & A-48 SERIES FOR KITCHEN ON TOP OF ONE ANOTHER AT EXTRACT CLADDING DRAWINGSIS COPYRIGHT OF AND SHALL REMAIN THIS DRAWING APPROXIMATELY THE PROPERTY OF:2400MM AFFL AND ALIGNED TO 8. AUTOMATED OPENING WINDOWS TO SUBCLOSEST FULL BRICK WHERE APPLICABLE.
STRUCTURE TO REVOLVING DOOR TO ENGINEER'S DESIGN
1150
FFL LEVEL 01
350
450
1150
3 A-44-C4433
+33.640 m AOD.
4 SCALE: 1 : 20 DIMENSIONS A-42-C4203
6. REFER TO LIGHTING CONSULTANTS DRAWINGS FOR 10. FOR 6TH AND & 7TH FLOOR TERRACES, EXTERNAL LIGHTING DESIGN SPECIFICATION.
FX-302 (N20) ENTRANCE MATWELL REFER TO A-55 SERIES
100
SCALE: NTS
450
690
4
700
CORTEN FLOOR WITH S/S STRIPS WITH REQUIRED SLIP FFL LEVEL 00 RATING RESISTANCE TO AOD. +26.970 m FFL LEVEL 02 SUBCONTRACTOR DESIGN
3D VIEW - MAIN ENTRANCE
350
EXT-202 (Q10) SLOT DRAIN
PRIMARY FFL LEVEL STRUCTURE PAVEMENT
9. PROVISION FOR CCTV. READ IN CONJUNCTION
REVOLVING DOOR FLOOR PIT
27.610
190
20
27.610
Site Diary 19
CHITTY STREET
EDR-124 (H11) REVOLVING DOOR
TO SUB-
5. REFER TO MEP AND SECURITY ENGINEERS SECURITY DRAWINGS AND SPECIFICATIONS. FINAL DRAWINGS AND SPECIFICATIONS FOR DETAILED LOCATIONS SERVICES DESIGN LAYOUT TO BE CONFIRMED BY SUBCONTRACTOR.
REVOLVING DOOR MACHINERY PIT
RAINWATER PIPES
ELECTRIC OUTLET POINTS
LOWER LEVELS
TO ACCESS REVOLVING DOOR FLOOR BOX. SIZE TO BE CONFIRMED WITH FACADE SUBCONTRACTOR
FIXED GLAZING UNIT
RWP CORTEN PLATE
EWS-150 ENGINEER'S CONTRACTOR DRAWINGS AND SPECIFICATIONS DESIGN AND MUST COMPLY WITH FIRE (H11) GLAZING UNIT STRATEGY REQUIREMENTS 4. REFER TO A-30 SERIES FOR WATERPROOFING TO SMOKE VENT
10.1 SQM OF COMBINED FREE AREA TO BE PROVIDED BY AUTOMATED SMOKE VENTS, SUBCONTRACTOR TO ENSURE COMPLIANCE REMOVABLE CORTEN BOX FLOOR
HA
EWS-150 (H11) AUTOMATIC FULL HEIGHT GLAZING FOR SMOKE AND NATURAL VENTILATION
6. REFER TO LIGHTING CONSULTANTS DRAWINGS FOR SPECIFICATION.
1. ALL PRECAST PANEL JOINTS TO BE 20MM WIDE AND EXTERNAL LIGHTING DESIGN AND RECESSED SILICONE SEALED
8. AUTOMATED OPENING WINDOWS PLANS AND READ IN CONJUNCTION WITH ELECTRICAL
175
RETE
FFL LEVEL 01 +30.305 m AOD.
FLASHING XENON BEACON20 MOUNTED AT MIN 2.4M AFFL
TO A-47 &OPENING A-48 SERIES FOR KITCHEN REFER TO 7. 65 REFER SERIES STRUCTURAL ON REVOLVING2.DOOR DOOR SCHEDULE EXTRACT CLADDING DRAWINGS FLOOR PIT 3. BEACONS AND FIRE ALARMS REFER TO 40 SERIES
LINE OF REVOLVING DOOR MACHINERY PIT
CORTEN PLATE
EWS-150 WPS-212 (J40) WATEPROOFING (H11) AUTOMATIC FULL HEIGHT MEMBRANE GLAZING FOR SMOKE AND CORTEN PLATE FLOOR NATURAL VENTILATION
Section 1.0
NOTES
350
2495
EDR-124 RIGID INSULATION (H11) REVOLVING DOOR TO
PAVEMENT
AOD. +30.305 m
MANIFESTATIONS MARKINGS GRAPHIC DESIGN TO BE CONFIRMED
ION - MAIN ENTRANCE INTERNAL ELEVATION VOID FORMER RFS-101
FFL LEVEL 01 10480
SCALE: NTS
M=MASTER, SM=SUB MASTER, S=SLAVE
5. REFER TO MEP AND SECURITY ENGINEERS EDGE OF UPSTAND DRAWINGS ANDBELOW SPECIFICATIONS FOR DETAILED SERVICES DESIGN LAYOUT
115
3550
EDR-124 (H11) GLASS REVOLVING DOOR
FIXED GLAZING UNIT
3
100
+30.305 m AOD.
[1.09]
1270 3D VIEW - MAIN ENTRANCE
365
FFL LEVEL 01
EWS-122 2280 (H11) PRECAST CONCRETE
3315
240 20
AOD. +30.305 m
EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ
DRAINAGE SLOT
CORTEN PLATE FFL LEVEL 01
4 A-44-C4406
ASTOR COLLEGE
REMOVABLE CORTEN BOX FLOOR TO ACCESS REVOLVING DOOR FLOOR BOX. SIZE TO BE CONFIRMED WITH FACADE SUBCONTRACTOR 1300
1700
3D VIEW - MAIN ENT Arney Fender Katsalidis 5 T / +44 20 3772 7320 SCALE: NTS E/ info@afkstudios.com W / afkstudios.com FX-302 (N20) ENTRANCE MATWELL 44-46 Scrutton Street, London, EC2A 4HH.
REFER TO A-55 SERIES EWS-101A R1 (F10) BRICK FACING EXTERNAL 125 CLIENT:
Section 1.0
DOCUMENTS FROM SUBCONTRACTOR
Here we can see a detailed drawing from Felix, which is the main facade subcontractor in this site. When subcontractor receives drawing from AFK, they start thinking how it could be produced in a way to comply with the architect’s guidelines. However, communication goes on. It may happen that initial requirements cannot be met, for example, due to the material size limits or lack of structural rigidity of architect’s design. In this case, subcontractor marks the drawings with revision clouds and comments and sends them back and the design process contines. Typical drawings usually have dozens of revisions, that is why to confirm one item it may take from several days to several years
MY OPINION I think that sometimes it is more efficient to meet and discuss the drawings, unless you have overseas subs, which was the case in this project. However, some tours were organised for prototype observation.
Site Diary 20
[1.10]
[1.11]
[1.12]
Section 1.0
Site Diary 21
MEETINGS
01
TYPES OF SITE MEETINGS Every subcontractor has its Lead Pacakage Manager and Quantity Surveyor, they are in charge of coordination with Site Manager. All the Package Managers and also once Client’s representative are sitting in the Site Office for more efficient communication between the sides. The Main Point of Contract on site is Multiplex, which has most control over the Design Team and subcontractors.
02
WHAT HAPPENS IN A SITE MEETING? Different sides meet and discuss any problems or issues and propose the solutions. Site meetings provide a good opportunity for two-way discussions of any issues that have arisen or that are anticipated. Holding meetings on site enables the stakeholders to see progress for themselves, and to look at problem areas, discuss quality issues, assess mock-ups, and so on.
DAB (Daily Activity Brief) is the most important meeting on-site, attended by 30-40 people, all the representatives of subcontractors, trades and supervisors, currently engaged in the construction process. Every day there are 2 DABs: one for the Residential and one for the Commercial Project. Weekly Logistics Meetings with the trades are attended by Project Manager, Contract Manager, Site Manager, Off-site Manger and a Site Supervisor.
H&S Week (Health and Safety)is a big event, held by the H&S Advisor for everyone working on-site. Weekly Engineering Meeting is attended by 2 Engineers and 2 Site Managers either on site or in the office. Project Director leads all the Client facing meetings and also communicates with the major Package Managers. Design Meeting is one attended by the Site Manager and Project Leads from “Make Architects” and “AFK”. Main subcontratcors, like “Amery Construction” (concrete) and “Bourne” (steel) are allocated Weekly individual meetings. Internal Site Meeting is held every 4 days and is for Multiplex only.
01 MEETING IN THE OFFICE photo provided by Make Architects
02 SITE OFFICE
02.
THE DESIGN TEAM
Section 2.0
[2.02]
Site Diary 23
ARCHITECT+ CLIENT
[2.01] What is the nature of the agreement between the Architect and the client? Standard RIBA agreement [2.02] How has the Architect’s fee been calculated? Why is the architect doing the project?
CLIENT Employer agent
SLW
D&C CONTRACTOR
(Non-contructual link)
DESIGN TEAM
[2.01]
Architect
Multiplex + AFK: it is scope of work to be done: certain amount of works, certain amount of time and resources, or can be people times fee – a profile of the amount they are paid for month. Sometimes the contractor pays extras, if the architect should do any changes to the project. Derwent + Make: fee rate per month. Fee may go up or down depending on various conditions. In 2007 the client and architect could not agree for the certain fee, as the scheme of work has changed. It is a communicative process and always negotiation. Make prefers fee to be based on similar projects on site or based on the scope of work they have on other sites. Sometimes when the quantity of
MY OPINION
Architect
CMT
I think that the main reason why Make is doing this project is a desire to implement their concept and widen their portfolio, because, in my view, the conditions and fee are not really what they wanted.
drawing reviews rises, the fee raises. Sometimes the number of people involved may increase, but the fee remain the same. Regarding the fee, Make is rather flexible. The model of AFK is very strict: exact amount of people and time, fee agreed by emloyee’s wage. The more people is involves – the more money AFK earns.
[2.06]
Section 2.0
[2.07]
Site Diary 24
BUDGET
HOW GOOD?
Increasing quality Increasing requirements Pressure on Scope and Shedule/Cost
60%
[2.06] What is driving the project? The client’s biggest value is appraisal of the design. They are also interested in maximizing the assets in their portfolio, which also means money or new projects with new design value or both.
QUALITY
In Derwent’s case the project is never driven by one factor. According to the client’s opinion, the priorities for 80 Charlotte project were in the following sequence: quality, budget and the programme. Two questions Derwent is interested to know about are: “What will be the result?” and “Will this result be viable?”
£ 190 million
[2.07] What are the penalties to the contractor if the project over runs?
SCOPE
There are 7 different stages and different penalties depending on the stage. In the last stage of completion, in case of delay Multiplex will be charged 243000 pounds every week since the time of completion date (December 2019). However, Derwent gives them one extra month to finish the works with an exemption from fine. This means, the final completion date is January 2020.
HOW CHEAP?
10 years HOW FAST?
BUDGET
10%
PROGRAMME
30%
[2.04]
Section 2.0
[2.05]
Site Diary 25
DESIGN TEAM
DESIGN TEAM
[2.03]
[2.03] Who are the Design Team? Logistics
Access
Structural Engineer
The Design Team consists of AFK (Novated Architect), Arup (both Structural Engineer and Building Services Engineer), Del Bueno (Landskape Design), Access=Design (Access), Clewlow (Transport), Madigan Gill (Logistics), BRCS (Building Control) and Orsa (Maintenance).
H&S
CLIENT
[2.04] Who is administering the contract? Architect / Project Manager / another? Building control
MEP
Architect
Project Manager
The contract is administrated by the Main Contractor - Multiplex, but there is also an Employent Agent -SLW and a Project Manager - Buro Four. [2.05] In your opinion has the Design Team worked efficiently together?
MY OPINION SLW
EMPLOYERS AGENT
D&C CONTRACTOR
I reckon that companies in the field of commercial building construction tend to have long-term partnership and are doing their job for decades, so it is not a problem for them to work efficiently enough on a new project.
I believe, that the Design Team has done a good job in competeing the design of a complex project and granting a planning permission. However, I guess it was rather challenging for the members of the Design Team to resume work after the period when the project was frozen for 2 years. Almost all representatives of the Constrcution Team who I was talking to during the site visits were relatively new to the project with a 10 years time scale, and I have not met anyone engaged in the project from its begining.
Section 2.0
Site Diary 26
QA WORKFLOW
CONSULTANT ENQUIRY
MCE Document Control QA Check &Log drawings on comments tracker
MCE DM and PM Review apply MCE status
Issues drawings to Multiplex
CMT comment on drawings and markup drawings
Via CMT Comment mail type
MCE DM & SLW meet weekly to review NonCompliance issues & agree actions
MCE DM & PM Amend Status as agreed and file replace with updated MCE stamp
Monday 12.30-1.30 slot
“FOR CONSTRUCTION” approved documents issued
Status C
Construction Document Management Software Status C
COORDINATION PROCESS
1 DAY
DM Design manager
10 DAYS
PM Package manager
10 DAYS
Max. 5 DAYS
CMT Compliance & Monitoring Team
1 DAY
SLW Employer agent from client’s side
1 DAY
[2.08]
[2.10]
Section 2.0
Site Diary 27
WORKFLOW
CLIENT
[2.08] What is the process and procedure for information and instructions going to the contractor? Is it efficient?
D&C CONTRACTOR
Official instructions are going on site through technical drawings marked “For construction”. The point of contract from Multiplex is their design manager, who negotiates with architects through on-line platform.
Contract design intent
[2.10] How does the Design Team share and Co-ordinate information and drawings? Is this efficient? Towards agreement there is a long approval process. In this project it is implemented through the Information Data Management.System, called “Acinex”. It is an on-line platform, in which every member of the Design Team has their personal accounts. Once the drawings are uploaded to programme, they are transmitted to QA Workflow.
ARCHITECT
Architect Coordintated design intent Drawing review Revision 00, 01, 02…
Information doesn’t come through once ususually, Drawing revew
the decisions are made through negotiations. There is a special CMT comments type between users.Comments may be A, B ,C, D type with, D – denied, A – approved. The hisory of comments is kept in the system, so that it would be easier to
analyze the data. Reporting delays via programme helps administering the process. Once the drawings receive A-A, they go to a final stage and are receive a stamp “For construction”. According to the diagram on the left, the whole process of approval should take 28 days. In real life it is longer then that, as it takes more one month to get A-A comments. The documents for construction may be reissued for 3 times The participants of the process would hardly call it efficient, as sometimes there can be up to 600 drawings to review for 1 person per month or 80 drawings to review for 1 person in a 10 day workflow.
Facade subcontractor Design responsibility
ARCHITECT’S OPINION METAL SYSTEMS
Specialist subcontractor
In a post-tender stage like this there shouldn’t be so many drawings to review The biggest problem is with residential buildings. Make developed design and AFK approved, but subcontractors said they couldn’t build this. This is the problem with bespoke items - may be 20 different arrangements of a single column and, of course, huge amount of information arising on the site. But people need quick answers.So it is quicker to use sketching in this process, however it is difficult to record that.
[2.09]
Section 2.0
Site Diary 28
GOING DIGITAL
There are 2 kinds of mockups subcontractor makes – performance and visual, they are aimed to reduce risk of the client and contractor – the aim of the mockups [2.09] Are any Modern Methods of Construction, such as prefabrication, being utilised? There is a great use of DFMA and prefabrication in this project. By simplifying the design of a product it has been made possible to manufacture and assemble it more efficiently, in the minimum time and at a lower cost.
Pre-fabricated concrete plank - bottom side (ceiling)
Almost everything for this project was prefabricated off-site: concrete floor slabs, structural columns, beams, facade elements. The number of assembly operations was reduced to minimum with simple bolting joinery and assembly of two floors at a time. Two floors are connected with one module of column.
Example of DFA: facade brackets on the external column for pre-fabricated facade assembly
Environmental testing of facade - simulation of rain
Pre-fabricated facade performance mockup
Pre-fabricated concrete plank - top side to be covered with in-situ concrete
[2.11]
[2.12]
Section 2.0
MY OPINION HAS CHANGED I have always thought that to build a complex building like this BIM technologies are mainly used. Contrary to this belief, in this project all drawings were made in CAD with the BIM used for reference for engineering and structure. The reason for this is that it is extremely hard to make a good output from BIM model because of its’ complexity, moreover there are constraints of creating BIM model of the existing building. Nevertheless, Muliplex uses BIM as a tool to coordinate works on-site.
BIM
QR for logistics and assembly
Intersection of primary structures with MEP were made possible with BIM. This allows to coordinate different services.
The prefabricated beams and columns of different types are also marked with unique codding to increase efficiency of construction.
Site Diary 29
ON SITE
[2.11] Identify how, if any, digital technology is influencing the progress of the site? As far as many elements in this building are prefabricated off-site, it is extremely important to distinguish them. QR codes contain a link to the inforamtion about every single beam, which can be found in a special system. The number of beam complies with its’ number in the technical drawing. It helps to track the production and transportation of beams, increasing logistics efficiency and allowing contractor to plan the works in case of delays. QR codes also help to assemble and maintain structure in future. [2.12] What opportunities are there for digital technology to influence site operations? The site is very technologically effective, so I could not spot any other opportunities.
INTERESTING There is also a crane anti-collision system, as the tower cranes are placed very close to each other. It is intetesing, that 3 vaults were designed to put the cranes during the constrcution process, they will be then dismantled.
QR for maintenance This yellow markings indicate the holes where MEP will come through. The condition of the holes is permanently reviewed and updated in the system.
The tower-cranes location scheme
03.
STATUTORY APPROVALS
[3.01]
[3.02]
Section 3.0
[3.04]
Site Diary 31
PLANNING SECTION 106 AGREEMENT are private agreements made between local authorities and developers and can be attached to a planning permission to make acceptable development which would otherwise be unacceptable in planning terms.
[3.01] How did the project achieve Planning permission? Was it complicated? Normally this process takes place after the feasibility studies. Design team attends preapplication meetings to discover the preferences of the local authorities, submit the planning application, waits 3-18 months to get the decision.
Agreement for this project: - provide affordable housing - build a public pocket park
Planning notices
This one was unusual, because it went through a political committee. There were two applications for different blocks - a detailed planning application (reference 2010/6873/P), alongside an application for conservation area consent (reference 2010/6879/C). Both of them were submitted to the London Borough of Camden (LBC) on 17 December 2010. The committee has turned it down. Thereafter the application was taken to GLA (Greater London Authority), as it has the power to over-ride planning decisions made by the London Boroughs if they are
believed to be against the interests of London as a whole. To navigate through complexity of Camden planning requirements, an expert planning consultant “DP9” was hired. Applications were approved by the Greater London Authority (GLA) on 16 March 2012. Scheme currently on site was amended in 2013 and 2014. The Decision Notice accompanying the permissions included 20 conditions which need to be satisfied at various stages of the project. Current position is that 18 of the 20 conditions have been discharged. The owners of these conditions are either Multiplex or Derwent London.
[3.02] Look up the project on the Planning Portal and view the Planning Drawings – are they being strictly adhered to? Yes, the Planning Drawings are strictly adhered to.
Existing structure
Initial partial demolition intent
[3.04] How are the Building Regulations being dealt with, i.e. Approved Inspector, Local Authority, why was the particular route chosen? Building regulations were dealt with through an Approved Inspector consultancy – “BRCS”. It worked closely with design and construction team and provided the client with Building Regulation compliance and the mandatory certificates that they needed to complete the construction project. Generally, on this project building regulations were easy to deal with, the only exception was focusing more on fire requirements since the Grenfell Tower fire tragedy. One biggest issue was compliance with disability requirements, which was really a pitfall of working with existing buildings, trying to adjust old structure to new requirements.
Actual demolition
CONSULTANTS
Planning consultant
Approved Inspector
AUTHORITIES
LBC
GLA
Section 3.0
[3.05]
Alternative entrance
INCLUSIVE DESIGN STRATEGY
Site Diary 32
Main entrance
Alternative entrance
[3.05]  What is the strategy for Inclusive Design and Access for All? Do you agree with this and how could this be improved?
In the center of the building there is an accessible central core, in which all the elevators, stairs and toilets along with the disbled WCs are placed. Lifts can accommodate wheel chair users or users who are not capable of using the stairs, taking them to each floor of the building. Wherever the toilet if placed, it is accompanied with adapted toilets to provide disabled users with suitable toilets, wash basins and grab rails for support.
VIP entrance
Access
Toilets for disabled
Lifts in central core
Howland St
The project if fully Life time home compliant. This means, that beyond the Building Regulations, which are not intended to provide the full standard of accessibility for disabled rather then making housing more accessible for visitors, a higher standard of 16 design features is met to ensure a new house will meet the needs of most households. For example, this includes wheelchair accessible WCs, easy access to windows, accessible for all sockets and many more.
Parking for disabled
The ground floor plan demonstrates that the entrances from the Charlotte St and Howland St are equipped with ramps and the Loading Bay has a safe route from the disabled parking bays.
Ramp
Main entrance Charlotte St
Gallery
[3.07]
[3.08]
PARTY WALL
Section 3.0
Site Diary 33
PARTY WALL AGREEMENT It is an act, which puts in place steps to safeguard the rights of those undertaking certain types of building work and the rights of their adjoining neighbours.
[3.07] Are there any Party Wall issues? Fortunately, there were no serious Party Wall issues, as it is an island site and almost all adjoining houses belong to the client.
This act is separate from planning permission or building regulation approval.
However, as 65 Whitfield Street has party wall there were some minor agreements, regarding scaffolding, crane rotating, access and construction boundaries, which did not take long. All the agreements were reached and can be reviewed at the Camden planning portal.
[3.08] If so how long did they take to reach Party Wall agreement? It only took several months to reach the agreements, however the other big issue was “difficult” neighbors, who were literally putting up roadblocks.
80 Charlotte Street & 65 Whitfield Street site boundary
Ownerships under Derwent London Group
CLIENT’S OPINION Constant pressure from neighbourhood did some damage to the project budget. 2,5 million pounds were lost on complying with affordable housing requirement of 106 agreement and also 10-15 millions pounds of value was lost on creating Pocket Park.
[3.09]
[3.11]
Section 3.0
Site Diary 34
CDM
[3.09] What is the project approach to CDM? Who is the Principal Designer and Principle Contractor? Are those persons that ‘create’ risk responsible for ‘managing’ that risk to the health and safety of others during construction, use and maintenance of the building? The CDM issue was managed by a subcontractor appointed by Multiplex, which is literally Multiplex’s other business. This 3rd party serves as both the Principle Designer and the Principle Contractor Even though the construction works have started long ago, the principal contractor still visits the site on a monthly basis.basis. The process of discharging the CDM issue is: Health and safety risk is labeled
and the risk goes to the CDM document, which is tendered. Thus, the main contractor is responsible for the risk they create themselves. ORSA is a CDM advisor of the project, but has bo obligations.
[3.11] In your view what are the key risks during the construction process and the eventual use of the building? Have all these risks been identified by the CDM team? Have you spotted any others? Visually/ graphically, how can you represent this? Cross link questions in this section with section 0.0 Formative Assessment/ Risk Assessment. I feel that the most dangerous risk on site may be a result of „competency failure” which can easily happen by mistake of one individual and lead to the increase of other health and safety risks. With all the hazards being monitored, however, if one individual
fails, there could be worrying results. An example of an easy competency failure, could be failing to remember to wear a hi-visibility jacket, which could lead to an accident.
THE CDM FLIPSIDE Sometimes CDM is used as an excuse by some sub-contractors when they do not want to produce the assigned scope of work.
The principal designer has responsibility for coordination of health and safety during the preconstruction phase, the principal contractor should coordinate the construction phase of the project.
Section 3.0
Site Diary 35
EXAMPLES OF H&S ON-SITE
SITE MANAGER James Hastie (Multiplex)
H&S MANAGER Louis Simo (Multiplex)
NAVIGATION
MOBILE PHONE USE AREA
HOLE MARKING
Reduces the risk of being trapped by vehicle. Faciliates the evacuation in case of emergency.
Reduces the risk of being distracted.
Reduces the risk of falling from a height.
EMERGENCY DOORS
EYES AND EARS PROTECTION
SCENE 6
Faciliates the evacuation in case of emergency.
Reduces the risk of injuries.
Reduces the risk of falling from a height.
I FOUND IT INTERESTING The situation in which the main contractor’s subsidiary serves as a principal designer/contractor is rather common. In case of big mistake they may dissolve it and have less obligations.
04.
BUILDING THE BUILDING
[4.01]
[4.02]
Section 4.0
Site Diary 37
MAIN CONTRACTOR
[4.01] Who is the Main contractor? How is the company set up? What are your personal thoughts on the performance of the main contractor? Multiplex is the Main contractor of the project Multiplex is an affiliated company of Brookfield, one of the world’s biggest asset managers. During my Site Diary Project I met mainly with Multiplex representatives and really liked the way everything was organised. The site was clean and the quality of construction works was just ideal. I was impressed to see such tidy construction site. It feels like Multiplex has high standards and gives a sense of performing beyond the expectations. [4.02] How was the main contractor selected for the project? Multiplex won a tender process, commenced in November 2014. The client was choosing between three main contactors - Bam, Multiplex and Mace, taking part in tender. There was a 2 stage tendering with the fee costs being specified at every stage. The pre-construction Agreement was signed first and then design information was sent for tender.
BROOKFIELD STRUCTURE
During the 1st stage a simple proposal has been received, and from that time a bigger package of design information has been calculated. The lumpsum fixed price was set. The overall construction cost was set at around 200 million pounds, including 5-6% for the job of Multiplex.
Two-stage tendering is used to allow early appointment of a supplier, prior to the completion of all the information required to enable them to offer a fixed price. In the first stage, a limited appointment is agreed to allow work to begin and in the second stage a fixed price is negotiated for the contract.
In the 2nd stage of tender the prices from the subcontractors and main contractor were confirmed and the Construction Phase has begun. Demolition had been done before the other packages were dealt with, as a measure to save time during cost estimation. fixed price. In the first stage, a limited appointment is agreed to allow work to begin and in the second stage a fixed price is negotiated for the contract.”
[4.03]
Section 4.0
[4.04]
Site Diary 38
SUB-CONTRACTORS 01
01
Atrium render [4.03] Who are the specialist sub-contractors? There is a bunch of sub-contractors engaged in the project. The two main sub-contractors are Amery Construction and Bourne Steel – they are permanent “tenants” of the site and have their own works areas. Amery Construction produces precast concrete soffits, concrete walls, cladding and interior panels. Bourne Steel makes the skeleton of the building. Most of the site is at disposal of Amery team. Some of sub-contractors are located outside UK, i.e. Felix façade systems from Switzerland.
02 lluminated exposed concrete soffit with surrounding steel structure
T shape profile anodised aluminium top rail Exposed top edge of glazed balustrade
As an example, I would like to illustrate how the concrete slabs were designed and produced. Concrete slabs. Typical 6x1,5 m, they form a 6x9 m structural grid. Inside them there is a steel rebar for rigidity. Soffits are the finished products, as the concrete ceiling will remain exposed. In between they are sealed with 100 mm seam and in-situ concrete is poured on top to make the floor flat.
Subtle grey frit for screening floor slab and plenum Central mullion to split larger glazing
The negotiations took around 2 years and subcontractor has made around 100 samples.
Opening windows to the side of the projecting bays
Subtle grey frit for screening and safety
02 [4.04] Were any of the specialist sub-contractors brought in during the design phase? Most of the sub-contractors were brought in during the design stage. The team of sub-contractors and suppliers also took part in tender and had a right to vote for the contractor of their choice.
Illuminated exposed concrete soffit with surrounding steel structure
[4.06]
[4.07]
Section 4.0
Site Diary 39
In this page I would like to demonstrate that the work of special subcontractors and the main contractor has been satisfactorily interfaced and give some examples of how the architectural vision as represented in the architect’s drawings are made manifest through the work of the builders on site.
FACADE CORNER
EXPOSED CONCRETE WALLS
PRE-CAST PLANKS SAMPLE
Concrete panels with wooden structure comply with the render.
The concrete panel seams are joined to create a single line through the full height of the main core.
The negotiations took around 2 years and subcontractor has made around 100 samples.. This is one of them.
CONCRETE FLOOR POURING
CONCRETE SOFFITS
SHADOW GAP
The structure is assembled and all items fit. The final step is making of concrete cap.
The texture of soffits comply with the approved sample.
An exposed staircase surface and a shadowgap between staircase and wall.
[4.08]
Section 4.0
Site Diary 40
MY OPINION [4.08]  WHAT DO YOU THINK ABOUT THE DESIGN OF THE BUILDING? WOULD YOU MAKE ANY CHANGES? AS FAR AS THE BUILDING IS LOCATED IN THE CONSERVATION AREA, I UNDERSTAND THAT THE ARCHITECTS WERE PRETTY MUCH RESTRICTED IN DEVELOPING THEIR CONCEPT. I LIKE THE PREVIOUS DESIGN PROPOSALS MORE THEN THE APPROVED PROJECT, AS THERE WAS MORE PASSION AND CREATIVITY IN THEM, BUT AT THE SAME TIME IT WAS A LITTLE BIT OUT OF CONTEXT. THE PROJECT WE SEE TODAY IS A BALANCED SOLUTION, SATISFYING DIFFERENT STAKEHOLDERS OF PROCESS. THE DETAILS THOUGH ARE RATHER GENTLE. THE BUILDING WILL NOT CAUSE TOO MUCH OF ATTENTION FROM THE WIDE PUBLIC, BUT WILL BE APPRECIATED BY SOPHISTICATED USERS. I WOULD PROBABLY MAKE NO CHANGES TO THE PROJECT, HOWEVER I WOULD WISH TO HAVE USED MORE CORTEN ELEMENTS IN IT.
Section 4.0
Site Diary 41
Section 4.0
DECEMBER 19 2018
Pre-fabricated beams and column junction
HOWLAND STREET
CHITTY STREET
WHITFIELD STREET
CHARLOTTE STREET
Site Diary 42
Section 4.0
Site Diary 43
JANUARY 17 2019
Temporary metal holding structure Temporary timber beams to flatten rebar
Holes filled with in-situ concrete
HOWLAND STREET
CHITTY STREET
WHITFIELD STREET
CHARLOTTE STREET
Section 4.0
DECEMBER 19 2018
In this photo we can see part of the retained faรงade at the Whitfield Street, assembled steel skeleton of 5th and 6th floors with several concrete planks forming 6x9 m soffits. The in-situ concrete is not poured yet.
HOWLAND STREET
CHITTY STREET
WHITFIELD STREET
CHARLOTTE STREET
Site Diary 44
Section 4.0
Site Diary 45
JANUARY 17 2019
Here we can see that the skeleton of 5th and 6th floors are finished, slabs are all put down and in-situ concrete is drying.
Raised floor
Isolation
Concrete cladding
Hole for maintenance Primary structure
Section of the typical floor and wall junction
05.
CONSTRUCTION SEQUENCE DRAWING
Section 5.0
Site Diary 47
READING THE BUILDING
TOWER CRANE
RETAINED FACADE RETAINED STRUCTURE CENTRAL CORE
VAULTS FOR CRANES
6x6 CONCRETE SOFFITS ASSEMBLED OF 1,6x6 PLANKS
Section 5.0
Site Diary 48
01
07/2016
10 YEARS PROJECT
04/2017 02
Section 5.0
06/2017 01 ROOF VIEW PHOTOS Charlotte St/Chitty St corner
01 ROOF VIEW PHOTOS Charlotte St/Howland St corner
Site Diary 49
11/2018
01/2019
Section 5.0
Site Diary 50
FEBRUARY 2019
Ground works are nearly finished First two tower cranes are set in place Temporary structures are holding the ground The foundation of the central core is ready Piling starts
HOWLAND STREET
CHITTY STREET
WHITFIELD STREET
CHARLOTTE STREET
2017
Q4
Q1 Q1
2016
Q2
Q3
Q4
2019 Q2
Q3
Q4
Q1 Q1
2018
Q2
Q3
Q4
Q2
Q3
Q4 Q1
2020
Q2
Q3
Section 5.0
Site Diary 51
DECEMBER 2020
Ground works are finished Last crane is set in place Temporary structures are holding the ground The central core in-situ concrete structure is being build
2017 Q1 Q1
2016
Q2
Q3
Q4
2019 Q2
Q3
Q4
Q1 Q1
2018
Q2
Q3
Q4
Q2
Q3
Q4 Q1
2020
Q2
Q3
Section 5.0
Site Diary 52
FEBRUARY 2019
Ground works are finished The central core is finished Steel structure of 2 first floors is assembled Temporary structures are removed
2017
Q4
Q1 Q1
2016
Q2
Q3
Q4
2019 Q2
Q3
Q4
Q1 Q1
2018
Q2
Q3
Q4
Q2
Q3
Q4 Q1
2020
Q2
Q3
Section 5.0
Site Diary 53
DECEMBER 2020
Concrete soffits of 2 first floors are fixed and the insitu concrete will now be poured
2017 Q1 Q1
2016
Q2
Q3
Q4
2019 Q2
Q3
Q4
Q1 Q1
2018
Q2
Q3
Q4
Q2
Q3
Q4 Q1
2020
Q2
Q3
Section 5.0
Site Diary 54
DECEMBER 2018
During the site visit: The structures of first 5 levels are done Steel skeleton for 6 and 7 levels if partly assembled
2017
Q4
Q1 Q1
2016
Q2
Q3
Q4
2019 Q2
Q3
Q4
Q1 Q1
2018
Q2
Q3
Q4
Q2
Q3
Q4 Q1
2020
Q2
Q3
Section 5.0
Site Diary 55
DECEMBER 2020
The building is finished and ready to welcome tenants Tower cranes are removed
The drawing was provided by the architects
HOWLAND STREET
CHITTY STREET
WHITFIELD STREET
CHARLOTTE STREET
2017 Q1 Q1
2016
Q2
Q3
Q4
2019 Q2
Q3
Q4
Q1 Q1
2018
Q2
Q3
Q4
Q2
Q3
Q4 Q1
2020
Q2
Q3
06.
CONLUSIONS AND THE FUTURE
[6.01] [6.03]
Section 6.0
Site Diary 57
CONCLUSION
[6.01]  What have you learnt by following the site diary project on site? My site diary experience was excellent. I have been able to see the inside of the ongoing project of a city scale, gaining the insight into how the construction industry works and how the collaborative processes between different parties are organized. I was lucky to communicate with the representatives of leading UK companies, engaged in this project, as the job they are doing is really high-end. Apart from good management, I found out how the digital technologies increase the efficiency of the site operations and reduce the risk of the human factor to minimum. I was surprised to discover that a number of people in the office and on-site is relatively small, which demonstrates the efficiency of the operational management and great use of the technologies.
I have also rediscovered significantly the role of the Architect in this regard. Before the project, I assumed that the project management is the responsibility of the Architectural Team, but that was not the case, as the majority of work is done by the Main Contractor. I also thought that Architects execute the whole spectrum of works from the concept to design development with the weekly reissue of the blueprints and dozens of architects attending the construction site in turn, while, in fact, the supervision is made by only 2 architects and the technical work is deligated to other parties. I have extended my interest in pre-fabrication observing the changes it makes to the time scale and the accuracy of construction.
[6.03]  How has the Site Diary experience informed your possible career direction in architecture? During the project I have realized that working on site appeals to me more then office . In future I will be searching for the project leading work
opportunities. The experience has also proved my interest in working in Make.
Section 6.0
[6.02]
01
02
03
PRIMARY BEAM 450d x 250w PG TIE BEAM RECESSED 150d x 250w PG EDGE BEAM 300d x 250w PG ATRIA EDGE BEAM 450d x 300w PG TRANSFER BEAM
01 CONCRETE SLAB IS UNLOADED Photo from the site
02 ASSEMBLY PROCESS Photo from the site
03 DIFFERENT TYPES OF BEAMS Drawing provided by the architect
[6.02] What materials, building processes and /or technologies have you observed that you may wish to incorporate in your own projects in the future?
Unique of this project is the primary steel structure. I have always liked the steel structures in architecture, and in this project I found the process of the metal structure assembly very inspiring.
HELPS REDUCE WASTE
Site Diary 58
04
Section 6.0
Site Diary 59
2 LEVELS AT ONCE
04 INTERIOR RENDER Provided by the architect
05 JUNCTION OF 2 PREFABRICATED ITEMS Sketch from the site
02 05 03
01
01
03
THANK YOU!
01 SITE MEETING With Andrea Buckle
02
02 MULTIPLEX SITE OFFICE MEETING With Marks Timson
02 DERWENT OFFICE MEETING With Derwent team
LETTER
OUR POINTS OF CONTACT Make Oliver Hall - Commercial Lead Multiplex Andrea Buckle – Community Engagement Marks Timson - Senior Project Manager Louis Simo - Health and Safety Manager James Hastie - Site Manager Oli Jones - Design Manager Derwent Jonathan Walker – Senior Project Manager Tom French – Associate, Development Peter Pulford – Development Manager Timothy Hyman – Group Architect