80 Charlotte Street Site Diary

Page 1

UNIVERSITY OF WESTMINSTER

OLGA KOROLKOVA (W1686546)

2018 - 2019

SITE DIARY

80 CHARLOTTE ST


MY OPINION Hello! My name is Olga Korolkova and this is my Site Diary about 80 Charlotte St. If you want to know my personal opinion on the project, look into these yellow boxes.


CONTENT

1.0  MAKING SENSE OF SITE 2.0  THE DESIGN TEAM 3.0  STATUTORY APPROVALS 4.0  BUILDING THE BUILDING 5.0  TIME LAPSE CONSTRUCTION SEQUENCE DRAWING 6.0  CONCLUSIONS AND THE FUTURE


01.

MAKING SENSE OF SITE


Section 1.0

01

02

Site Diary 5

03

Location

01

LONDON, UK

CHARLOTTE APARTMENTS

Sectors

Exterior proposal Whitfield St/Chitty St Corner

RESIDENTIAL, RETAIL, WORKPLACE Client DERWENT LONDON

02 GROUND FLOOR CAFE Interior proposal

Main contractor MULTIPLEX

03 RECEPTION AREA Interior proposal

Contract value £220 MILLION Area 50,200 M²/540,300 FT² Project length

Architect

Q1 2007 - Q1 2020

MAKE ARCHITECTS


ON

ST

RE

RE

ET

ET

RI

NT

ET

U MO

L MA

DG

HI

S

NS

D

TO

IE L

GD

TF

ST

RE

RI

ET

DG

U MO

M

ET

HA

RE

EN TT

M

ST

C

U

NT

O

HA

FR

ST

AL

RT

ED

RO

AC

D

PL

A

E

CH

LE

AR

LO

O

TT

GO

ST

AT

E

DG

T IT C

F IE L

D LAN OR T AT P

G OS

GR E

ET RE ST

OG

N NS O

GR E

PLA

ST

L

H F IE

RE

LD

ET

B5

NA

S TR

E ET

T D S

S TR

EET

RE L

E WS E M

S TR

TH M

CE

MO U

LEY

POL

T MO

S

06

SS

AU

EET

S MA N

A ND

F IE L

TH

EL

E

RW

AD

MO

RA

ST

T D S

BO

N

BE

L

E

ST

ER

ST

RN

S

RD

RE

ER

S

ST

W ME

Y

W

D

D

AN

AN

EL

EL

EV

ET

CL

RE

ST

ST

AY

EV

NE M

EET

S TO

CL

C L IP

S TR

ND

EET TR M S LLA

T LA

HA

P OR

WE Y

HA R

W IM

WE S

EN

GO

UA

W

S

LE

OY

NW

ER

E C

EET

W IM

H

ET

SQ

IE

GO

EN

NT

ZR

CO

S OV

H IR

S TR

B ON E S

EP

RE

ET RE ST

CH

HU

F IT

B OL

01

ONS

NT

MA R Y L E

B 50

C HA

POL

6

E

LL

H

N DO

E

T

AN

RA

WM

WE

S

B

S EW S M

NE

ST

N

ST

O

00

SQ

N

ST

TO

RD

A4

R GH S T REET

H

VI

22

ST

6

A 42

DE V

U MO

S

IG

TA

GO

B5

O S NA B U

LE

ET

AY

1

CE

ST M WE

P LA

PL M BEA

L

DS

RE

NW

B 50

20

H IR E

H IR E

H IR E

AL

EN

ST

CO

A 420 1

Y WA ER

T EAS

A4

T

W

W

SQ

PET O PL

A4201

RK

E W UA R K SQ

N

ER

GO

A 40 0

PA

PAR

ONS

ONS

ONS

H IG H S T

A

S S

M

LS EL ST

TH

TR O

DE V

DE V

DE V

ONE

B

S

G

R

ES NG LA

RC PE

ER RI OU

MO

ST

E ST LS'

S

RE S

E U

HO D ING

Y BA ET E R W

IN

DM

IL L

S

Y LE

ST

T EE TR M S L AN

G HA

S

IM RT EET STR

EET STR HES

P

E

EY

IS H

L FO C

C DU

DF BE DG

E

ST

R

T EE

O GO

ST

E RE

T

T

T REE ST ND AV E

NE W

ST

OR

E

GO

W

ER

ME

T EE SC

T OT

C

R ST 2 A5

04 ST A AL

AM H EN

R ST

H T MO U WE Y

CH

O

PST

T EE

T EE STR

IE

S A Y IT T

CLI

T

N HE

T R ST

EE M R LF

ED

W HO

ST

NE

ND LA EE R ST

W

DE

C AR

BU

ET

I RR TO

ON T NG

E MA

PL

E ET S TR N RTO

E PL

AC

C

T EE R ST

ER P AP

PA R K

S

H IR E

ST E C

Z F IT

E TR

T EE S TR

NS E VO D

NE AN N EE QU

ST

UL S

P TE R

Y ST R LE U HA

TER K

T EAS E RAC

ES CR

G

I UN

VE

R

TY SI

F RA

T

ON A

Y RO

S

E TR

ET AY W EN RR WA

501

ET RE ST

EN

D

E SL

IG

H R WE GO

E AC

S TR E E T

N TO

PL

L ONG FOR D

RO EP

D

S EU

DS EN AD H

O ND

ST S QUAR E

G H IG LE ON S EN

S EN D AR S EU

T EE R ST MU NS T E R

01

M R UM

ST N TO


W

O

Section 1.0

[1.01]

Site Diary 7

P

LOCATION

CHARLOTTE APARTMENTS

80 CHARLOTTE ST

02

[1.01] Where is the site, what is the purpose of the building? Located in Fitzrovia near London’s West End, the site is bounded by four streets – Charlotte St, Howland St, Whitfield St and Chitty St. The building is multi-purpose, and the Site is split into 3 areas: 80 Charlotte Street (Commercial Block), The Charlotte Apartments (Residential Block) and “Asta House” (Residential Block).

T

W

FO

EL

B

In my Site Diary I will be focusing on researching about the Commercial Block Construction. There are 2 Main Entrances to 80 Charlotte Street, 1 VIP Discreet Car Entrance and 2 Alternative Entrances. The finished building will be partly refurbished and partly new build, with 30% of the original structures retained, including retained façade. The scheme is a major step forward the wider regeneration of the area and completion is expected in H1 2020.

01 FITZROVIA MAP

02 SITE SCHEME

CH AR LO TT ES

T

Y IT T CH

ST

ASTA HOUSE


Section 1.0

[1.02]

01

[1.02]  How did the project originate? Who is the client? The client of this project is Derwent London. Their initial intent was to retain most of the Saatchi&Saatchi Block, but during the design stage it turned out that the structure was not stable enough, as the construction technologies have changed significantly from that time. Moreover, it was decided to dig down to increase the height of the building, so boundary walls were demolished except for the corner of the Charlotte Apartments, located in conservation area. The building previously belonged to LMS, but the company became merged with Derwent London. Client describes the former building as a “square donut with lots of buildings inside with different qualities”. In fact, there were a lot of extensions of different style and even some Vicrorian buildings.

SAATCHI&SAATCHI Saatchi & Saatchi is a global communications and advertising agency network, founded in 1970 and headquartered in London. 80 Charlotte Street has been the home of Saatchi & Saatchi London for more than 40 years since the year 1975, over which time the building has been the home of some of the most famous creativity. Now the building is in need of a makeover. Architects are transforming this set of 1960s, single-use blocks into a contemporary, fully integrated development of office, residential, retail and vibrant public space.

01 SAATCHI&SAATCHI In front of the old building

04 80 CHARLOTTE ST Before the reconstruction

Site Diary 8

02

03

MY OPINION I reckon, that the concept was dictated by these prerequisites. Combination of various styles, textures, heights and qualities – this messiness gained its’ new reading in the new project..


Section 1.0

Project origins DIRECT APPOINTMENT

Site Diary 9

04

Building/site area GIA OFFICE = 434,822FT2 / 40,395M2 NIA OFFICE = 320,626 FT2 / 29,786M2 Height 9 STOREYS PLUS LOWER GROUND Planning Authority: CAMDEN

NEW LIFE Client’s brief:

03

• Regeneration and extension of existing ‘city block’. • New office, residential (including affordable housing), retail, new public pocket park

80 CHARLOTTE ST Design proposal

Client’s design intent: • Exposed concrete elements and steel beams • Communications left visible • Corten elements

04 CHARLOTTE ST/CHITTY ST Before and after


Section 1.0

[1.04]

VIABILITY

01 [1.04]  What makes the project financially viable? How is it funded and why? The project is funded by Derwent London, who made it financially viable by smart use of space. Their intent was to clear the site of everything and make it super efficient. Inside the yard was a car park, which was replaced with a central core with staircases, lifts and toilets, it gave a way for spacious open-space office spaces around the core. Former building was around 200.000 square ft of space - this was incresed up to 380.000 square ft in a new building. The corner building is to become a residential building with 19 flats. Old building had a pretty terrible structure, so the planning application suggesting to increase the height of the building was submitted to the authorities. Levels G-05 will be 3 m high from floor finishing to soffit, Levels 06-08 2.9 meters high. For maximum use of height it was decided to lower the basement – every wall around the basement went deeper and beautiful lightwells appeared. Following this intent, all of the basement walls were to be rebuilt. So, the basement was digged out and the temporary structures, holding the ground around was put. That made a project 6 months longer to build, but 1,8 meters heigher. For the same reason of height usage, the ground level went down and the ramp was built, so now reception is lower then the ground. To earn money on residential block, 2 extra floors were built on top – now there will be penthouses.

Site Diary 10


Section 1.0

[4.10]

Site Diary 11

ADDED VALUE

02

What is the added value? •

3.3m floor-to-floor

accommodated to provide 3m floor to soffit with highly efficient 6x9m steel frame and precast planks.

Air supply from central core in 150mm raised floor.

What are the project key features? •

315,000ft2 NIA CAT A office

55 residential apartments, including 14 affordable units

Which sustainability features project has? •

Designed to achieve BREEAM ‘Excellent’

Code for Sustainable Homes level 4

01 INCREASED HEIGHT Scheme provided by Make Architects

02 INCREASED OFFICE SPACE Scheme provided by Make Architects


[1.04]

What is the contract value of the project? What is the time scale?

Derwent London is a Real Estate Investment Trust, specializing mostly in commercial buildings and less in residential sector. The project is the biggest residential scheme in portfolio of the client. It is a long-term investment.

Architectural statement

CONTRACT VALUE

£190 MILLION

CONSTRUCTION COST

2011

“Make” is appointed for the project

SECTION 106 AGREEMENT My Name is John Doe Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et minim veniam, quis.

RIBA STAGE 2 RIBA STAGE 1

2013

2014

20 CONDITIONS My Name is John Doe Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et minim veniam, quis.

RIBA STAGE 0

2012

PLANNING PROCESS & CONCEPT CHANGES

2008

The time scale of any project is never known exactly before the project start. Changings of the client’s plans changes the project’s parameters, which, in turn, changes the project time scale. The unpresicatable conditions may also take place. For example, they may be an underground water or any other weather conditions, which expand the time scale.

2010

Back to planning process

PROJECT START

Construction cost – a total amount that has to be paid for the man-hours and building materials in order to build a building.

In this project particularly, a high water table was detected while the construction, forcing main contractor to build the temporary drainage system.

2009

Structure not stable enough

Contract value (Contract sum) - is the price agreed with the contractor and entered into the contract. However, the contract sum does not constitute a ‘fixed price’ even if the contract is described as a fixed price contract, a lump sum contract or a guaranteed maximum price contract.

2007

First planning application

It is essential to tell the difference between the contract value and the construction cost.

Tender start

£220 MILLION

RIBA STAGE 3


The 1st contract period was August 2018, now the practical completion date is planned for 20 December 2019 with a small lead time till the end of February. Project timeline was dependent on several various factors. Firstly, planning applications took longer. Declined by the Committee, the project was forwarded for further jurisdiction to GLA to be supported by mayor – this took twice as much time. The second major issue was a 2 year pause in the project. The reason for that was that the lease for Saatchi&Saatchi was ending and their office should have been relocated to another Derwent’s building. However, Derwent needed to finish construction of that building first to put Saatchi there. Once it had been finished and Saatchi&Saatchi had moved, the work was resumed in 2014 with RIBA stage 3.

Q4

Q1 Q1

Q2

Q3

Q2

Q4

RIBA STAGE 5

Concrete slabs installation starts

Design and Build Contract with “Multiplex”

Sreelwork installation starts

“AFK” was employed during the render.

RIBA STAGE 4

Q1 Q2

Q3

Q2

Q3

Q4

Q4 Q1

2018

Ground works

Demolition starts Piling starts

Phaze 1 Hearing erected

Planning granted

RIBA STAGE 3

Q4 Q1

2016

Client has signed the Demolition Contract long before the Main Contractor was assigned, which is rather a common practice.

Q3

Q2

Q3

2020

MY OPINION It is interesting, that it took only around 3 years to erect the main structure of the building. The rest of project time was deicated to the planning, changing of concept and tendering processes.

Residential site to be finished

Q3

2019

Electricity came in site

Q2

2017

Commercial site to be finished

First tower crane erected

Phaze 2 Hearing

No, the project is delayed.

Tender agreement

2015 Q1

[4.10]  Is the project on course to be completed within the contract period? If not why?

RIBA STAGE 6

RIBA STAGE 7


Section 1.0

Access

Logistics

Structural Engineer

Site Diary 14

SUBCONTRACTORS & SUPPLIERS

DESIGN TEAM

CONTRACTURAL DIAGRAM

[1.06]

H&S

CLIENT

Building control

MEP

Architect

MEP

Drywall

Scaffolding

Demolition

Brickwork

Facade system

Concrete

Steel

SLW

D&C CONTRACTOR

EMPLOYERS AGENT

(Non-contructual link)

CLIENT COST CONSULTANT (QS)

Architect

Facades

Comissioning

MEP

Structural Engineer Borough Council AUTHORITIES

COMPLIANCE & MONITORING TEAM

MAIN ON-SITE MEETINGS

Design coordination meeting

Daily Activity Brief (DAB)

Individual meetings


[1.05]

DESIGN &BUILD

Section 1.0

is a term describing a procurement route in which the main contractor is appointed to design and construct the works, as opposed to a traditional contract, where the client appoints consultants to design the development and then a contractor is appointed to construct the works.

Site Diary 15

[1.05.]  Who are the key professionals and companies involved in the project? In this project the key companies could be split into 3 major groups: the Design Team, the Compliance and Monitoring Team and Subcontractors & Suppliers. It is not difficult to guess, that the DT designs, while the CMT monitors and checks for compliance. The DT consists of Architects, and Service & Structure engineers, and is usually appointed by the Client, but in this project particularly it was appointed by the Main Contractor. The quantity of Consultants increase with complexity of the project.

There is also a design co-ordinator or Project Manager. All the subcontractors were also appointed by the Main Contractor. However, Multiplex has a noncontractual link with the CMT, which means they can negotiate, but the members of the CMT are out of contractor’s control.

ARCHITECT

CLIENT

MAIN CONTRACTOR

In September 2007 Make was first appointed to work with this project. There was a small competition, but the choice has been done by the client long before.

Client wants this control of the development of the work, so they would rather prefer “Design and Build” contract type to a traditional one. Design and build can be seen as giving a single point of responsibility for delivering the entire project. Some clients, however, consider it is only appropriate for simple projects, where design quality is not the main consideration.

Multiplex was appointed in November 2014, as a result of a two-stage tendering.Before working on site the main contractor usually does risk estimating, as a huge of responsibility is transferred once the contract is signed.

Working in “Design and Build” conditions was uncomfortable for Make: a lot of documents, too many people involved, long confirmations and dependence on the contractor. From the architect’s point of view, reality is that sometimes contractor makes the decisions, which are not correct. Of course, traditional contract is of more preference for an architect, and “Design and Build” is better for simple projects, where the main contractor acts as an architect.

I was interested, which type of contract is of highest preference for each side of this project. I have asked whether they prefer Design and Build or not.

Multiplex would like to prefer “Design and Build” contract type, because even though they have most of risk, they can manage it and earn more money, so, in this case, risk becomes a profit. The contractor may use their own in-house designers to design the building, or they can appoint consultant designers, or the client’s designers can be employed by the contractor to complete the design (either by novation or consultant switch). In this project, apart from “Make”, there is an inhouse designer from the main contractor’s side and novated designer – “AFK”.


PROJECT TEAM

BEFORE ON-SITE

ON-SITE

2007-2016

RIBA STAGE 0-2

SINCE 2016 RIBA STAGE 4+

RIBA STAGE 2-4

PROJECT LEAD

PROJECT LEAD Make Partner

Manages the whole project. Controls that there is enough people on the job, checks fees and appointments with the Client.

Project Lead

5 PACKAGE LEADS Part ll

PACKAGE LEADS + JUNIOR ARCHITECTS Part I/ll

These people are developing the basic design from the very early stages, usually for the competition. The concept is provided by the Lead Architect.

These 5 architects are also called Package Leads. Every Lead has their own element of the project (facade, basement, roof, etc) which they work on to produce all the needed project documentation before the building is on site.

RESIDENTIAL LEAD

OLIVER HALL

Make Partner

COMMERCIAL LEAD

Leads the Residential Block at the 80 Charlotte St., which is smaller, but more comlicated.

Make Partner

Leads the main Project of Commercial Block at the 80 Charlotte St.


[1.07]

Section 1.0

[1.08]

Site Diary 17

MAKE ARCHITECTS

MY OPINION I think it is rather convenient, that main architect has a laid-back position, while their project is being developed by 3rd parties, however, the quantity of drawings to review increases and sometimes it is more difficult to address the idea to other people rather then to draw it. The quality of design may fail.

“Make is a different kind of architecture practice. Founded by Ken Shuttleworth in 2004, we’re an employee-owned firm pursuing a democratic design process that values everyone’s input. Today we have more than 150 people in London, Hong Kong and Sydney providing architecture, interior and urban design services from concept to completion.”

[1.07]  What is the architect’s appointment and role on the whole project? The way Derwent chooses architect is a very organic process. “Make” was appointed directly in the early stages and the Design process was a collaborative work with client. The contract type is standard RIBA. This architect has been designing the project until RIBA Stage 4, until the AFK has been appointed by Multiplex to take on the further development of the project.

[1.08]  What is the architect’s role whilst the project is on site? Is it effective? Under the traditional contract there is no influence from the Main Contractor, Architect is the key professional in the project. The role of “Make Architects” in this particular project whilst on-site is to review the drawings from novated architect AFK and check their compliance with the initial design. Architects do their job rather effectively, even though only 3 people are engaged now.

MAKE ARCHITECTS OFFICE


Section 1.0

Site Diary 18 THIS DRAWING IS COPYRIGHT OF AND SHALL REMAIN THE PROPERTY OF:

H31

H33 120 120 EQ EQ EQ EQ EQ EQ

H29

1490

10480

20

ARNEY FENDER KATSALIDIS NOTES CHECK AND VERIFY ALL DIMENSIONS PRIOR TO COMMENCEMENT OF WORK. THIS DRAWING SHALL BE READ IN CONJUNCTION WITH ALL OTHER CONTRACT DOCUMENTS INCLUDING THOSE BY OTHER CONSULTANTS, AND INCLUDING SPECIFICATIONS. SEEK CLARIFICATION OF INCONSISTENCIES/ CONFLICTS. FIGURED DIMENSIONS SHALL TAKE PRECEDENCE TO SCALED DIMENSIONS.

DIVIDE 2835 INTO 23 EQUAL PARTS (APPROX. 123) REFER TO A-44-C4401

FFL LEVEL 02

FACADE LEGEND

+33.640 m AOD. 1490

20

SJ

STACK JOINT

PJ

PANEL JOINT

750

MJ - MOVEMENT JOINT

2240

FIRE CURTAIN ON DELAYED ACTION BRICKWORK BONDS ARE SHOWN AS INDICATIVE. REFER TO A-44-3215 FOR BRICKWORK BOND SETOUT.

EWS-150 (H11) GLAZING UNIT

SLAB EDGE

2495

FRIT/BACKPAINTED GLASS TO HIDE FIRE AND ACOUSTIC BARRIER

EWS-122 (H11) PRECAST CONCRETE

3D VIEW - MAIN ENTRANCE 3

EDGE OF UPSTAND BELOW

SCALE: NTS NOTES 1. ALL PRECAST PANEL JOINTS TO BE 20MM WIDE AND RECESSED SILICONE SEALED 2. REFER TO 65 SERIES STRUCTURAL OPENING ON DOOR SCHEDULE

20

3. BEACONS AND FIRE ALARMS REFER TO 40 SERIES PLANS AND READ IN CONJUNCTION WITH ELECTRICAL ENGINEER'S DRAWINGS AND SPECIFICATIONS 4. REFER TO A-30 SERIES FOR WATERPROOFING TO LOWER LEVELS

CCTV 700

CORTEN PLATE

5. REFER TO MEP AND SECURITY ENGINEERS DRAWINGS AND SPECIFICATIONS FOR DETAILED SERVICES DESIGN LAYOUT

FFL LEVEL 01

6. REFER TO LIGHTING CONSULTANTS DRAWINGS FOR EXTERNAL LIGHTING DESIGN AND SPECIFICATION.

+30.305 m AOD.

DIVIDE 6170 INTO 50 EQUAL PARTS (APPROX.123) REFER TO A-44-C4419

7. REFER TO A-47 & A-48 SERIES FOR KITCHEN EXTRACT CLADDING DRAWINGS

EDR-125

FIXED GLAZING UNIT

8. AUTOMATED OPENING WINDOWS TO SUBCONTRACTOR DESIGN AND MUST COMPLY WITH FIRE STRATEGY REQUIREMENTS

EDR-124 (H11) REVOLVING DOOR

9. PROVISION FOR CCTV. READ IN CONJUNCTION SECURITY DRAWINGS AND SPECIFICATIONS. FINAL LOCATIONS TO BE CONFIRMED BY SUBCONTRACTOR.

EWS-150 (H11) AUTOMATIC FULL HEIGHT GLAZING FOR SMOKE AND NATURAL VENTILATION

10. FOR 6TH & 7TH FLOOR TERRACES, FIRE ALARM AND FLASHING XENON BEACONS TO BE MOUNTED DIRECTLY ON TOP OF ONE ANOTHER AT APPROXIMATELY 2400MM AFFL AND ALIGNED TO CLOSEST FULL BRICK WHERE APPLICABLE.

1500

FOR 9TH FLOOR TERRACES, FIRE ALARM AND FLASHING XENON BEACONS TO BE MOUNTED DIRECTLY ON TOP OF ONE ANOTHER AT APPROXIMATELY 3000MM AFFL.

FACADE SERVICES LEGEND

3D VIEW - MAIN ENTRANCE CORTEN FLOOR WITH S/S STRIPS WITH REQUIRED SLIP RATING RESISTANCE TO SUBCONTRACTOR DESIGN

900

240 20

H28

EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ 120 120

240 20 240

H25

4

SCALE: NTS

FA - FIRE ALARM. MOUNTED AT MIN 2.3M AFFL, ALIGNED TO CLOSEST FULL BRICK UNLESS NOTED OTHERWISE RED BREAK GLASS UNIT/ MANUAL CALL POINT MOUNTED AT 1.0M AFFL

FFL LEVEL PAVEMENT

DISABLED REFUGE CALL POINT MOUNTED AT 0.9M AFFL

+27.570 m AOD. CCTV

SCALE: 1 : 20

PROVISION FOR FIXED CCTV CAMERA VIDEO INTERCOM AT 1.5M AFFL M=MASTER, SM=SUB MASTER, S=SLAVE

VIC

10.1 SQM OF COMBINED FREE AREA TO BE PROVIDED BY AUTOMATED SMOKE VENTS. SUBCONTRACTOR TO ENSURE COMPLIANCE

EXTERNAL ELEVATION - LEVEL 00 TO 01 - CHARLOTTE ST MAIN ENTRANCE 2

FIRE TELEPHONE MOUNTED AT 1.3M AFFL

4 A-42-C4203

1 A-42-C4203

2 A-42-C4203

MANIFESTATION MARKINGS GRAPHIC DESIGN TO BE CONFIRMED

FLASHING XENON BEACON MOUNTED AT MIN 2.4M AFFL RAINWATER PIPES

RWP

ELECTRIC OUTLET POINTS

EXTERNAL LIGHTING INTERNAL

H29

1368

1300

1700

HC

- CORTEN BOX SETTING OUT UPDATED - REVOLVING DOORS POSITION CHANGED - LEGEND ADDED

150

SCALE: NTS

450

LOCATION PLAN

100

1320

CORTEN FLOOR WITH S/S STRIPS WITH REQUIRED SLIP RATING RESISTANCE TO SUBCONTRACTOR DESIGN

27.610

CHITTY STREET

EDR-124 (H11) GLASS REVOLVING DOOR

2030

2280

WHITFIELD STREET

EWS-150 (H11) AUTOMATIC FULL HEIGHT GLAZING FOR SMOKE AND NATURAL VENTILATION HOWLAND STREET

3550

HOWLAND MEWS EAST

EWS-101A (F10) BRICK FACING EXTERNAL

1:48

100

CONCEALED RAINWATER DRAINAGE SLOT

150

27.590

27.590

9518

50

50

9618

2 A-42-C4203

LINE OF UPSTAND TO STRUCTURE ENGINEER'S DESIGN

CONCRETE PAVERS LAID TO FALLS

REVOLVING DOOR PIT 2

1 A-42-C4203

LINE OF REVOLVING DOOR MACHINERY PIT BELOW

ASTOR COLLEGE

CONCEALED RAINWATER DRAINAGE SLOT

80

27.590

50

CHARLOTTE STREET

EDGE LIGHTING STRIP UNDERNEATH REFER TO ELECTRICAL ENGINEER'S AND EQ2 DRAWINGS AND SPECIFICATIONS

960

80

CORTEN PLATE

CHARLOTTE MEWS

N

CORTEN PLATE

EDGE LIGHTING STRIP UNDERNEATH REFER TO ELECTRICAL ENGINEER'S AND EQ'2 DRAWINGS AND SPECIFICATIONS

EXT-202 (Q10) S/S SLOT DRAIN

STAGE F UPDATE PL PV UNITIZED FACADE STAGE F ISSUE JML PV STAGE E ISSUE GL PV DRAFT STAGE E ISSUE GL PV CLADDING DRAFT ISSUE 2 JML PV CLADDING DRAFT ISSUE 1 JML PV DESCRIPTION DRAWN BY:CHECK BY

3D VIEW - MAIN ENTRANCE

ENTRY PANEL TO SECURITY ENGINEER SPECIFICATION AND EMPLOYER REQUIREMENTS. COVER PANEL TO BE CORTEN PANEL TO BE SUPLIED BY CORTEN BOX SUB CONTRACTOR

LINE OF DRAINAGE CHANNEL ABOVE

05 11/05/2018 04 24/03/2017 03 28/10/2016 02 07/10/2016 01 23/09/2016 00 16/09/2016 REV DD/MM/YY

5 150

EWS-122 (H11) PRECAST CONCRETE FACADE

EXT-410 (Q40) METAL FENCING TO LIGHTWELL AREAS

3 A-42-C4203

4 A-44-C4406

R1 12 5

R1 12 5

SOFFIT MOUNTED CCTV CAMERA REFER TO SECURITY ENGINEER'S DRAWINGS AND SPECIFICATIONS

RWP TO COLLECT AND DRAIN CORTEN BOX RAINWATER TO LIGHTWELL BELOW LOCATION TO BE COORDINATED BY SUBCONTRACTORS

FT TYPE

750

REVISION 05 COMMENTS

EDR-125 (H11) AUTOMATED PASSDOOR & SMOKE VENT

HA

1050

FV TYPE

EWS-101A (F10) BRICK FACING EXTERNAL

1200 MIN

1 A-44-C4433 1270

LIN-120 (H42) CONCRETE WALL LINING SYSTEM

1950

FP TYPE

H33

27.590

115

HC

1500

H31

EMERGENCY DOOR RELEASE BUTTON

1:21

H28

REMOVABLE CORTEN BOX FLOOR TO ACCESS REVOLVING DOOR FLOOR BOX. SIZE TO BE CONFIRMED WITH FACADE SUBCONTRACTOR

50

RWP TO COLLECT AND DRAIN CORTEN BOX RAINWATER TO LIGHTWELL BELOW LOCATION TO BE COORDINATED BY SUBCONTRACTORS EXT-410 (Q40) METAL FENCING TO LIGHTWELL AREAS

Arney Fender Katsalidis T / +44 20 3772 7320 E/ info@afkstudios.com W / afkstudios.com 44-46 Scrutton Street, London, EC2A 4HH.

4 A-42-C4203

CLIENT:

A-42-A3235

EXTERNAL

PROJECT

PLAN - LEVEL 00 - CHARLOTTE ST MAIN ENTRANCE 1

SCALE: 1 : 20

80 CHARLOTTE STREET

3D VIEW - MAIN ENTRANCE 6

SCALE: NTS DRAWING TITLE

CHARLOTTE ST MAIN ENTRANCE CORTEN BOX PROJECT NO.

44034 05

STATUS

SCALE

FOR CONSTRUCTION

As indicated@A0

DRAWING NO.

REVISION

A-42-A3235

05


CCTV

440

4

FACADE LEGEND FACADE SERVICES LEGEND MANUAL CALL POINT MOUNTED AT 1.0M AFFL

RED BREAK GLASS UNIT/ MANUAL CALL POINT AT MJ MOUNTED - MOVEMENT JOINT FIRE TELEPHONE MOUNTED 1.0M AFFL

AT 1.3M AFFL

PROVISION FOR FIXED CCTV CAMERA CONFIRMED

CCTV BONDS ARE SHOWN AS FIRE TELEPHONE BRICKWORK MOUNTED EDR-125

JUNCTIONS

1.3M AFFL INDICATIVE. REFER TO A-44-3215 FOR ALIGNED TO COLUMN BEHIND VIDEO INTERCOM AT 1.5M AFFL VERTICAL SECTION AT -VIC MAIN ENTRANCE INTERNAL ELEVATION BRICKWORK BOND SETOUT.

3

PROVISION FOR FIXED CCTV CAMERA

FLASHING XENON BEACON LIN-120 M=MASTER, SM=SUB MASTER, S=SLAVE MOUNTED AT MIN 2.4M AFFL GLASS TO HIDE (H42) CONCRETE FLASHING XENONFRIT/BACKPAINTED BEACON AND BARRIER This part of the drawing isACOUSTIC always to MOUNTED AT MIN FIRE 2.4M AFFL WALL LINING SYSTEM RAINWATER PIPES RWP

HC

PIPES be read, contains fundamental RWPas itRAINWATER EDGE OF UPSTAND BELOW ELECTRIC OUTLET POINTS OUTLET POINTS information,ELECTRIC which applies to the whole 4 page or series of drawings. EXTERNAL LIGHTING EWS-122 NOTES

PRIMARY STRUCTURE

A-42-C4203

LIGHTING (H11) PRECAST CONCRETE EXTERNAL FP TYPE FPPANEL TYPE 1. ALL PRECAST JOINTS TO BE 20MM WIDE AND FV TYPE EWS-150 RECESSED SILICONE SEALED 10.1 SQM OF COMBINED (H11) GLAZING UNIT FV TYPE FT TYPE FREE AREA TO BE PROVIDED 2. REFER TO 65 SERIES STRUCTURAL OPENING ON DOOR SCHEDULE BY AUTOMATED SMOKE

3 A-42-C4203

FFL LEVEL 01

4 A-44-C4406

INTEGRATED RAINWATER

31.025

DETAIL

1:21

EMERGENCY DOOR GUTTER +30.305 m AOD. RELEASE BUTTON

REMOVABLE CORTEN BOX FLOOR TO ACCESS REVOLVING DOOR FLOOR BOX. SIZE TO BE H31 CONFIRMEDBY WITH FACADE A-42-C4203/4 SUPERSEDED A-42-A3235/2 CONFIRMED SUBCONTRACTOR

EXTERNAL ELEVATION - LEVEL 00 TO 01 - CHARLOTTE5 ST MAIN NTS ENTRANCE 4 SCALE: CONCEALED RAINWATER FIXED GLAZING UNIT

A-44-C4433

1050

SCALE: 1 : 20

7. REFER TO A-47 REVISION 05 COMMENTS

& A-48 SERIES FOR KITCHEN EXTRACT CLADDING DRAWINGS

CORTEN SIDE PLATE

30.925

1300

1700

LOCATION PLAN

D

WHITFIELD STREET

5

10. FOR 6TH & 7TH FLOOR TERRACES, FIRE ALARM AND FLASHING XENON BEACONS TO BE MOUNTED DIRECTLY ON TOP OF ONE ANOTHER AT LOCATION PLAN APPROXIMATELY 2400MM AFFL AND ALIGNED TO EWS-150 CLOSEST FULL BRICK WHERE APPLICABLE. (H11) GLAZING UNIT SOMKE VENT

H28

1368

DOOR & SMOKE VENT

27.590

H31

1050

REVISION AND COMMENTS FACADE SERVICES LEGEND

FA - FIRE ALARM. MOUNTED AT MIN 2.3M AFFL, ALIGNED TO CLOSEST FULL BRICK UNLESS NOTED OTHERWISE CHITTY STREET

EXT-410 (Q40) METAL FENCING TO LIGTHWELL AREAS

1270

900

27.610

FX-302 (N20) ENTRANCE MATWELL REFER TO A-55 SERIES

1200 MIN

27.610

WHITFIELD STREET

ASTOR COLLEGE

In this footnote architect suggests that FLOOR TO BE Once the drawing has been revised, all the CONCRETE BREAK GLASS UNIT/ list, as CANTILEVERED AND 1 the corten box should be removable changes should be RED added to the MANUAL CALL POINT MOUNTED AT SUPPORTED VIA SECONDARY A-44-C4433 5 FX-302 Katsalidis 1.0M SUPPORT FIXED TO with its’ size to be confirmed withSTEEL facade well as Arney theFender number of AFFL revision, date andN A-44-C4433 CONCRETE BEAM(N20) ENTRANCE MATWELL T / +44 20 3772 7320 DISABLED REFUGE CALL POINT E/ info@afkstudios.com subcontractor once it is developed. name of its’ author. 100 MOUNTED AT 0.9M AFFL REFER TO A-55 SERIES 100

PAVEMENT

EDGE LIGHTING STRIP UNDERNEATH +27.570 m AOD.27.590 A-42-C4203 REFER TO ELECTRICALEDR-125 ENGINEER'S AND SLOT DRAIN + 27.320 EQ2 DRAWINGS AND SPECIFICATIONS (H11) AUTOMATED SSL PASS-

FLASHING XENON BEACONS TO BE MOUNTED DIRECTLY ON TOP OF ONE ANOTHER AT APPROXIMATELY 3000MM AFFL. 1950

1500 115

R1 12 5

SCALE: NTS

SYSTEM this junction, specifying the number of the 50 50(J40) WATERPROOFING MEMBRANE SUBCONTRACTOR DESIGN EXT-410 (Q40) METAL FENCING TO LIGHTWELL FFL LEVEL CORTEN PLATE FLOOR page inside CORTEN PLATEthe circle. AREAS

INTERNAL

HOWLAND MEWS EAST

REFERENCE TO OTHER DRAWINGS3D VIEW - MAIN ENTRANCE COMMUNICATION RWP TO COLLECT AND DRAIN CORTEN STRIPS WITH REQUIRED SLIP BOX RAINWATER TO LIGHTWELL LIN-120 CORTEN FLOOR WITH S/S STRIPS WITHTO RATING RESISTANCE This marking refers to detailed drawing of BELOW LOCATION TO BE 27.590 (H42) CONCRETE WALL LINING SUBCONTRACTOR DESIGN REQUIRED WPS-212 SLIP RATING RESISTANCE TO COORDINATED BY SUBCONTRACTORS

3 FFL LEVEL 01 +30.305 m AOD. A-42-C4203

CHARLOTTE MEWS

EMERGENCY DOOR N FIRE FOR 9TH FLOOR TERRACES, ALARM AND RELEASE BUTTON CHARLOTTE STREET

HC

RIGID INSULATION TO RFS-101

H29

3315

450

CHITTY STREET

HOWLAND STREET

CONCEALED RAINWATER DRAINAGE SLOT

  

4 A-42-C4203

CHARLOTTE STREET

HC

9. PROVISION FOR CCTV. READ IN CONJUNCTION SECURITY DRAWINGS AND SPECIFICATIONS. FINAL LOCATIONS TO BE CONFIRMED BY SUBCONTRACTOR.

1270 3550

EWS-150 EDR-125 (H11) AUTOMATIC FULL HEIGHT GLAZING EWS-150 (H11) AUTOMATED PASS-DOOR FOR SMOKE AND NATURAL VENTILATION SCALE: NTS & SMOKE VENT (H11) AUTOMATIC FULL HEIGHT CORTEN FLOOR WITH S/S STRIPS WITH GLAZING FOR SMOKE AND ENTRY PANEL TO SECURITY REQUIRED SLIP RATING RESISTANCE TO NATURAL VENTILATIONSUBCONTRACTOR DESIGN ENGINEER SPECIFICATION COVER PANEL TO BE CORTEN CORTEN PLATE PANEL TO BE SUPPLIED BY EWS-101A CORTEN BOX EDGE LIGHTING STRIP UNDERNEATH (F10) BRICKSUBCONTRACTOR FACING EXTERNAL REFER TO ELECTRICAL ENGINEER'S AND ENTRANCE SIGNAGE FEQ2 I T Z DRAWINGS R O V I A WAND 1 SPECIFICATIONS EWS-150 REFER TO DRAWING R1 1 12 CONCEALED RAINWATER DRAINAGE A-66-C6694 FOR SETTING (H11) 80 AUTOMATIC FULL HEIGHT GLAZING 5 SLOT A-44-C4435 4 OUT AND DETAILS CORTEN FLOOR WITH S/S FOR SMOKE AND NATURAL VENTILATION

PAVEMENT 4

F

750

1:21

2280

UPSTAND TO CORTEN BOX TO STRUCTURAL ENGINEER'S

W / afkstudios.com 44-46 Scrutton Street, London, EC2A 4HH. MOUNTED FIRE TELEPHONE AT 1.3M AFFL

CHARLOTTE MEWS

CHARLOTTE STREET

PAVEMENT

ASTOR COLLEGE

SLOT DRAIN

CLIENT:

CCTV RWP TO COLLECT AND

R1 12 5

PROVISION FOR FIXED CCTV CAMERA

CHARLOTTE MEWS

N

- CORTEN BOX SETTING OUT UPDATED - REVOLVING DOORS POSITIONWINDOWS CHANGED TO SUB8. AUTOMATED OPENING - LEGEND ADDED DESIGN AND MUST COMPLY WITH FIRE CONTRACTOR

HOWLAND STREET

EWS-101A

LIN-120 (H42) CONCRETE WALL LINING SYSTEM

DETAIL A-42-C4203/4 SUPERSEDED BY A-42-A3235/2 1 EWS-101A A-42-C4203 (F10) BRICK FACING EXTERNAL

H33

3D VIEW - MAIN ENTRANCE

REVOLVING DOOR ERY PIT BELOW

ALIGNED TO COLUMN BEHIND

HOWLAND MEWS EAST

(F10) BRICK FACING EXTERNAL (H11) REVOLVING DOOR

TO

TO

STRATEGY REQUIREMENTS

A-44-C4406 EDR-124 AOD. +30.305 m

EDR-124 (H11) GLASS REVOLVING DOOR

INTERIOR

GUTTER

4 LEVEL 01 FFL

590

WHITFIELD STREET

PV 045. 24/03/2017 UNITIZED STAGE F ISSUE JML PV REFER TO MEP AND FACADE SECURITY ENGINEERS REVISION 05 COMMENTS 03DRAWINGS 28/10/2016 AND STAGE E ISSUE GL PV SPECIFICATIONS FOR DETAILED - CORTEN BOX SETTING OUT UPDATED 02SERVICES 07/10/2016 DRAFTLAYOUT STAGE E ISSUE GL PV DESIGN - REVOLVING DOORS POSITION CHANGED 01 23/09/2016 CLADDING DRAFT ISSUE 2 JML PV - LEGEND ADDED RECESSED AUTOMATIC DOOR SENSOR 6. 16/09/2016 REFER TO LIGHTING CONSULTANTS DRAWINGS FOR PV 2 MANIFESTATION MARKINGS 00 CLADDING DRAFT ISSUE 1 JML 31.025 INTEGRATED RAINWATER EXTERNAL LIGHTING DESIGN AND SPECIFICATION. REV DD/MM/YY DESCRIPTION DRAWN BY:CHECK BY GRAPHIC DESIGN TO BE A-42-C4203

LIN-120 (H42) CONCRETE WALL LINING SYSTEM

3D VIEW - MAIN ENTRANCE

DRAINAGE SLOT 1950

HOWLAND MEWS EAST

HOWLAND STREET

INTERNAL

ENGINEER'S DRAWINGS AND SPECIFICATIONS 04 24/03/2017 UNITIZED FACADE STAGE F ISSUE JML PV 03 28/10/2016 STAGE E ISSUE GL PV 02 07/10/2016 DRAFT STAGE ETO ISSUE GL FOR PV 4. REFER A-30 SERIES WATERPROOFING 01 23/09/2016 CLADDING ISSUE 2 JML PV LOWERDRAFT LEVELS 00 16/09/2016 05 CLADDING DRAFT ISSUE 1 JML PV 11/05/2018 STAGE F UPDATE PL REV DD/MM/YY DESCRIPTION DRAWN BY:CHECK BY

+30.305 mALIGNED AOD.TO COLUMN BEHIND

FIXING BRACKETS TO CORTEN BOX TO SUBCONTRACTOR & STRUCTURE ENGINEER'S DESIGN

PAVEMENT

This technical drawing of the corten entrace by AFK +27.570 m AOD. serves a good example of a typical drawing to be sent to subcontarctors for further development. It can also LOCATION PLAN be05 used on meetings (not for construction) when marked “for reference only”. Once the drawing is finally confirmed, it goes on-site.

VENTS. SUBCONTRACTOR 3. BEACONS AND FIRE ALARMS REFER TO 40 SERIES PLANS AND READ IN CONJUNCTION WITH ELECTRICAL TO ENSURE COMPLIANCE 05 11/05/2018 STAGE F UPDATE PL PV EXTERIOR

FFL LEVEL 01

REVOLVING DOOR

interaction with subcontractors and suppliers belong to AFK, while Make only reviews their documents. FFL LEVEL

FT TYPE

900

VAPOUR BARRIER

3 A-42-C4203

LINE OF REVOLVING

- DETAIL A-42-C4203/4 SUPERSEDED DOOR MACHINERY PIT FLOOR PIT RATING RESISTANCE TO The responsibilities of developing the drawings and - LEGEND UPDATED SUBCONTRACTOR DESIGN

HA

STRUCTURAL SLAB

1500

INTERIOR

EWS-101A (F10) BRICK FACING EXTERNAL

RECESSED WEATHER SEAL

2

M=MASTER, SM=SUB MASTER, S=SLAVE CCTV NOTES AND LEGEND VIDEO INTERCOM SLAB AT 1.5MEDGE AFFL

SCALE: 1 : 20

VIC

CORTEN PLATE

OMKE VENT

MANIFESTATIONS MARKINGS

DISABLED REFUGEFIRE CALLCURTAIN POINT ON DELAYED ACTION GRAPHIC DESIGN TO BE MOUNTED AT 0.9M AFFL

HA

EPDM SEALCORTEN PLATE

H29

CALL POINT MOUNTED AT 0.9M AFFL

+27.570 m AOD.

HC

PL PV JML PV 03 24/03/2017 UNITIZED FACADE STAGE F ISSUE JML PV 02 28/10/2016 STAGE E ISSUE GL PV [1.09]  What documents and drawings 01 07/10/2016 DRAFT STAGE E ISSUEare beingGL PV 00 23/09/2016 DRAFT ISSUE 2 JML PV referred to on-site and inCLADDING meetings? REV DD/MM/YY DESCRIPTION DRAWN BY:CHECK BY 900

Unique of this project is that there are two architectural REVISION 05 COMMENTS 3D VIEW - MAIN ENT practices involved: “Make”(compliance architect) and - REVOLVING UPDATED 4 CORTEN FLOORDOOR WITHDETAILS S/S SCALE: NTS “AFK” (novated architect). - DIMENSION AND NOTESSLIP UPDATED STRIPS WITH REQUIRED

SJ ALARM. MOUNTED STACK JOINT FA - FIRE AT MIN 2.3M AFFL, ALIGNED TO CLOSEST FULL BRICK DISABLED REFUGE UNLESS PJ NOTED OTHERWISE PANEL JOINT

3 A-42-C4203

(H11) GLAZING UNIT

HC

CONSULTANTS, AND INCLUDING SPECIFICATIONS.

FIRE AND ALARM. MOUNTED AT MIN 2.3M FOR 9TH FLOOR TERRACES, FA FIRE- ALARM SEEK CLARIFICATION OF INCONSISTENCIES/ FLASHING XENON BEACONS AFFL, TO BE MOUNTED ALIGNED TO CLOSEST FULL BRICK FIGURED DIRECTLY ONCONFLICTS. TOP OF ONE ANOTHER ATDIMENSIONS SHALL TAKE UNLESS NOTED OTHERWISE PRECEDENCE TO SCALED DIMENSIONS. APPROXIMATELY 3000MM AFFL.

FFL LEVEL PAVEMENT

EWS-101A MINERAL WOOL INSULATION (F10) BRICK FACING EXTERNAL 750

FACADE SERVICES LEGEND

10.1 SQM OF COMBINED FREE AR TO BE PROVIDED BY AUTOMATE SMOKE VENTS, SUBCONTRACTO TO ENSURE COMPLIANCE

EWS-150 (H11) AUTOMATIC FULL HEIGHT 05 11/05/2018 STAGE F UPDATE GLAZING FOR SMOKE AND 900 04 25/05/2017 STAGE F UPDATE NATURAL VENTILATION

APPROXIMATELY 3000MM AFFL.

10. FOR 6TH & 7TH FLOOR TERRACES, FIRE ALARM AND CHECK AND VERIFY ALL DIMENSIONS PRIOR TO FLASHING XENON BEACONS TO BE MOUNTED OFATWORK. THIS DRAWING SHALL BE DIRECTLY ONCOMMENCEMENT TOP OF ONE ANOTHER READ IN CONJUNCTION WITH APPROXIMATELY 2400MM AFFL AND ALIGNED TO ALL OTHER CONTRACT CLOSEST FULL BRICK WHEREINCLUDING APPLICABLE. THOSE BY OTHER DOCUMENTS

MINERAL WOOL INSULATION

SUBCONTRACTOR DESIGN

EWS-122 (H11) PRECAST CONCRETE

H33

1500

900

AOD. +27.570 m

In this drawing architect provides the It is extremely important to explain subEWS-122 STRUCTURAL SLAB contractors how their products should be sub-contractor(H11) with the guidelines by PRECAST CONCRETE 3D VIEW - MAIN ENTRANCE 3 built into the main structure or joined with SCALE: NTS specifying that dimensions should be EXTERIOR 1 other customized items. A-42-C4203 PRIMARY STRUCTURE equal.

TER

TER

FFL LEVEL PAVEMENT

INTERIOR

EWS-150 VERTICAL SECTION - REVOLVING DOOR

10.1 SQM OF COMBINED FREE AREA TO BE PROVIDED BY AUTOMATED SMOKE VENTS. SUBCONTRACTOR TO ENSURE COMPLIANCE

ARNEY FENDER KATSALIDIS

STRUCTURAL SLAB

SCALE: NTS

FT TYPE EDR-124 (H11) REVOLVING DOOR

9. PROVISIONFLASHING FOR CCTV. READ IN CONJUNCTION XENON BEACONS TO BE MOUNTED SECURITY DRAWINGS AND SPECIFICATIONS. FINAL N BE O CONFIRMED T E S ON BY DIRECTLY TOP OF ONE ANOTHER AT LOCATIONS TO SUBCONTRACTOR.

RED BREAK GLASS UNIT/

DIVIDE 6170 INTOCORTEN 50 FLOOR WITH S/S EQUAL PARTSSTRIPS WITH REQUIRED SLIP (APPROX.123)RATING RESISTANCE TO REFER TO A-44-C4419

DOCUMENTS FP TYPE FIXED GLAZING UNITFV TYPE FROM ARCHITECT

FOR 9TH FLOOR TERRACES, FIRE ALARM AND

SSL + 26.820

3D VIEW - MAIN ENTRANCE

+30.305EXTERNAL m AOD. LIGHTING

CONTRACTOR DESIGN AND MUST COMPLY WITH FIRE STRATEGY REQUIREMENTS

VAPOUR BARRIER

+27.570 m AOD. EXTERIOR

1

FIRE ALARM AND FLASHING XENON BEACONS TO BE MOUNTED 7. REFER TO DIRECTLY A-47 & A-48 SERIES FOR KITCHEN ON TOP OF ONE ANOTHER AT EXTRACT CLADDING DRAWINGSIS COPYRIGHT OF AND SHALL REMAIN THIS DRAWING APPROXIMATELY THE PROPERTY OF:2400MM AFFL AND ALIGNED TO 8. AUTOMATED OPENING WINDOWS TO SUBCLOSEST FULL BRICK WHERE APPLICABLE.

STRUCTURE TO REVOLVING DOOR TO ENGINEER'S DESIGN

1150

FFL LEVEL 01

350

450

1150

3 A-44-C4433

+33.640 m AOD.

4 SCALE: 1 : 20 DIMENSIONS A-42-C4203

6. REFER TO LIGHTING CONSULTANTS DRAWINGS FOR 10. FOR 6TH AND & 7TH FLOOR TERRACES, EXTERNAL LIGHTING DESIGN SPECIFICATION.

FX-302 (N20) ENTRANCE MATWELL REFER TO A-55 SERIES

100

SCALE: NTS

450

690

4

700

CORTEN FLOOR WITH S/S STRIPS WITH REQUIRED SLIP FFL LEVEL 00 RATING RESISTANCE TO AOD. +26.970 m FFL LEVEL 02 SUBCONTRACTOR DESIGN

3D VIEW - MAIN ENTRANCE

350

EXT-202 (Q10) SLOT DRAIN

PRIMARY FFL LEVEL STRUCTURE PAVEMENT

9. PROVISION FOR CCTV. READ IN CONJUNCTION

REVOLVING DOOR FLOOR PIT

27.610

190

20

27.610

Site Diary 19

CHITTY STREET

EDR-124 (H11) REVOLVING DOOR

TO SUB-

5. REFER TO MEP AND SECURITY ENGINEERS SECURITY DRAWINGS AND SPECIFICATIONS. FINAL DRAWINGS AND SPECIFICATIONS FOR DETAILED LOCATIONS SERVICES DESIGN LAYOUT TO BE CONFIRMED BY SUBCONTRACTOR.

REVOLVING DOOR MACHINERY PIT

RAINWATER PIPES

ELECTRIC OUTLET POINTS

LOWER LEVELS

TO ACCESS REVOLVING DOOR FLOOR BOX. SIZE TO BE CONFIRMED WITH FACADE SUBCONTRACTOR

FIXED GLAZING UNIT

RWP CORTEN PLATE

EWS-150 ENGINEER'S CONTRACTOR DRAWINGS AND SPECIFICATIONS DESIGN AND MUST COMPLY WITH FIRE (H11) GLAZING UNIT STRATEGY REQUIREMENTS 4. REFER TO A-30 SERIES FOR WATERPROOFING TO SMOKE VENT

10.1 SQM OF COMBINED FREE AREA TO BE PROVIDED BY AUTOMATED SMOKE VENTS, SUBCONTRACTOR TO ENSURE COMPLIANCE REMOVABLE CORTEN BOX FLOOR

HA

EWS-150 (H11) AUTOMATIC FULL HEIGHT GLAZING FOR SMOKE AND NATURAL VENTILATION

6. REFER TO LIGHTING CONSULTANTS DRAWINGS FOR SPECIFICATION.

1. ALL PRECAST PANEL JOINTS TO BE 20MM WIDE AND EXTERNAL LIGHTING DESIGN AND RECESSED SILICONE SEALED

8. AUTOMATED OPENING WINDOWS PLANS AND READ IN CONJUNCTION WITH ELECTRICAL

175

RETE

FFL LEVEL 01 +30.305 m AOD.

FLASHING XENON BEACON20 MOUNTED AT MIN 2.4M AFFL

TO A-47 &OPENING A-48 SERIES FOR KITCHEN REFER TO 7. 65 REFER SERIES STRUCTURAL ON REVOLVING2.DOOR DOOR SCHEDULE EXTRACT CLADDING DRAWINGS FLOOR PIT 3. BEACONS AND FIRE ALARMS REFER TO 40 SERIES

LINE OF REVOLVING DOOR MACHINERY PIT

CORTEN PLATE

EWS-150 WPS-212 (J40) WATEPROOFING (H11) AUTOMATIC FULL HEIGHT MEMBRANE GLAZING FOR SMOKE AND CORTEN PLATE FLOOR NATURAL VENTILATION

Section 1.0

NOTES

350

2495

EDR-124 RIGID INSULATION (H11) REVOLVING DOOR TO

PAVEMENT

AOD. +30.305 m

MANIFESTATIONS MARKINGS GRAPHIC DESIGN TO BE CONFIRMED

ION - MAIN ENTRANCE INTERNAL ELEVATION VOID FORMER RFS-101

FFL LEVEL 01 10480

SCALE: NTS

M=MASTER, SM=SUB MASTER, S=SLAVE

5. REFER TO MEP AND SECURITY ENGINEERS EDGE OF UPSTAND DRAWINGS ANDBELOW SPECIFICATIONS FOR DETAILED SERVICES DESIGN LAYOUT

115

3550

EDR-124 (H11) GLASS REVOLVING DOOR

FIXED GLAZING UNIT

3

100

+30.305 m AOD.

[1.09]

1270 3D VIEW - MAIN ENTRANCE

365

FFL LEVEL 01

EWS-122 2280 (H11) PRECAST CONCRETE

3315

240 20

AOD. +30.305 m

EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ EQ

DRAINAGE SLOT

CORTEN PLATE FFL LEVEL 01

4 A-44-C4406

ASTOR COLLEGE

REMOVABLE CORTEN BOX FLOOR TO ACCESS REVOLVING DOOR FLOOR BOX. SIZE TO BE CONFIRMED WITH FACADE SUBCONTRACTOR 1300

1700

3D VIEW - MAIN ENT Arney Fender Katsalidis 5 T / +44 20 3772 7320 SCALE: NTS E/ info@afkstudios.com W / afkstudios.com FX-302 (N20) ENTRANCE MATWELL 44-46 Scrutton Street, London, EC2A 4HH.

REFER TO A-55 SERIES EWS-101A R1 (F10) BRICK FACING EXTERNAL 125 CLIENT:


Section 1.0

DOCUMENTS FROM SUBCONTRACTOR

Here we can see a detailed drawing from Felix, which is the main facade subcontractor in this site. When subcontractor receives drawing from AFK, they start thinking how it could be produced in a way to comply with the architect’s guidelines. However, communication goes on. It may happen that initial requirements cannot be met, for example, due to the material size limits or lack of structural rigidity of architect’s design. In this case, subcontractor marks the drawings with revision clouds and comments and sends them back and the design process contines. Typical drawings usually have dozens of revisions, that is why to confirm one item it may take from several days to several years

MY OPINION I think that sometimes it is more efficient to meet and discuss the drawings, unless you have overseas subs, which was the case in this project. However, some tours were organised for prototype observation.

Site Diary 20


[1.10]

[1.11]

[1.12]

Section 1.0

Site Diary 21

MEETINGS

01

TYPES OF SITE MEETINGS Every subcontractor has its Lead Pacakage Manager and Quantity Surveyor, they are in charge of coordination with Site Manager. All the Package Managers and also once Client’s representative are sitting in the Site Office for more efficient communication between the sides. The Main Point of Contract on site is Multiplex, which has most control over the Design Team and subcontractors.

02

WHAT HAPPENS IN A SITE MEETING? Different sides meet and discuss any problems or issues and propose the solutions. Site meetings provide a good opportunity for two-way discussions of any issues that have arisen or that are anticipated. Holding meetings on site enables the stakeholders to see progress for themselves, and to look at problem areas, discuss quality issues, assess mock-ups, and so on.

DAB (Daily Activity Brief) is the most important meeting on-site, attended by 30-40 people, all the representatives of subcontractors, trades and supervisors, currently engaged in the construction process. Every day there are 2 DABs: one for the Residential and one for the Commercial Project. Weekly Logistics Meetings with the trades are attended by Project Manager, Contract Manager, Site Manager, Off-site Manger and a Site Supervisor.

H&S Week (Health and Safety)is a big event, held by the H&S Advisor for everyone working on-site. Weekly Engineering Meeting is attended by 2 Engineers and 2 Site Managers either on site or in the office. Project Director leads all the Client facing meetings and also communicates with the major Package Managers. Design Meeting is one attended by the Site Manager and Project Leads from “Make Architects” and “AFK”. Main subcontratcors, like “Amery Construction” (concrete) and “Bourne” (steel) are allocated Weekly individual meetings. Internal Site Meeting is held every 4 days and is for Multiplex only.

01 MEETING IN THE OFFICE photo provided by Make Architects

02 SITE OFFICE


02.

THE DESIGN TEAM


Section 2.0

[2.02]

Site Diary 23

ARCHITECT+ CLIENT

[2.01]  What is the nature of the agreement between the Architect and the client? Standard RIBA agreement [2.02]  How has the Architect’s fee been calculated? Why is the architect doing the project?

CLIENT Employer agent

SLW

D&C CONTRACTOR

(Non-contructual link)

DESIGN TEAM

[2.01]

Architect

Multiplex + AFK: it is scope of work to be done: certain amount of works, certain amount of time and resources, or can be people times fee – a profile of the amount they are paid for month. Sometimes the contractor pays extras, if the architect should do any changes to the project. Derwent + Make: fee rate per month. Fee may go up or down depending on various conditions. In 2007 the client and architect could not agree for the certain fee, as the scheme of work has changed. It is a communicative process and always negotiation. Make prefers fee to be based on similar projects on site or based on the scope of work they have on other sites. Sometimes when the quantity of

MY OPINION

Architect

CMT

I think that the main reason why Make is doing this project is a desire to implement their concept and widen their portfolio, because, in my view, the conditions and fee are not really what they wanted.

drawing reviews rises, the fee raises. Sometimes the number of people involved may increase, but the fee remain the same. Regarding the fee, Make is rather flexible. The model of AFK is very strict: exact amount of people and time, fee agreed by emloyee’s wage. The more people is involves – the more money AFK earns.


[2.06]

Section 2.0

[2.07]

Site Diary 24

BUDGET

HOW GOOD?

Increasing quality Increasing requirements Pressure on Scope and Shedule/Cost

60%

[2.06]  What is driving the project? The client’s biggest value is appraisal of the design. They are also interested in maximizing the assets in their portfolio, which also means money or new projects with new design value or both.

QUALITY

In Derwent’s case the project is never driven by one factor. According to the client’s opinion, the priorities for 80 Charlotte project were in the following sequence: quality, budget and the programme. Two questions Derwent is interested to know about are: “What will be the result?” and “Will this result be viable?”

£ 190 million

[2.07]  What are the penalties to the contractor if the project over runs?

SCOPE

There are 7 different stages and different penalties depending on the stage. In the last stage of completion, in case of delay Multiplex will be charged 243000 pounds every week since the time of completion date (December 2019). However, Derwent gives them one extra month to finish the works with an exemption from fine. This means, the final completion date is January 2020.

HOW CHEAP?

10 years HOW FAST?

BUDGET

10%

PROGRAMME

30%


[2.04]

Section 2.0

[2.05]

Site Diary 25

DESIGN TEAM

DESIGN TEAM

[2.03]

[2.03]  Who are the Design Team? Logistics

Access

Structural Engineer

The Design Team consists of AFK (Novated Architect), Arup (both Structural Engineer and Building Services Engineer), Del Bueno (Landskape Design), Access=Design (Access), Clewlow (Transport), Madigan Gill (Logistics), BRCS (Building Control) and Orsa (Maintenance).

H&S

CLIENT

[2.04]  Who is administering the contract? Architect / Project Manager / another? Building control

MEP

Architect

Project Manager

The contract is administrated by the Main Contractor - Multiplex, but there is also an Employent Agent -SLW and a Project Manager - Buro Four. [2.05]  In your opinion has the Design Team worked efficiently together?

MY OPINION SLW

EMPLOYERS AGENT

D&C CONTRACTOR

I reckon that companies in the field of commercial building construction tend to have long-term partnership and are doing their job for decades, so it is not a problem for them to work efficiently enough on a new project.

I believe, that the Design Team has done a good job in competeing the design of a complex project and granting a planning permission. However, I guess it was rather challenging for the members of the Design Team to resume work after the period when the project was frozen for 2 years. Almost all representatives of the Constrcution Team who I was talking to during the site visits were relatively new to the project with a 10 years time scale, and I have not met anyone engaged in the project from its begining.


Section 2.0

Site Diary 26

QA WORKFLOW

CONSULTANT ENQUIRY

MCE Document Control QA Check &Log drawings on comments tracker

MCE DM and PM Review apply MCE status

Issues drawings to Multiplex

CMT comment on drawings and markup drawings

Via CMT Comment mail type

MCE DM & SLW meet weekly to review NonCompliance issues & agree actions

MCE DM & PM Amend Status as agreed and file replace with updated MCE stamp

Monday 12.30-1.30 slot

“FOR CONSTRUCTION” approved documents issued

Status C

Construction Document Management Software Status C

COORDINATION PROCESS

1 DAY

DM Design manager

10 DAYS

PM Package manager

10 DAYS

Max. 5 DAYS

CMT Compliance & Monitoring Team

1 DAY

SLW Employer agent from client’s side

1 DAY


[2.08]

[2.10]

Section 2.0

Site Diary 27

WORKFLOW

CLIENT

[2.08]  What is the process and procedure for information and instructions going to the contractor? Is it efficient?

D&C CONTRACTOR

Official instructions are going on site through technical drawings marked “For construction”. The point of contract from Multiplex is their design manager, who negotiates with architects through on-line platform.

Contract design intent

[2.10]  How does the Design Team share and Co-ordinate information and drawings? Is this efficient? Towards agreement there is a long approval process. In this project it is implemented through the Information Data Management.System, called “Acinex”. It is an on-line platform, in which every member of the Design Team has their personal accounts. Once the drawings are uploaded to programme, they are transmitted to QA Workflow.

ARCHITECT

Architect Coordintated design intent Drawing review Revision 00, 01, 02…

Information doesn’t come through once ususually, Drawing revew

the decisions are made through negotiations. There is a special CMT comments type between users.Comments may be A, B ,C, D type with, D – denied, A – approved. The hisory of comments is kept in the system, so that it would be easier to

analyze the data. Reporting delays via programme helps administering the process. Once the drawings receive A-A, they go to a final stage and are receive a stamp “For construction”. According to the diagram on the left, the whole process of approval should take 28 days. In real life it is longer then that, as it takes more one month to get A-A comments. The documents for construction may be reissued for 3 times The participants of the process would hardly call it efficient, as sometimes there can be up to 600 drawings to review for 1 person per month or 80 drawings to review for 1 person in a 10 day workflow.

Facade subcontractor Design responsibility

ARCHITECT’S OPINION METAL SYSTEMS

Specialist subcontractor

In a post-tender stage like this there shouldn’t be so many drawings to review The biggest problem is with residential buildings. Make developed design and AFK approved, but subcontractors said they couldn’t build this. This is the problem with bespoke items - may be 20 different arrangements of a single column and, of course, huge amount of information arising on the site. But people need quick answers.So it is quicker to use sketching in this process, however it is difficult to record that.


[2.09]

Section 2.0

Site Diary 28

GOING DIGITAL

There are 2 kinds of mockups subcontractor makes – performance and visual, they are aimed to reduce risk of the client and contractor – the aim of the mockups [2.09]  Are any Modern Methods of Construction, such as prefabrication, being utilised? There is a great use of DFMA and prefabrication in this project. By simplifying the design of a product it has been made possible to manufacture and assemble it more efficiently, in the minimum time and at a lower cost.

Pre-fabricated concrete plank - bottom side (ceiling)

Almost everything for this project was prefabricated off-site: concrete floor slabs, structural columns, beams, facade elements. The number of assembly operations was reduced to minimum with simple bolting joinery and assembly of two floors at a time. Two floors are connected with one module of column.

Example of DFA: facade brackets on the external column for pre-fabricated facade assembly

Environmental testing of facade - simulation of rain

Pre-fabricated facade performance mockup

Pre-fabricated concrete plank - top side to be covered with in-situ concrete


[2.11]

[2.12]

Section 2.0

MY OPINION HAS CHANGED I have always thought that to build a complex building like this BIM technologies are mainly used. Contrary to this belief, in this project all drawings were made in CAD with the BIM used for reference for engineering and structure. The reason for this is that it is extremely hard to make a good output from BIM model because of its’ complexity, moreover there are constraints of creating BIM model of the existing building. Nevertheless, Muliplex uses BIM as a tool to coordinate works on-site.

BIM

QR for logistics and assembly

Intersection of primary structures with MEP were made possible with BIM. This allows to coordinate different services.

The prefabricated beams and columns of different types are also marked with unique codding to increase efficiency of construction.

Site Diary 29

ON SITE

[2.11]  Identify how, if any, digital technology is influencing the progress of the site? As far as many elements in this building are prefabricated off-site, it is extremely important to distinguish them. QR codes contain a link to the inforamtion about every single beam, which can be found in a special system. The number of beam complies with its’ number in the technical drawing. It helps to track the production and transportation of beams, increasing logistics efficiency and allowing contractor to plan the works in case of delays. QR codes also help to assemble and maintain structure in future. [2.12]  What opportunities are there for digital technology to influence site operations? The site is very technologically effective, so I could not spot any other opportunities.

INTERESTING There is also a crane anti-collision system, as the tower cranes are placed very close to each other. It is intetesing, that 3 vaults were designed to put the cranes during the constrcution process, they will be then dismantled.

QR for maintenance This yellow markings indicate the holes where MEP will come through. The condition of the holes is permanently reviewed and updated in the system.

The tower-cranes location scheme


03.

STATUTORY APPROVALS


[3.01]

[3.02]

Section 3.0

[3.04]

Site Diary 31

PLANNING SECTION 106 AGREEMENT are private agreements made between local authorities and developers and can be attached to a planning permission to make acceptable development which would otherwise be unacceptable in planning terms.

[3.01]  How did the project achieve Planning permission? Was it complicated? Normally this process takes place after the feasibility studies. Design team attends preapplication meetings to discover the preferences of the local authorities, submit the planning application, waits 3-18 months to get the decision.

Agreement for this project: - provide affordable housing - build a public pocket park

Planning notices

This one was unusual, because it went through a political committee. There were two applications for different blocks - a detailed planning application (reference 2010/6873/P), alongside an application for conservation area consent (reference 2010/6879/C). Both of them were submitted to the London Borough of Camden (LBC) on 17 December 2010. The committee has turned it down. Thereafter the application was taken to GLA (Greater London Authority), as it has the power to over-ride planning decisions made by the London Boroughs if they are

believed to be against the interests of London as a whole. To navigate through complexity of Camden planning requirements, an expert planning consultant “DP9” was hired. Applications were approved by the Greater London Authority (GLA) on 16 March 2012. Scheme currently on site was amended in 2013 and 2014. The Decision Notice accompanying the permissions included 20 conditions which need to be satisfied at various stages of the project. Current position is that 18 of the 20 conditions have been discharged. The owners of these conditions are either Multiplex or Derwent London.

[3.02]  Look up the project on the Planning Portal and view the Planning Drawings – are they being strictly adhered to? Yes, the Planning Drawings are strictly adhered to.

Existing structure

Initial partial demolition intent

[3.04]  How are the Building Regulations being dealt with, i.e. Approved Inspector, Local Authority, why was the particular route chosen? Building regulations were dealt with through an Approved Inspector consultancy – “BRCS”. It worked closely with design and construction team and provided the client with Building Regulation compliance and the mandatory certificates that they needed to complete the construction project. Generally, on this project building regulations were easy to deal with, the only exception was focusing more on fire requirements since the Grenfell Tower fire tragedy. One biggest issue was compliance with disability requirements, which was really a pitfall of working with existing buildings, trying to adjust old structure to new requirements.

Actual demolition

CONSULTANTS

Planning consultant

Approved Inspector

AUTHORITIES

LBC

GLA


Section 3.0

[3.05]

Alternative entrance

INCLUSIVE DESIGN STRATEGY

Site Diary 32

Main entrance

Alternative entrance

[3.05]  What is the strategy for Inclusive Design and Access for All? Do you agree with this and how could this be improved?

In the center of the building there is an accessible central core, in which all the elevators, stairs and toilets along with the disbled WCs are placed. Lifts can accommodate wheel chair users or users who are not capable of using the stairs, taking them to each floor of the building. Wherever the toilet if placed, it is accompanied with adapted toilets to provide disabled users with suitable toilets, wash basins and grab rails for support.

VIP entrance

Access

Toilets for disabled

Lifts in central core

Howland St

The project if fully Life time home compliant. This means, that beyond the Building Regulations, which are not intended to provide the full standard of accessibility for disabled rather then making housing more accessible for visitors, a higher standard of 16 design features is met to ensure a new house will meet the needs of most households. For example, this includes wheelchair accessible WCs, easy access to windows, accessible for all sockets and many more.

Parking for disabled

The ground floor plan demonstrates that the entrances from the Charlotte St and Howland St are equipped with ramps and the Loading Bay has a safe route from the disabled parking bays.

Ramp

Main entrance Charlotte St

Gallery


[3.07]

[3.08]

PARTY WALL

Section 3.0

Site Diary 33

PARTY WALL AGREEMENT It is an act, which puts in place steps to safeguard the rights of those undertaking certain types of building work and the rights of their adjoining neighbours.

[3.07] Are there any Party Wall issues? Fortunately, there were no serious Party Wall issues, as it is an island site and almost all adjoining houses belong to the client.

This act is separate from planning permission or building regulation approval.

However, as 65 Whitfield Street has party wall there were some minor agreements, regarding scaffolding, crane rotating, access and construction boundaries, which did not take long. All the agreements were reached and can be reviewed at the Camden planning portal.

[3.08] If so how long did they take to reach Party Wall agreement? It only took several months to reach the agreements, however the other big issue was “difficult” neighbors, who were literally putting up roadblocks.

80 Charlotte Street & 65 Whitfield Street site boundary

Ownerships under Derwent London Group

CLIENT’S OPINION Constant pressure from neighbourhood did some damage to the project budget. 2,5 million pounds were lost on complying with affordable housing requirement of 106 agreement and also 10-15 millions pounds of value was lost on creating Pocket Park.


[3.09]

[3.11]

Section 3.0

Site Diary 34

CDM

[3.09]  What is the project approach to CDM? Who is the Principal Designer and Principle Contractor? Are those persons that ‘create’ risk responsible for ‘managing’ that risk to the health and safety of others during construction, use and maintenance of the building? The CDM issue was managed by a subcontractor appointed by Multiplex, which is literally Multiplex’s other business. This 3rd party serves as both the Principle Designer and the Principle Contractor Even though the construction works have started long ago, the principal contractor still visits the site on a monthly basis.basis. The process of discharging the CDM issue is: Health and safety risk is labeled

and the risk goes to the CDM document, which is tendered. Thus, the main contractor is responsible for the risk they create themselves. ORSA is a CDM advisor of the project, but has bo obligations.

[3.11]  In your view what are the key risks during the construction process and the eventual use of the building? Have all these risks been identified by the CDM team? Have you spotted any others? Visually/ graphically, how can you represent this? Cross link questions in this section with section 0.0 Formative Assessment/ Risk Assessment. I feel that the most dangerous risk on site may be a result of „competency failure” which can easily happen by mistake of one individual and lead to the increase of other health and safety risks. With all the hazards being monitored, however, if one individual

fails, there could be worrying results. An example of an easy competency failure, could be failing to remember to wear a hi-visibility jacket, which could lead to an accident.

THE CDM FLIPSIDE Sometimes CDM is used as an excuse by some sub-contractors when they do not want to produce the assigned scope of work.

The principal designer has responsibility for coordination of health and safety during the preconstruction phase, the principal contractor should coordinate the construction phase of the project.


Section 3.0

Site Diary 35

EXAMPLES OF H&S ON-SITE

SITE MANAGER James Hastie (Multiplex)

H&S MANAGER Louis Simo (Multiplex)

NAVIGATION

MOBILE PHONE USE AREA

HOLE MARKING

Reduces the risk of being trapped by vehicle. Faciliates the evacuation in case of emergency.

Reduces the risk of being distracted.

Reduces the risk of falling from a height.

EMERGENCY DOORS

EYES AND EARS PROTECTION

SCENE 6

Faciliates the evacuation in case of emergency.

Reduces the risk of injuries.

Reduces the risk of falling from a height.

I FOUND IT INTERESTING The situation in which the main contractor’s subsidiary serves as a principal designer/contractor is rather common. In case of big mistake they may dissolve it and have less obligations.


04.

BUILDING THE BUILDING


[4.01]

[4.02]

Section 4.0

Site Diary 37

MAIN CONTRACTOR

[4.01]  Who is the Main contractor? How is the company set up? What are your personal thoughts on the performance of the main contractor? Multiplex is the Main contractor of the project Multiplex is an affiliated company of Brookfield, one of the world’s biggest asset managers. During my Site Diary Project I met mainly with Multiplex representatives and really liked the way everything was organised. The site was clean and the quality of construction works was just ideal. I was impressed to see such tidy construction site. It feels like Multiplex has high standards and gives a sense of performing beyond the expectations. [4.02]  How was the main contractor selected for the project? Multiplex won a tender process, commenced in November 2014. The client was choosing between three main contactors - Bam, Multiplex and Mace, taking part in tender. There was a 2 stage tendering with the fee costs being specified at every stage. The pre-construction Agreement was signed first and then design information was sent for tender.

BROOKFIELD STRUCTURE

During the 1st stage a simple proposal has been received, and from that time a bigger package of design information has been calculated. The lumpsum fixed price was set. The overall construction cost was set at around 200 million pounds, including 5-6% for the job of Multiplex.

Two-stage tendering is used to allow early appointment of a supplier, prior to the completion of all the information required to enable them to offer a fixed price. In the first stage, a limited appointment is agreed to allow work to begin and in the second stage a fixed price is negotiated for the contract.

In the 2nd stage of tender the prices from the subcontractors and main contractor were confirmed and the Construction Phase has begun. Demolition had been done before the other packages were dealt with, as a measure to save time during cost estimation. fixed price. In the first stage, a limited appointment is agreed to allow work to begin and in the second stage a fixed price is negotiated for the contract.”


[4.03]

Section 4.0

[4.04]

Site Diary 38

SUB-CONTRACTORS 01

01

Atrium render [4.03]  Who are the specialist sub-contractors? There is a bunch of sub-contractors engaged in the project. The two main sub-contractors are Amery Construction and Bourne Steel – they are permanent “tenants” of the site and have their own works areas. Amery Construction produces precast concrete soffits, concrete walls, cladding and interior panels. Bourne Steel makes the skeleton of the building. Most of the site is at disposal of Amery team. Some of sub-contractors are located outside UK, i.e. Felix façade systems from Switzerland.

02 lluminated exposed concrete soffit with surrounding steel structure

T shape profile anodised aluminium top rail Exposed top edge of glazed balustrade

As an example, I would like to illustrate how the concrete slabs were designed and produced. Concrete slabs. Typical 6x1,5 m, they form a 6x9 m structural grid. Inside them there is a steel rebar for rigidity. Soffits are the finished products, as the concrete ceiling will remain exposed. In between they are sealed with 100 mm seam and in-situ concrete is poured on top to make the floor flat.

Subtle grey frit for screening floor slab and plenum Central mullion to split larger glazing

The negotiations took around 2 years and subcontractor has made around 100 samples.

Opening windows to the side of the projecting bays

Subtle grey frit for screening and safety

02 [4.04]  Were any of the specialist sub-contractors brought in during the design phase? Most of the sub-contractors were brought in during the design stage. The team of sub-contractors and suppliers also took part in tender and had a right to vote for the contractor of their choice.

Illuminated exposed concrete soffit with surrounding steel structure


[4.06]

[4.07]

Section 4.0

Site Diary 39

In this page I would like to demonstrate that the work of special subcontractors and the main contractor has been satisfactorily interfaced and give some examples of how the architectural vision as represented in the architect’s drawings are made manifest through the work of the builders on site.

FACADE CORNER

EXPOSED CONCRETE WALLS

PRE-CAST PLANKS SAMPLE

Concrete panels with wooden structure comply with the render.

The concrete panel seams are joined to create a single line through the full height of the main core.

The negotiations took around 2 years and subcontractor has made around 100 samples.. This is one of them.

CONCRETE FLOOR POURING

CONCRETE SOFFITS

SHADOW GAP

The structure is assembled and all items fit. The final step is making of concrete cap.

The texture of soffits comply with the approved sample.

An exposed staircase surface and a shadowgap between staircase and wall.


[4.08]

Section 4.0

Site Diary 40

MY OPINION [4.08]  WHAT DO YOU THINK ABOUT THE DESIGN OF THE BUILDING? WOULD YOU MAKE ANY CHANGES? AS FAR AS THE BUILDING IS LOCATED IN THE CONSERVATION AREA, I UNDERSTAND THAT THE ARCHITECTS WERE PRETTY MUCH RESTRICTED IN DEVELOPING THEIR CONCEPT. I LIKE THE PREVIOUS DESIGN PROPOSALS MORE THEN THE APPROVED PROJECT, AS THERE WAS MORE PASSION AND CREATIVITY IN THEM, BUT AT THE SAME TIME IT WAS A LITTLE BIT OUT OF CONTEXT. THE PROJECT WE SEE TODAY IS A BALANCED SOLUTION, SATISFYING DIFFERENT STAKEHOLDERS OF PROCESS. THE DETAILS THOUGH ARE RATHER GENTLE. THE BUILDING WILL NOT CAUSE TOO MUCH OF ATTENTION FROM THE WIDE PUBLIC, BUT WILL BE APPRECIATED BY SOPHISTICATED USERS. I WOULD PROBABLY MAKE NO CHANGES TO THE PROJECT, HOWEVER I WOULD WISH TO HAVE USED MORE CORTEN ELEMENTS IN IT.


Section 4.0

Site Diary 41


Section 4.0

DECEMBER 19 2018

Pre-fabricated beams and column junction

HOWLAND STREET

CHITTY STREET

WHITFIELD STREET

CHARLOTTE STREET

Site Diary 42


Section 4.0

Site Diary 43

JANUARY 17 2019

Temporary metal holding structure Temporary timber beams to flatten rebar

Holes filled with in-situ concrete

HOWLAND STREET

CHITTY STREET

WHITFIELD STREET

CHARLOTTE STREET


Section 4.0

DECEMBER 19 2018

In this photo we can see part of the retained faรงade at the Whitfield Street, assembled steel skeleton of 5th and 6th floors with several concrete planks forming 6x9 m soffits. The in-situ concrete is not poured yet.

HOWLAND STREET

CHITTY STREET

WHITFIELD STREET

CHARLOTTE STREET

Site Diary 44


Section 4.0

Site Diary 45

JANUARY 17 2019

Here we can see that the skeleton of 5th and 6th floors are finished, slabs are all put down and in-situ concrete is drying.

Raised floor

Isolation

Concrete cladding

Hole for maintenance Primary structure

Section of the typical floor and wall junction


05.

CONSTRUCTION SEQUENCE DRAWING


Section 5.0

Site Diary 47

READING THE BUILDING

TOWER CRANE

RETAINED FACADE RETAINED STRUCTURE CENTRAL CORE

VAULTS FOR CRANES

6x6 CONCRETE SOFFITS ASSEMBLED OF 1,6x6 PLANKS


Section 5.0

Site Diary 48

01

07/2016

10 YEARS PROJECT

04/2017 02


Section 5.0

06/2017 01 ROOF VIEW PHOTOS Charlotte St/Chitty St corner

01 ROOF VIEW PHOTOS Charlotte St/Howland St corner

Site Diary 49

11/2018

01/2019


Section 5.0

Site Diary 50

FEBRUARY 2019

Ground works are nearly finished First two tower cranes are set in place Temporary structures are holding the ground The foundation of the central core is ready Piling starts

HOWLAND STREET

CHITTY STREET

WHITFIELD STREET

CHARLOTTE STREET

2017

Q4

Q1 Q1

2016

Q2

Q3

Q4

2019 Q2

Q3

Q4

Q1 Q1

2018

Q2

Q3

Q4

Q2

Q3

Q4 Q1

2020

Q2

Q3


Section 5.0

Site Diary 51

DECEMBER 2020

Ground works are finished Last crane is set in place Temporary structures are holding the ground The central core in-situ concrete structure is being build

2017 Q1 Q1

2016

Q2

Q3

Q4

2019 Q2

Q3

Q4

Q1 Q1

2018

Q2

Q3

Q4

Q2

Q3

Q4 Q1

2020

Q2

Q3


Section 5.0

Site Diary 52

FEBRUARY 2019

Ground works are finished The central core is finished Steel structure of 2 first floors is assembled Temporary structures are removed

2017

Q4

Q1 Q1

2016

Q2

Q3

Q4

2019 Q2

Q3

Q4

Q1 Q1

2018

Q2

Q3

Q4

Q2

Q3

Q4 Q1

2020

Q2

Q3


Section 5.0

Site Diary 53

DECEMBER 2020

Concrete soffits of 2 first floors are fixed and the insitu concrete will now be poured

2017 Q1 Q1

2016

Q2

Q3

Q4

2019 Q2

Q3

Q4

Q1 Q1

2018

Q2

Q3

Q4

Q2

Q3

Q4 Q1

2020

Q2

Q3


Section 5.0

Site Diary 54

DECEMBER 2018

During the site visit: The structures of first 5 levels are done Steel skeleton for 6 and 7 levels if partly assembled

2017

Q4

Q1 Q1

2016

Q2

Q3

Q4

2019 Q2

Q3

Q4

Q1 Q1

2018

Q2

Q3

Q4

Q2

Q3

Q4 Q1

2020

Q2

Q3


Section 5.0

Site Diary 55

DECEMBER 2020

The building is finished and ready to welcome tenants Tower cranes are removed

The drawing was provided by the architects

HOWLAND STREET

CHITTY STREET

WHITFIELD STREET

CHARLOTTE STREET

2017 Q1 Q1

2016

Q2

Q3

Q4

2019 Q2

Q3

Q4

Q1 Q1

2018

Q2

Q3

Q4

Q2

Q3

Q4 Q1

2020

Q2

Q3


06.

CONLUSIONS AND THE FUTURE


[6.01] [6.03]

Section 6.0

Site Diary 57

CONCLUSION

[6.01]  What have you learnt by following the site diary project on site? My site diary experience was excellent. I have been able to see the inside of the ongoing project of a city scale, gaining the insight into how the construction industry works and how the collaborative processes between different parties are organized. I was lucky to communicate with the representatives of leading UK companies, engaged in this project, as the job they are doing is really high-end. Apart from good management, I found out how the digital technologies increase the efficiency of the site operations and reduce the risk of the human factor to minimum. I was surprised to discover that a number of people in the office and on-site is relatively small, which demonstrates the efficiency of the operational management and great use of the technologies.

I have also rediscovered significantly the role of the Architect in this regard. Before the project, I assumed that the project management is the responsibility of the Architectural Team, but that was not the case, as the majority of work is done by the Main Contractor. I also thought that Architects execute the whole spectrum of works from the concept to design development with the weekly reissue of the blueprints and dozens of architects attending the construction site in turn, while, in fact, the supervision is made by only 2 architects and the technical work is deligated to other parties. I have extended my interest in pre-fabrication observing the changes it makes to the time scale and the accuracy of construction.

[6.03]  How has the Site Diary experience informed your possible career direction in architecture? During the project I have realized that working on site appeals to me more then office . In future I will be searching for the project leading work

opportunities. The experience has also proved my interest in working in Make.


Section 6.0

[6.02]

01

02

03

PRIMARY BEAM 450d x 250w PG TIE BEAM RECESSED 150d x 250w PG EDGE BEAM 300d x 250w PG ATRIA EDGE BEAM 450d x 300w PG TRANSFER BEAM

01 CONCRETE SLAB IS UNLOADED Photo from the site

02 ASSEMBLY PROCESS Photo from the site

03 DIFFERENT TYPES OF BEAMS Drawing provided by the architect

[6.02] What materials, building processes and /or technologies have you observed that you may wish to incorporate in your own projects in the future?

Unique of this project is the primary steel structure. I have always liked the steel structures in architecture, and in this project I found the process of the metal structure assembly very inspiring.

HELPS REDUCE WASTE

Site Diary 58

04


Section 6.0

Site Diary 59

2 LEVELS AT ONCE

04 INTERIOR RENDER Provided by the architect

05 JUNCTION OF 2 PREFABRICATED ITEMS Sketch from the site

02 05 03


01

01

03

THANK YOU!

01 SITE MEETING With Andrea Buckle

02

02 MULTIPLEX SITE OFFICE MEETING With Marks Timson

02 DERWENT OFFICE MEETING With Derwent team


LETTER

OUR POINTS OF CONTACT Make Oliver Hall - Commercial Lead Multiplex Andrea Buckle – Community Engagement Marks Timson - Senior Project Manager Louis Simo - Health and Safety Manager James Hastie - Site Manager Oli Jones - Design Manager Derwent Jonathan Walker – Senior Project Manager Tom French – Associate, Development Peter Pulford – Development Manager Timothy Hyman – Group Architect